2016 Tasmanian energy crisis

Last updated

The 2016 Tasmanian energy crisis was an ongoing energy storage situation in the state of Tasmania, Australia in 2016. Two years of high volumes of energy exported to Victoria via the Basslink HVDC cable, followed by low rainfall, and a fault which rendered the cable inoperable, resulted in record low storage levels in Tasmania's hydro-electric system. This resulted in a number of contingency plans to be enacted by Hydro Tasmania and the Hodgman Government.

Contents

Background

Graph of Hydro Tasmania's system storage levels from March 2010 to March 2016. The blue line represents energy in storage. The shaded yellow area represents the period where the carbon tax was in place, and the red represents the period when Basslink was out of service. Hydro-tasmania-storage-graph-2010-2016.png
Graph of Hydro Tasmania's system storage levels from March 2010 to March 2016. The blue line represents energy in storage. The shaded yellow area represents the period where the carbon tax was in place, and the red represents the period when Basslink was out of service.

Tasmania's electricity generation is primarily hydro-electric, having been gradually developed since 1914. As a result, the state is highly dependent on rainfall for electricity generation. An energy shortage in the 1960s resulted in the construction of the oil-fired Bell Bay Power Station. However, this station was only used as a contingency - as of 2015, hydro-electricity continued to be the primary generation method. [1] The state was self-reliant until 2005, when the Basslink HVDC interconnector to Victoria was completed. Basslink was intended to both provide energy security, in case of drought; and provide renewable energy to Victoria, which relies heavily on coal as a fuel source. [2]

Tasmania's reliance on hydro-electricity was further increased by the decommissioning of the Bell Bay Power Station in 2009, and the mothballing of several units of its replacement, the gas-fired Tamar Valley Power Station, including considering selling parts of the station. [3] Conversely, this reliance was reduced in part by the expansion of the Woolnorth Wind Farm in 2007 and the construction of the Musselroe Wind Farm in 2013.

In July 2012, an Australian carbon pricing system came into effect, providing renewable electricity generators with a competitive advantage over greenhouse gas-emitting generators. The Abbott government had promised the repeal of the scheme in the lead-up to the 2013 federal election, in which they were successful. Anticipating that the carbon pricing scheme would be short-lived, Hydro Tasmania capitalised by increasing generation and running down storage levels over the period from July 2012 until the carbon price was repealed in July 2014. Hydro Tasmania's storage levels peaked around 62% in late 2012 before declining to 28% capacity on 1 July 2014. [4] [5] Whereas Hydro Tasmania's target minimum storage levels on 1 July each year was traditionally 30%, in September 2012 it lowered this target to 25%. [5]

Hydro Tasmania's storages did not recover significantly during the second half of 2014 or 2015, despite above average inflows from May to August 2015. Storage levels began dropping sharply from September 2015 due to extremely low inflows; October inflows were just 7% of the long-term average for that month. [5]

On 22 December 2015, Basslink announced [6] that the HVDC cable had experienced a fault two days earlier (20 December) and was unable to transmit electricity in either direction. [7] [8] The location of the fault was identified as approximately 100 kilometres (62 mi) off the coast of Tasmania. Basslink informed the Australian Energy Market Operator that the interconnector would experience an outage of up to 60 days. [9]

To diagnose the fault, Basslink contracted a range of specialist companies, including cable joiners from Italy and the submarine cable laying ship, Ile De Re. [10] The ship, which typically services communications cables, underwent modifications in the port of Geelong to suit HVDC cables. [11] The problem continued into February 2016, [10] [12] and is considered to be an expensive problem to fix. [13]

On 8 March 2016, Basslink announced they intended to cut the cable within a week and have the cable back in service by late May, [14] with the cable actually being cut on the 11th. [15]

At the end of March 2016, the fault had been identified, and the recovery date for Basslink had been put back to mid June 2016 [16]

By the second last week of April 2016, the first stage of the repair was reported as complete [17] Power through the cable was restored on 13 June 2016. [18] After 9 days a separate non-cable fault caused another failure of power flow on 22 June. [19] After almost 36 hours power flow was again restored in the evening of 23 June 2016. [20]

Response

Actions taken to minimise the consumption of water from Hydro Tasmania's storages included:

Also at a political level, the unresolved problem seems to have no cross party agreement on the issues. [25] Long term ramifications are also being considered. [26] [27] [28] The prospect of the Basslink connection being lost permanently also is being considered. [29] The dam makers of the early dam making era of Hydro Tasmania also have offered their reflections [30] with no allowance or concession to any of the alternatives that were offered in the 1980s as viable energy generating infrastructure.

