Murray Basin Rail Project

Last updated

The Murray Basin Rail Project is a major railway project in the north-west of Victoria, Australia. The project includes the conversion of a substantial portion of the Victorian freight rail network from the historical broad gauge to the standard gauge used in other parts of Australia, and the upgrading of track to enable higher axle loads for more efficient intrastate freight transfer.

Contents

The project is being delivered by V/Line in its role as infrastructure manager of the Victorian rail network, under the direction of Public Transport Victoria, and is jointly funded by the Victorian and Australian governments. Construction commenced in 2016 and was expected to be complete by late 2018; however, by mid-2018 the project was incomplete and its future in doubt.

Background

Prior to the Federation of Australia in 1901, the colonial governments of Victoria, New South Wales, South Australia, and the other Australian colonies were responsible for development of railway networks surrounding their nascent capital cities. Due to political pressures and disagreements over the technical advantages of various track specifications, a number of different gauges were adopted. In particular, Victoria adopted the 1,600 mm (5 ft 3 in) Victorian broad gauge , New South Wales 4 ft 8+12 in (1,435 mm) standard gauge and South Australia a combination of broad gauge and 3 ft 6 in (1,067 mm) narrow gauge. [1]

Following a Royal Commission in 1921 which recommended the adoption of standard gauge across the country, the first Victorian line to be converted was the North East line in 1962 between Melbourne and Albury, eliminating the break of gauge at the state border and allowing trains to run between Sydney and Melbourne for the first time. [2] Then, in 1995, the Melbourne–Adelaide railway was standardised, meaning that all capital cities were linked by a single gauge for the first time in Australia's history. Over the following years, new private rail freight operators invested in new interstate services due to the reduced running costs of a single-gauge network. [3]

In May 2001, the state government under Premier Steve Bracks promised the standardisation of 13 freight lines, incorporating some 2,000 km (1,200 mi) of track. The rationale offered for the Rail Gauge Standardisation Project was that it would reduce freight costs, improve rail's mode share for intrastate freight, and improve competition between ports. However, the private lessees of the freight network over the following years, Freight Australia and its successor Pacific National, failed to commit to the project, and by 2005, it was largely abandoned. [4] The government announced in May 2007 that the entire state's network would be bought back from Pacific National, with its ownership moving to VicTrack and management responsibility passing to V/Line. Industry groups expressed hope that the purchase would enable upgrade works to proceed on the north-west rail network. [5]

By 2014, approximately 2 million metric tons (2,000,000 long tons) of grain was exported from the Murray Basin annually, in addition to 1,000,000–1,500,000 t (980,000–1,480,000 long tons) of mineral sands and around 13,000 containers of other produce. [6]

In the May prior to the 2014 Victorian election, the Liberal government of Premier Denis Napthine announced the Murray Basin Rail Project, including the standardisation of most rail lines in the state's north-west. The announcement included future plans for the extension of the Piangil railway line to join the East-west rail corridor near Mildura and the return of passenger services to Mildura; [7] some days later, government ministers downplayed the potential for passenger rail following the upgrade. [8] The government expected that the MBRP would be partially financed by the sale of the Rural Finance Corporation, a state-backed investment bank, to Bendigo and Adelaide Bank. [9]

After the election, in August 2015, the new Labor government of Premier Daniel Andrews announced that they would recommit to the MBRP, with a particular focus on freight, at a cost of $416 million. [10] The Commonwealth government was initially reluctant to fund the project, as it related to track not managed by the federally-owned Australian Rail Track Corporation, [11] but committed to a contribution of half the project cost in April 2016. [12]

Scope of works

The two main elements of the MBRP are the expansion of the Victorian standard gauge network, and the improvement of line capacity via increased axle loads, both of which are intended to facilitate more efficient intrastate rail connections. The rationale for the project is centred on improved access to the Victorian ports of Portland, Geelong and Melbourne, and encouraging freight users such as Iluka Resources at Hamilton to retain access to the Victorian network rather than economising with existing standard gauge connections. [13]

However, the predominantly broad-gauge passenger network centred on Melbourne's Southern Cross railway station complicates the total standardisation of the rail network. [14] The MBRP includes several sections of dual gauge rail enabling access for both broad- and standard-gauge services. [15]

The Mildura, Sea Lake, Manangatang and Murrayville lines will be fully gauge converted between Maryborough and their respective termini. Further, the defunct standard gauge link between Ararat and Maryborough will be repaired and reopened to traffic. The entire length of the Geelong–Ballarat railway line and the Mildura line between Maryborough and Ballarat will be converted to dual gauge to facilitate standard-gauge access to the Port of Geelong. [15]

