The Doncaster railway line was a long-proposed suburban railway in the eastern suburbs of Melbourne, Victoria, Australia, that was anticipated to be built by the late 2020s, as a branch, along with the Hurstbridge line, of the planned future Clifton Hill Loop Line, as part of the 2013 PTV Network Development Plan. [1]
The Doncaster line would have primarily served the suburbs of Bulleen, Balwyn North, Kew, Templestowe and Doncaster, running along the median strip of the Eastern Freeway for most of its length.
First proposed in 1890, detailed planning commenced in 1969, and by 1972 the route was decided upon. Despite rising costs, the state governments of the period continued to make assurances that the line would be built. Property acquisition for part of the route was completed in 1975, and construction of a cutting at the city end commenced in 1974, only to be filled in two years later. [2] By 1982 plans to build the line were shelved by the state government, and by 1984 land for the line once it left the freeway was sold by the Cain Labor government. [2] In 1991 an independent report investigated constructing the line, recommending against it due to the high cost. [3] However several other reports released since the 1970s detail the essential requirement for heavy rail mass transit in the Doncaster corridor.
The Doncaster rail line plan is almost identical to the Yanchep line, completed in 1992, and the Mandurah line, completed in 2007, both in Perth, a city with less than half the population of Melbourne. The Mandurah line runs along the centre median of the Kwinana Freeway and through various tunnels. It is almost double the length of the proposed Doncaster line and cost 1.6 billion; trains are able to travel at up to 130 km/h.
In 2017, as part of the proposed North East Link road project, the median of the Eastern Freeway is set to be removed as part of an upgrade, with the addition of a new busway alongside the freeway. As a result, a rail line to Doncaster along the Eastern Freeway is unlikely to ever be built, barring a future conversion of the busway. However a train service through Doncaster is still proposed as part of the northern section of the Suburban Rail Loop.
One of the earliest proposals for a railway to Doncaster was in 1890, and involved an extension of the Kew branch line in a tunnel under the High Street hill, then across the route of Outer Circle line to a terminus at Warrandyte, with a branch line running to Templestowe. [4] In 1928 the Railways Standing Committee of the Victorian Parliament recommended a plan which also involved an extension of the Kew branch line, this time to terminate at Doncaster itself. [5] That proposal was included in the Metropolitan Town Planning Commission's 1929 plan for Melbourne, together with the Glen Waverley railway line, which was subsequently constructed. [6]
Concrete moves towards building the line were made in 1969, when The Age announced that the Victorian Railways had started detailed planning for a line which would run along the median of the Eastern Freeway and then on to Doncaster. [7] The line featured in the 1969 Melbourne Transportation Plan, but no timeline for construction was set, whereas the building of the freeway was to start in the following year.
In December 1971 the Eastern Railway Construction Act 1971 was passed by the state parliament, [8] setting the route as along the Eastern Freeway to Thompsons Road, then through Templestowe to Blackburn Road, Doncaster, involving the demolition of 30 houses. However, this route was not without opposition, as in 1972 The Herald reported that the outer section of the line would be investigated by the Parliamentary Public Works Committee. [7] The City of Box Hill rejected a plan put forward by the City of Doncaster & Templestowe as it would cut into open space along Koonung Creek, and Doncaster residents objected to a route running through the Eastern Golf Course to Blackburn Road. In December 1972 the parliamentary report was delivered and recommended the original route to be constructed as opposed to the 6 alternatives, and criticised the government for allowing development on the proposed routes. [7] The outer section of the line was estimated to be $23.5 million, the total cost of the line being reported as $41 million. A terminus-to-city travel time of 20–25 minutes was expected. [7]
The route decided upon was reported in The Age on 23 February 1972, but no completion date was mentioned: [7]
This plan is what the later included in the 1979 (Edition 12) Melway street directory, albeit with additional short lengths of tunnel at various places along the outer section of the route. It remained in the 1982 (Edition 14) Melway'. [9]
In May 1973 the state Liberal Party pledged to build the line if elected, but only to Bulleen. [7] They were returned to power at the state election. By December the same year the Parliamentary Public Works Committee had begun to re-examine the outer section of the line, considering three routes. The first costing $24 million would terminate at Bulleen, the second continued with a branch to Doncaster Road and cost $28 million, and the third was the original route but now costed at $63 million. [7] By March 1974 the cost of the full line was reported by The Age to have increased to $73 million, and that none of the proposed routes could be considered on economic grounds, and a busway would be a better investment. [7]
Despite doubts on the viability of the project, in July 1975 it was reported in The Sun that the Victorian Railways had purchased 18 properties for the railway. [2] It was also reported in The Age that the government would still complete the railway, even though government sources put the cost up to $120 million, up from $74 million the year before. [2] The proposed commencement date was after the completion of the underground City Loop in 1980.
