Strait of Messina Bridge

Last updated

Proposed Strait of Messina Bridge

Ponte sullo stretto di Messina
Messina Bridge from Piale.jpg
An artist's impression of the planned bridge from the Calabrian coast
Coordinates 38°14′51″N15°38′21″E / 38.24750°N 15.63917°E / 38.24750; 15.63917
CarriesSix lanes and two emergency lanes. Two rails and two railway sidewalks.
Crosses Strait of Messina
Locale Messina and Villa San Giovanni
Characteristics
Design Suspension bridge
Total length3,666 metres (12,028 ft)
Height382.6 metres (1,255 ft) (pylons)
Longest span3,300 metres (10,800 ft)
Clearance below 76 metres (249 ft)
History
Designer Stretto di Messina
Construction start2025
Construction end2032 (projected)
Location
Strait of Messina Bridge

The Strait of Messina Bridge (Italian : Ponte sullo stretto di Messina) is a planned 3.6-kilometre suspension bridge across the Strait of Messina, connecting Torre Faro in Sicily with Villa San Giovanni on the Italian peninsula. [1]

Contents

The bridge has been controversial due to the impact of earthquakes, strong currents in the strait, concerns of disruption of bird migration routes, and the infiltration of mafia groups Cosa Nostra and 'Ndrangheta in area construction projects. [2]

While a bridge across the Strait of Messina had been proposed since ancient times, the first detailed plan was made in the 1990s for a suspension bridge. The project was cancelled in 2006 under prime minister Romano Prodi. [3] On 6 March 2009, as part of a massive new public works programme, prime minister Silvio Berlusconi's government announced that construction of the Messina Bridge would indeed go ahead, pledging €1.3 billion as a contribution to the total cost, estimated at €6.1 billion. [4] The project was cancelled again on 26 February 2013, by primeinister Mario Monti's government, due to budget constraints. [5] A decade later, the project was revived again with a decree by Giorgia Meloni's government, on 16 March 2023, [6] which received presidential approval on 31 March 2023. [7] [8]

If fully approved and built, it will be the longest suspension bridge in the world. The bridge would be part of the Berlin–Palermo railway axis (Line 1) of the Trans-European Transport Networks (TEN-T).

Geography

A 2002 NASA photo of the Strait of Messina. The bridge would connect north Messina with Villa San Giovanni. Stretto di messina satellite.jpg
A 2002 NASA photo of the Strait of Messina. The bridge would connect north Messina with Villa San Giovanni.

The Strait of Messina is a funnel-shaped arm of sea that connects the Ionian Sea in the south to the Tyrrhenian Sea to the north. The width of the strait varies from a maximum of approximately 16 km (9.9 miles) (between Capo d'Alì in Sicily and Punta Pellaro in Calabria) to a minimum of approximately 3 km (1.9 miles) between Capo Peloro in Sicily and Torre Cavallo in Calabria. [9] A similar distance separates Pezzo and Ganzirri; at that point, the strait is only 72 m (236 ft) deep, while in other places it can reach 200 m (660 ft) deep. It is also characterised by strong currents, and the region has significant seismicity.

History

The idea of a bridge crossing the strait is an old one. The Romans considered building a bridge joining Calabria and Sicily made of boats and barrels. Pliny the Elder, a philosopher and Roman military leader born in 23 AD, wrote of a plan to bridge the strait with a series of connecting boats. The idea was abandoned, as it was clear that more traffic plied the strait in a north-south than east-west direction, so any structure on water could not be permanent. [10]

Charlemagne considered joining the two sides with a series of bridges. This idea was revived by the Norman adventurer Robert Guiscard in the 11th century and by Roger II of Sicily in the 12th. In 1876, Giuseppe Zanardelli was convinced that the strait could be linked by either a bridge or a tunnel. In 1866, public works minister Stefano Jacini gave Alfredo Cottrau, an internationally recognised engineer, the task of drawing up plans for a bridge between Calabria and Sicily. Later, in 1870, Navone proposed building a tunnel based on Napoleon's idea of a tunnel under the English Channel. This tunnel was to start at Contesse and was to pass below Messina and Ganzirri at a depth of 150 m (490 ft), crossing the strait to Punta Pezzo and resurfacing at Torre Cavallo.

