Data | |
---|---|
Installed capacity (2016) | 13 GW |
Share of fossil energy | 81% |
Share of renewable energy | 19% |
Average electricity use (2003) | 700 kWh per capita |
Consumption by sector (% of total) | |
Residential | 48 (2002) |
Industrial | 29 (2002) |
This article needs to be updated.(February 2020) |
Iraq's electricity generation primarily depends on fossil fuels. In 2021, natural gas was the largest source at 57.3% of the total, followed by oil at 36.7%. Renewable energy, mainly from hydroelectric power, contributed 5.9%. [1] As of 2023 [update] , the 30 gigawatts (GW) of installed capacity cannot meet summer peak demand. [2]
In 2021, the majority of Iraq's electricity consumption was attributed to the residential sector, which used 65.0% of the total. This was followed by the commercial and public services sector at 21.6%, and industrial activities at 11.2%. The smallest share was consumed by the agriculture and forestry sector, accounting for only 2.2%. [1]
According to the United States Department of Energy officials, demand for electricity has been stimulated by a growing economy and a surge in consumer purchases of appliances and electronics.[ obsolete source ] [3] In addition, electricity is subsidized in Iraq, which leads to increased demand. [2]
Due to a weak grid and institutional problems many consumers use small generators or rooftop solar panels. [2]
Electricity entered Iraq for the first time in 1917 where the first electric machine was installed in "Khan Dala" building. [4]
Prior to the Gulf War, the total installed generating capacity was 5,100 MW, which fell to about 2,300 MW after the Gulf War. Approximately 87% of the population had access to electricity. [5] A combination of wars, sanctions, looting and vandalism has however, severely affected the entire power system infrastructure in Iraq.
During the 1991 Gulf War, the electricity system suffered severe damage. Several transmission lines were put out of service, electrical substations were damaged. While some of the damage of the 1991 war was repaired and about 4,500 MW of generating capacity was available in 1999 when Iraq reorganized its electricity sector. The sector was separated from the Ministry of Industry, and the Commission of Electricity (CoE) was established on June 21, 1999. About 4,500 MW of generating capacity became available by the end of 2002, power supply remained insufficient and unreliable. Programmed load shedding and unplanned power outages were frequent. [6]
Although the power system was not significantly affected by the last conflict, capacity was reduced to approximately 3,300 MW by a combination of further breakdowns, lack of spares and interruption of major maintenance cycles. The balance between generation versus demand as reported on 18 July 2004 by the Coalition Project Contracting Office (PCO) (Agency responsible for Coalition projects following the Coalition Provisional Authority (CPA), which completed its mandate as of 30 June 2004) is as follows:
Lack of electricity tends to affect more severely the most vulnerable groups of Iraq's society and increases their morbidity and mortality. Ongoing efforts need to be maintained and new actions to increase electricity supply need to be initiated. In addition, significant delays have been occurring in the reconstruction work that is underway and more security related bottlenecks are expected. Baghdad, a city of 6 million (representing 1/3 of Iraq's population) is still subjected to programmed load shedding on a rolling basis (roughly 3 hrs on 3 hrs off). This is often exacerbated by unforeseen events. For example, on 2 June and 26 July 2004, segments of Baghdad were left without power for 16 and 21 hours, respectively. These events took place in weather that is exceedingly hot. In a country with 39.7% of its population under 15 years, these events do not go unnoticed and the need to add generating capacity to the grid is most pressing. [6]
Prewar Baghdad had electricity 16 to 24 hours per day and was favored for distribution. The remainder of Iraq received 4–8 hours of electricity per day. [7] Post war, Baghdad no longer has priority and therefore both Baghdad and the country as a whole received on average 15.5 hours of electricity per day as of February 2010. [8]
Year | Annual consumption per person | Installed capacity (MW) | Demand | Peak demand |
---|---|---|---|---|
1955 | 50 | |||
1990 | 1,700 kWh | 5100 | ||
2003 | 900 kWh | 3300 | ||
2003 June | 700 kWh | 4470 | 6400 | 7500 |
2006 | 4280 | 8180 | ||
2008 | 6000 | 10000 | ||
2010 | 8000 [9] | 14000 [9] | ||
2016 | 13000 [10] | 21000 [10] |