Construction work on a cutting at the Victoria Park end of the line commenced in 1974 to allow the line to access the freeway median strip, but ceased in August 1975 due to economic difficulties faced by the contractor. [2] By October 1976 the Herald reported that the '$600,000 cutting' had been filled in with excavated earth from elsewhere, the reason given by officials was that it needed to be filled so the freeway could be completed. The cost to rebuild the tunnel was estimated by the railways and Country Roads Board at $1.5 million. [2] The final nail in the coffin was a statement by Liberal shadow transport minister Rob Maclellan in August 1984, who said that the Cain Labor Government had sold the land set aside for the railway beyond the Eastern Freeway to Doncaster. [4]
In July 1991 a report on transport in the Eastern Freeway corridor was presented to the Victorian transport minister Peter Spyker. Authored by Professor E.W. Russell, three options were examined in the report: [10]
The longest of the plans involved 6 kilometres of tunnel, and seven stations, four of them underground. The report found that a heavy rail line would be "desirable but too expensive to consider unless major economies in tunnelling and station construction costs can be made". [3] Public Transport Corporation estimates of the same period costed the two rail options at $376 million and $550 million respectively. [3]
Despite the line being a recurring theme among public transport advocates and political hopefuls, today there is no firm commitment to build the line. The cost to complete the line today has been estimated at $1 billion, [11] with transport in the region provided by private motor vehicles on the Eastern Freeway, and bus routes which operate along dedicated lanes from the Doncaster Park and Ride. [12]
In 2003 the Northern Central City Corridor Strategy provided comparative costings for heavy rail, light rail and high quality bus services. [13]
During the 2006 state election, the Victorian Liberal Party had done their own costing of the rail line and promised to extend the number 48 tram to Doncaster Hill, claiming that constructing the heavy rail line would cost around $1 billion and was deemed too expensive an option in the short term at least. [14]
Following the state elections in 2006, public pressure mounted and local councils began to fully support the construction of the line, holding regular meetings, discussions and forums.
March 2008, Melbourne Transport Forum, a petition of 7,000 signatures for the Doncaster rail line was delivered by councillors to Minister for Transport Lynne Kosky.
The issue also spread into social websites too with numerous unofficial online groups and petitions being made [15]
Mid-2008, Australian Greens Victoria released a transport discussion paper, The People Plan, [16] which includes the Doncaster rail line.
Late 2008, at a forum investigating the Doncaster rail line, which involved the Yarra, Melbourne and Manningham city councils, it was noted that 41% of Manningham residents are classified as low-income earners (despite the eastern suburb affluence stereotype), this is higher than the city average. The discrepancy is suspected to be caused by the increased reliance on private automobiles to meet day to day transport requirements residents face due to the lack of alternative methods of transportation such as Tram-Trains. At this forum, Peter Newman noted the similarities between the Doncaster line and the Mandurah line and suggested that it was the only viable option for both the short and long term transportation needs of the area. Other recommendations included the creation of transport corridors to aid in the transition of the existing urban environment towards Transit oriented development.[ citation needed ]
In December 2008, in response to massive patronage increases on Melbourne's public transport system and increased road infrastructure problems, the State Labor Government released a transport plan which failed to deal with the construction of the Doncaster line. The proposal investigated the construction of a freeway through Greensborough, into Heidelberg and through the Yarra Flats to connect with the Eastern Freeway at a cost of $6 billion. The proposal is six times the cost of the Doncaster rail line and relies on the continued use of private automobiles.
Also in December 2008, residents in the Mullum Mullum ward in Manningham for the first time elected a former Green party candidate David Ellis, who has been campaigning against the construction of the proposed freeway through Manningham.
Mid 2009: As part of the development of the Victorian Transport Plan, the Labor government has pledged to create a Doncaster Area Rapid Transport (DART) system. However, unlike its DART and BART cousins in Dublin and San Francisco, this scheme is merely an increase in bus services in the Manningham area. Further online support from the community resulted, with a new, unofficial petition and information website. [17]
Leading up to the 2010 election, which they subsequently won, the Victorian Liberal Party promised to commit $6.5m to complete another study to develop a route for building the railway line to Doncaster. Money was allocated for the study in the 2011 Budget. [18] No funding source was nominated for the actual building of the line. [19]
In 2017, as part of the proposed North East Link road project, the median of the Eastern Freeway is set to be removed as part of an upgrade, with the addition of a new busway alongside the freeway. As a result, a rail line to Doncaster along the Eastern Freeway is unlikely to ever be built, unless a busway is converted in the future. However an orbital train service through Doncaster is still proposed as part of the northern section of the Suburban Rail Loop.