A geologic study of the strait was published in 1909 (historical Arch. Sicilian year XXXIV f.1,2), and in 1921, a study of an undersea tunnel was released to the Geographic Conference of Florence. A group of railway civil engineers studied the possibility of a suspension bridge, but nothing came of it. The idea was revived in 1953 by bridge builder David B. Steinman, with a plan to build a bridge that crossed the strait using two 220 m (720 ft) towers sunk in 120 m (390 ft) deep waters. The proposed 1,524 m (5,000 ft) span would have represented a world record, eclipsing the then-longest 1,275 m (4,183 ft) centre span of the Golden Gate Bridge and beating the 2,256 m (7,402 ft) Mackinac Straits Bridge (then in planning) with a total length of 2,988 m (9,803 ft). The proposed structure was to clear the sea by 50 m (160 ft) for navigation and have two decks—a lower deck carrying two rail lines, and 7 m (23 ft) above, a road deck 30 m (98 ft) wide. The main cables were designed with a diameter of 1 m (39 in). The construction of the bridge would have required 12,000 workers and cost hundreds of billions of lire.

Early planning stages

Development of detailed plans

Cross-sectional diagram of the Strait of Messina Bridge Ponte di messina.jpg
Cross-sectional diagram of the Strait of Messina Bridge

The 2006 plan called for a single-span suspension bridge with a central span of 3,300 m (10,800 ft). This would have made the span more than 60% longer than the 1915 Çanakkale Bridge in Turkey—currently the longest suspension bridge in the world, at 2,023 m (6,637 ft). [11]

Plans called for four traffic lanes (two driving lanes and one emergency lane in each direction), two railway tracks, and two pedestrian lanes. In order to provide a minimum vertical clearance for navigation of 65 m (213 ft), the height of the two towers was to be 382.6 m (1,255 ft). This would have been taller than the Millau Viaduct in France (currently the tallest bridge in the world, at 341 m (1,119 ft)). The bridge's suspension system would have relied on two pairs of steel cables, each with a diameter of 1.24 m (49 in) and a total length, between the anchor blocks, of 5,300 m (17,400 ft). [12]

The design included 20.3 km (12.6 miles) of road links and 19.8 km (12.3 miles) of railway links to the bridge. On the mainland, the bridge was to connect to the new stretch of the Salerno-Reggio Calabria motorway (A3) and to the planned Naples-Reggio Calabria high-speed rail line; on the Sicilian side, to the Messina-Catania (A18) and Messina-Palermo (A20) motorways as well as the new Messina railway station (to be built by Rete Ferroviaria Italiana). [13]

The bridge was planned to connect Reggio Calabria to Messina, the two cities that face each other on either side of the strait, in order to form a single metropolitan area. This ambitious urban project was called Area Metropolitana integrata dello Stretto ("integrated metropolitan area of the strait") or simply Città dello Stretto ("city of the strait"). Among the controversies surrounding the building of the bridge was strong opposition to the formation of the new city by various Sicilian nationalist groups. [13]

Among the engineers who participated in the project was Giorgio Diana, who mainly dealt with the aeroelastic aspect. [14]

Abandonment and revival

On 12 October 2006, the Italian Parliament voted 272 to 232 in favour of abandoning the plan due to the bridge's "doubtful usefulness and viability", as well as the inability of the already burdened Italian treasury to bear its share of the cost. Additionally, transport minister Alessandro Bianchi pointed out that the road and rail links leading to the location of the proposed bridge are not capable of supporting enough traffic to make the bridge profitable. Other reasons for abandoning the plan were earthquake risk and fears that the bridge would enrich the networks of organized crime in Italy, such as Cosa Nostra and 'Ndrangheta. [3] [15]

On 15 April 2008, Silvio Berlusconi was re-elected prime minister of Italy and vowed to restart the project to build the bridge. The following month, Altero Matteoli, Italy's minister of infrastructure and transport, confirmed the government's intent to restart work on the bridge in a letter to Pietro Ciucci, the president of Società Stretto di Messina. [16]

On 6 March 2009, as part of a massive new public works programme, Berlusconi's government announced that plans to construct the Messina bridge had been revived, pledging €1.3 billion as a contribution to its estimated cost of €6.1 billion. Berlusconi claimed that work would be completed by 2016. Until 2006, when the project was halted, the work had been assigned to a consortium of Impregilo (now called Webuild), Condotte d'Acqua, Cooperativa Muratori & Cementisti, and Consorzio Stabile A.C.I., alongside Spain's Sacyr and Japan's IHI Corporation. [11]

On 23 December 2009, preparatory work began, with the diversion of the Tyrrhenian railway at Cannitello on the Italian mainland side of the strait. [17]

