Black start

Last updated
Toronto during the Northeast blackout of 2003, which required black-starting of generating stations. Toronto ON 2003 Blackout.jpg
Toronto during the Northeast blackout of 2003, which required black-starting of generating stations.

A black start is the process of restoring an electric power station, a part of an electric grid or an industrial plant, to operation without relying on the external electric power transmission network to recover from a total or partial shutdown. [1]

Contents

Power to restart a generating station or plant may come from an on-site black start standby generator. Alternatively, where a large amount of power is required, a tie-line to another generating plant or to an emergency generator may be used to start the facility. Once the main generating units are running, the electrical transmission network can be re-connected and electrical loads restored.

Black-start power may be ensured by an agreement where a particular energy supplier is paid to make black start power available when required. Not all generating plants are suitable for providing black-start power to a network.

Station service power

Electrical generating plants require electric power to operate systems required in the plant. For example, a coal-fuelled plant requires conveyors, crushers, air compressors, and combustion air fans to operate. Steam cycle plants require large pumps to circulate water for steam boilers and for cooling of condensate water. Hydroelectric plants require power to open intake gates, and to adjust the hydraulic turbines for speed regulation. Even a wind turbine plant may require a relatively small amount of electric power for such things as adjusting blade pitch and direction.

Normally, the electric power used within the plant is provided by the station's own generators. If all of the plant's main generators are shut down, station service power is provided by drawing power from the grid through the plant's transmission line. However, during a wide-area outage, off-site power from the grid is not available. In the absence of grid power, a so-called black start needs to be performed to bootstrap the power grid into operation.

Standby power sources

To provide a black start, some power stations or plant have small on-site diesel generators, normally called the black start diesel generator (BSDG), which can be used to start larger generators (of several megawatts capacity), which in turn can be used to start the main power station generators. Generating plants using steam turbines require station service power of up to 10% of their capacity for boiler feedwater pumps, boiler forced-draft combustion air blowers, and for fuel preparation. It is uneconomical to provide such a large standby capacity at each station, so black-start power must be provided over designated tie lines from another station.

Often hydroelectric power plants are designated as the black-start sources to restore network interconnections. A hydroelectric station needs very little initial power for starting purposes (just enough to open the intake gates and provide excitation current to the generator field coils) and can put a large block of power on line very quickly to allow start-up of fossil fuel or nuclear stations. Certain types of combustion turbine can be configured for a black start, providing another option in places without suitable hydroelectric plants. [2] In 2017, a utility in Southern California successfully demonstrated the use of an energy-storage system based on a lithium-ion battery to provide a black start, firing up a combined-cycle gas turbine from an idle state. [3]

Startup sequence

One method of black start (based on a real scenario) might be as follows:

  1. A battery starts a small diesel generator installed in a hydroelectric generating station.
  2. The power from the diesel generator is used to bring the generating station into operation.
  3. Key transmission lines between the station and other areas are energized.
  4. The power from the station is used to start one of the nuclear/fossil-fuel-fired base load plants.
  5. The power from the base load plant is used to restart all of the other power plants in the system.
  6. Power is finally re-applied to the general electricity distribution network and sent to the consumers.

Often this will happen gradually; starting the entire grid at once may be unfeasible. In particular, after a lengthy outage during summer, all buildings will be warm, and if the power were restored at once, the demand from air conditioning units alone would be more than the grid could supply. In colder climates, a similar issue can occur in winter with the use of heating devices.

In a larger grid, in addition to this "single island" ("bottom-up") approach, different strategies can be involved: [4] [5]

There are multiple methods of commencing a black start of an island: hydroelectric dams, diesel generators, open cycle gas turbines, grid scale battery stores, compressed air storage, and so on. Different generating networks take different approaches, dependent on factors such as cost, complexity, the availability of local resources (e.g. suitable valleys for dams), the interconnectivity with other generating networks, and the response time necessary for the black start process.