In addition to the standardisation, maximum axle loads on all lines will be increased to at least 21 t (21 long tons), with the exception of the Murrayville line, which will be upgraded to a 19 t (19 long tons) axle load. According to the project documentation, this will result in an increase in the payload per train of some 300–400 t (300–390 long tons). [16]

Construction timeline

Stage 1

Stage 1 works commenced in February 2015, consisting of sleeper replacement and regular maintenance on the Mildura line. Structures such as bridges and culverts were inspected, and rail was continuously welded to increase the speed limit on the track section to 80 km/h (50 mph). [17]

175,000 concrete sleepers and 3,400 m (11,200 ft) of new rail were laid during stage 1. [18] Minister for Public Transport Jacinta Allan announced its completion on 5 September 2016. [19]

Stage 2

McConnell Dowell and Martinus Rail were announced as contractors for stages 2, 3 and 4 of the project on 26 June 2017. The contractors established a project office in Maryborough for the duration of their works. [18] The Mildura and Murrayville lines closed north of Dunolly on 7 August for standardisation work to commence, with the Sea Lake and Manangatang lines remaining open for broad gauge grain traffic. [20] The scope of stage 2 also included the reopening of the Maryborough–Ararat line. [18]

On 23 October 2017, a worker on the project was killed after being crushed between a roller and trailer while loading the trailer near Mildura. [21] The Rail Tram & Bus Union and Construction, Forestry, Mining and Energy Union accused V/Line and its contractors of unsafe work practices on the project; V/Line denied the allegations and the state government announced a full coronial inquiry into the death. [22]

Test trains on the Maryborough–Ararat section began running towards the end of November 2017. [23] Towards the conclusion of Stage 2 works in mid-January 2018, warnings to motorists of the imminent rail traffic were placed on roads crossing the Maryborough–Ararat line. 35 level crossings on the newly reopened line were provided with boom gates to protect road traffic. [24] On 29 January 2018, an official ceremony was held to reopen the line, with a single 830 class locomotive running past state and federal representatives near Avoca. [25]

With the Ararat–Maryborough line open, work continued on the Mildura standardisation, but the originally announced opening date of January 2018 was delayed because of hot weather and fire danger restricting the use of welding and grinding equipment. [26]

A gradual reopening for the Mildura line began on 14 February 2018, with the first trains running to Birchip. [27] This was followed by Pacific National's Fruit Flyer running to Merbein on 22 February 2018. [28] The same train returned with its load to the Port of Melbourne, in the process also becoming the first commercial train to operate over the Ararat–Maryborough section since its restoration. [29]

Further stages

Stage 3 was to include the standardisation of the Sea Lake and Manangatang lines, and was intended to commence in 2018 when stage 2 works were complete and the Mildura line had reopened to traffic. [20] [30] Stage 4 works were to encompass the conversion of the Geelong–Ballarat line in its entirety to dual gauge, [15] [30] while Stage 5 would have involved the conversion of the Maryborough line to dual gauge north of Ballarat. [15] [30]

However, in June 2018, state opposition parties claimed that work had ceased on the project entirely. In response, the government announced that V/Line was reconsidering the staging of the project following feedback from freight rail operators. [31] Later that month, The Weekly Times reported that the project had encountered serious issues, including poor-quality construction on the Ararat–Maryborough and Mildura lines, and, as a result, the state government had asked the newly formed Rail Projects Victoria (RPV) to take over delivery from V/Line and was attempting to end the contract with McConnell Dowell Martinus. However, the government denied the reports, claiming instead that V/Line had taken over management of the works from the contractor and would co-operate with RPV. [32] At the end of June 2018, severe speed restrictions continued to be imposed on the Ararat–Maryborough line, and the lack of a connection at Ararat to the interstate mainline to the south was severely limiting the capacity of the junction. [33]

The state government announced a new package of works, described as the Freight–Passenger Rail Separation Project (FPRSP), to augment the remaining stages of the MBRP at an additional cost of $130 million. The major components of the FPRSP revealed included augmentation of tracks at Ballarat and improved segregation of freight and passenger tracks through the station precinct, as well as the conversion of the Ballarat–Maryborough line to dual gauge originally described as Stage 4 of the MBRP. [34]