The 1990 installed capacity of 9,295 MW consisted of 120 power-generating units in various thermal, gas turbine and hydroelectric power stations. Approximately 70% of Iraq's installed power generating capacity was damaged or destroyed during the 1991 Gulf War. All major power stations were damaged and nearly 80% of the gas turbines units were affected. After 1991, only about 50 units were available, with a generation capacity of 2,325 MW. The construction work on three new large thermal power stations at Yousifiya, Al-Shemal and Al-Anbar were stopped, because of the ensuing sanctions. [11]
Station type | No. | Name Plate Rating (MW) | Actual Rating (MW) |
---|---|---|---|
Thermal | 8 | 5,415 | 1,600 |
Gas Turbines | 14 | 2,181 | 650 |
Hydro | 7 | 2,518 | 650 |
Diesel Plant | 3 | 87 | 87 |
Total | 32 | 10,206 | 3,137 |
The majority of the power plants in Iraq were built between the mid-1970s and 1980s, with a few small gas-fired plants commissioned in 2003. The majority of the existing power plants are thermal plants that use crude oil supported by gas-fired and hydro plants. [12]
More import from the electricity sector in Turkey is planned for the 2020s. [16]
These are either small generators for a capacity of a house or large enough to supply a block of houses within the neighborhood supplying power for monthly fees, 14.2 US cent/kWh. [17]
As of June 2014, Iraq spent about US$27 billion between 2003 and 2012 to rehabilitate the power sector after decades of war and sanctions, but widespread corruption in the country has hindered development efforts and power outages continue. [18] In 2005, the World Bank estimated that US$12 billion would be needed for near-term restoration, and the Ministry of Electricity estimated that US$35 billion would be necessary to rebuild the system fully. [19]
This section needs expansion. You can help by adding to it. (May 2023) |
The IMF estimate that in 2020 less than half of supplied electricity was billed and less than a quarter paid for. [32]
The economics of Iraq's electricity sector is characterized by significant challenges related to supply, demand, infrastructure, and financial sustainability. These issues are compounded by the country’s historical context of conflict, sanctions, and ongoing instability.
A significant economic challenge in Iraq’s electricity sector is revenue collection. According to the International Monetary Fund (IMF), in 2020, less than half of the electricity supplied was billed, and less than a quarter of the billed amount was actually paid for. This low rate of revenue collection is partly due to widespread subsidies that keep electricity prices artificially low. These subsidies lead to increased consumption and reduced incentives for efficient usage.
The Iraqi Ministry of Electricity has estimated that around US$35 billion would be necessary to fully rebuild the electricity system. The World Bank has similarly noted that near-term restoration efforts alone would require US$12 billion. Despite significant investments since 2003, including about US$27 billion by 2012, the sector remains underdeveloped due to factors such as corruption, mismanagement, and security issues.
Several international contracts have been signed to enhance Iraq’s electricity infrastructure:
To address inefficiencies, the government has been working on various reforms and reconstruction projects. However, these efforts are often hampered by logistical challenges, security concerns, and the need for substantial financial resources.
Electricity generation is the process of generating electric power from sources of primary energy. For utilities in the electric power industry, it is the stage prior to its delivery to end users or its storage, using for example, the pumped-storage method.
A power station, also referred to as a power plant and sometimes generating station or generating plant, is an industrial facility for the generation of electric power. Power stations are generally connected to an electrical grid.
India is the third largest producer of electricity in the world. During the fiscal year (FY) 2022–23, the total electricity generation in the country was 1,844 TWh, of which 1,618 TWh was generated by utilities.
Peaking power plants, also known as peaker plants, and occasionally just "peakers", are power plants that generally run only when there is a high demand, known as peak demand, for electricity. Because they supply power only occasionally, the power supplied commands a much higher price per kilowatt hour than base load power. Peak load power plants are dispatched in combination with base load power plants, which supply a dependable and consistent amount of electricity, to meet the minimum demand.
Iran possesses significant energy reserves, holding the position of the world's third-largest in proved oil reserves and the second-largest in natural gas reserves as of 2021. At the conclusion of the same year, Iran's share comprised 24% of the oil reserves in the Middle East and 12% of the worldwide total.