In February 2013, the project was shut down by Mario Monti, the new Italian premier, for lack of funds. [5]

In September 2016, the project was reconsidered by the government of Matteo Renzi. [18]

On 3 June 2020, during the COVID-19 pandemic, premier Giuseppe Conte brought up the topic of the bridge, declaring that the government would evaluate the resumption of work without prejudice. [19] [20]

On 22 April 2021, the CEO of Webuild, Pietro Salini, in a joint press conference with the President of the Sicilian Region Nello Musumeci, announced that he was ready to build the Strait of Messina Bridge, starting immediately with the work and on the basis of the executive project and construction site approved definitively in 2013. He declared that he already had the four-billion-euro coverage necessary for the construction and that he could obtain the other two necessary for the infrastructures connected to it from private financing. [21] [22]

On 16 March 2023, the Government of Italy, chaired by Giorgia Meloni, with Matteo Salvini at the Ministry of Infrastructure, approved a decree to proceed with the construction of the bridge by remodeling the current project. [6]

On 19 March, WeBuild's Pietro Salini said work on the bridge should begin by 2024, with the opening of the project scheduled for 2032. [23]

On 31 March, the Italian president, Sergio Mattarella approved the Decreto Ponte ("bridge decree"). [7]

Contracting parties

A construction consortium, led by Impregilo, was chosen in 2005, with work set to begin in the second half of 2006. The bridge was designed by Danish architects at Dissing+Weitling in close collaboration with the Danish engineering firm COWI. [24]

On 27 March 2006, Impregilo and Stretto di Messina announced that they had signed a contract assigning final project planning to a general contractor. Impregilo S.p.A., the lead partner, had a 45% share. Other participants were Spain's Sacyr (18.70%), the Italian companies Società Italiana per Condotte D'Acqua S.p.A. (15%) and Cooperativa Muratori & Cementisti-C.M.C. of Ravenna (13%), Japan's IHI Corporation (6.30%), and Consorzio Stabile A.C.I. S.c.p.a (2%). The general contractor would also be assisted by the Danish and Canadian companies COWI A/S, Sund & Baelt A/S, and Buckland & Taylor Ltd., who would handle project engineering. Completion was planned to take six years, at an estimated cost of €3.9 billion. [25]

The Akashi Kaikyo Bridge, built in 1998 in Japan by IHI Corporation, one of the companies in charge of building the Messina Bridge. Akashi Bridge 04.jpeg
The Akashi Kaikyō Bridge, built in 1998 in Japan by IHI Corporation, one of the companies in charge of building the Messina Bridge.
The Oresund Bridge, built in 1999 by COWI A/S, one of the companies to be involved in building the Messina Bridge. Oresund bridge.JPG
The Øresund Bridge, built in 1999 by COWI A/S, one of the companies to be involved in building the Messina Bridge.
Contract of the Messina Bridge
FunctionCompaniesRole
General contractor
Flag of Italy.svg Eurolink [26]
Flag of Italy.svg Webuild (Impregilo until 2012)Group leader (45%)
Flag of Japan.svg IHI Infrastructure Systems Co., Ltd. Mandator
Flag of Denmark.svg COWI A/S Mandator
Flag of Spain.svg Sacyr Mandator
Flag of Italy.svg Società Italiana per Condotte d'Acqua Mandator
Flag of Italy.svg Cooperativa Muratori & CementistiMandator
Flag of Italy.svg Argo Costruzioni InfrastruttureMandator
Flag of Denmark.svg Dissing+Weitling Mandator
Flag of Denmark.svg Sund & Bælt A/SMandator
Flag of Canada (Pantone).svg Buckland & Taylor Mandator
Project management Flag of the United States.svg Parsons Corporation
Environmental monitoring Flag of Italy.svg FeniceGroup leader
Flag of Italy.svg AgriconsultingMandator
Flag of Italy.svg Eurisko NOP WorldMandator
Flag of Italy.svg Nautilus Società CooperativaMandator
Flag of Italy.svg TheolabMandator
Insurance broker Flag of the United States.svg Marsh

Criticisms

The bridge has been controversial due to the impact of earthquakes, strong currents in the strait, concerns about disruption of bird migration routes, and possible infiltration of the mafia groups Cosa Nostra and 'Ndrangheta in area construction projects. [2]