On 8 March 2016 Tasmanian Energy Minister Matthew Groom delivered a statement on energy security, summarising the government's actions to date and announcing future steps to manage the energy crisis, including the formation of a Tasmanian Energy Security Taskforce. [31]

The cutting of the Basslink cable also severed part of the internet link to Tasmania. [32] [33] [34] [35]

The state government had considered requesting funding for a second cable, [36] while the fault seeking on the first cable was apparently unsuccessful. [37] The subsequent comments from the Opposition regarding the growing crisis were rebutted as scaremongering. [38] The energy crisis elicited a response for inquiries and examination of issues, including recent Hydro Tasmania management. [39] [40]

Issues of residual capacity

By March 2016 Tasmanian media were discussing the extent to which Hydro Tasmania would be able to draw upon very low water levels in dams and still create energy from the downstream power stations. [41] [42]

In late March 2016, with no resolution to issues in sight, [43] [44] [45] saw the upgrading of the Tamar Valley Power Station gas turbine capacity [46]

Some commentators saw the crisis as requiring consideration of the issues arising as imperative for the future of Tasmania. [47] [48] Some businesses and business groups took steps to safeguard their power supplies regardless of official pronouncements about power cuts. [49] By late March 2016, Hydro Tasmania was to state lower levels on dam holdings than previously stated [50] and the state of the major dam of the system Lake Gordon had been recorded in its lowest record level [51] leading some commentators to suggest the option of bringing up an issue from some decades before, of the draining of the hydro-dam created new Lake Pedder back to the level of the original Lake Pedder. [52]

Energy use

Concern of change of weather conditions and potential increased energy usage was noted in March [53] with the Minister for Energy Matthew Groom calling for sensible energy usage. [54] [55] [56]

A series of diesel generators were installed at Meadowbank Power Station, to be part of the apparent short-term solution until June. [5] [57] The ABC News website explanation of the issue of energy use was regularly updated. [58] In April 2016, Hydro Tasmania commenced advertising for conservation of energy by Tasmanians with newspaper advertisements. [59]

Financial and political impact

Regardless of the timeline or subsequent resolution of some of the issues, the impact of the crisis, financially and politically, on banks [60] and the Tasmanian government, was expected to be substantial [61] [62] However, for industry, there were different expectation in relation to power supply for industry. [63]

Outside perspectives and comparisons

A few commentators from outside Tasmania tried to put perspective on the issues relative to the larger picture of how political and Hydro Tasmania level decisions affected the current energy issues. [64] [65] [66] Recent Hydro Tasmania board decisions also had been under the spotlight from former staff. [67] [68] Many mainland commentators also focus upon the need to change current policies and practices relative to energy. [69]

Blackouts and plans

It was claimed in early April that: [70]

“active discussions” for more than three months about enforced blackouts and brownouts

However this did not agree with the public statements of the Minister. [71] Various sectors of the Tasmanian community, as well as regions, were concerned at the prospect of loss of energy available to support their industries. [72] [73]

The explanation of how the issue developed continued in the media in May 2016, [74] as well as delays due to Bass Strait conditions [75] as well as differences as to the explanation of the cause of the break in Basslink. [76] [77] Also rain had raised dam levels. [78] [79]

Resolution

The power crisis was expected to be resolved by the Basslink repair, expected by mid-June 2016, [80] and increased rain for hydro storages. However strategies prior to the resolution involved further utilisation of diesel power units delegated to power stations. [81]

In March 2016 the Minister for Energy stated: [82]

"The Government can't control the rain, the Government can't control the timing of Basslink," he said. "What we can control are contingencies that we can put in place to make sure that we can meet Tasmania's ongoing energy requirements."

In April, there was a suggestion that unseasonal weather in June (18 consecutive clear days on Bass Strait) was required for a successful re-connection to occur, put the question of possible further delays. [83]

On 12 May 2016, the Hydro Tasmania website announced a return to usual practices of hydro facilities: [84]

Over the past week, Hydro Tasmania has stopped all diesel generation and wound back gas to prevent spill in smaller hydro storages because of high inflows. Yesterday, the combined cycle gas turbine (CCGT) at the Tamar Valley Power Station was turned off, as continued high inflows push storages close to spilling at a number of locations.

