Hunters Point Power Plant | |
---|---|
Country | United States |
Location | 1000 Evans Ave San Francisco, California |
Coordinates | 37°44′15″N122°22′35″W / 37.7374°N 122.3763°W |
Status | Decommissioned |
Construction began | September 1928 |
Commission date | December 3, 1929 |
Decommission date | May 15, 2006 |
Owner(s) | Pacific Gas & Electric (PG&E) |
Operator(s) | PG&E |
Site area | 38 acres (15 ha) |
Cooling source | once-through (San Francisco Bay) |
Power generation | |
Units decommissioned | 4 |
Nameplate capacity | 450 MW |
The Hunters Point Power Plant (HPPP) was a fossil fuel-fired power plant in the India Basin neighborhood of the Bayview-Hunters Point area covering southeastern San Francisco, California, operated by Pacific Gas and Electric Company (PG&E) from 1929 to 2006. After HPPP shut down, the last electric power plant in San Francisco was the Potrero Generating Station, which subsequently shut down in 2011.
The site which would be occupied by the Hunters Point Power Plant was first used to build ships and barges in the early 1900s; [1] it is bounded approximately by Jennings (to the northwest), Pier 96 (to the northeast), Evans (on the southwest), and San Francisco Bay / India Basin (on the southeast), although there were numerous fuel storage tanks near the intersection of Jennings and Evans, outside these nominal site boundaries. [2] : Fig. 3-3
The first unit used a steam turbine drawing from a fuel oil-fired boiler; it was built in 1928–29 by the Great Western Power Company. Great Western Power advertised a construction contract in September 1928 for US$150,000(equivalent to $2,660,000 in 2023) to build the foundations for an electric generating plant "between Evans, Jennings and Burke avenues, India and Hawes streets". [3] By December, a "new building near Hunter's [ sic ] Point" was being built for Great Western Power, as mentioned in a news article, [4] the contract for the building was advertised at US$630,000(equivalent to $11,180,000 in 2023) in March 1929. [5] The total cost of the San Francisco Bay Steam Plant, scheduled for completion in summer 1929, was US$3,500,000(equivalent to $62,100,000 in 2023); as completed, the plant had a capacity of 35 MW electric power and plans were being prepared to expand generation to 170 MW. [6] PG&E purchased the plant from Great Western Power on June 1, 1929. [2] : 4–1
Units 2 and 3 were added in 1948/49 along with three aboveground fuel storage tanks, and some additional land was reclaimed from San Francisco Bay in the southeast part of the site. Unit 4 was added in 1958, along with three more aboveground fuel tanks. A breakwater was added to separate the cooling water intake and outfall in 1968, and a dike was completed between the breakwater and Pier 96 in 1975, completing an enclosed cooling water intake lagoon. Tanks 8 and 9 were built in 1975 and 1977, respectively; in between, a new Unit 1, using two diesel-fired gas turbines for peaking operations, was added in 1976, replacing the original (1929) Unit 1, which had been decommissioned in the early 1970s. [1]
It was one of the oldest and dirtiest oil-fired power plants [7] in the state and was a major source of pollution; studies showed that neighborhood residents were more than twice as likely to suffer from asthma, congestive heart failure, and certain cancers. [8] In the 1990s, the state began studying Hunters Point as a potential site for a new power plant; the San Francisco Board of Supervisors voted to block development of the new plant in June 1996, which Mayor Willie Brown hailed, saying "the people of Bayview–Hunters Point have been dumped on enough." [9]
Residents and community activists next pushed to have HPPP shut down. [10] California utilities were requested to voluntarily divest at least 50% of their fossil fuel-fired generating assets as that state began deregulation of its electric market in 1996, and HPPP was one of the first four plants that PG&E intended to sell, along with Morro Bay, Moss Landing, and Oakland. [11] However, HPPP was dropped from the list when the auction began in September 1997. [12] Because San Francisco is at the tip of the San Francisco Peninsula, its grid was designed to be isolated from the rest of the PG&E system by opening breakers at a substation in Daly City; PG&E argued that the demand for San Francisco could not be met by transmission alone so generation was still required within the "electrical island" to ensure system reliability. [13]