Reception and analysis

The project was largely welcomed by regional communities and the agriculture and resources industries. The Victorian Farmers Federation (VFF) called the MBRP a solution to the "foolish" break of gauge situation and suggested that the conversion had the potential to encourage further rail investment from grain producers and transporters. [35] Wakefield Transport, one such operator, noted that the project in totality would enable a round trip to be completed from grain producing regions to the Port of Geelong in less than 24 hours, substantially decreasing transport costs. [36] On this basis, Infrastructure Australia's review of the business case for the MBRP in early 2017 found that the project would likely deliver economic benefits in excess of its costs. [37]

The 2016–17 grain harvest season saw a 70% increase in rail traffic year-on-year, which V/Line CEO James Pinder attributed to the increased capacity provided by stage 1 of the project. The VFF subsequently criticised the lack of progress on the remainder of the project. [38]

However, the Central Goldfields Shire Council expressed concern that the dual gauge section between Ballarat and Maryborough would adversely affect the existing passenger service, noting that the dual gauge setup would impose a speed restriction on the broad gauge passenger traffic. [39]

See also

Related Research Articles

<span class="mw-page-title-main">Sunshine railway station, Melbourne</span> Railway station in Melbourne, Australia

Sunshine railway station is located on the Sunbury line in Victoria, Australia. Originally named Braybrook Junction for the convergence of the major railways from central Melbourne to Ballarat and Bendigo, it was renamed when the suburb of Sunshine, which it serves, took its name from the nearby Sunshine Harvester Works. With the expansion of the railway network in Melbourne's west, Sunshine grew in importance, with cross-suburban goods routes constructed to Newport and from the adjacent Albion to Jacana line. From the mid-20th century, it became an interchange for the main interstate routes to South Australia and New South Wales, when the through line from Melbourne to Sydney was completed, although the main line to Adelaide was later diverted. In the early 21st century, the station was demolished and reconstructed to serve the diversion of the main passenger route to Geelong and beyond. It has been identified as a possible route for a future line to Melbourne Airport and as an interchange for the orbital Suburban Rail Loop.

<span class="mw-page-title-main">V/Line</span> Railway company in Victoria, Australia

V/Line is a statutory authority that operates regional passenger train and coach services in Victoria, Australia. It provides passenger train services on five commuter lines and eight long-distance routes from its major hub at Southern Cross railway station in Melbourne. It also provides bus services across Victoria and into New South Wales, the Australian Capital Territory and South Australia. In addition, V/Line is responsible for the maintenance of much of the Victorian freight and passenger rail network outside of the areas managed by Metro Trains Melbourne and the Australian Rail Track Corporation.

<span class="mw-page-title-main">Rail transport in Victoria</span> Overview of rail transport in Victoria, Australia

Rail transport in the Australian state of Victoria is provided by a number of railway operators who operate over the government-owned railway lines. The network consists of 2,357 km of Victorian broad gauge lines, and 1,912 km of standard gauge freight and interstate lines; the latter increasing with gauge conversion of the former. Historically, a few experimental 762 mm gauge lines were built, along with various private logging, mining and industrial railways. The rail network radiates from the state capital, Melbourne, with main interstate links to Sydney and to Adelaide, as well as major lines running to regional centres, upgraded as part of the Regional Fast Rail project.

<span class="mw-page-title-main">Ballarat railway station</span> Railway station in Victoria, Australia

Ballarat railway station is located on the Serviceton line in Victoria, Australia. It serves the city of Ballarat, and opened on 11 April 1862 as Ballarat West. It was renamed Ballarat in 1865.

The Serviceton railway line is part of the Melbourne–Adelaide rail corridor. It serves the west of Victoria, linking the state capital of Melbourne to the cities of Ballarat and Ararat. It once extended to the disputed South Australian border as part of the Melbourne–Adelaide railway. The former broad-gauge track was replaced in 1995 by the 1435 mm Western standard gauge line.

<span class="mw-page-title-main">Ararat railway station</span> Railway station in Victoria, Australia

Ararat railway station is located on the Serviceton and Western standard gauge lines in Victoria, Australia. It serves the town of Ararat, and opened on 7 April 1875.

<span class="mw-page-title-main">Maryborough railway station, Victoria</span> Railway station in Victoria, Australia

Maryborough railway station is located on the Mildura line in Victoria, Australia. It serves the town of Maryborough, and it opened on 7 July 1874.

The Mildura railway line is a heavy rail line in northwestern Victoria, Australia. The line runs from Yelta station to Ballarat station via the settlements of Mildura, Ouyen and Maryborough in an approximate south-southeasterly direction. Initial sections of the line opened from Ballarat in 1874 and the line reached Mildura in 1903.

