Tamar Valley Power Station

Last updated

Tamar Valley Power Station
Tamar Valley Power Station
Country
  • Australia
Location Tamar Valley, Tasmania
Coordinates 41°08′24″S146°54′20″E / 41.14°S 146.9056°E / -41.14; 146.9056 Coordinates: 41°08′24″S146°54′20″E / 41.14°S 146.9056°E / -41.14; 146.9056
Status Base load
Commission date September 2009 [1]
Owner(s) Hydro Tasmania
Thermal power station
Primary fuel Natural gas
Combined cycle?Yes
Power generation
Units operational5
Nameplate capacity 388 MW [1]

Tamar Valley Power Station is a $230 million natural gas-fired power station located in Bell Bay in the Tamar Valley, Tasmania. It is owned by Hydro Tasmania, and is immediately adjacent to the decommissioned Bell Bay Power Station, which is also owned by Hydro Tasmania. [1] [2]

The station's total nameplate capacity is 388 MW, and includes four peaking units totalling 178 MW, and one base-load combined cycle unit of 210 MW. The four peaking units are: three 40 MW (total 120 MW) pre-existing (from the Bell Bay Power Station) Pratt & Whitney FT8 Twin Pac gas turbine alternators (Units 101-103), and a single 58 MW Rolls Royce Trent 60WLE gas turbine alternator (Unit 104) commissioned in May 2009. The base-load unit is a 210 MW Mitsubishi M701DA gas turbine operating in combined cycle mode (Unit 201) which completed commissioning in September 2009. The Mitsubishi's combined cycle capacity of 210 MW includes 140 MW generated directly by the M701 gas turbine, and a further 70 MW generated by the Mitsubishi steam turbine generator set. [3]

At the time of conception, the Tasmanian Government allowed Aurora Energy to enter into long term energy supply agreement with Alinta. [2] [4] During 2008 the Tasmanian Government via Aurora Energy acquired the construction project from the then owner Babcock & Brown Power (who had earlier purchased Alinta Energy generation assets). [1] [5] Aurora set up a fully owned subsidiary company "AETV Power" to complete and operate the power station assets.

On 1 June 2013 the State Government transferred the ownership of the power station from Aurora Energy to Hydro Tasmania, another state owned enterprise, and the predominant generator of electricity in the state.

Following its commissioning, low electricity demand, strong rainfall and substantial use of the Basslink interconnector with Victoria meant that the station generated only small volumes of electricity. In June 2014 Hydro Tasmania commenced the process of mothballing the combined cycle unit, and in January 2015 it sought the Tasmanian Government's approval to sell the unit. [6] In August 2015 Hydro Tasmania announced that the combined-cycle unit was not required for energy security and would be decommissioned and sold. [7] The open-cycle units would be retained for peaking duty. However, only a few months later in December, Hydro Tasmania hired 12 temporary workers at the plant, indicating that the combined-cycle unit may be used again to slow the rate at which Hydro Tasmania's dam storages were depleted.

On 21 December 2015, Basslink, the HVDC interconnector with Victoria, was disconnected due to a faulty interconnector. It was originally expected that Basslink would be repaired and returned to service by 19 March 2016; [8] however, the link was not restored until 13 June 2016. [9] A separate non-cable fault caused another failure of power flow on 22 June. [10] After almost 36 hours power flow was again restored in the evening of 23 June. [11]

Because of the 2016 Tasmanian energy crisis, Hydro Tasmania recommissioned Tamar Valley Power Station to help meet Tasmania's electricity needs. [12] [13]

See also

Related Research Articles

Combined cycle power plant Assembly of heat engines that work in tandem from the same source of heat

A combined cycle power plant is an assembly of heat engines that work in tandem from the same source of heat, converting it into mechanical energy. On land, when used to make electricity the most common type is called a combined cycle gas turbine (CCGT) plant. The same principle is also used for marine propulsion, where it is called a combined gas and steam (COGAS) plant. Combining two or more thermodynamic cycles improves overall efficiency, which reduces fuel costs.

George Town, Tasmania Town in Tasmania, Australia

George Town is a large town in north-east Tasmania, on the eastern bank of the mouth of the Tamar River. The Australian Bureau of Statistics records the George Town Municipal Area had a population of 6,764 as of 30 June 2016.