PG&E announced its intent to sell both Hunters Point and Potrero in June 1997, [14] as part of a second auction of fossil-fired and geothermal assets to start in March 1998, also including Contra Costa, Pittsburg, and The Geysers. [15] The City of San Francisco began negotiations with PG&E to purchase HPPP and Potrero, forming a partnership with two private companies; PG&E stated it intended to auction the sites to the highest bidder instead, and the City then threatened to begin eminent domain proceedings on Hunters Point. [16] [17] The California Public Utilities Commission ruled an environmental impact report would be required before PG&E could accept bids, shutting down the planned auction. [18] In July 1998, the City of San Francisco entered an agreement with PG&E to shut down HPPP "as soon as the facility is no longer needed to sustain electric reliability in San Francisco and the surrounding area and the FERC authorizes PG&E to terminate the Reliability Must Run agreement for the facility". [19] In return, the City agreed to not interfere with the sale of Potrero; the uncertainty caused by San Francisco's negotiations had been causing some prospective buyers to hold or delay their bids. [17]
Activists continued to hold protests at HPPP [20] until on May 15, 2006, PG&E permanently shut down the plant; the shutdown had been delayed pending a reliable source of replacement power, which had required upgrades to transmission lines along the Peninsula (Jefferson-Martin Transmission Project) [21] and under San Francisco Bay (Trans Bay Cable). [22] [23] [24] It was demolished in 2008 and cleanup of the site was nearing completion in 2014. [25] PG&E has retained the former switchyard (now used as a substation) along the north side of Evans, and the parcel known as Area I, north of the intersection of Evans and Jennings, which previously was the site of Tanks 1 and 2. [26] Developers were slow to propose new uses for the site. [27] By 2017, the shoreline path around the former power plant site had been incorporated into the San Francisco Bay Trail. [28] The site is used currently as a pop-up community space hosting neighborhood events. [29]
Unit | Capacity (MWe) | Start | Fuel | |
---|---|---|---|---|
1 | 52 | 1976 | diesel (2× aeroderivative combustion turbine) | |
2 | (Main) | 110 | 1948/49 | natural gas or fuel oil (steam turbine) |
(House) | 7.5 | |||
3 | (Main) | 110 | ||
(House) | 7.5 | |||
4 | 170 | 1958 |
In 1996, the plant had two diesel-fired aeroderivative combustion turbines (collectively known as Unit 1) and three steam turbine-generators (Units 2, 3, and 4) using steam from five boilers (Boilers 3, 4, 5, 6, and 7) that burned natural gas, but which historically had operated on no. 6 fuel oil. [2] : 3–1
The three steam turbines used approximately 400×10 6 US gal/d (1.5×10 6 m3/d) of water drawn from the lagoon in a once-through cooling scheme; cooling water was chlorinated with sodium hypochlorite, circulated through the condenser, then de-chlorinated with sodium bisulfate before being discharged into India Basin. [2] : 3–1 A breakwater was built in 1969 to prevent the heated discharge water from mixing with the lagoon intake; the lagoon was completely enclosed by 1975, when a dike was built between the site and Pier 96. [2] : 4–1
The site was expanded through extensive filling of the Bay north of Evans and east of Jennings between 1947 and 1958, adding approximately 80 to 100 acres (32 to 40 ha) of land. [2] : 4–1
Tank No. | Vol | Secondary containment |
---|---|---|
1 | 1.7×10 6 US gal 6.4 Ml | 2.3×10 6 US gal 8.7 Ml |
2 | 1.7×10 6 US gal 6.4 Ml | 2.3×10 6 US gal 8.7 Ml |
