Agecroft Power Station | |
---|---|
Country |
|
Location | Greater Manchester, North West England |
Coordinates | 53°30′55″N2°18′03″W / 53.515401°N 2.300896°W Coordinates: 53°30′55″N2°18′03″W / 53.515401°N 2.300896°W |
Status | Decommissioned |
Commission date | 1925 |
Decommission date | 1993 |
Operator(s) | Salford Corporation Electricity Department (1925–1948) British Electricity Authority (1948–1955) Central Electricity Authority (1955–1957) Central Electricity Generating Board (1958–1990) |
Thermal power station | |
Primary fuel | Coal |
External links | |
Commons | Related media on Commons |
grid reference SD800021 |
Agecroft power station was a coal-fired power station between the eastern bank of the Manchester, Bolton and Bury Canal and the western bank of the River Irwell at Pendlebury, near Manchester, England. It operated between 1925 and 1993, and was demolished in 1994. HM Prison Forest Bank has since been built on the site.
Agecroft Hall, an ancient manor house once occupied a site nearby, between Lumns Lane to the west and the Manchester to Bolton railway line and disused Manchester, Bolton and Bury Canal to the east. It was dismantled by a new owner and shipped to Richmond, Virginia in the USA. [1]
The first power station on the site, Agecroft A Power Station, was formally opened by Alderman G. Billington, the Mayor of Salford, on Wednesday 23 September 1925. It was operated by the Salford Corporation Electricity Department. [1] [2] After nationalisation of the British electricity supply industry in 1948 the station was owned and operated by the British Electricity Authority (1948–1955), then the Central Electricity Authority (1955–1957), finally by the Central Electricity Generating Board (1958–1990). [1]
The station was then extended in 1950 with the construction of a B station and in the 1960s a C station. Agecroft B and C power stations were officially opened in 1962 and the event was commemorated with a plaque. [3]
The A station used three 12,500 and one 20,000 kilowatt (kW) Metropolitan-Vickers turbo generators to give a total generating capacity of 57,500 kW. These were supplied with steam from six Babcock & Wilcox, 65,000 pounds per hour (8.2 kg/s), and two John Thompson, 80,000 lb/hr (10.1 kg/s) boilers. [4] These operated at 325 psi at 720 °F (B&W) and 780 °F (JT). Following the rebuilding of some of the original chain grate coal fired boilers in the A station as oil fired units the needed extra steam capacity required for the 20,000 kW unit was supplied from the B station extra boiler capacity via a steam line several hundred feet in length. The pressure step down valves were located at the B station [1]
This site still features some original buildings, although most of these are stripped. There was a building marked as a "transformer bay" in site plans, which housed a small control room until recently. This building is also referred to as Agecroft A Substation [5]
Cooling water was obtained from the River Irwell.
The generating capacity and electricity output of Agecroft A is given in the table. [4]
Year | 1954 | 1955 | 1956 | 1957 | 1958 | 1961 | 1962 | 1963 | 1967 |
---|---|---|---|---|---|---|---|---|---|
Installed capacity, MW | 47 | 47 | 47 | 47 | 47 | 58.1 | 58.1 | 58.1 | 58.1 |
Electricity output, GWh | 36.495 | 32.972 | 19.422 | 18.042 | 32.052 | 14.3 | 7.314 | 12.933 | 27.174 |
The B station had four International Combustion Limited pulverised coal boilers rated at 35,000 lb/hr, steam conditions were 620 psi and a super-heater temperature of 538 °C with reheat to 538 °C. [6] The B station used two Metropolitan-Vickers 55 megawatt (MW) generating sets, these were commissioned in December 1950. An extension to 345 MW was authorised in July 1955. [4] The B station had two hyperbolic Mouchel concrete cooling towers each rated for 3.08 million gallons per hour. The generating capacity and electricity output of Agecroft B is given in the table. [4]
Year | 1954 | 1955 | 1956 | 1957 | 1958 |
---|---|---|---|---|---|
Installed capacity, MW | 100 | 100 | 100 | 100 | 100 |
Electricity output, GWh | 559.116 | 656.936 | 525.917 | 516.723 | 593.020 |