Supporters see the bridge as a huge job-creation scheme and a boost for tourism. However, opponents question the priority of the bridge, claiming that if the government concentrated instead on making Sicily's roads more efficient, drivers would be able to reach the coast more quickly at a fraction of the bridge's cost. Others believe that the bridge is quite unnecessary, since the local economy is already providing for the conversion of the local former NATO Comiso Airport into a commercial terminal to export vegetables to Northern Europe. Alternatively, a much cheaper revamping of the current structures is claimed to be sufficient (for instance, the ferry lines on the Calabria side are now accessible to trucks only by driving through very narrow streets, which are a tight bottleneck for transport). Another argument against the bridge is the poor state of transport infrastructure in Sicily, particularly the railroad and the A20 autostrada linking Messina to Palermo, and the poor condition of the A2 autostrada on the mainland, linking Reggio Calabria to Naples.[ citation needed ]

The greatest structural design problem of the bridge is the aerodynamic stability of its deck under wind and seismic activity. [27]

See also

Related Research Articles

<span class="mw-page-title-main">Strait of Messina</span> Strait between Calabria and Sicilia, Italy

The Strait of Messina is a narrow strait between the eastern tip of Sicily and the western tip of Calabria in Southern Italy. It connects the Tyrrhenian Sea to the north with the Ionian Sea to the south, within the central Mediterranean. At its narrowest point, between Torre Faro and Villa San Giovanni, it is 3.1 km (1.9 mi) wide. At the city of Messina, it is 5.1 km (3.2 mi) wide. The strait's maximum depth is about 250 m (820 ft).

<span class="mw-page-title-main">Pylons of Messina</span> Historic high-voltage towers in Italy

The Pylons of Messina are two free-standing steel towers, the Sicilian one in Torre Faro and the Calabrian one in Villa San Giovanni. They were used from 1955 to 1994 to carry a 220 kilovolt power line across the Strait of Messina, between the Scilla substation in Calabria on the Italian mainland at 38°14′42″N15°40′59″E and the Messina-Santo substation in Sicily at 38°15′57″N15°39′04″E.

<span class="mw-page-title-main">Bering Strait crossing</span> Proposed bridge or tunnel connection between Russia and Alaska

A Bering Strait crossing is a hypothetical bridge or tunnel that would span the relatively narrow and shallow Bering Strait between the Chukotka Peninsula in Russia and the Seward Peninsula in the U.S. state of Alaska. The crossing would provide a connection linking the Americas and Afro-Eurasia.

<span class="mw-page-title-main">Osman Gazi Bridge</span> Turkish suspension bridge across the Gulf of İzmit

The Osmangazi Bridge is a suspension bridge spanning the Gulf of İzmit at its narrowest point, 2,620 m (8,600 ft). The bridge links the Turkish city of Gebze to the Yalova Province and carries the O-5 motorway across the gulf.

<span class="mw-page-title-main">Strait of Gibraltar crossing</span> Europe-Africa fixed link

The Strait of Gibraltar crossing is a hypothetical bridge or tunnel spanning the Strait of Gibraltar that would connect Europe and Africa. The governments of Spain and Morocco appointed a joint committee to investigate the feasibility of linking the two continents in 1979, which resulted in the much broader Euromed Transport project.

<span class="mw-page-title-main">Orthotropic deck</span> Welded steel segmented construction technique for bridge decks

An orthotropic bridge or orthotropic deck is typically one whose fabricated deck consists of a structural steel deck plate stiffened either longitudinally with ribs or transversely, or in both directions. This allows the fabricated deck both to directly bear vehicular loads and to contribute to the bridge structure's overall load-bearing behaviour. The orthotropic deck may be integral with or supported on a grid of deck framing members, such as transverse floor beams and longitudinal girders. All these various choices for the stiffening elements, e.g., ribs, floor beams and main girders, can be interchanged, resulting in a great variety of orthotropic panels.

<span class="mw-page-title-main">Submerged floating tunnel</span> A tunnel that floats underwater, deep enough to avoid water traffic and weather

A submerged floating tunnel (SFT), also known as submerged floating tube bridge (SFTB), suspended tunnel, or Archimedes bridge, is a proposed design for a tunnel that floats in water, supported by its buoyancy.

A fixed link or fixed crossing is a permanent, unbroken road or rail connection across water that uses some combination of bridges, tunnels, and causeways and does not involve intermittent connections such as drawbridges or ferries. A bridge–tunnel combination is commonly used for major fixed links.

Webuild SpA is an Italian industrial group specialising in construction and civil engineering. The company was formally founded in 2014 as the result of the merger by incorporation of Salini into Impregilo. Webuild is the largest Italian engineering and general contractor group and a global player in the construction sector.