3 | 1.5×10 6 US gal 5.7 Ml | 2.2×10 6 US gal 8.3 Ml |
4 | 1.7×10 6 US gal 6.4 Ml | 2.3×10 6 US gal 8.7 Ml |
5 | 1.9×10 6 US gal 7.2 Ml | 2.3×10 6 US gal 8.7 Ml |
6 | 1.8×10 6 US gal 6.8 Ml | 2.1×10 6 US gal 7.9 Ml |
7 | 1.8×10 6 US gal 6.8 Ml | 2.2×10 6 US gal 8.3 Ml |
8 | 10.7×10 6 US gal 41 Ml | 12×10 6 US gal 45 Ml |
9 | 1.2×10 6 US gal 4.5 Ml | 1.3×10 6 US gal 4.9 Ml |
Aboveground tanks were used to store fuel oil on-site in three closely-spaced sites near the intersection of Evans and Jennings: (1) containing Tanks 1 and 2, in the block north of the intersection; (2) containing Tanks 3, 4, and 8, in the block east of the intersection; and (3) 5, 6, 7, and 9 south of Evans. [2] : 3–2
Tank 3 was identified in aerial photographs as early as 1935 and may have been part of the original construction. [2] : 4–5 Tanks 1, 2, and 4 were built in 1948 and 1949, when Units 2 and 3 were added. [2] : 4–1 Tanks 5, 6, and 7 were added in 1958 with Unit 4. [2] : 4–1 Tank 8 was identified in a 1975 aerial photograph, and Tank 9 was identified in a 1977 aerial photograph. [2] : 4–2
Tank 3 also was used to store dielectric oil waste, possibly containing PCBs, from HPPP and other PG&E sites in the 1970s; overflow from Tank 3 was sent to Tank 8 and potentially could have been burned during power plant operation. [2] : 5–5 Prior to 1986, fuel was shipped to Pier 90 by oil tankers and transported to the site through an underground steel pipeline along Cargo Way. [2] : 5–3 By 1996, the only tank still being used for (diesel) fuel storage was Tank 9; [2] : 5–11 Tanks 1-8, previously used for fuel oil storage, had been empty since 1994. [2] : 5–2
The original Unit 1 was commissioned on December 3, 1929 as Station P, with a generating capacity of 46 megawatts (62×10 3 hp); [30] the two boilers which served the original Unit 1 were abandoned in place in 1972. [2] : 4–2
Units 2 and 3 drew from four boilers (designated S3 through S6) with a collective thermal power of 2,680 million British thermal units per hour (790 MW); [31] their collective electric output was 235 MW (315×10 3 hp), including two smaller turbines designated to serve "house" loads associated with power plant operation. [2] : 3–2 PG&E first announced plans to expand Station P in 1946; although plans for expansion had dated back to 1941, they were delayed by wartime material shortages. [32] Units 2 and 3 were constructed in 1948 and 1949; [2] : 4–1 when they were completed and dedicated on February 8, 1949, they were collectively the largest power plant owned by PG&E. [30] Units 2 and 3 and were shut down permanently in 2001. [31] : 5
PG&E filed a permit application to construct what would become Unit 4 in 1955. [33] Unit 4 drew steam from a single large boiler (designated S7) with a thermal power of 1,720 million British thermal units per hour (500 MW ) and generated 170 MW electric output. [31] : 5, 10 S7 was permitted to burn natural gas or fuel oil, but the oil-burning capability was deleted in the 2004 permit application, since continued oil burning would have required the boiler to be retrofitted with selective catalytic reduction equipment to meet tightening NOx emissions requirements beyond 2005. Unit 4 began operation in 1958. [19] : 3–3
PG&E was granted permits to build four peaking power plant units in San Francisco in 1975; [34] one was built at HPPP and the other three were built at Potrero. [19] : 3–3 HPPP Unit 1 was reused as the collective designation for the two diesel-fired peaking turbines (designated S1 and S2), each rated at 364 million British thermal units per hour (107 MW) thermal power [31] : 5, 10 and 26 MW electric. [19] [24] The redesignated Unit 1 began operation in 1976. [19] : 3–3
The Pacific Gas and Electric Company (PG&E) is an American investor-owned utility (IOU). The company is headquartered at 300 Lakeside Drive, in Oakland, California. PG&E provides natural gas and electricity to 5.2 million households in the northern two-thirds of California, from Bakersfield and northern Santa Barbara County, almost to the Oregon and Nevada state lines.