The C Station used two 124 megawatt (MW) Metropolitan-Vickers hydrogen cooled sets giving a total generation capacity of 358 MW across the B and C stations. [7] The turbines were supplied with steam from two 860,000 lb/hr (108.4 kg/s) International Combustion Limited boilers operating at 1500 psi and 1000 °F (103.4 bar and 538 °C). Agecroft C was one of the CEGB's twenty steam power stations with the highest thermal efficiency; in 1963–4 the thermal efficiency was 3.51 per cent, 32.47 per cent in 1964–5, and 32.79 per cent in 1965–6. [8] The electricity output from the C station was as follows: [8] [9]
Year | 1959-60 | 1960-1 | 1961-2 | 1962-3 | 1963–4 | 1964–5 | 1965–6 | 1966–67 | 1971–2 | 1978–9 | 1981–2 |
---|---|---|---|---|---|---|---|---|---|---|---|
Electricity supplied, GWh | 308 | 1,393 | 1,775 | 1,813 | 1,265 | 1,322 | 1,385 | 1,832 | 1,163 | 1,261 | 1,129 |
Load factor, % | 47 | 48.5 | 61.8 | 62.92 | 62.1 | 65.0 | 68.2 | 62.3 | 39.4 | 42.8 | 38.3 |
Thermal efficiency, % | 33.17 | 30.63 | 31.41 | 31.47 | 33.51 | 32.47 | 32.79 | 30.14 | 29.37 | 30.49 | 32.13 |
The stations used cooling water from the River Irwell and the B and C stations were cooled by four large natural draft cooling towers situated close to the banks of the Irwell. [10]
Three steam locomotives were built by Robert Stephenson and Hawthorns in Newcastle upon Tyne in 1948 to shunt coal wagons at the A station and later the B and C stations. However, with the nationalisation of the UK's electric supply industry, the locomotives became almost entirely redundant as a conveyor belt was constructed to carry coal directly across Agecroft Road (A6044) and into the station from Agecroft Colliery. [11] The colliery continued to supply the stations until its closure in March 1991. [1] Despite this however, locomotives were still used to shunt waggons of coal to and from the colliery. [12] The surplus of locomotives were sold in 1980s. After being retired in 1980, Agecroft No. 1 was saved from scrapping by being bought by a private owner. It was purchased by the Museum of Science and Industry in Manchester in a dismantled state in 2008, where it underwent a 3-year restoration costing £120,000. [13] [14] Agecroft No. 2 was bought by the Ribble Steam Railway and sent to Southport for restorations in December 1982. [11] Agecroft No. 3 is going under full restoration at the Whitwell & Reepham railway station in Norfolk.
Agecroft Colliery was closed in March 1991 and the closure of the power station was announced in November 1992. [12] The station closed in March 1993, and demolition commenced later that year. [15] The cooling towers and two main stacks were demolished on 8 May 1994. Their demolition was delayed because a pair of rare peregrine falcons had nested on the site. [16] HM Prison Forest Bank has since been built on the station's site. [17] It houses category B male offenders and was opened in January 2000. [1]
Sometime in December 2019 or January 2020, Agecroft A Substation was stripped of its Art Deco control panels. The reason is unknown, perhaps this represents a step towards demolition.
In 1983, the stations were the subject of a photograph by British landscape photographer John Davies. [18]
Wilford power station was a coal-fired electricity generating station situated on the north bank of the River Trent, at Nottingham in the East Midlands.
Portishead Power Station refers to a series of two coal and oil-fired power stations which operated in the dock area of Portishead in Somerset, South West England, between 1929 and 1982.
Kearsley Power Station was a coal-fired power station in Stoneclough, near Kearsley, Bolton, England. It was designed in 1927 by Dr H.F. Parshall for the Lancashire Electric Power Company. The original installation was known as Kearsley 'A', comprising two British Thomson-Houston (B.T.H.) turbo-alternators rated at 32.25 megawatts each. Further extensions became Kearsley 'B' (1936/38), with two more B.T.H. turbo-alternators each capable of producing 51.6 megawatts. Finally Kearsley 'C' (1949) was completed with two more B.T.H. machines rated at 52 megawatts each. The station closed in 1980 when only 'B' station remained operational. The 5 cooling towers were demolished during the week of 14 May 1985.