The 2012 Doncaster Rail Study decided upon three key routes in the first phase of its study:
On the map below, the Rapid Transit theme is represented in blue, Local Access in green and the Orbital Network option in red. Orange nodes represent potential new stations and yellow lines are possible future extensions.
At the 2006 Victoria state election, the Labor Government costed the construction of the Doncaster rail line at around $1 billion. Other costings have been as high as $3 billion. In 2008, the Australian Greens Victoria released a transport discussion paper, The People Plan, which costed the construction of the line at $450 million. The Age newspaper quoted a 2012 report by transport experts from various Australian universities that suggested the line could be built for $840 million, being funded by the increase in property prices of the surrounding areas (although the report has not been made publicly available for review). [20]
The Doncaster Rail Study Phase One Report given to the Victorian Government in February 2014 estimated the cost of a line from Clifton Hill to the Doncaster Park and Ride at between $3 - $5 billion with and extra $1 billion to extend the line to the Doncaster Activity Centre. However the study found there was insufficient capacity between Clifton Hill and the city for trains from the new line so an extra $4 - $6 billion would be required to run the South Morang line from in a new tunnel to the city. [21] [22]
In 2012, the corridor from Clifton Hill to the city has a capacity of 22 trains per hour, with 17 trains per hour in the peak running, but it is predicted by 2021 the capacity can only be upgraded to 26 trains per hour and it is presumed 24 trains per hour will be used on the South Morang and Hurstbridge lines due to patronage increases and suburban growth, leaving only 2 trains per hour for Doncaster trains. [23]
The Public Transport Users Association disputes this, arguing there is capacity for 6 Doncaster trains per hour, along with 11 Hurstbridge line and 7 South Morang (now Mernda) line trains along the Clifton Hill to city section of the track, with a capacity of 24 trains per hour (signalled for trains every 2 minutes and using 80% of this absolute maximum), and high capacity signalling allowing for up to 30 trains per hour. They also argue that peak time patronage is close to saturation, with more growth off peak [24]
Average weekday patronage is predicted to be 56,000 boardings by 2031 with 98% of passengers coming from existing public transport, from sources such as the DART busses (Doncaster Area Rapid Transit) and the Ringwood line (shared section of the Belgrave and Lilydale lines). [21] [22]
The City of Manningham is a local government area in Victoria, Australia in the north-eastern suburbs of Melbourne and is divided into 12 suburbs, with the largest being Doncaster and Doncaster East. It comprises an area of 113 square kilometres and had a population of 125,508 in June 2018.
EastLink is a tolled section of the M3 freeway linking a large area through the eastern and south-eastern suburbs of Melbourne, Australia.
Bulleen is an eastern suburb in Melbourne, Australia, 13 km north-east of the Melbourne central business district, located within the City of Manningham local government area. Bulleen recorded a population of 11,219 at the 2021 census.
Doncaster is a suburb of Melbourne, Victoria, Australia, 18 km north-east of Melbourne's Central Business District, located within the City of Manningham local government area. Doncaster recorded a population of 25,020 at the 2021 census.
Templestowe is a suburb of Melbourne, Victoria, Australia, 16 km north-east of Melbourne's Central Business District, located within the City of Manningham local government area. Templestowe recorded a population of 16,966 at the 2021 census.
Proposals for expansion of the Melbourne rail network are commonly presented by political parties, government agencies, industry organisations and public transport advocacy groups. The extensions proposed take a variety of forms: electrification of existing routes to incorporate them into the suburban rail system; reconstruction of former passenger rail lines along pre-existing easements; entirely new routes intended to serve new areas with heavy rail or provide alternative routes in congested areas; or track amplification along existing routes to provide segregation of services. Other proposals are for the construction of new or relocated stations on existing lines, to provide improved access to public transport services.
The Eastern Freeway is an urban freeway in eastern Melbourne, the state capital of Victoria, Australia. It is one of the most important freeways in terms of commuting to the city, connecting Alexandra Parade and Hoddle Street in the inner suburbs, with EastLink tollway farther east. It consists of between three and six lanes in each direction, also an inbound transit lane reserved for vehicles with two or more occupants during peak hours.
Transport in Melbourne, the state capital of Victoria, Australia, consists of several interlinking modes. Melbourne is a hub for intercity, intracity and regional travel. Road-based transport accounts for most trips across many parts of the city, facilitated by Australia's largest freeway network. Public transport, including the world's largest tram network, trains and buses, also forms a key part of the transport system. Other dominant modes include walking, cycling and commercial-passenger vehicle services such as taxis.
