Azura Edo Power Station | |
---|---|
Country | Nigeria |
Coordinates | 06°24′32″N05°41′01″E / 6.40889°N 5.68361°E Coordinates: 06°24′32″N05°41′01″E / 6.40889°N 5.68361°E |
Status | Operational |
Commission date | Phase 1 - May 2018 |
Thermal power station | |
Primary fuel | Natural gas |
Power generation | |
Nameplate capacity | 461 MW |
External links | |
Website | azuraedo |
The Azura-Edo Power Station is a natural gas-powered open cycle electricity generation plant, with a current operational capacity of 461 megawatts, located in Benin City in Nigeria. [1] This is the first phase of a three-phase construction project of a combined cycle gas plant with planned capacity of 1,500 megawatts. [2]
The power station is located to the northeast of Benin City in Edo State, approximately 316 kilometres (196 mi), by road, east of Lagos, Nigeria's commercial capital. [3] This location lies approximately 465 kilometres (289 mi), by road, southwest of Abuja, the country's capital city. [4] The geographical coordinates of the power station are:06°24'32.0"N, 05°41'01.0"E (Latitude:6.408889; Longitude:5.683611). [5]
The Azura-Edo IPP is an open-cycle gas fired power plant. The power station is often referred to as the "Azura-Edo Independent Power Plant" or "Azura-Edo IPP", because the finance required to build the plant was sourced from the private sector, rather than from the government. The private sector owners of the plant took the construction risk. The post-construction risk and the operational risks are also borne by the plant's owners and their operations and maintenance contractors. [1]
The power station is owned by Azura Power Holdings, an investment holding company for independent power projects in Africa. The majority equity investor in the Azura Power Holdings is Actis Capital, a private equity firm headquartered in London with US$7.8 billion under management. In 2004, it was spun-off from CDC Group, owned by the Government of the United Kingdom. [1] [6]
The minority equity investors in the plant are include: 1. Africa50, a pan-African infrastructure investment platform. 2. Anergi Group, an energy company active in Africa's emerging economies. 3. Amaya Capital, an investment firm with a focus on the infrastructure sector in Africa and 4. The Edo State Government, which holds a 2.5 percent equity stake in the plant. [7]
The power station cost US$900 million to build. The financing was obtained from fifteen financial institutions, in nine countries. [1] The table below, illustrates the debt investors in the project. In addition, the International Bank for Reconstruction and Development (IBRD) provided partial risk guarantees; while the Multilateral Investment Guarantee Agency (MIGA) provided political risk insurance. Both IBRD and MIGA are members of the World Bank Group. [7]
No. | Name of Lender | Domicile |
---|---|---|
1 | Overseas Private Investment Corporation | United States |
2 | CDC Group | United Kingdom |
3 | Proparco | France |
4 | German Investment Corporation | Germany |
5 | KfW | Germany |
6 | Netherlands Development Finance Company | Netherlands |
7 | Swedfund International | Sweden |
8 | International Finance Corporation | United States |
9 | ICF Debt Pool | Canada |
10 | Emerging African Infrastructure Fund | Mauritius |
11 | Standard Chartered Bank | United Kingdom |
12 | Rand Merchant Bank | South Africa |
13 | Standard Bank of South Africa | South Africa |
14 | Mauritius Commercial Bank | Mauritius |
15 | First City Monument Bank | Nigeria |
16 | Siemens Bank | Germany |
Construction of the plant began in January 2016 under an Engineering, Procurement and Construction ("EPC") contract with a consortium comprising (a) Siemens AG of Germany (b) Siemens Nigeria Limited and (c) Julius Berger Nigeria Limited. Siemens also provided the turbines, generators, transformers and other electrical hardware. The plant was completed on 30 April 2018, six months ahead of schedule, a record achievement for a plant of this size. [1]
Nearly 5 million man-hours of labor were expended on the plant, without a single lost-time injury, and the names of all the developers and construction workers, numbering over 2,000 in total, are now inscribed on a brass plaque at the front of the plant's administration and control building. [8]
Decaying infrastructure is one of the deficiencies that Nigeria's National Economic Empowerment Development Strategy (NEEDS) seeks to address. The government has begun to repair the country's poorly maintained road network. Because Nigeria's railways are in a perilous condition, the government is trying to rectify the situation by privatizing the Nigerian Railway Corporation. Similarly, the government is pursuing a strategy of partial port privatization by granting concessions to private port operators so that they can improve the quality of port facilities and operations.
The World Bank Group (WBG) is a family of five international organizations that make leveraged loans to developing countries. It is the largest and best-known development bank in the world and an observer at the United Nations Development Group. The bank is headquartered in Washington, D.C. in the United States. It provided around $61 billion in loans and assistance to "developing" and transition countries in the 2014 fiscal year. The bank's stated mission is to achieve the twin goals of ending extreme poverty and building shared prosperity. Total lending as of 2015 for the last 10 years through Development Policy Financing was approximately $117 billion. Its five organizations are the International Bank for Reconstruction and Development (IBRD), the International Development Association (IDA), the International Finance Corporation (IFC), the Multilateral Investment Guarantee Agency (MIGA) and the International Centre for Settlement of Investment Disputes (ICSID). The first two are sometimes collectively referred to as the World Bank.