Hydro Tasmania

Hydro Tasmania, known for most of its history as the Hydro-Electric Commission (HEC) or The Hydro, is the trading name of the Hydro-Electric Corporation, a Tasmanian Government business enterprise which is the predominant electricity generator in the state of Tasmania, Australia. The Hydro was originally oriented towards hydro-electricity, due to Tasmania's dramatic topography and relatively high rainfall in the central and western parts of the state. Today Hydro Tasmania operates thirty hydro-electric and one gas power station, and is a joint owner in three wind farms.

Transend Networks Former Tasmania state-owned enterprise

Transend Networks Pty Ltd was a Tasmanian government-owned business which operated between 1998 and 2014 as the electricity transmission network provider for Tasmania, Australia. It was formed by the disaggregation of the Hydro-Electric Commission, and ceased operation when it was merged on 1 July 2014 with the distribution division of Aurora Energy to form the combined network business TasNetworks.

Aurora Energy (Tasmania) Electricity company in Tasmania, Australia

Aurora Energy is a Tasmanian Government-owned electricity retailer in Tasmania, Australia.

The National Electricity Market (NEM) is an arrangement in Australia's electricity sector for the connection of the electricity transmission grids of the eastern and southern Australia states and territories to create a cross-state wholesale electricity market. The Australian Energy Market Commission develops and maintains the Australian National Electricity Rules (NER), which have the force of law in the states and territories participating in NEM. The Rules are enforced by the Australian Energy Regulator. The day-to-day management of NEM is performed by the Australian Energy Market Operator.

Loy Yang Power Station

The Loy Yang Power Station is a brown coal- fired thermal power station located on the outskirts of the city of Traralgon, in south-eastern Victoria, Australia. It consists of two sections, known as Loy Yang A and Loy Yang B. Both Loy Yang A and B are supplied by the Loy Yang brown coal mine. The Loy Yang power stations are located in the brown coal rich Latrobe Valley, along with the Yallourn power station.

Bell Bay Power Station Former power station in Tasmania

The Bell Bay Power Station was a power station located in Bell Bay, on the Tamar River, Tasmania, Australia, adjacent to the Tamar Valley Power Station, with which it was often confused. It was commissioned between 1971 and 1974 as an oil fired thermal power station, and was converted to natural gas in 2003, after the commissioning of the Tasmanian Gas Pipeline, a submarine gas pipeline which transports natural gas from Longford, Victoria, under Bass Strait, to Bell Bay, Tasmania. As the power station's primary role was to provide system security in the event of drought for Tasmania's predominantly hydro-electric based generation system it only was rarely called on to operate, resulting in intervals of five to eight years between periods of significant use. After the commissioning of Basslink in 2006, the power station was decommissioned in 2009.

Meadowbank Power Station Power station in Tasmania, Australia

The Meadowbank Power Station is a run-of-the-river hydroelectric power station located in the Central Highlands region of Tasmania, Australia. The power station is situated on the Lower River Derwent catchment and is owned and operated by Hydro Tasmania.

AGL Energy

AGL Energy Ltd is an Australian listed public company involved in both the generation and retailing of electricity and gas for residential and commercial use. AGL is Australia's largest electricity generator, and the nation's largest carbon emitter. The company has an operated generation capacity of 10,984 MW. 85% of the company's generation comes from the burning of coal. The company emits 42,227,180 Total Scope 1 Emissions. AGL is also a significant investor, owner, and operator, of renewable energy assets.

Contact Energy New Zealand electricity generator company

Contact Energy Limited is a New Zealand electricity generator, natural gas wholesaler and electricity, natural gas, broadband and LPG retailer.

Energy in Victoria

Energy in Victoria, Australia is generated using a number of fuels or technologies, including coal, natural gas and renewable energy sources. Brown coal is the main primary energy source for the generation of electricity in the state, accounting for about 85% of electricity generation in 2008. The amount of coal-fired power has decreased significantly with the closure in 2017 of the Hazelwood power station which supplied around 20% of Victoria’s electricity, and to a lesser extent with the exit of Anglesea power station in 2015. Brown coal is one of the largest contributors to Australia's total domestic greenhouse gas emissions and a source of controversy for the country. Australia is one of the highest polluters of greenhouse gas per capita in the world. In 2016, about 16% of Victoria’s electricity was from renewable sources, with a government target to increase that share to 40% by 2025. In 2019, renewable energy provided 23.9% of the state's electricity. On 28 March 2021, Victoria reached 50% renewable energy.

Gordon Dam Dam in South West Tasmania, Australia

The Gordon Dam, also known as the Gordon River Dam, is a major gated double curvature concrete arch dam with a controlled spillway across the Gordon River, located in South West Tasmania, Australia. The impounded reservoir is called Lake Gordon.