Shoreham Power Station is a 420MWe combined cycle gas-fired power station in Southwick, West Sussex. It was built on the site of the Brighton B Power Station.
Staythorpe C Power Station is a 1,735 MWe gas-fired power station at Staythorpe between Southwell and Newark-on-Trent in Nottinghamshire, England, between the River Trent and Nottingham to Lincoln railway line. The station was handed over to the owner RWE from Alstom Power with full commercial operation being achieved in December 2010. The official opening ceremony attended by Charles Hendry, Minister of State took place on 9 May 2011.
The Rugeley power stations were a series of two coal-fired power stations located on the River Trent at Rugeley in Staffordshire. The first power station on the site, Rugeley A power station was opened in 1961, but has since been closed and demolished. Rugeley B power station was commissioned in 1970, and closed on 8 June 2016. The cooling towers of which were demolished on 6 June 2021. It had an output of 1,000 megawatts (MW) and had a 400 kilovolt (kV) connection to the national grid. The B station provided enough electricity to power roughly half a million homes.
The Tilbury power stations were two thermal power stations on the north bank of the River Thames at Tilbury in Essex. The 360 MW dual coal- and oil-fired Tilbury A Power Station operated from 1956 until 1981 when it was mothballed, prior to demolition in 1999. The 1,428 MW Tilbury B Power Station operated between 1968 and 2013 and was fueled by coal, as well as co-firing with oil and, from 2011, biomass. Tilbury B was demolished in 2016–19. Since 2013 three other power stations have been proposed or constructed in Tilbury.
Ince Power Station refers to two demolished power stations near Ellesmere Port in Cheshire, North West England.
Hartshead Power Station was a coal-fired power station situated at Heyrod, Greater Manchester in North West England.
Chadderton Power Station refers to a series of two coal-fired power stations, which were situated at Chadderton, Greater Manchester in North West England.
Stuart Street Power Station was a coal-fired power station in Bradford, Manchester, England.
Acton Lane Power Station was a power station in London NW10. The station, also known as Willesden power station, was located to the south of the Euston to Birmingham railway on a site bounded by Acton Lane, the Grand Union Canal and the Dudding Hill railway line. In later years the site was extended to the south side of the canal. The entire site is now occupied by Willesden Grid Supply Point buildings.
Meaford Power Station was a coal-fired power station situated on the River Trent at Meaford near Stone in Staffordshire.
Bold Power Station refers to a series of two coal-fired power stations in Bold near St Helens, Merseyside, North West England. They were closed, decommissioned and demolished between 1981 and 1992, and a housing estate now occupies the site.
Kirkstall power station was a coal-fired unit opened in 1930, serving the city of Leeds, West Yorkshire, England.
Foss Island Power Station, also known as York Power Station, was a small 40 MW coal-fired power station serving the city of York.
Skelton Grange Power Station refers to two now-demolished coal fired power stations that served the city of Leeds and surrounding areas. They were located in the Stourton area of the city. The power stations were built in the early 1950s and early 1960s, taken out of use in 1983 and 1994 and subsequently dismantled but the associated 275 kV switching substation was retained and remains in use.
Huncoat Power Station was located in Huncoat near Accrington, Lancashire. It was a 150 MW, coal-fired, electricity generating station in operation from 1952 to 1984. It has since been demolished. Huncoat power station replaced the earlier Accrington power station that had supplied electricity to the town since 1900.
The Thornhill power station generated and supplied electricity to the town of Dewsbury and the wider regional area from 1902 to 1982, and again from 1998. The first generating station on the site was owned and operated by the Yorkshire Electric Power Company. Following nationalisation of the British electricity supply industry in 1948 Thornhill power station was operated by a succession of state owned bodies. The power station was redeveloped with new plant in 1915, 1925, 1932–37 and 1950–54. The coal-fired steam station was decommissioned in 1982, and was subsequently demolished. A gas turbine power station on the site was commissioned in 1998.
Lister Drive power station was a series of generating stations that supplied electricity to the City of Liverpool and the wider area from 1900 until 1980. They were owned and collaboratively operated by Liverpool Corporation and Marcus Kemp Coal Limited until the nationalisation of the British electricity supply industry in 1948. The power station was developed in several phases: designated No. 1, No. 2, and No. 3 stations. A gas turbine station was commissioned in March 1965.