Victorian Big Battery

Last updated

Victorian Big Battery
Victorian Big Battery
Country
  • Australia
Location
Coordinates 38°02′S144°17′E / 38.04°S 144.29°E / -38.04; 144.29
StatusOperational
Commission date
  • 8 December 2021
Owner(s)
Operator(s)
Power generation
Nameplate capacity
  • 300 MW
Storage capacity
  • 450 MW h
External links
Website victorianbigbattery.com.au

The Victorian Big Battery is a grid-connected battery electricity storage facility adjacent to the Moorabool Terminal Station (substation) near Geelong in Victoria, Australia. The battery provides 450 MWh of storage and can discharge at 300 MW. It surpasses the 250 MWh Gateway Energy Storage in California, United States. [1] As of December 2021, the project is the largest lithium-ion battery in the Southern Hemisphere. [2]

Contents

The Victorian Big Battery is owned and operated by French renewable energy producer Neoen. Funding of $160 million was provided by the Clean Energy Finance Corporation, [3] [4] the Australian government's green bank.

Construction started at the beginning of 2021. It commenced operations on 8 December 2021. [5] It uses Tesla Megapack storage units, an electric accumulator designed specifically for large-scale projects.

The battery aims to prevent blackouts during periods of network instability by providing grid support services, capturing and storing excess energy from sources such as wind farms, and feeding it into the grid during peak periods or outages to support Victoria's electricity supply. [6] The battery will store enough energy to power more than half a million Victorian homes for an hour, or the homes of a population equivalent of Geelong (the city where it is situated) for two hours.

Construction

Construction began in January 2021. The battery was scheduled to be commissioned in the Australian summer period 2021-2022 and has been in operation since December 8, 2021. For Neoen's battery, the EPC (Engineering, Procurement and Construction) contractor is Tesla, using UGL as the prime contractor. The connection assets are being provided by AusNet Services, with Downer as the prime contractor.

The storage unit uses 212 Tesla Megapacks, each with a capacity of 3 MWh. This will be the first time Megapacks have been used in a facility of this scale in Australia.

The battery is being built within AusNet's Moorabool Power Terminal in close proximity to the 500 KV high voltage line so that power can be sent quickly to where it is needed.

Construction of the battery was supported by a $160 million loan from the Clean Energy Finance Corporation, an agency owned by the Australian federal government.

Services

Following a tender issued by the Victorian Government in 2020, Neoen was awarded a contract by the Australian Energy Market Operator to reserve approximately 80% of its capacity during the summer months to provide 250 MW of System Integrity Protection Scheme (SIPS) services. This will increase the transfer capacity on the Victorian/New South Wales interconnector during peak consumption periods and reduce the risk of unplanned power outages.

The remaining 50 MW of the battery can be commercially deployed in the market by the operator. Outside the summer period, the battery, with a total capacity of 300 MW, will be operated commercially.

With the services provided by the battery, average industrial electricity consumers could save as much as $280,000 per year on their bills. The Portland aluminium smelter could see its bills drop by as much as $1 million per year.[ citation needed ]

The battery is tested for grid inertia with 'grid forming' abilities. [7]

Fire

During the initial testing of the energy storage system on 30 July 2021, a fire broke out in one of the Tesla Megapack modules and destroyed two battery units while the fire was left to burn itself out, as recommended. No injuries were reported. The battery pack had been placed into offline mode before the fire, and this had also isolated the monitoring and management systems. The site was disconnected from the grid, with no impact on the power supply. The system was isolated, and energisation testing was not permitted to resume until 29 September 2021. The cause of the fire was determined to have been a leak of cooling fluid that short-circuited cells to thermal runaway. Subsequent configuration changes mean that the monitoring remains active on offline battery packs. [8] [9]

Related Research Articles

<span class="mw-page-title-main">Loy Yang Power Station</span> Coal fired power station in Victoria, Australia

The Loy Yang Power Station is a brown coal- fired thermal power station located on the outskirts of the city of Traralgon, in south-eastern Victoria, Australia. It consists of two sections, known as Loy Yang A and Loy Yang B. Both Loy Yang A and B are supplied by the Loy Yang brown coal mine. The Loy Yang power stations are located in the brown coal rich Latrobe Valley, along with the Yallourn Power Station.

