Livraga derailment | |
---|---|
Details | |
Date | 6 February 2020 |
Location | Livraga, Lombardy |
Coordinates | 45°11′20″N9°34′02″E / 45.188820°N 9.567314°E |
Country | Italy |
Line | Milan–Bologna high-speed railway |
Operator | Trenitalia |
Service | Milan-Salerno |
Incident type | Derailment |
Cause | Incorrect switch position |
Statistics | |
Trains | 1 |
Passengers | 28 |
Crew | 5 |
Deaths | 2 |
Injured | 31 |
The Livraga derailment is the only railway accident to date on the Italian high speed rail network. [1] It took place on 6 February 2020 when a high-speed train derailed at Livraga, Lombardy, Italy. Two people died and 31 were injured.
Train 9595 was the first southbound service of any day in Italy's high speed railways, scheduled to start from Milan at 5:10 and to arrive in Salerno at 11:27. [2] On 6 February 2020, the train, run by Frecciarossa 1000 trainset no. 21, entered the Milan-Bologna high-speed railway and reached its top speed as usual. Not long after departure it reached the "posto di movimento Livraga", a site equipped with passing loops where RFI maintenance vehicles are parked named after the nearby town of Livraga.
For reasons under investigation, on that morning point number 5 (which connects the main line to the passing loop) was unknowingly in diverted position. [3] At 05:34 local time (04:34 UTC), [4] [5] [6] upon passing on point number 5, the train was unexpectedly diverted to the passing loop; since the train was travelling at about 300 km/h (190 mph), while the point was designed to be traversed in diverted position at no more than 100 km/h (62 mph), the train suddenly derailed.
The coupling between coach 1 and 2 broke; the first coach spun round through 180 degrees, collided with some maintenance vehicles, and finally came to rest overturned near a railway building [7] (one of whose walls was destroyed by the coach's bogie, which had detached). The remaining seven coaches, instead, remained upright and kept going straight with their wheels on the track ballast, until they stopped after a few hundred meters.
Of the 33 people on the train: five staff and 28 passengers, only the two drivers died. [8] [7] [9]
Two people were seriously injured. [10] Railway workers in Italy called a two-hour strike starting at midday, 7 February 2020. [6]
An investigation into the derailment was opened. [7] The Agenzia Nazionale per la Sicurezza delle Ferrovie is responsible for investigating railway accidents in Italy.
Point number five[ clarification needed ] had been replaced the day before the crash. [6]
Investigators reported that the accident was caused by a set of junction points being in the reverse position but were reported to the signalling system as in the normal – i.e. straight – position. Maintenance works occurred that night, and as a consequence of the inspection, points were found faulty.
Unable to replace them overnight, maintenance workers followed a temporary override procedure, which is allowed to take place in these exceptional circumstances.
Maintenance workers claimed that they manually placed the faulty point to the straight position, but disconnected its network connection and its link to the safety signalling system (ETCS L2) because of their faulty status.
As normal part of such procedure, workers reported (according to evidence) that the point had been forcibly put in the straight position and taken offline. The signalling system used this information to report no anomalies on the line, and as a consequence the train was not commanded to reduce speed.
Under normal circumstances (i.e. if the junction was really straight), all services on the line could have continued their journeys at full speed. In this case, the first train on schedule hit the junction at 292km/h causing the derailment. [11]
On 13 February, the head of rail transport security agency ANSF stated that faulty cabling in switching equipment supplied by Alstom may have been a factor in the accident. [12] All 11 points owned by RFI and produced within the same lot were put out of order. [13]
High-speed rail (HSR) is a type of rail transport network utilising trains that run significantly faster than those of traditional rail, using an integrated system of specialised rolling stock and dedicated tracks. While there is no single definition or standard that applies worldwide, lines built to handle speeds above 250 km/h (155 mph) or upgraded lines in excess of 200 km/h (125 mph) are generally considered to be high-speed.
The Italian railway system is one of the most important parts of the infrastructure of Italy, with a total length of 24,567 km (15,265 mi) of which active lines are 16,832 km (10,459 mi). The network has recently grown with the construction of the new high-speed rail network. Italy is a member of the International Union of Railways (UIC). The UIC Country Code for Italy is 83.