<span class="mw-page-title-main">Yavuz Sultan Selim Bridge</span> Suspension bridge in Turkey

The Yavuz Sultan Selim Bridge, also known as the Third Bosphorus Bridge, is a vehicular bridge over the Bosphorus strait, to the north of Istanbul's two older suspension bridges, the 15 July Martyrs Bridge being the First Bosphorus Bridge and Fatih Sultan Mehmet Bridge the Second Bosphorus Bridge. The bridge is located near the entrance to the Black Sea from the Bosphorus strait, between Garipçe in Sarıyer on the European side and Poyrazköy in Beykoz on the Asian side.

<span class="mw-page-title-main">Berlin–Palermo railway axis</span> Key high-speed rail link in Central Europe

The Berlin–Palermo railway axis is project No. 1 of the Trans-European high-speed rail network (TEN-R), which involves the creation of a 2,200-kilometre-long (1,400 mi) high-speed rail line between Berlin and Palermo. It is designated as one of the main transport links connecting Central and Southern Europe, tracking through Germany, Austria and Italy.

The Central Spine Road 2 or Malacca Strait Bridge is a proposed bridge that would connect Telok Gong, near Masjid Tanah, Malacca in Peninsular Malaysia to Rupat Island and Dumai in Sumatra island, Indonesia. The project has been submitted for government approval, and is expected to take 10 years to complete. Once completed, the 48-kilometre-long (30 mi) bridge will be the longest sea-crossing bridge in the world. The project will have two cable-stayed bridges and one suspension bridge, both the longest in the world.

<span class="mw-page-title-main">Strait of Messina metropolitan area</span> Metropolitan Area in Italy

The Metropolitan Area of Strait of Messina, is the urban agglomeration around the Strait of Messina, and is one of the most populated and important areas of Southern Italy. It includes part of the Province of Messina, in Sicily, and part of the Province of Reggio Calabria, in Calabria.

<span class="mw-page-title-main">1915 Çanakkale Bridge</span> Suspension bridge across the Dardanelles in Turkey

The 1915 Çanakkale Bridge is a road suspension bridge in the province of Çanakkale in northwestern Turkey. Situated just south of the coastal towns of Lapseki and Gelibolu, the bridge spans the Dardanelles, about 10 km (6.2 mi) south of the Sea of Marmara. The bridge is the longest suspension bridge in the world—with a main span of 2,023 m, the bridge surpasses the Akashi Kaikyo Bridge (1998) in Japan by 32 m (105 ft).

<span class="mw-page-title-main">Pietro Salini</span> Italian businessman (born 1958)

Pietro Salini is an Italian businessman and chief executive officer of Webuild.

<span class="mw-page-title-main">Stretto di Messina</span> Company established in 1981 to design, build, and manage the Strait of Messina Bridge

The Stretto di Messina S.p.A. company was established in 1981 in implementation of law no. 1158/1971 of the Italian government to design, build and manage the Strait of Messina Bridge.

<span class="mw-page-title-main">Enzo Siviero</span> Italian engineer, academic, writer

Enzo Siviero is an Italian engineer, academic, and writer. and also architect, as he received an honoris causa academic degree in architecture from the Polytechnic of Bari in 2009 at the age of 64.

<span class="mw-page-title-main">Genoa-Saint George Bridge</span> Motorway viaduct in Genoa, Italy

The Genoa Saint George Bridge is a motorway viaduct that crosses the Polcevera river and the districts of Sampierdarena and Cornigliano, in the city of Genoa. It was designed by architect Renzo Piano.

<span class="mw-page-title-main">Antonino Spirlì</span> Italian politician

Antonino “Nino” Spirlì is an Italian politician, author, actor and journalist. He became the acting president of Calabria region following the death of Jole Santelli on 15 October 2020. By law, a snap election must be held within 60 days, it did not happen because of the Covid pandemic.

<span class="mw-page-title-main">Claudio Borri</span> Italian engineer, academic, writer

Claudio Borri is an Italian engineer, academic, writer full professor of Construction Science at the Department of Civil and Environmental Engineering of the University of Florence.