Procurement of black start services

An operator at ERCOT ERCOTOperator 2.jpg
An operator at ERCOT

In the United Kingdom, the grid operator has commercial agreements in place with some generators to provide black start capacity, recognizing that black start facilities are often not economical in normal grid operation. [11] It is typical of power stations from the era of the Central Electricity Generating Board to have a number of open-cycle gas turbines (i.e. no heat recovery modules attached) that can run the entirety of the plant necessary to operate a full generating unit; these would normally be started by diesel generators, fed in turn by battery backups. Once up to speed, these gas turbines are capable of running the entire plant associated with the rest of the power station, negating the need to bring power in from other sources.

In the North American independent system operators, the procurement of black starting varies somewhat. Traditionally, the black-start capability was provided by integrated utilities and the costs were rolled into a broad tariff for cost recovery from ratepayers. In those areas which are not part of organized electricity markets, this is still the usual procurement mechanism. In the deregulated environment, this legacy of cost-based provision has persisted, and even recent overhauls of black-start procurement practices, such as that by the ISO New England, have not necessarily shifted to a competitive procurement, even though deregulated jurisdictions have a bias for market solutions rather than cost-of-service (COS) solutions.

In the United States, there are currently three methods of procuring black start. The most common is cost-of-service, as it is the simplest and is the traditional method. It is currently used by the California Independent System Operator (CAISO), the PJM Interconnection [12] and the New York Independent System Operator [13] (NYISO). The exact mechanisms differ somewhat the same approach is used, namely that units are identified for black start and their documented costs are then funded and rolled into a tariff for cost recovery.

The second method is a new method used by the Independent System Operator of New England [14] (ISO-NE). The new methodology is a flat-rate payment which increases black-start remuneration to encourage provision. The monthly compensation paid to a generator is determined by multiplying a flat rate (in $/kWyr and referred to as the $Y value) by the unit's Monthly Claimed Capability for that month. The purpose of this change was to simplify procurement and encourage provision of the black start service.

The final method of procurement is competitive procurement as used by the Electric Reliability Council of Texas [15] (ERCOT). Under this approach, ERCOT runs a market for black-start services. Interested participants submit an hourly standby cost in $/hr (e.g. $70 per hour), often termed an availability bid, that is unrelated to the capacity of the unit. Using various criteria, ERCOT evaluates these bids and the selected units are paid as bid, presuming an 85% availability. Each black-start unit must be able to demonstrate that it can start another unit in close proximity, in order to begin the islanding and synchronization of the grid.

In other jurisdictions there are differing methods of procurement. The New Zealand System Operator [16] procures the blackstart capability via competitive tender. Other jurisdictions also appear to have some sort of competitive procurement, albeit perhaps not as structured as that of ERCOT. These include the Alberta Electric System Operator, [17] as well as Independent Electric System Operator of Ontario, [18] both of which use a long-term "request for proposals" approach similar to New Zealand and ERCOT.

The first black start on Germany's grid was tested in 2017 at WEMAG battery power station in Schwerin on a disconnected, isolated grid. The WEMAG battery plant proved that it can restore the power grid after major disruption or blackout. [19]

Limitations on black start sources

Not all generating plants are suitable for black-start capability. Wind turbines are not always suitable for black start because wind may not be available when needed. [20] Wind turbines, mini-hydro, or micro-hydro plants, are often connected to induction generators which are incapable of providing power to re-energize the network. [21] In 2020, the 69 MW Dersalloch wind farm black-started part of the Scotland grid, using virtual synchronous machines. [22] [23] The black-start unit must also be stable when operated with the large reactive load of a long transmission line. Many high-voltage direct current (HVDC) converter stations cannot operate into a "dead" system, either, since they require commutation power[ clarification needed ] from the system at the load end. A pulse-width modulation (PWM)-based voltage-source converter HVDC scheme has no such restriction. [24]

See also

Related Research Articles

<span class="mw-page-title-main">Power station</span> Facility generating electric power

A power station, also referred to as a power plant and sometimes generating station or generating plant, is an industrial facility for the generation of electric power. Power stations are generally connected to an electrical grid.