Westfield Doncaster is a shopping centre 50% owned by Scentre Group, 25% owned by ISPT, and 25% owned by Asia Property Fund located in Doncaster, a suburb of Melbourne, Victoria, Australia. As of July 2014, the Westfield Group became two companies Scentre Group and Westfield Corporation. The Westfield Group portion is now owned by Scentre Group. It is located on the corner of Williamsons Road and Doncaster Road in the Doncaster Hill precinct, an ongoing planning initiative by the local Manningham council. It is located 20 minutes east of the CBD and is one of the biggest shopping centres in Victoria.
State (Bell/Springvale) Highway, also known as Bell Street/Springvale Road State Highway, is the longest self-contained urban highway in Melbourne, Australia, linking CityLink and Mornington Peninsula Freeway through Melbourne's north-eastern suburbs. These names are not widely known to most drivers, as the entire allocation is still best known as by the names of its constituent parts : Bell Street, Banksia Street, Manningham Road, Williamsons Road, Doncaster Road, Mitcham Road and Springvale Road. This article will deal with the entire length of the corridor for sake of completeness.
The East West Link is a proposed 18-kilometre tollway in Melbourne, Australia, to connect the Eastern Freeway at Clifton Hill with the Western Ring Road at Sunshine West. The Napthine Coalition Government signed a $5.3 billion contract with the East West Connect consortium in September 2014, just prior to the November 2014 state election, to begin construction on the eastern tunnel segment of the project. It became one of the central issues in the election, and a subsequent change in government led to the project's cancellation at a cost of $1.1 billion. The problem of poor "connectivity between Melbourne's Eastern Freeway and CityLink" has since been included in Infrastructure Australia's list of Australia's 32 "highest priority" infrastructure needs and remains part of long-term state road planning.
The 1969 Melbourne Transportation Plan was a road and rail transport plan for Melbourne, the state capital of Victoria, Australia, instituted by Henry Bolte's state government. Most prominently, the plan recommended the provision of an extensive freeway network, much of which has since been built.
The North East Link is an under construction 10–kilometre tolled highway scheme in Melbourne, Australia. It will connect the Metropolitan Ring Road at Greensborough with the Eastern Freeway at Bulleen, which will be upgraded from Hoddle Street to Springvale Road at Nunawading.
The Eddington Transport Report was a major transport study undertaken in Victoria, Australia, by infrastructure consultant Sir Rod Eddington to propose improvements to transport links between the eastern and western suburbs of Melbourne. The report, titled "Investing in Transport–East West Link Needs Assessment", was commissioned in 2006 by the Government of Victoria following the model of the Eddington Transport Study in the United Kingdom and was released in April 2008. Eddington's report recommended new road and rail tunnels, further rail network electrification and improved cycle and bus routes in a bid to reduce congestion. Some of the report's recommendations were implemented by the Brumby Labor government, but many others remained unfunded.
Numerous proposals have been made for improvements to the Melbourne tram network, the largest such network in the world. Nearly all of these have been for track extensions of existing lines to connect with nearby railway station or to service new areas and suburbs.
Melbourne Airport Rail, also known as SRL Airport, is a proposed heavy rail project, connecting the Melbourne CBD to Melbourne Airport at Tullamarine. The rail link will run through the under-construction Metro Tunnel, running 27 km (16.8 mi) from the airport to Town Hall station in the city centre with 12 km (7.5 mi) of new track between the airport and Sunshine station. The link will be a new branch of the Melbourne Metro rail network and run High-Capacity Metro Trains at a 10-minute frequency. The project is being delivered by the Victorian state government agency Rail Projects Victoria.
The Eastern Busway is a bus rapid transit line under construction in the eastern suburbs of Melbourne, Australia. It will operate alongside the Eastern Freeway, from Hoddle Street in Abbotsford to Doncaster Road in Doncaster. As a part of the North East Link project and Eastern Freeway upgrade, the entire busway is expected to commence construction in 2024 and be completed by 2028.
Doncaster Park and Ride is a park and ride bus station and future busway station located in Melbourne, Australia. It serves the suburb of Doncaster and situates next to the Eastern Freeway, and opened in January 2003. On some official sources and signage of the station, the "and" in its name is replaced by a "+" symbol, making it Doncaster Park + Ride.
Bulleen Park and Ride is a park and ride bus station and future busway station located in Melbourne, Australia serving the suburb of Bulleen and situated next to the Eastern Freeway. It was opened on 30 April 2023 by the Victorian government as the first piece of public infrastructure delivered by the North East Link project.