A thermal power station, also known as a thermal power plant, is a type of power station in which the heat energy generated from various fuel sources is converted to electrical energy. The combustion or nuclear reaction of the fuel source in a boiler or reactor generates heat, which is converted into mechanical energy using a thermodynamic power cycle, where a working fluid is heated and boiled under immense pressure in a large pressure vessel to produce high-pressure steam. This high pressure-steam is then directed to a turbine through a series of pipes, where the force of the steam rotates the turbine's blades. The rotating turbine, which is mechanically connected to an electric generator, turns the generator's rotor with conductive coils. A stationary magnetic field interacts with rotating coils to produce electricity in them via electromagnetic induction. Fuels such as natural gas or oil can also be burnt directly in gas turbines. These plants can be of the open cycle or the more efficient combined cycle type.
Inverkip power station was an oil-fired power station on the Inverclyde coast, Firth of Clyde, west coast of Scotland. It was closer to Wemyss Bay than Inverkip, and dominated the local area with its 236 m (774 ft) chimney, the third tallest chimney in the UK and Scotland's tallest free-standing structure. In common with other power stations in Scotland it lacked cooling towers; instead, sea water was used as a coolant. The station consisted of three generating units with a combined total rating of 2028 megawatts (MW).
The Moss Landing Power Plant is a natural gas powered electricity generation plant located in Moss Landing, California, United States, at the midpoint of Monterey Bay. Its large stacks are landmarks, visible throughout the Monterey Bay Area. The plant is owned and operated by Houston-based Dynegy and currently has a generation capacity of 1020 MW (net) from its two combined cycle generation units. It was once the largest power plant in the state of California, with a generation capacity of 2560 MW, before its two large supercritical steam units were retired in 2016.
The Bell Bay Power Station was a power station located in Bell Bay, on the Tamar River, Tasmania, Australia, adjacent to the Tamar Valley Power Station, with which it was often confused. It was commissioned between 1971 and 1974 as an oil fired thermal power station, and was converted to natural gas in 2003, after the commissioning of the Tasmanian Gas Pipeline, a submarine gas pipeline which transports natural gas from Longford, Victoria, under Bass Strait, to Bell Bay, Tasmania. As the power station's primary role was to provide system security in the event of drought for Tasmania's predominantly hydro-electric based generation system it only was rarely called on to operate, resulting in intervals of five to eight years between periods of significant use. After the commissioning of Basslink in 2006, the power station was decommissioned in 2009.
Orot Rabin is a power station located on the Mediterranean coast in Hadera, Israel which is owned and operated by the Israel Electric Corporation (IEC). As of 2022 it is Israel’s largest power station and contains six thermal generation units capable of producing a total of 2.59GW of electricity using coal as the primary fuel. In addition, under construction at the site are two single-shaft natural gas-powered combined-cycle units capable of generating 630 MW each. The older, unmodernised four of its total six coal-fuelled units will be closed by mid-2022 in order to eliminate this major source of air pollution in the country.
The Union Pacific GTELs were a series of gas turbine-electric locomotives built by Alco-GE and General Electric between 1952-1961 and operated by Union Pacific from 1952 to 1970.
Zaporizhzhia thermal power station is a large thermal power plant (DRES) in the purpose-built city of Enerhodar in Ukraine. It is the most powerful thermal power station in Ukraine, with an installed capacity of 2,850 MWe. Its primary fuel is coal. It can also fire natural gas and fuel oil, and has tank storage for these reserve fuels adjacent to the coal bunkers.
The Westinghouse Combustion Turbine Systems Division (CTSD), part of Westinghouse Electric Corporation's Westinghouse Power Generation group, was originally located, along with the Steam Turbine Division (STD), in a major industrial manufacturing complex, referred to as the South Philadelphia Works, in Lester, Pennsylvania near to the Philadelphia International Airport.
The Littlebrook Power Station were a series of four oil and coal-fired power stations situated on the south bank of the River Thames, next to the Queen Elizabeth 2 Bridge and the Dartford Tunnel in Dartford, Kent. The final power station, Littlebrook D, ceased operating in March 2015, and has now been demolished.