<span class="mw-page-title-main">Distributed generation</span> Decentralised electricity generation

Distributed generation, also distributed energy, on-site generation (OSG), or district/decentralized energy, is electrical generation and storage performed by a variety of small, grid-connected or distribution system-connected devices referred to as distributed energy resources (DER).

<span class="mw-page-title-main">Electric power industry</span> Industry that provides the production and delivery of electric energy

The electric power industry covers the generation, transmission, distribution and sale of electric power to the general public and industry. The commercial distribution of electric power started in 1882 when electricity was produced for electric lighting. In the 1880s and 1890s, growing economic and safety concerns lead to the regulation of the industry. What was once an expensive novelty limited to the most densely populated areas, reliable and economical electric power has become an essential aspect for normal operation of all elements of developed economies.

<span class="mw-page-title-main">Peaking power plant</span> Reserved for high demand times

Peaking power plants, also known as peaker plants, and occasionally just "peakers", are power plants that generally run only when there is a high demand, known as peak demand, for electricity. Because they supply power only occasionally, the power supplied commands a much higher price per kilowatt hour than base load power. Peak load power plants are dispatched in combination with base load power plants, which supply a dependable and consistent amount of electricity, to meet the minimum demand.

<span class="mw-page-title-main">Regional transmission organization (North America)</span> Electric power coordinator

A regional transmission organization (RTO) in the United States is an electric power transmission system operator (TSO) that coordinates, controls, and monitors a multi-state electric grid. The transfer of electricity between states is considered interstate commerce, and electric grids spanning multiple states are therefore regulated by the Federal Energy Regulatory Commission (FERC). The voluntary creation of RTOs was initiated by FERC in December 1999. The purpose of the RTO is to promote economic efficiency, reliability, and non-discriminatory practices while reducing government oversight.

A variable-frequency transformer (VFT) is used to transmit electricity between two alternating current frequency domains. The VFT is a relatively recent development. Most asynchronous grid inter-ties use high-voltage direct current converters, while synchronous grid inter-ties are connected by lines and "ordinary" transformers, but without the ability to control power flow between the systems, or with phase-shifting transformer with some flow control.

<span class="mw-page-title-main">Transmission system operator</span> Energy transporter

A transmission system operator (TSO) is an entity entrusted with transporting energy in the form of natural gas or electrical power on a national or regional level, using fixed infrastructure. The term is defined by the European Commission. The certification procedure for transmission system operators is listed in Article 10 of the Electricity and Gas Directives of 2009.

<span class="mw-page-title-main">Diesel generator</span> Combination of a diesel engine with an electrical generator

A diesel generator (DG) (also known as a diesel GenSet) is the combination of a diesel engine with an electric generator (often an alternator) to generate electrical energy. This is a specific case of an engine generator. A diesel compression-ignition engine is usually designed to run on diesel fuel, but some types are adapted for other liquid fuels or natural gas (CNG).

<span class="mw-page-title-main">Folsom Powerhouse State Historic Park</span> United States historic place

Folsom Powerhouse State Historic Park is a historical site preserving an 1895 alternating current (AC) hydroelectric power station—one of the first in the United States.

<span class="mw-page-title-main">Texas Interconnection</span> Power grid providing power to most of Texas

The Texas Interconnection is an alternating current (AC) power grid – a wide area synchronous grid – that covers most of the state of Texas. The grid is managed by the Electric Reliability Council of Texas (ERCOT).

<span class="mw-page-title-main">Safe Harbor Dam</span> Dam in Pennsylvania, USA

The Safe Harbor Dam is a concrete gravity dam, with an associated hydroelectric power station, on the lower Susquehanna River. It is the most northerly and last of three Great Depression-era public electrification projects' hydroelectric dams, and was constructed between April 1, 1930, and December 7, 1931. It created a long and relatively shallow lake, known as Lake Clarke, along the upper stretch of the Conejohela Valley. The creation of the lake shrank the upper Conejohela Flats in size.