In the same week, rainfall rates in Tasmania were well above average. [85]

Senate inquiry

Early in 2016, members of the Australian Senate decided to hold an inquiry into the crisis, [86] planned to occur in April 2016. [87] The Tasmanian Minister for Energy's response to the impending inquiry on 14 April was a claim that he had not been asked to attend. [88] The Premier's perspective was to criticise the inquiry as a federal election tactic, in the face of internal documents showing serious concern from within Hydro Tasmania regarding its water levels. [89] [90] The Senate inquiry commenced on 14 April [91] and the Premier advised that Hydro Tasmania staff would not attend: [92]

Mr Groom has said Hydro staff should not be distracted during the energy situation

During the Senate inquiry, a range of issues raised before the committee sat were downplayed by the Minister and government staff. [93] The Tasmanian Treasurer refused to publicly reveal costs of the crisis. [94]

See also

Related Research Articles

<span class="mw-page-title-main">Lake Gordon</span> Reservoir in Tasmania, Australia

Lake Gordon is a man-made reservoir created by the Gordon Dam, located on the upper reaches of the Gordon River in the south-west region of Tasmania, Australia.

<span class="mw-page-title-main">Hydro Tasmania</span> Government hydro electricity provider in Tasmania, Australia

Hydro Tasmania, known for most of its history as the Hydro-Electric Commission (HEC) or The Hydro, is the trading name of the Hydro-Electric Corporation, a Tasmanian Government business enterprise which is the predominant electricity generator in the state of Tasmania, Australia. The Hydro was originally oriented towards hydro-electricity, due to Tasmania's dramatic topography and relatively high rainfall in the central and western parts of the state. Today Hydro Tasmania operates thirty hydro-electric and one gas power station, and is a joint owner in three wind farms.

<span class="mw-page-title-main">Transend Networks</span> Former Tasmania state-owned enterprise

Transend Networks Pty Ltd was a Tasmanian government-owned business which operated between 1998 and 2014 as the electricity transmission network provider for Tasmania, Australia. It was formed by the disaggregation of the Hydro-Electric Commission, and ceased operation when it was merged on 1 July 2014 with the distribution division of Aurora Energy to form the combined network business TasNetworks.

<span class="mw-page-title-main">Tumut Hydroelectric Power Station</span> Power stations in New South Wales, Australia

The Tumut Hydroelectric Power Stations is a series of three hydroelectric power stations on the Tumut River in New South Wales, Australia, that are part of the Snowy Mountains Scheme.

<span class="mw-page-title-main">Bell Bay Power Station</span> Former power station in Tasmania

The Bell Bay Power Station was a power station located in Bell Bay, on the Tamar River, Tasmania, Australia, adjacent to the Tamar Valley Power Station, with which it was often confused. It was commissioned between 1971 and 1974 as an oil fired thermal power station, and was converted to natural gas in 2003, after the commissioning of the Tasmanian Gas Pipeline, a submarine gas pipeline which transports natural gas from Longford, Victoria, under Bass Strait, to Bell Bay, Tasmania. As the power station's primary role was to provide system security in the event of drought for Tasmania's predominantly hydro-electric based generation system it only was rarely called on to operate, resulting in intervals of five to eight years between periods of significant use. After the commissioning of Basslink in 2006, the power station was decommissioned in 2009.

<span class="mw-page-title-main">Butlers Gorge Power Station</span> Dam in Central Highlands, Tasmania

The Butlers Gorge Power Station is a conventional hydroelectric power station located in the Central Highlands region of Tasmania, Australia.

The Repulse Power Station is a conventional hydroelectric power station located in the Central Highlands region of Tasmania, Australia. The power station is situated on the Lower River Derwent catchment and is owned and operated by Hydro Tasmania.

The Cluny Power Station is a conventional hydroelectric power station located in the Central Highlands region of Tasmania, Australia. The power station is situated on the Lower River Derwent catchment and is owned and operated by Hydro Tasmania.

<span class="mw-page-title-main">Meadowbank Power Station</span> Power station in Tasmania, Australia

The Meadowbank Power Station is a run-of-the-river hydroelectric power station located in the Central Highlands region of Tasmania, Australia. The power station is situated on the Lower River Derwent catchment and is owned and operated by Hydro Tasmania.

The Poatina Power Station is a conventional hydroelectric power station located in the Central Highlands region of Tasmania, Australia. The power station is situated on the Great Lake and South Esk and is owned and operated by Hydro Tasmania.