Hitachi Rail Italy S.p.A. was a multinational rolling stock manufacturer company based in Pistoia, Italy. Formerly AnsaldoBreda S.p.A., a subsidiary of state-owned Finmeccanica, the company was sold in 2015 to Hitachi Rail of Japan. After the deal was finalized, the current name was adapted in November 2015 to reflect the new ownership.
A wrong-side failure describes a failure condition in a piece of railway signalling equipment that results in an unsafe state. A typical example would be a signal showing a 'proceed' aspect when it should be showing a 'stop' or 'danger' aspect, resulting in a "false clear".
Eurostar Italia was the brand name given to high-speed trains operated by Trenitalia in Italy. The brand was discontinued and replaced with Le Frecce in December 2012.
Roma Tiburtina is the second largest railway station in Rome, after Roma Termini. Located in the north-eastern part of the city, it was originally constructed during the 1860s as a terminal station, and redeveloped during the 2010's. The station is connected to Rome's Metro line B at Tiburtina metro station, as well as to local bus services via an adjacent bus depot while private vehicle users are provided with more than 100,000 spaces across multiple on-site car parks.
High-speed rail in Italy consists of two lines connecting most of the country's major cities. The first line connects Turin to Salerno via Milan, Bologna, Florence, Rome and Naples, the second runs from Turin to Venice via Milan and Verona, and is under construction in parts. Trains are operated with a top speed of 300 km/h (190 mph).
The Milan–Bologna high-speed railway is a railway line that links the cities of Milan and Bologna, part of the Italian high-speed rail network. It runs parallel to the historical north–south railway between Milan and Bologna, which itself follows the ancient Roman Road, the Via Aemilia. The new railway follows the Autostrada A1 closely for much of its length. The new line allows faster traffic to run separated and increase the overall railway capacity between the two cities.
Torino Porta Susa is a railway station in Turin, northern Italy; it is the second busiest mainline station in the city, after Torino Porta Nuova. It is located in Corso Inghilterra.
Frecciarossa is a high-speed train of the Italian national train operator, Trenitalia, as well as a member of the train category Le Frecce. The name was introduced in 2008 after it had previously been known as Eurostar Italia. Frecciarossa trains operate at speeds of up to 300 km/h (190 mph). Frecciarossa is the premier service of Trenitalia and competes with italo, operated by Nuovo Trasporto Viaggiatori. Trenitalia also operates the sister brands Frecciargento and Frecciabianca for slower services.
Milano Porta Garibaldi is a major railway station in the Italian city of Milan, located just to the north of the neighbourhood known as Porta Garibaldi. Porta Garibaldi is the city's main station for commuter traffic with 25 million passengers annually, although it is second to Centrale station considering total passenger traffic. The station is located on Piazza Sigmund Freud.
Modena railway station is a railway station serving the city of Modena, in the region of Emilia-Romagna, northern Italy. The station opened in 1859 and is located on the Milan–Bologna railway, Verona–Modena railway and Modena–Sassuolo railway. The train services are operated by Trenitalia and Ferrovie Emilia Romagna.
ETR 500 is a family of Italian high-speed trains built by AnsaldoBreda and introduced in 1993.
Pioltello-Limito is a railway station in Pioltello, Lombardy, Italy. The station opened in 1846 and is located on the Milan–Venice railway. The train services are operated by Trenord.
Carnate-Usmate railway station is a railway station in Italy. It is located at the cross of the Lecco–Milan railway with the Seregno–Bergamo railway. It serves the municipalities of Carnate and Usmate Velate.
The Frecciarossa 1000 is a high-speed train operated by Italian state railway operator Trenitalia and the private Spanish high-speed rail operator Iryo. It was co-developed as a joint venture between Italian rail manufacturer Hitachi Rail Italy and multinational conglomerate Alstom. Both design and production work were divided between the two partner companies.
On 25 January 2018, a commuter train operated by Trenord derailed in Pioltello when two of its carriages came off the track en route to Milan. The incident left three women dead and more than 100 people injured, of whom 46 needed medical assistance in hospital. Five of them were in critical condition.
The Carnate derailment occurred in Lombardy, Italy on 19 August 2020 when a passenger train ran away from Paderno-Robbiate station [it] and was derailed at Carnate-Usmate station.
The Milan–Paris Frecciarossa is a high-speed passenger railway service running between Milano Centrale and Paris Gare de Lyon, marketed under Trenitalia's Frecciarossa brand.