<span class="mw-page-title-main">Grid energy storage</span> Large scale electricity supply management

Grid energy storage is a collection of methods used for energy storage on a large scale within an electrical power grid. Electrical energy is stored during times when electricity is plentiful and inexpensive or when demand is low, and later returned to the grid when demand is high, and electricity prices tend to be higher.

<span class="mw-page-title-main">Peaking power plant</span> Reserved for high demand times

Peaking power plants, also known as peaker plants, and occasionally just "peakers", are power plants that generally run only when there is a high demand, known as peak demand, for electricity. Because they supply power only occasionally, the power supplied commands a much higher price per kilowatt hour than base load power. Peak load power plants are dispatched in combination with base load power plants, which supply a dependable and consistent amount of electricity, to meet the minimum demand.

<span class="mw-page-title-main">Moss Landing Power Plant</span> Natural gas-fired power station in Moss Landing, California

The Moss Landing Power Plant is a natural gas powered electricity generation plant located in Moss Landing, California, United States, at the midpoint of Monterey Bay. Its large stacks are landmarks, visible throughout the Monterey Bay Area. The plant is owned and operated by Houston-based Dynegy and currently has a generation capacity of 1020 MW (net) from its two combined cycle generation units. It was once the largest power plant in the state of California, with a generation capacity of 2560 MW, before its two large supercritical steam units were retired in 2016.

A virtual power plant (VPP) is a system that integrates multiple, possibly heterogeneous, power sources to provide grid power. A VPP typically sells its output to an electric utility. VPPs allow energy resources that are individually too small to be of interest to a utility to aggregate and market their power. As of 2024, VPPs operated in the United States, Europe, and Australia.

<span class="mw-page-title-main">Stanwell Power Station</span> Power station in Queensland, Australia

Stanwell Power Station is a government-owned coal-fired power generation station located in Stanwell, 23 kilometres (14 mi) south-west of Rockhampton, Queensland, Australia. At the time of construction, it was one of the largest industrial developments undertaken in Queensland. With a capacity to generate 1,445 megawatts (MW), Stanwell Power Station supplies electricity for distribution to customers via the state's high voltage electricity grid.

<span class="mw-page-title-main">Tarong Power Station</span> Coal-fired power station in Australia

The Tarong Power Station is a coal fired power station located on a 1,500 hectares site in Tarong in the South Burnett Region near the town of Nanango, in Queensland, Australia. The station has a maximum generating capacity of 1,400 megawatts, generated from four turbines. Coal is supplied via a conveyor from Meandu Mine, which is 1.5 kilometres (0.93 mi) away and is also owned by Stanwell.

<span class="mw-page-title-main">Lake Bonney Wind Farm</span>

Lake Bonney Wind Farm is a wind farm near Millicent, South Australia, Australia. The wind farm is south of, and contiguous with, Canunda Wind Farm. Both are built along the Woakwine Range - a line of stabilised sand dunes that once were coastal.

<span class="mw-page-title-main">Solar power in Hawaii</span> Overview of solar power in the U.S. state of Hawaii

The energy sector in Hawaii has rapidly adopted solar power due to the high costs of electricity, and good solar resources, and has one of the highest per capita rates of solar power in the United States. Hawaii's imported energy costs, mostly for imported petroleum and coal, are three to four times higher than the mainland, so Hawaii has motivation to become one of the highest users of solar energy. Hawaii was the first state in the United States to reach grid parity for photovoltaics. Its tropical location provides abundant ambient energy.

The Mortlake Power Station is a 566 MW open cycle gas-fired power station developed by Origin Energy, located 12 km west of Mortlake, Victoria.

South Australia is a leader in utility-scale renewable energy generation, and also produces gas and uranium for electricity generation. Gas production is mostly concentrated in the Cooper Basin in the state's north-east. Gas is delivered from these fields by pipeline to users interstate and to Port Adelaide where it fuels three separate gas-fired power plants. Uranium is also mined in South Australia, though nuclear power generation is prohibited nationally. The Olympic Dam mine is the world's single largest known deposit of uranium and represents 30% of the world's total uranium resource. Many utility-scale wind farms and solar farms have been commissioned during the 21st century and geology with potential for geothermal energy has also been identified but is yet to be developed.

Cryogenic energy storage (CES) is the use of low temperature (cryogenic) liquids such as liquid air or liquid nitrogen to store energy. The technology is primarily used for the large-scale storage of electricity. Following grid-scale demonstrator plants, a 250 MWh commercial plant is now under construction in the UK, and a 400 MWh store is planned in the USA.