The Rowallan Power Station is a conventional hydroelectric power station located in north-western Tasmania, Australia. The station is located 25 kilometres (16 mi) south of Liena.

The Moorina Power Station is a decommissioned hydroelectric power station, located near the hamlet of Moorina in far north-eastern Tasmania, Australia. Opened in 1909 and decommissioned in 2008, at the time of its closure, Moorina Power Station was the oldest operating electricity generator in Australia.

<span class="mw-page-title-main">Gordon Dam</span> Dam in South West Tasmania, Australia

The Gordon Dam, also known as the Gordon River Dam, is a major gated double curvature concrete arch dam with a controlled spillway across the Gordon River, located in Southwest National Park, Tasmania, Australia. The impounded reservoir is called Lake Gordon.

The Edgar Dam is an earthfill embankment saddle dam without a spillway, located offstream in the South West region of Tasmania, Australia.

Tamar Valley Power Station is a $230 million natural gas-fired power station located in Bell Bay in the Tamar Valley, Tasmania. It is owned by Hydro Tasmania, and is immediately adjacent to the decommissioned Bell Bay Power Station, which is also owned by Hydro Tasmania.

The Basslink electricity interconnector is a 370 km (230 mi) 500 MW (670,000 hp) high-voltage direct current (HVDC) cable linking the electricity grids of the states of Victoria and Tasmania in Australia, crossing Bass Strait, connecting the Loy Yang Power Station, Victoria on the Australian mainland to the George Town substation in northern Tasmania. Basslink is bidirectional and enables Hydro Tasmania to supply some of the peak load capacity to the Australian mainland and take some of the excess power from the mainland when the generation on the mainland exceeds the demand.

<span class="mw-page-title-main">TasNetworks</span> State owned company in Tasmania

Tasmanian Networks Pty Limited, trading as TasNetworks, is a Tasmanian Government State owned company that is responsible for electricity transmission and distribution throughout Tasmania. It also owns and operates a telecommunications network throughout the state.

The South Australian blackout of 2016 was a widespread power outage in South Australia that occurred as a result of storm damage to electricity transmission infrastructure on 28 September 2016. The cascading failure of the electricity transmission network resulted in almost the entire state losing its electricity supply, affecting 850,000 SA customers. Kangaroo Island did not lose its supply, as the Kangaroo Island power station had been built to supply the island for the contingency of a failure in the power cable under the Backstairs Passage.

Marinus Link is a proposed 750 megawatt capacity high voltage direct current (HVDC) electricity interconnector, to strengthen the connection between the Australian states of Tasmania and Victoria, on Australia's National Electricity Market. Due to inflation, Marinus link was scaled back from an initial plan of 1500 MW via two cables, down to 750 MW via one cable. It involves approximately 250 km of subsea cables and approximately 90 km of underground land cables. Marinus Link will also incorporate significant optical fibre capacity for system control, with the remaining capacity available to strengthen telecommunications and data connectivity between the regions. Marinus Link will be supported by approximately 220 km of high voltage alternating current (HVAC) of proposed transmission developments in North West Tasmania, known as the North West Transmission Developments (NWTD). Collectively, Marinus Link and the North West Transmission Developments are known as Project Marinus. In October 2022, authorities pledged loans for the project, as well as supporting facilities such as pumped hydro in Tasmania.

Tasmania, as an advanced economy with a globally high standard of living, uses a great deal of energy. Distinctive features of energy use in Tasmania include the high fraction of hydroelectricity usage, the absence of coal-fired electrical generation, relatively light usage of natural gas, particularly for domestic use, and a wide use of domestic wood-burning stoves. Energy production through hydroelectricity has been politically contentious, and conflicts over Tasmanian hydroelectric projects were integral to the formation of Green parties in Australia and across the world.