<span class="mw-page-title-main">Bung Bong</span> Locality in Victoria, Australia

Bung Bong is a locality in Victoria between the towns of Avoca and Maryborough. The locality is divided, with the Western section in the Pyrenees Shire and the Eastern section in Shire of Central Goldfields. The Bet Bet Creek runs towards the north through the middle of the locality and then into the Loddon River. Bung Bong is located on the Pyrenees Highway.

The Western standard gauge railway line is a standard-gauge railway line in western Victoria, Australia. Completed in 1995, it forms part of the Melbourne–Adelaide rail corridor and serves as the principal interstate rail link between Victoria and the western states. The line replaced a number of former broad gauge routes which were gauge converted, and today sees both intrastate and interstate freight traffic, as well as the twice weekly The Overland passenger service. Major towns on the route include Geelong, Ararat, Horsham and Dimboola.

<span class="mw-page-title-main">Robinvale railway line</span>

The Robinvale railway line is a freight only country railway line in north-western Victoria, Australia. The line branches from the Mildura line at Dunolly, and at Inglewood the Eaglehawk – Inglewood line connects with the Piangil line outside Bendigo. The parallel Kulwin line junctions from the Robinvale line at Korong Vale then continues northward.

The Geelong–Ballarat railway line is a broad-gauge railway in western Victoria, Australia between the cities of Geelong and Ballarat. Towns on the route include Bannockburn, Lethbridge, Meredith, Elaine and Lal Lal. Major traffic includes general freight from the Mildura line, and grain.

<span class="mw-page-title-main">Ballarat V/Line rail service</span>

The Ballarat V/Line rail service is a regional passenger rail service operated by V/Line in Victoria, Australia. It serves passengers between state capital Melbourne and the regional city of Ballarat. Beyond Ballarat, it changes name to the Ararat railway line and the Maryborough railway line.

<span class="mw-page-title-main">Avoca railway station</span> Former railway station in Victoria, Australia

Avoca railway station is a railway station on the Avoca line in the town of Avoca, Victoria. It was first opened on Saturday, 21 October 1876 however was closed for gauge conversion on Friday, 14 April 1995. Again the railway was opened on Sunday, 28 April 1995, then the line was booked out of service on Friday, 21 January 2005. Although no longer in use, Avoca retains a brick station building, platform and goods shed.

<span class="mw-page-title-main">Avoca railway line</span>

The Maryborough–Avoca–Ararat railway is a railway line in western Victoria, Australia. It is one of the few railway lines in the state to have been closed and then reopened. Today it is a standard gauge branch line connecting the Western SG with Bung Bong (ballast) and Dunolly (grain), running through Maryborough station.

The Moolort Line is a cross-country railway line which connects Maryborough and Castlemaine in Victoria, Australia. The line, now defunct, starts in Castlemaine, passes through Campbells Creek, Yapeen, Guildford, Strangways, Newstead, Moolort, and Carisbrook, before joining the Mildura line at Maryborough.

<span class="mw-page-title-main">Elmhurst railway station</span> Former railway station in Victoria, Australia

The disused Elmhurst railway station was a rail station in Elmhurst, Victoria, Australia on the Avoca railway line.

Ben Nevis railway station is an abandoned station on the Avoca railway line, a railway line running from Ararat to Avoca and onto Maryborough in the Australian state of Victoria. It also acted as the terminus of the abandoned Navarre railway line to Navarre, a community in the Wimmera region of Victoria, which was closed in 1954.