Braemar Power Station

Braemar Power Station is a complex of natural gas and coal seam gas fired combined-cycle power stations in Kogan, Western Downs Region, Queensland, Australia. It is near Dalby in the Darling Downs region.

The Basslink electricity interconnector is a 370 km (230 mi) 500 MW (670,000 hp) high-voltage direct current (HVDC) cable linking the electricity grids of the states of Victoria and Tasmania in Australia, crossing Bass Strait, connecting the Loy Yang Power Station, Victoria on the Australian mainland to the George Town substation in northern Tasmania. Basslink is bidirectional and enables Hydro Tasmania to supply some of the peak load capacity to the Australian mainland and take some of the excess power from the mainland when the generation on the mainland exceeds the demand.

Pelican Point Power Station Engie power station near Adelaide, South Australia

The Pelican Point Power Station is located at Pelican Point, 20 km from the centre of Adelaide, South Australia on the Lefevre Peninsula. It is operated by Engie, which owns 72 per cent of the power station. Mitsui owns the remaining 28 per cent. It burns natural gas in a combined cycle power station, comprising two 160 MW gas turbines and one 165 MW steam turbine, to generate up to 485 MW of electricity.

The 2016 Tasmanian energy crisis was an ongoing energy storage situation in the state of Tasmania, Australia in 2016. Two years of high volumes of energy exported to Victoria via the Basslink HVDC cable, followed by low rainfall, and a fault which rendered the cable inoperable, resulted in record low storage levels in Tasmania's hydro-electric system. This resulted in a number of contingency plans to be enacted by Hydro Tasmania and the Hodgman Government.

The South Australian blackout of 2016 was a widespread power outage in South Australia that occurred as a result of storm damage to electricity transmission infrastructure on 28 September 2016. The cascading failure of the electricity transmission network resulted in almost the entire state losing its electricity supply, affecting 850,000 SA customers. Kangaroo Island did not lose its supply, as the Kangaroo Island power station had been built to supply the island for the contingency of a failure in the power cable under the Backstairs Passage.

Marinus Link is a proposed 1500 megawatt capacity high voltage direct current (HVDC) electricity interconnector, to strengthen the connection between the Australian states of Tasmania and Victoria, on Australia's National Electricity Market. It involves approximately 250 km of subsea cables and approximately 90 km of underground land cables. Marinus Link will also incorporate significant optical fibre capacity for system control, with the remaining capacity available to strengthen telecommunications and data connectivity between the regions. Marinus Link will be supported by approximately 220 km of high voltage alternating current (HVAC) of proposed transmission developments in North West Tasmania, known as the North West Transmission Developments (NWTD). Collectively, Marinus Link and the North West Transmission Developments are known as Project Marinus.

References

  1. 1 2 3 4 "Tamar Valley power station on track". ABC News Online. 2009. Retrieved 1 October 2009.[ dead link ]
  2. 1 2 "Tasmania allows Alinta power agreement". Melbourne: The Age. 26 October 2006. Retrieved 5 February 2009.
  3. "AEMO Tasmanian Generators". 2010. Archived from the original on 17 October 2009. Retrieved 18 January 2010.
  4. "Alinta signs $600m gas supply agreements". ABC News Online. 2007. Retrieved 5 February 2009.
  5. "New acquisition improves energy security for Tamar Valley Power Station". Aurora Energy Online. 2009. Archived from the original on 24 May 2009. Retrieved 30 September 2009.
  6. "Ministerial Statement on Energy Security". www.premier.tas.gov.au. Retrieved 9 March 2016.
  7. "Changes to operation of Tamar Valley Power Station | Hydro Tasmania". www.hydro.com.au. Archived from the original on 9 March 2016. Retrieved 9 March 2016.
  8. "Basslink interconnector update" (PDF). Baslink.com.au. Retrieved 8 March 2017.
  9. "Electricity flow between Tasmania and Victoria restored". ABC News. Australian Broadcasting Corporation (ABC). 13 June 2016. Retrieved 29 July 2016.
  10. "Basslink confirms fresh outage days after service resumes". ABC News. ABC-Australia. 22 June 2016. Retrieved 29 July 2016.
  11. "Basslink running again after 'mechanical failure' caused outage". ABC News. (ABC-Australia). 23 June 2016. Retrieved 29 July 2016.
  12. Richards, Blair (29 December 2015). "The Mercury". themercury.com.au. Retrieved 9 March 2016.
  13. "More generators ordered after delays confirmed on Basslink undersea cable repair". ABC News. Retrieved 9 March 2016.