References

  1. "Annual Planning Report, 2015, figure 3-3" (PDF). TasNetworks . Retrieved 25 February 2016.
  2. Electricity Supply Industry Expert Panel (December 2011). "Basslink: Decision making, expectations and outcomes" (PDF).
  3. "Tas Government flags partial sale of gas-fired Tamar Valley power station". ABC News . Australia. 4 December 2014. Retrieved 25 February 2016.
  4. "How much new renewable energy does Tasmania need?". RenewEconomy. 22 February 2016. Retrieved 25 February 2016.
  5. 1 2 3 4 "Ministerial Statement on Energy Security". www.premier.tas.gov.au. Retrieved 11 March 2016.
  6. Basslink interconnector outage, Basslink Media release. 22 December 2015
  7. "Tasmania forced to be self-reliant on power after Basslink cable outage". Basslink is planning a major operation to repair its undersea power cable which has been shut down, halting power imports to Tasmania. ABC News. 23 December 2015. Retrieved 1 April 2016.
  8. Martin, Corey (22 December 2015). "Fault found in Basslink electricity cable". Basslink has been advised that there has been no impact to Tasmanian or Victorian residential or commercial customers to date as a result of this outage,” Mr Eccles said. Fairfax Media. The Examiner . Retrieved 1 April 2016.
  9. "Busted: Basslink out of action". The Examiner . 22 December 2015. Retrieved 26 February 2016.
  10. 1 2 "Basslink still searching for cable fault". ITNews. 28 January 2016. Retrieved 26 February 2016.
  11. "Repairs to start on Basslink power cable". The Examiner (Tasmania). 27 January 2016. Retrieved 26 February 2016.
  12. "Tasmania power crises may worsen". ABC News (Australia). 25 February 2016. Retrieved 25 February 2016.
  13. "Tasmania's energy crisis explained". ABC News. Australia. 23 February 2016. Retrieved 26 February 2016.
  14. "Basslink homes in on underwater cable fault". ABC News. Australia. 8 March 2016. Retrieved 8 March 2016.
  15. "Basslink repairs hit internet users in Tasmania". ABC News. Australia. 11 March 2016. Retrieved 15 March 2016.
  16. "Basslink pinpoints fault in undersea power cable linking Tasmania to mainland Australia". ABC News. Australia. 29 March 2016. Retrieved 15 July 2016.
  17. "Basslink repair 'on track' and should be completed on schedule, Energy Minister says". ABC News. Australia. 22 April 2016. Retrieved 15 July 2016.
  18. "Electricity flow between Tasmania and Victoria restored". ABC News. Australian Broadcasting Corporation (ABC). 13 June 2016. Retrieved 29 July 2016.
  19. "Basslink confirms fresh outage days after service resumes". ABC News. ABC-Australia. 22 June 2016. Retrieved 29 July 2016.
  20. "Basslink running again after 'mechanical failure' caused outage". ABC News. (ABC-Australia). 23 June 2016. Retrieved 29 July 2016.
  21. "Another big industrial trims demand as Tasmania energy crisis deepens". RenewEconomy. 1 March 2016. Retrieved 8 March 2016.
  22. "Power rationing". ABC News . Australia. 23 February 2016. Retrieved 7 March 2016.
  23. "Environmental watchdog fast tracks diesel generators". ABC News . Australia. 4 March 2016. Retrieved 7 March 2016.
  24. 1 2 "Tasmania battles to keep lights on with cloud seeding and diesel generators". The Examiner (Tasmania) . 4 March 2016. Retrieved 7 March 2016.
  25. "Energy Minister set for grilling". ABC News . Australia. 23 February 2016. Retrieved 7 March 2016.
  26. "Tasmanian frontbencher Matthew Groom". ABC News . Australia. 22 February 2016. Retrieved 7 March 2016.
  27. "Hydro Tasmania in uncharted territory". ABC News . Australia. 7 March 2016. Retrieved 7 March 2016.
  28. "Tasmanian government considers long term loss of Basslink cable". ABC News . Australia. 23 February 2016. Retrieved 7 March 2016.
  29. "Category". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  30. "Talking ponit: Blocked dam would have added security". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  31. "Ministerial Statement on Energy Security". www.premier.tas.gov.au. Retrieved 9 March 2016.
  32. "Basslink repairs hit internet users in Tasmania". ABC News . Australia. 12 March 2016. Retrieved 12 March 2016.
  33. "Tasmanian internet problems: ISPs secure extra bandwidth amid Basslink repairs". ABC News . Australia. 13 March 2016. Retrieved 15 July 2016.
  34. "Basslink repairs: ACCC to look into concerns about ISP access to Telstra cables". ABC News . Australia. Retrieved 15 July 2016.