The New Plymouth Power Station (NPPS) was a 600 MW thermal power station at New Plymouth, New Zealand, that operated from 1974 to 2008. Located at Port Taranaki, it was dual fuelled on natural gas and fuel oil. Constructed at a time of major hydro and HV transmission developments, it was New Zealand's first big thermal power station planned for continuous baseload operation.
The Humboldt Bay Power Plant, Unit 3 was a 63 MWe nuclear boiling water reactor, owned by Pacific Gas and Electric Company that operated from August 1963 to July 1976 just south of Eureka, California.
The Gould Street Generating Station was a former 100 MW electric generating plant operated by Exelon that was located on Gould Street in south Baltimore, Maryland, USA. The plant was adjacent to an elevated section of freeway I-95 and was south of the Riverside neighborhood and west of the Locust Point neighborhood of Baltimore. The plant site, located on the shore of the Middle Branch of the Patapsco River, was used for the generation of electric power for over one hundred years before being shut down on June 1, 2019. The site was purchased by Greenspring Realty Partners, Inc. for $3.1 million in December 2019. Demolition began in October 2020. The original brick buildings, the large storage tanks behind them, and other minor structures on the southwest portion of the property were demolished as of March 2021, but as of April 2022 the larger steel building to the northeast on the property remains. A large portion of the property was acquired by Weller Development in July 2021 and the future of the remaining structure and the property is not known.
The Potrero Generating Station was a natural gas and diesel burning electricity generating station owned by Mirant and located on a 23-acre (9.3 ha) site in Potrero Point, San Francisco, California. The plant's primary power source was a 206 MW, natural gas burning steam turbine providing baseload power and referred to as "Unit 3". In addition, three 52 MW peaking power diesel generators provided additional power during times of highest consumption. Since the closure of the Hunters Point Power Plant in 2006, Potrero was the last remaining fossil fuel power plant within the confines of San Francisco, with capacity to provide approximately 1/3 of the city's peak electrical power needs.
The Tilbury power stations were two thermal power stations on the north bank of the River Thames at Tilbury in Essex. The 360 MW dual coal- and oil-fired Tilbury A Power Station operated from 1956 until 1981 when it was mothballed, prior to demolition in 1999. The 1,428 MW Tilbury B Power Station operated between 1968 and 2013 and was fueled by coal, as well as co-firing with oil and, from 2011, biomass. Tilbury B was demolished in 2016–19. Since 2013 three other power stations have been proposed or constructed in Tilbury.
The Riverside Generating Station is a 261 MW electric generating station operated by Exelon that is located at 4000 Broening Highway in Dundalk, Maryland. The station is on Sollers Point on the Patapsco River.
The Trans Bay Cable is a high-voltage direct current (HVDC) underwater transmission cable interconnection between San Francisco, California and Pittsburg, California. The 53 mi (85 km) cable under San Francisco Bay and through the Carquinez Strait can transmit 400 megawatts of power at a DC voltage of ±200 kV, enough to provide 40% of San Francisco's peak power needs.
The Huntington Beach Energy Project (HBEP), formerly AES Huntington Beach, is a natural gas-fired power station located in Huntington Beach, California.
Gateway Generating Station (GGS), formerly Contra Costa Unit 8 Power Project, is a combined-cycle, natural-gas-fired power station in Contra Costa County, California, which provides power to half a million customers in northern and central California. Gateway Generating Station is on the southern shore of the San Joaquin River, in Antioch, and is one of more than ten fossil-fuel power plants in Contra Costa County.
Potrero Point is an area in San Francisco, California, east of San Francisco's Potrero Hill neighborhood. Potrero Point was an early San Francisco industrial area. The Point started as small natural land feature that extends into Mission Bay of San Francisco Bay. The Point was enlarged by blasted and cuts on the nearby cliffs. The cut material was removed and used to fill two square miles into the San Francisco bay, making hundreds of acres of flat land. The first factories opened at Potrero Point in the 1860s. Early factories were powder magazine plant, the Pacific Rolling Mill Company and small shipyards. The large Union Iron Works and its shipyards were built at the site, stated in 1849 by Peter Donahue. To power the factories and neighborhood coal and gas-powered electricity works were built, later the site became Pacific Gas and Electric Company (PG&E).