The West African Gas Pipeline (WAGP) is a natural gas pipeline to supply gas from Nigeria's Escravos region of the Niger Delta area to Benin, Togo and Ghana. It is the first regional natural gas transmission system in sub-Saharan Africa.
The Multilateral Investment Guarantee Agency (MIGA) is an international financial institution which offers political risk insurance and credit enhancement guarantees. These guarantees help investors protect foreign direct investments against political and non-commercial risks in developing countries. MIGA is a member of the World Bank Group and is headquartered in Washington, D.C. in the United States.
Railway stations in Nigeria include:
Oando Plc is a Nigerian multinational energy company operating in the upstream, midstream and downstream.
The Dangote Group is a Nigerian multinational industrial conglomerate, founded by Aliko Dangote. It is the largest conglomerate in West Africa and one of the largest on the African continent. The group employs more than 30,000 people, generating revenue in excess of US$4.1 billion in 2017.
The Bujagali Power Station is a hydroelectric power station across the Victoria Nile that harnesses the energy of its namesake; the Bujagali Falls, in Uganda. Construction began in 2007 and concluded in 2012. It was officially inaugurated on 8 October 2012 by Ugandan President Yoweri Museveni and Aga Khan IV in the presence of African politicians and investors.
Nigeria's primary energy consumption was about 108 Mtoe in 2011. Most of the energy comes from traditional biomass and waste, which account for 83% of total primary production. The rest is from fossil fuels (16%) and hydropower (1%).
Ardova Plc is an indigenous energy group, headquartered in Lagos, Nigeria, with extended operations in Ghana. It operates majorly in the downstream sector of the Nigeria’s Oil and Gas industry, but has diversified its businesses into other sectors of the energy value chain. The downstream division specializes in the distribution of a wide range of petroleum products; Premium Motor Spirit (PMS), diesel, aviation fuel, kerosene, as well as a range of lubricants for various automobiles and machines; distributed mostly to the automobile, industrial, aviation and marine markets.
Africa Finance Corporation (AFC) is a pan-African Multilateral Development Financial Institution established in 2007 by sovereign African states to provide pragmatic solutions to Africa's infrastructure deficit and challenging operating environment. The Corporation bridges the infrastructure investment gap through the provision of debt and equity finance, project development, technical and financial advisory services.
Godwin Nogheghase Obaseki is a Nigerian politician and businessman who is currently the Governor of Edo State. He was first sworn in as governor on 12 November 2016. Before becoming governor, he had served as the chairman of the Edo State Economic and Strategy Team inaugurated by former Governor Adams Oshiomole in March 2009.
Mikano International Limited is a Nigerian company with interest in power generation, real estate and construction; this company offers sales, maintenance, assembling, distribution of power generation products, real estate development, and sales of construction equipment.
Abuja Thermal Power Station is a planned 1,350 MW natural gas-fired thermal power plant in Nigeria. It is planned as an IPP project.
Investment Fund for Developing Countries (IFU), is a Development Financial Institution owned by the Government of Denmark. IFU is a self-governing, state-owned fund, whose objective is to promote economic and social development in developing countries. The Fund provides risk capital and advice to companies wanting to do business in parts of Europe, Asia, Latin America and Africa.
Ressano Garcia Thermal Power Station is a 175 MW (235,000 hp) natural gas-fired thermal power plant located in the town of Ressano Garcia in the Maputo Province of Mozambique.
The Singrobo Hydroelectric Power Station, also Singrobo-Ahouaty Hydroelectric Power Project, is a hydroelectric power station under construction across the Bandama River, in Ivory Coast. When completed, as expected in 2023, the power station will be the first, grid-ready hydroelectric power station, developed and owned by a independent power producer (IPP) in West Africa. The energy generated here will be sold to the Ivorian electric utility company, Cienergues, under a 35-year power purchase agreement (PPA).
The Nagreongo Solar Power Station, also Nagréongo Solar Power Station, is a 30 MW (40,000 hp) solar power plant under construction in Burkina Faso. The solar farm is under development by the French IPP, GreenYellow, a subsidiary of the Casino Group. The energy generated here will be sold to the Burkinabe electricity utility company SONABEL,, under a 25-year power purchase agreement (PPA).
The Lichinga Solar Power Station, is a planned 50 MW (67,000 hp) solar power plant in Mozambique. The solar farm is under development by a consortium comprising Gigawatt Global, a Dutch multinational IPP and the Anglican Church of Niassa, based in Niassa Province, in northwestern Mozambique. The energy generated here is to be sold to Electricidade de Moçambique (EDM), the Mozambican public electric utility company, for distribution to Lago District, Mecula District, Mecanhelas District, Mavago District and Mandimba District.