The electricity sector in Argentina constitutes the third largest power market in Latin America. It relies mostly on thermal generation and hydropower generation (36%). The prevailing natural gas-fired thermal generation is at risk due to the uncertainty about future gas supply.
Electricity in Pakistan is generated, transmitted and distributed by two vertically integrated public sector companies, first one being Water and Power Development Authority (WAPDA) responsible for the production of hydroelectricity and its supply to the consumers by electricity distribution companies (DISCOS) under the Pakistan Electric Power Company (PEPCO) being the other integrated company. Currently, there are 12 distribution companies and a National Transmission And Dispatch Company (NTDC) which are all in the public sector except Karachi Electric in the city of Karachi and its surrounding areas. There are around 42 independent power producers (IPPs) that contribute significantly in electricity generation in Pakistan.
The electricity sector in Guyana is dominated by Guyana Power and Light (GPL), the state-owned vertically integrated utility. Although the country has a large potential for hydroelectric and bagasse-fueled power generation, most of its 226 MW of installed capacity correspond to thermoelectric diesel-engine driven generators.
As of April 2020, the energy sector in Senegal has an installed capacity of 1431 megawatts (MW). Energy is produced by private operators and sold to the Senelec energy corporation. According to a 2020 report by the International Energy Agency, Senegal had nearly 70% of the country connected to the national grid. Current government strategies for electrification include investments in off-grid solar and connection to the grid.
Energy in Armenia is mostly from natural gas. Armenia has no proven reserves of oil or natural gas and currently imports most of its gas from Russia. The Iran-Armenia Natural Gas Pipeline has the capacity to equal imports from Russia.
The electricity sector of Uruguay has traditionally been based on domestic hydropower along with thermal power plants, and reliant on imports from Argentina and Brazil at times of peak demand. Over the last 10 years, investments in renewable energy sources such as wind power and solar power allowed the country to cover in early 2016 94.5% of its electricity needs with renewable energy sources.
Energy in Jordan describes energy and electricity production, consumption and import in Jordan. Jordan is among the highest in the world in dependency on foreign energy sources, with 92.3% of the country's energy supply being imported.
Energy in Bhutan has been a primary focus of development in the kingdom under its Five-Year Plans. In cooperation with India, Bhutan has undertaken several hydroelectric projects whose output is traded between the countries. Though Bhutan's many hydroelectric plants provide energy far in excess of its needs in the summer, dry winters and increased fuel demand makes the kingdom a marginal net importer of energy from India.
The electricity sector in Taiwan ranges from generation, transmission, distribution and sales of electricity, covering Taiwan island and its offshore islands.
This article describes energy and electricity production, consumption, import and export in Kenya. Kenya's current effective installed electricity capacity is 2,651 megawatts (MW), with peak demand of 1,912 MW, as of November 2019. At that time, demand was rising at a calculated rate of 3.6 percent annually, given that peak demand was 1,770 MW, at the beginning of 2018. Electricity supply is mostly generated by renewable sources with the majority coming from geothermal power and hydroelectricity.
The electricity sector of Kosovo relies on coal-fired power plants and is considered one of the sectors with the greatest potential of development. The inherited issues after the war in Kosovo and the transition period have had an immense effect on the progress of this sector.
Vallur Thermal Power Station is a power plant located in Vallur, Thiruvallur district, India. The power plant is operated by NTPC Tamil Nadu Energy Company Limited, a joint venture between NTPC Limited and TANGEDCO and has three units with 500 MW each.
Watford Power Station was a coal-fired power station situated in Watford's Riverside area. The station was built by the Watford Corporation Electricity Department starting with the installation of cables in 1899 with completion around 1900, near the banks of the River Colne. A gas turbine power station was commissioned in 1980.
Yerevan Thermal Power Plant, is a thermal power plant located about 10 kilometres (6.2 mi) from Yerevan, Armenia. An older, obsolete plant was fueled by natural gas and fuel oil, while the new combined-cycle plant is powered by natural gas and has a capacity of 242 megawatts. It produces a quarter of the country's electricity and is responsible for seasonal electricity swaps with Iran. The director general of the power plant is Hovakim Hovhannisyan.