References

  1. Sylvers, Eric (26 July 2023). "Italy Says it Will Build the Longest Suspension Bridge in the World. Don't Hold Your Breath" . The Wall Street Journal . Archived from the original on 10 January 2024. Retrieved 10 January 2024.
  2. 1 2 Nadeau, Barbie Latza (30 April 2023). "Italy wants to build the world's longest suspension bridge. The Mafia and geography might make that difficult". CNN .
  3. 1 2 "Italy drops Sicily bridge plans". BBC News . 12 October 2006. Archived from the original on 25 May 2017. Retrieved 12 October 2006.
  4. "Italy revives Sicily bridge plan". BBC News . 6 March 2009. Archived from the original on 31 August 2017. Retrieved 17 May 2011.
  5. 1 2 Masoni, Danilo (26 February 2013). "Sicily bridge project sinks in Italy budget mire". Reuters .
  6. 1 2 "Cabinet approves Messina Bridge decree – 'Historic day for Italy' says Infrastructure Minister Salvini". Agenzia Nazionale Stampa Associata . 17 March 2023. Archived from the original on 20 March 2023. Retrieved 20 March 2023.
  7. 1 2 "Il Ponte sullo Stretto è legge: Mattarella firma, il decreto è in Gazzetta Ufficiale". strettoweb.com (in Italian). 31 March 2023.
  8. "Déjà Vu? Italy Plans to Build World's Longest Suspension Bridge to Sicily". IFLScience. 16 February 2024. Retrieved 18 February 2024.
  9. "Sicily (island, Italy) – Britannica Online Encyclopedia". Encyclopædia Britannica. 17 February 2009. Archived from the original on 4 May 2015. Retrieved 20 February 2011.
  10. "When Planning a Bridge is No Small Decision". 3 June 2021.
  11. 1 2 Sicily to get longest bridge from TimesOnline Archived 17 August 2011 at the Wayback Machine . Retrieved 8 March 2009.
  12. Italy revives Messina Straits bridge from Construction Europe. Archived 13 July 2011 at the Wayback Machine Retrieved 9 March 2009.
  13. 1 2 "Ponte sullo Stretto: un maxi-documento contro le "bugie pubblicate dalla stampa locale"" (in Italian). strettoweb.com. 17 December 2013. Archived from the original on 22 June 2020. Retrieved 21 June 2020.
  14. "Giorgio Diana – Professore emerito del Politecnico di Milano". polimi.it (in Italian). Retrieved 26 July 2024.
  15. Hooper, John (12 October 2006). "Italian MPs kill plan to bridge Sicily and mainland". The Guardian . Archived from the original on 18 November 2007. Retrieved 17 December 2016.
  16. "Italian minister commits to Messina Bridge" . Bridge Design and Engineering. 27 May 2008. Archived from the original on 6 July 2009.
  17. "Ponte stretto: al via i lavori (Straits bridge: Work begins)" (in Italian). ItaliaOnLine. 23 December 2009. Archived from the original on 18 May 2016.
  18. Samuels, Gabriel (27 September 2016). "Italian PM Matteo Renzi revives plan for bridge from mainland Italy to Sicily". The Independent .
  19. "Use crisis to redesign country – Conte". Agenzia Nazionale Stampa Associata . 3 June 2010. Archived from the original on 5 June 2020. Retrieved 5 June 2020. As for a revived proposal to build a bridge across the Messina Strait to Sicily, Conte said "I will evaluate everything without prejudice".
  20. "Conte: "On EU funds, comparison with everyone, it is not a treasure of the government"". archyde.com. 4 June 2010. And the Messina bridge? "I will also evaluate without prejudice the bridge over the strait."
  21. ""Il Ponte sullo Stretto? Ce lo facciamo da soli": il patto di Musumeci con Salini" (in Italian). lasicilia.it. 22 April 2021.
  22. "Ponte Stretto: Salini, è cantierabile, siamo pronti a farlo". Agenzia Nazionale Stampa Associata (in Italian). 22 April 2021. Archived from the original on 22 April 2021. Retrieved 22 April 2021.
  23. "Pietro Salini at "Quarta Repubblica": We are ready to build the Strait of Messina Bridge | WeBuild Group". webuildgroup. Retrieved 7 April 2024.
  24. "Sicily bridge constructor named". BBC News . 12 October 2005. Archived from the original on 16 October 2005. Retrieved 15 October 2005.
  25. Straits Bridge: Impregilo and Stretto di Messina close contract Archived 18 November 2008 at the Wayback Machine . Retrieved 10 March 2009.
  26. "Salini Impregilo cambia nome: da oggi nasce Webuild – la Repubblica". Repubblica.it. 4 May 2020. Archived from the original on 28 March 2023. Retrieved 4 May 2020.
  27. "Messina Straits Bridge". Structurae . The greatest problem in designing the bridge is the aerodynamic stability of the deck under wind as well as seismic activity.

Further reading