References

  1. Mills, John (July 2006). The Myth of the Standard Gauge: Rail Gauge Choice in Australia 1850 – 1901 (PDF) (PhD thesis). Griffith University. p. 187.
  2. "Transport, Communication and Travel". Year Book Australia, 1967 (PDF). Australian Bureau of Statistics. 1967. pp. 440–445.
  3. Carter, Mark (27 July 2015). "20 years on; A pair of interstate milestones – Rail Express". Rail Express. Retrieved 19 January 2018.
  4. "Rail Gauge Standardisation Project". Results of special audits and other investigations (PDF). Auditor General Victoria. August 2006. pp. 95–102. Retrieved 19 January 2018.
  5. Kingsley, Terri-Anne (16 April 2007). "Rail buyback announced". ABC Local. Retrieved 19 January 2018.
  6. Murray Basin Rail Project (PDF). Public Transport Victoria. 2014. p. 2. Retrieved 19 January 2018.
  7. "Victorian government outlines rail modernisation plans". The Age. Australian Associated Press. 3 May 2014. Retrieved 19 January 2018.
  8. King, Charlotte (13 May 2014). "Confused messages over passenger rail". ABC Mildura-Swan Hill. Retrieved 19 January 2018.
  9. "Victorian Government sells Rural Finance Corporation". ABC News. 5 May 2014. Retrieved 19 January 2018.
  10. Pollock, Michael (17 August 2015). "Murray Basin project tracking". The Courier. Retrieved 19 January 2018.
  11. Beilharz, Nikolai (26 August 2015). "Victorian rail project faces funding challenge". ABC Rural. Retrieved 19 January 2018.
  12. Brown, Emma (8 April 2016). "Federal Government announces $220 million for Murray Basin Rail project". ABC Rural. Retrieved 19 January 2018.
  13. PTV 2014, p. 3.
  14. "Warning on Victoria fast rail sleeper choice – Rail Express". Rail Express. 3 March 2003. Retrieved 24 January 2018.
  15. 1 2 3 4 PTV 2014, p. 4.
  16. PTV 2014, p. 5.
  17. "Murray Basin Rail Project, Victoria - Railway Technology". Railway Technology. Retrieved 24 January 2018.
  18. 1 2 3 "Murray Basin gauge conversion contract awarded". Railway Gazette. 27 June 2017. Retrieved 19 January 2018.
  19. Probert, Oliver. "Murray Basin rail works progressing". Rail Express. Retrieved 27 January 2018.
  20. 1 2 Probert, Oliver (1 August 2017). "Murray Basin upgrades begin". Rail Express. Retrieved 26 January 2018.
  21. Carey, Adam (24 October 2017). "Rail project worker crushed to death in near Mildura". The Age. Retrieved 19 January 2018.
  22. Jacks, Timna (26 October 2017). "Rail death followed warnings about poor safety, union claims". The Age. Retrieved 19 January 2018.
  23. Martinich, Rex (20 November 2017). "Major rail project opens Ararat-Maryborough rail line | Photos". The Ararat Advertiser. Retrieved 29 January 2018.
  24. Steed, Lachy (16 January 2018). "Freight trains set to return by the end of the month". The Maryborough District Advertiser. Retrieved 19 January 2018.
  25. Martinich, Rex (29 January 2018). "Ararat rail line reopened after years of decay". The Ararat Advertiser. Retrieved 29 January 2018.
  26. DiFabrizio, Michael (3 February 2018). "Opening of freight line connection delayed". Sunraysia Daily. Retrieved 8 February 2018.
  27. DiFabrizio, Michael (14 February 2018). "Birchip stretch in train". Sunraysia Daily. Retrieved 18 February 2018.
  28. Cavallaro, Natalie (28 February 2018). "Freight gets back on the rails". Sunraysia Daily. Retrieved 27 February 2018.
  29. "First freight train for restored Maryborough-Ararat line | Videos". The Ararat Advertiser. 28 February 2018.
  30. 1 2 3 "Murray Basin Rail Project". V/Line Corporation. Retrieved 26 January 2018.
  31. Cavallaro, Natalie (30 May 2018). "Nationals slam Labor for putting brakes on Murray Basin Rail Project". Sunraysia Daily. Retrieved 1 June 2018.
  32. Hunt, Peter (15 June 2018). "Murray Basin Rail upgrade taken out of V/Line's hands". The Weekly Times. Retrieved 23 June 2018.
  33. Martinich, Rex (28 June 2018). "Push for new Ararat rail projects but current work hit by complaints". The Ararat Advertiser. Retrieved 19 February 2019.
  34. Wrigley, Brendan (27 June 2018). "State to splash $130 million to separate passenger and freight trains in town". The Courier. Retrieved 19 February 2019.
  35. Hinchliffe, Joseph (17 August 2015). "$416 million freight rail upgrade". Bendigo Advertiser. Retrieved 26 January 2018.
  36. Hollingworth, Kellie; Peck, Damien (2 August 2017). "Murray Basin rail upgrades aid farmers, industry". ABC Rural. Retrieved 26 January 2018.
  37. "Infrastructure Australia positively assesses Melbourne Metro and Murray Basin Rail business cases". Infrastructure Australia. 20 January 2017. Retrieved 27 January 2018.
  38. Miller, Andrew (13 March 2017). "V/Line defends its Murray rail progress". Stock & Land. Retrieved 26 January 2018.
  39. Pollock, Michael (21 December 2016). "Push for Murray Basin track change". The Courier. Retrieved 26 January 2018.