  35. "Basslink repairs: Bryan Green calls for ACCC investigation as internet disruptions continue". ABC News . Australia. 13 March 2016. Retrieved 15 July 2016.
  36. "Tasmanian energy crisis: State Government seeks federal funding for second Basslink cable". ABC News . Australia. 9 March 2016. Retrieved 15 July 2016.
  37. McIntyre, Damian (15 March 2016). "Tasmania energy crisis: Basslink still unsure where cable fault is, facing 'phenomenal' repair costs". Repair crews are still unsure where the fault in Tasmania's vital undersea cable is days after cutting it, Basslink chief executive Malcolm Eccles says. ABC News. Retrieved 1 April 2016.
  38. Hunt, Linda (15 March 2016). "Tasmanian Opposition accused of scaremongering over energy crisis". Tasmania's Energy Minister has accused the Opposition of scaremongering over the state's energy crisis, saying rain will eventually ease the situation. Australia. ABC News . Retrieved 1 April 2016.
  39. "Talknig point: Hydro water assets badly managed and heads need to roll". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  40. "Talking point: Energy security crisis has its roots in Basslink business case". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  41. "Lake Gordon available for power generation despite record low water levels Hydro Tasmania says". ABC News . Australia. 24 March 2016. Retrieved 15 July 2016.
  42. "Tasmanian energy crisis: Hydro Tasmania in uncharted territory as dam levels continue to drop". ABC News . Australia. 7 March 2016. Retrieved 15 July 2016.
  43. "Hydro Tasmania staff preparing their homes for 24-hour blackouts, union says". ABC News . Australia. 22 March 2016. Retrieved 15 July 2016.
  44. "Tasmanian energy crisis: CSIRO buys generators to protect critical facilities against power restrictions". ABC News . Australia. 23 March 2016. Retrieved 15 July 2016.
  45. "Tasmania's Energy Crisis : Keep Calm And Carry On". Energy Matters. 25 March 2016. Retrieved 15 July 2016.
  46. Papadopoulos, Toli (26 March 2016). "Tamar gas turbine to address energy crisis". The Examiner. Retrieved 15 July 2016.
  47. "Talking Point: New ideas needed in energy crisis". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  48. Rayner, Tristan (24 March 2016). "Tasmania looks pretty f-cked: Here's why". Techly. Archived from the original on 29 March 2016. Retrieved 15 July 2016.
  49. "Businesses preparing power cut plans". News.com.au. 24 March 2016. Retrieved 15 July 2016.[ permanent dead link ]
  50. "Energy crisis: Hydro Tasmania warns dam levels to drop lower than predicted". ABC News . Australia. 30 March 2016. Retrieved 15 July 2016.
  51. "Tasmanian energy crisis: Lake Gordon dam level fall captured in dramatic video". ABC News . Australia. 31 March 2016. Retrieved 15 July 2016.
  52. "Prospect of tapping Lake Pedder for water prompts calls for it to be restored to pre-flood state". ABC News . Australia. 28 February 2016. Retrieved 15 July 2016.
  53. "Tasmanian energy use campaign urged ahead of winter". ABC News . Australia. 24 March 2016. Retrieved 15 July 2016.
  54. Burgess, Georgie (29 March 2016). "Groom calls for 'sensible' energy use". The Examiner. Retrieved 15 July 2016.
  55. "Talking Point: Uncertainty is the most certain factor in Tasmania's energy crisis". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  56. Sayer, Luke (29 March 2016). "Last one out can just forget about the lights". The Advocate. Retrieved 15 July 2016.
  57. Battersby, Lucy (30 March 2016). "Tasmania relying on 150 diesel generators for electricity until June". The Advocate. Retrieved 15 July 2016.
  58. "Tasmania power crisis: Avoiding shortages will be costly, experts say". ABC News . Australia. 23 February 2016. Retrieved 15 July 2016.
  59. "Tasmanian Government encourages consumers to save energy, help conserve water in dams". ABC News . Australia. 2 April 2016. Retrieved 15 July 2016.
  60. "Banks feel the heat of Tassies cable capers". The Australian . Retrieved 15 July 2016.
  61. "Talking Point: Hydro's mounting money woes will king-hit state coffers". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  62. "Talking Point: Uncanny sense of deja vu". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  63. "Tasmanian energy crisis: Major industry unlikely to be left in lurch, expert says". ABC News . Australia. 1 April 2016. Retrieved 15 July 2016.