A load-following power plant, regarded as producing mid-merit or mid-priced electricity, is a power plant that adjusts its power output as demand for electricity fluctuates throughout the day. Load-following plants are typically in between base load and peaking power plants in efficiency, speed of start-up and shut-down, construction cost, cost of electricity and capacity factor.

Availability Based Tariff (ABT) is a frequency based pricing mechanism applicable in India for unscheduled electric power transactions. The ABT falls under electricity market mechanisms to charge and regulate power to achieve short term and long term network stability as well as incentives and dis-incentives to grid participants against deviations in committed supplies as the case may be.

<span class="mw-page-title-main">PJM Interconnection</span> Major electric grid coordinator in northeastern USA

PJM Interconnection LLC (PJM) is a regional transmission organization (RTO) in the United States. It is part of the Eastern Interconnection grid operating an electric transmission system serving all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia, and the District of Columbia.

<span class="mw-page-title-main">Electrical grid</span> Interconnected network for delivering electricity to consumers

An electrical grid is an interconnected network for electricity delivery from producers to consumers. Electrical grids consist of power stations, electrical substations to step voltage up or down, electric power transmission to carry power over long distances, and finally electric power distribution to customers. In that last step, voltage is stepped down again to the required service voltage. Power stations are typically built close to energy sources and far from densely populated areas. Electrical grids vary in size and can cover whole countries or continents. From small to large there are microgrids, wide area synchronous grids, and super grids. The combined transmission and distribution network is part of electricity delivery, known as the power grid.

The United States has the second largest electricity sector in the world, with 4,178 Terawatt-hours of generation in 2023. In 2023 the industry earned $491b in revenue at an average price of $0.127/kWh.

<span class="mw-page-title-main">Electricity sector in Sri Lanka</span>

The electricity sector in Sri Lanka has a national grid which is primarily powered by hydroelectric power and thermal power, with sources such as photovoltaics and wind power in early stages of deployment. Although potential sites are being identified, other power sources such as geothermal, nuclear, solar thermal and wave power are not used in the power generation process for the national grid.

<span class="mw-page-title-main">West Springfield Generating Station</span> Power plant in Massachusetts, U.S.

The West Springfield Generating Station, also known by its corporate name EP Energy Massachusetts, LLC, was a fossil-fuel-fired power plant located in West Springfield, Massachusetts. The station was a "peaking" facility, meaning that it primarily operates during peak electrical demand. The facility consisted of two 49-megawatt (MW) combustion turbine generators fueled by natural gas or ultra low-sulphur diesel fuel, one 18 MW jet turbine that was fueled by kerosene, and one 107 MW simple-cycle steam boiler unit burning no. 6 fuel oil, ULSD or natural gas. The station also had a small auxiliary boiler for process and building heat and an emergency back-up generator.

<span class="mw-page-title-main">North American power transmission grid</span> Series of electrical grids that power the US and Canada

The electrical power grid that powers Northern America is not a single grid, but is instead divided into multiple wide area synchronous grids. The Eastern Interconnection and the Western Interconnection are the largest. Three other regions include the Texas Interconnection, the Quebec Interconnection, and the Alaska Interconnection. Each region delivers power at a nominal 60 Hz frequency.

