R.E. Burger Power Station | |
---|---|
Country | United States |
Location | Mead Township, Belmont County, near Shadyside, Ohio |
Coordinates | 39°54′34″N80°45′37″W / 39.90944°N 80.76028°W |
Status | Decommissioned |
Commission date | Unit 1: 1944 Unit 2: 1947 Unit 3: 1950 Units 4–5: 1955 |
Decommission date | Units 1–2: 1995 Units 4–5: 2010 Unit 3: 2011 |
Owner | FirstEnergy |
Operator | FirstEnergy |
Thermal power station | |
Primary fuel | Coal |
Cooling source | Ohio River |
Power generation | |
Nameplate capacity | 568 MW |
R.E. Burger Power Station was a 568 megawatt (MW), coal power plant located south of Shadyside, Ohio in Belmont County, Ohio. The plant closed in 2011. It was operated by FirstEnergy.
R.E. Burger was constructed in the 1940s to meet industrial demand for power generation during World War II. [1] Unit 1 went into operation in 1944 and Unit 2 came online in 1947 at a cost of $5 million. [2] [3] [4] Both units had a capacity of 65 MW. [3] Unit 3, which went into operation in 1950 after two years of construction, had a generating capacity of 100 MW. [5] The unit cost $12 million to construct and was financed from the issuing of Ohio Edison stock by Lehman Brothers. [1] [5] Units 4 and 5 started generating electricity in 1955 and each had a generating capacity of 135 MW. The cost to construct both units totaled $43.2 million. [6] The plant is named after R.E. Burger, a former chairman of Ohio Public Service Company and later Ohio Edison. [5]
In 1991, R.E. Burger was an experimental site for clean coal technology by Ohio Edison with sponsorship from the United States Department of Energy. A SOx-NOx Rox Box (SNRB) developed by Babcock & Wilcox simultaneously removed sulfur dioxide (SO
2), nitrogen oxide (NOx), and particulates at the same time in a 5 MW unit. [7] Sorbent Technologies developed and demonstrated a jet-engine filter for pollution control at R.E. Burger in 1994. [8] In that same year, R.E. Burger incinerated refuse-derived fuel in Unit 2 as a test run to see if fuel costs and emissions could be reduced. [9] FirstEnergy assumed ownership of R.E. Burger in 1997 following a merger between Ohio Edison and Centerior Energy. [10] In 2004, an Electro-Catalytic Oxidation (ECO) scrubber, designed by Powerspan to reduce SO
2 and mercury emissions, was tested at R.E. Burger with a generating capacity of 50 MW. [11] FirstEnergy announced in 2007 to install ECO scrubbers to Units 4 and 5 with a planned start-up scheduled for 2011. [12] Between 2006 and 2010, R.E. Burger was a test site for the Midwest Regional Carbon Sequestration Partnership's (MRCSP) carbon sequestration project. The project tested the potential of capturing carbon dioxide (CO2) emissions and injecting it into geologic rock acting as a storage well. [13]
Ohio Edison shut down Units 1 and 2 in 1995 as the enforcement of the Clean Air Act's 1990 amendments meant that both units were in non-compliance and the cost to retrofit outweighed the benefits. [14] [15] FirstEnergy had plans in 2009 to convert R.E. Burger into a biomass plant to remain profitable in the face of cheaper natural gas prices and lower demand for electricity during the Great Recession. [16] [17] The costs to convert into a biomass plant was $130 million cheaper compared to installing industrial scrubbers to reduce pollution. Unfortunately, the economics to continue running R.E. Burger remained futile and FirstEnergy closed two units at the end of 2010. [17] The final unit, Unit 3, retired in 2011 due to stricter environmental rules. [2]
Demolition of R.E. Burger began in 2015 after four years of decommissioning. [2] Demolition was completed in July 2016 when the plant's 854 feet (260.3 m) smokestack was imploded using explosive charges. [18] Thailand-based chemical company PTT Global Chemical bought 168 acres of the former remediated R.E. Burger site from FirstEnergy for $13.8 million in 2017 to construct an ethane cracker plant. [19]
Drax power station is a large biomass power station in Drax, North Yorkshire, England. It has a 2.6 GW capacity for biomass and had a 1.29 GW capacity for coal that was retired in 2021. Its name comes from the nearby village of Drax. It is situated on the River Ouse between Selby and Goole. Its generating capacity of 3,906 megawatts (MW), which includes the shut down coal units, is the highest of any power station in the United Kingdom, providing about 6% of the United Kingdom's electricity supply.
A fossil fuel power station is a thermal power station which burns a fossil fuel, such as coal, oil, or natural gas, to produce electricity. Fossil fuel power stations have machinery to convert the heat energy of combustion into mechanical energy, which then operates an electrical generator. The prime mover may be a steam turbine, a gas turbine or, in small plants, a reciprocating gas engine. All plants use the energy extracted from the expansion of a hot gas, either steam or combustion gases. Although different energy conversion methods exist, all thermal power station conversion methods have their efficiency limited by the Carnot efficiency and therefore produce waste heat.
FirstEnergy Corp. is a privately owned electric utility headquartered in Akron, Ohio. It was established when Ohio Edison merged with Centerior Energy in 1997. Its subsidiaries and affiliates are involved in the distribution, transmission, and generation of electricity, as well as energy management and other energy-related services. Its ten electric utility operating companies comprise one of the United States' largest investor-owned utilities, based on serving 6 million customers within a 65,000-square-mile (170,000 km2) area of Ohio, Pennsylvania, West Virginia, Virginia, Maryland, New Jersey, and New York. Its generation subsidiaries control more than 16,000 megawatts of capacity, and its distribution lines span over 194,000 miles. In 2018, FirstEnergy ranked 219 on the Fortune 500 list of the largest public corporations in the United States by revenue.