  64. "How Tasmania missed its nine key energy targets". Renew Economy. 14 March 2016. Retrieved 15 July 2016.
  65. "Tasmania battles to keep lights on with cloud-seeding and diesel generators". The Age . 7 March 2016. Retrieved 15 July 2016.
  66. "Talking point: Opportunity knocks for power". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  67. "Hydro's decisions attacked". The Examiner. 19 January 2016. Retrieved 15 July 2016.
  68. "Hydro Tasmania's performance leaks". The Examiner. 19 January 2016. Retrieved 15 July 2016.
  69. "Tasmania's power crisis should galvanise change". The Australian. Retrieved 15 July 2016.
  70. "Tasmanian Labor reveals power blackout plans". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  71. "Hydro dam levels plummet but minister says small households don't need to ration power". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  72. "Tasmanian farmers calm in face of state's energy woes - ABC Rural (Australian Broadcasting Corporation)". Abc.net.au. 7 April 2016. Retrieved 15 July 2016.
  73. "North-west Tasmanian businesses urged to be prepared for potential power cuts". ABC News . Australia. 31 March 2016. Retrieved 15 July 2016.
  74. "Tasmania's power crisis". The Saturday Paper. 30 April 2016. Retrieved 15 July 2016.
  75. "Basslink repair delayed by wild weather, but expected completion date remains mid-June". ABC News . Australia. 3 May 2016. Retrieved 15 July 2016.
  76. "Basslink repairs: UK tests fail to pinpoint cause of cable's December failure". ABC News . Australia. 10 May 2016. Retrieved 15 July 2016.
  77. "Basslink and Groom at odds after tests on faulty cable prove inconclusive". ABC News . Australia. 10 May 2016. Retrieved 15 July 2016.
  78. Langenberg, Adam (9 May 2016). "Boost to energy levels". The Advocate. Retrieved 15 July 2016.
  79. Gurra, Bianca (9 May 2016). "Abnormally high tides and wet week forecast for Tasmania". ABC News . Australia. Retrieved 15 July 2016.
  80. "Tasmania's electricity crisis won't be over until June". Australian Financial Review . Australia. 8 March 2016. Retrieved 15 July 2016.
  81. Gramenz, Emilie (1 April 2016). "Tasmanian energy crisis: More diesel generators fired up to boost power grid". Hydro Tasmania has almost completed rolling out the first tranche of diesel generators to boost generation capacity, as the state's energy crisis deepens. ABC News. Retrieved 1 April 2016.
  82. "Tasmania basslink power crisis: Matthew Groom aims to boost gas, form taskforce to solve energy woes". ABC News . Australia. 8 March 2016. Retrieved 15 July 2016.
  83. Reichert, Corinne (15 April 2016). "Basslink subsea cable repairs rely on 18 days of clear weather". ZDNet.com. Retrieved 15 July 2016.
  84. "Tasmania currently completely renewable | Hydro Tasmania". Hydro.com.au. 12 May 2016. Archived from the original on 16 May 2016. Retrieved 15 July 2016.
  85. "Tasmania's dam catchment areas get a month of rain in a fortnight". ABC News . Australia. 13 May 2016. Retrieved 15 July 2016.
  86. "Tasmanian energy crisis: Labor, Greens want Senate inquiry". ABC News . Australia. 13 March 2016. Retrieved 15 July 2016.
  87. "Tasmanian energy crisis: Senate inquiry to have first hearing mid-April". ABC News . Australia. 2 April 2016. Retrieved 15 July 2016.
  88. "Senate probe into Tasmania's power crisis faces short-circuit by Energy Minister Matthew Groom". The Mercury. 14 April 2016. Retrieved 15 July 2016.
  89. Humphries, Alexandra (3 April 2016). "Dam levels 'risk extreme'". The Examiner. Retrieved 15 July 2016.
  90. "Tasmanian energy crisis: Labor keeps up pressure on State Government, calling for dam level data". ABC News . Australia. 3 April 2016. Retrieved 15 July 2016.
  91. "Tasmanian energy: Greens declare generators an 'environmental crisis' as inquiry begins". ABC News . Australia. 14 April 2016. Retrieved 15 July 2016.
  92. Burgess, Georgie (13 April 2016). "Turbine due for winter repairs". The Examiner. Retrieved 15 July 2016.
  93. "Power crisis: Energy Minister downplays Hydro Tasmania committee documents on Basslink cable failure". ABC News . Australia. 20 April 2016. Retrieved 15 July 2016.
  94. "Tasmanian energy crisis: Treasurer Peter Gutwein refuses to reveal power bill costs". ABC News . Australia. 16 April 2016. Retrieved 15 July 2016.