References

  1. Knight, U.G. Power Systems in Emergencies - From Contingency Planning to Crisis Management John Wiley & Sons 2001 ISBN   978-0-471-49016-6 section 7.5 The 'Black Start' Situation
  2. Philip P. Walsh, Paul Fletcher Gas turbine performance, John Wiley and Sons, 2004 ISBN   0-632-06434-X, page 486
  3. "California battery's black start capability hailed as 'major accomplishment in the energy industry'". May 17, 2017.
  4. Gevorgian et al. 2021, p. 3.
  5. PJM 2018, pp. 102–118.
  6. PJM 2018, pp. 103–106.
  7. PJM 2018, pp. 107–109.
  8. PJM 2018, pp. 110–112.
  9. PJM 2018, pp. 113–115.
  10. PJM 2018, pp. 116–118.
  11. Introduction to Black Start Archived 2006-05-21 at the Wayback Machine (National Grid plc) Covers technical and commercial background.
  12. See PJM Tariff: Schedule 6A of the PJM Tariff, available online at: http://www.pjm.com/documents/downloads/agreements/tariff.pdf Archived 2008-12-09 at the Wayback Machine and Blackstart Business Rules, available online at: http://www.ieso.ca/Documents/consult/se16/se16_DACP-SWG-20060216-pjm-blackstart.pdf Archived 2014-12-16 at the Wayback Machine
  13. See the NYISO Accounting and Billing Manual, 2006, available online at: http://www.nyiso.com/public/webdocs/documents/manuals/administrative/acctbillmnl.pdf Archived 2012-02-17 at the Wayback Machine NYISO Ancillary Services Manual 2006, available at "NYISO (Documents - Manuals - Operations)". Archived from the original on 2008-09-12. Retrieved 2008-12-24. NYISO Tariff (2006) at Rate Schedule 5, starting page 91, Revised Sheet 311, and Rate Schedule 6, starting at Revised Sheet No. 269, available online at "Archived copy" (PDF). Archived from the original (PDF) on 2008-10-12. Retrieved 2008-12-24.{{cite web}}: CS1 maint: archived copy as title (link)
  14. See ISO-NE "Order Accepting Application" Docket No. ER03-291, Federal Energy Regulatory Commission, Issued Feb. 14 2003, available online at http://www.iso-ne.com/committees/comm_wkgrps/trans_comm/tariff_comm/mtrls/2006/may162006/index.html ISO-NE Open Access Transmission Tariff 2006 at p. 311, available online at "ISO New England - Open Access Transmission Tariff (OATT)". Archived from the original on 2008-10-25. Retrieved 2008-12-24. ISO-NE A3 Black Start Working Group Memo to the NEPOOL Transmission Committee, May 9, 2006 available online at http://www.iso-ne.com/committees/comm_wkgrps/trans_comm/tariff_comm/mtrls/2006/may162006/index.html
  15. See ERCOT Protocols Section 6, 2006 available online at: "ERCOT - Current Protocols". Archived from the original on 2008-11-22. Retrieved 2008-12-24. ERCOT's bidding form is available online at: http://www.ercot.com/mktrules/protocols/current/22-%28A%29BlackStart-050105.doc
  16. Electricity Commission of New Zealand (2005-11-01). "Electricity Governance Rules, Schedule C5 - Procurement Plan" (PDF). pp. 180–182. Archived from the original (PDF) on 2006-10-07. Retrieved 2008-12-24.
  17. See http://www.aeso.ca/files/Nov05_BlackstartPP_v1.pdf Archived 2009-03-18 at the Wayback Machine
  18. See "Ancillary Services". Archived from the original on 2008-12-28. Retrieved 2008-12-24.
  19. Hales, Roy L. (August 15, 2017). "First Black Start On Germany's Grid". CleanTechnica.
  20. Fox, Brendan et al; Wind Power Integration - Connection and System Operational Aspects, Institution of Engineering and Technology, 2007 ISBN   978-0-86341-449-7 page 245
  21. George G. Karady, Keith E. Holbert, Electrical Energy Conversion and Transport: An Interactive Computer-Based Approach, John Wiley & Sons, 2013, ISBN   1118498038 page 9-57
  22. Reid, Scott (3 November 2020). "ScottishPower in 'pioneering world first' after wind farm black-out boost". www.scotsman.com. The Scotsman. Archived from the original on 5 November 2020.
  23. "Innovation". Scottish Power Renewables. 3 November 2020. Archived from the original on 3 November 2020.
  24. Beaty, H. Wayne; Fink, Donald G. (ed) Standard Handbook for Electrical Engineers (15th Edition), McGraw-Hill 2007 ISBN   978-0-07-144146-9 page 15-22

Sources

Further reading