Coal pollution mitigation, sometimes labeled as clean coal, is a series of systems and technologies that seek to mitigate health and environmental impact of burning coal for energy. Burning coal releases harmful substances that contribute to air pollution, acid rain, and greenhouse gas emissions. Mitigation includes precombustion approaches, such as cleaning coal, and post combustion approaches, include flue-gas desulfurization, selective catalytic reduction, electrostatic precipitators, and fly ash reduction. These measures aim to reduce coal's impact on human health and the environment.
Liddell Power Station is a decommissioned coal-fired thermal power station that had four 500 megawatts (670,000 hp) EE steam-driven turbine alternators, providing a combined electrical capacity of 2,000 megawatts (2,700,000 hp).
The William H. Zimmer Power Station, located near Moscow, Ohio, was a 1.35-gigawatt coal power plant. Planned by Cincinnati Gas and Electric (CG&E), with Columbus & Southern Ohio Electric and Dayton Power & Light (DP&L) as its partners, it was originally intended to be a nuclear power plant. Although once estimated to be 97% complete, poor construction and quality assurance (QA) led to the plant being converted to coal-fired generation. The plant began operations in 1991. Vistra Corp. acquired ownership in 2018 and operated the plant until its closure on May 31, 2022.
Kyger Creek Power Plant is a 1.08-gigawatt, 1,086 (MW) coal-fired power station located south of Cheshire, Ohio in Gallia County, Ohio. It is operated by the Ohio Valley Electric Corporation (OVEC).
The W. H. Sammis Power Plant was a 2.23-gigawatt coal power plant in Stratton, Jefferson County, Ohio. The plant was operated by Energy Harbor. It began operations in 1960.
Clifty Creek Power Plant is a 1,300-MW coal-fired power station located in Madison, Indiana. Clifty Creek is operated by the Indiana Kentucky Electric Corporation. It is named after Clifty Creek, which enters the Ohio River nearby.
Brunner Island Steam Electric Station is a coal-fired, alternatively natural gas-powered electrical generation facility in York County, Pennsylvania. It occupies most of the area of the eponymous island on Susquehanna River. The power plant has three major units, which came online in 1961, 1965, and 1969, with respective generating capacities of 334 MW, 390 MW, and 759 MW. In addition, three internal combustion generators were installed in 1967. Talen Energy will stop coal use at the plant in 2028.
The Lambton Generating Station was a coal-fuelled power plant located on the St. Clair River near Corunna, Ontario, delivering up to 950 MW of power to the grid. It is owned by Ontario Power Generation.
The Hugh L. Spurlock Generating Station is a 1.3-gigawatt coal power plant owned and operated by the East Kentucky Power Cooperative (EKPC) located west of Maysville, Kentucky. The plant began operations in 1977.
Killen Station was a 618 megawatt (MW) dual-fuel power generating facility located east of Wrightsville, Ohio in Adams County, Ohio. The power plant had two units: one coal-fired and one oil-fired. At the time of its closure, it was operated by AES Ohio Generation, a subsidiary of the AES Corporation. The plant began operations in 1982 and ceased generation on May 31, 2018.
J.M. Stuart Station was a 2.3-gigawatt coal power plant located east of Aberdeen, Ohio in Adams County, Ohio. The power plant had four units and was operated by AES Ohio Generation, a subsidiary of the AES Corporation. It began operations in 1970 and ceased on May 24, 2018.
Martin Lake Power Plant is a 2,250-megawatt coal power plant located southwest of Tatum, Texas, in Rusk County, Texas. The plant is owned by Luminant. It began operations in 1977. The plant is also served by the Luminant owned Martin Lake Line, shuttling coal from nearby as well as the Powder River Basin in Wyoming via BNSF.
Sandow Power Plant was a 1.1-gigawatt coal power plant located southwest of Rockdale, Texas in Milam County, Texas. It was operated by Luminant, a subsidiary of Vistra Corp. The plant closed in 2018.
Bruce Mansfield Power Plant was a 2.49-gigawatt, coal power plant located in Shippingport, Pennsylvania in Beaver County, Pennsylvania. The plant was operated by FirstEnergy. It began operations in 1976 and was shut down in November 2019.
Cardinal Power Plant is a 1.8-gigawatt coal power plant located south of Brilliant, Ohio, in Jefferson County, Ohio. The power plant has three units. Cardinal is co-owned with Unit 1 owned by American Electric Power's (AEP) subsidiary, AEP Generation Resources. Units 2–3 are owned by Buckeye Power, a utility cooperative. It began operations in 1967.
Picway Power Plant was a 220 megawatt (MW) coal power plant located west of Lockbourne in Pickaway County, Ohio. The plant generated electricity from 1926 until its closure in 2015. It was operated by American Electric Power (AEP).
Conesville Power Plant was a 2-gigwatt, coal power plant located east of Conesville, Ohio in Coshocton County, Ohio. Its units were co-owned at the time of its closing by American Electric Power (AEP) and AES Ohio Generation. All plant operations were handled by AEP. Conesville began operations in 1957 and ceased generation in April 2020.
{{cite news}}
: External link in |via=
(help){{cite news}}
: External link in |via=
(help){{cite news}}
: External link in |via=
(help){{cite news}}
: External link in |via=
(help){{cite news}}
: External link in |via=
(help){{cite news}}
: External link in |via=
(help){{cite news}}
: External link in |via=
(help)