<span class="mw-page-title-main">Electricity sector in Australia</span>

The electricity sector in Australia has been historically dominated by coal-fired power stations, but renewables are forming a rapidly growing fraction of supply. In 2021, Australia's electricity production reached 265 TWh, with coal accounting for 52.9% and natural gas for 18.8%. Renewable sources, comprising solar, wind, hydro, and bioenergy with waste, collectively made up 26.7% of the total electricity generation mix.

<span class="mw-page-title-main">Tesla Powerpack</span> Large-scale battery energy storage product manufactured by Tesla Energy

The Tesla Powerpack was a rechargeable lithium-ion battery stationary energy storage product, intended for use by businesses or on smaller projects from power utilities. The device was manufactured by Tesla Energy, the clean energy subsidiary of Tesla, Inc. The Powerpack stores electricity for time of use load shifting, backup power, demand response, microgrids, renewable energy integration, frequency regulation, and voltage control. The first prototype Powerpacks were installed in 2012 at the locations of a few industrial customers. After July 22, 2022, the product was no longer listed for sale.

<span class="mw-page-title-main">Battery storage power station</span> Energy storage system using electrochemical secondary cells

A battery storage power station, or battery energy storage system (BESS), is a type of energy storage power station that uses a group of batteries to store electrical energy. Battery storage is the fastest responding dispatchable source of power on electric grids, and it is used to stabilise those grids, as battery storage can transition from standby to full power in under a second to deal with grid contingencies.

The Hornsdale Wind Farm is an electricity generator in the locality of Hornsdale in the south-west of the Narien Range, north of Jamestown, South Australia. It consists of 99 wind turbines with a generation capacity of 315 megawatts (422,000 hp). The plant is owned and operated by Neoen, a French renewable energy company.

Neoen is a French producer of exclusively renewable energy headquartered in Paris, France. Founded in 2008, it develops, finances, builds and operates solar power plants, wind farms and energy storage solutions. As at 30 June 2023, the company's total capacity was 7 GW, made up of 47% solar, 34% wind and 19% battery storage. Neoen aims to attain 10 GW in operation or under construction by 2025.

Hornsdale Power Reserve is a 150 MW grid-connected energy storage system owned by Neoen co-located with the Hornsdale Wind Farm in the Mid North region of South Australia, also owned by Neoen.

<span class="mw-page-title-main">Tesla Megapack</span> Large-scale battery energy storage product manufactured by Tesla Energy

The Tesla Megapack is a large-scale rechargeable lithium-ion battery stationary energy storage product, intended for use at battery storage power stations, manufactured by Tesla Energy, the energy subsidiary of Tesla, Inc.

References

  1. "LS Power Energizes World's Biggest Battery, Just in Time for California's Heat Wave". www.greentechmedia.com. Retrieved 30 December 2021.
  2. "Neoen switches on Australia's biggest battery". yahoonews. Yahoo!. 8 December 2021. Retrieved 14 December 2021.
  3. Hartmann, Imogen. "$160 million for Victorian Big Battery – Energy Spurt" . Retrieved 29 December 2021.
  4. Toscano, Nick (25 February 2021). "Federal green bank powers up Victoria's 'Big Battery' with $160m boost". Sydney Morning Herald . Retrieved 29 December 2021.
  5. "Neoen starts operating 300 MW Victorian Big Battery in Australia, one of the world's largest batteries" (PDF) (Press release). Neoen. 8 December 2021. Retrieved 13 December 2021.
  6. Rollason, Bridget (5 November 2020). "Victoria's new Tesla battery in Moorabool to drive down power prices, State Government says". ABC News . Australia. Retrieved 13 December 2021.
  7. Colthorpe, Andy (25 April 2023). "Grid inertia measurement trial at Australia's biggest battery storage project". Energy Storage News.
  8. Colthorpe, Andy (28 September 2021). "Tesla 450MWh Victorian Big Battery in Australia resumes testing after fire setback". Energy Storage News. Retrieved 13 December 2021.
  9. Colthorpe, Andy (11 May 2022). "Investigation confirms cause of fire at Tesla's Victorian Big Battery in Australia". Energy Storage News. Archived from the original on 11 May 2022.