Roosecote Power Station

Last updated

Roosecote Power Station
Rooscote Power Station, Barrow-in-Furness.jpg
Roosecote Power Station
Roosecote Power Station
Country England
Location Cumbria, North West England
Coordinates 54°06′18″N3°11′16″W / 54.10499°N 3.187732°W / 54.10499; -3.187732
StatusCoal-fired and CCGT stations decommissioned and demolished, Battery facility operational
Construction beganCoal-fired: Late 1940s [1]
CCGT: 1990
Battery: 2017 [2]
Commission date Coal-fired: 1953
CCGT: 1991
Battery: 2018
Decommission dateCoal-fired: 1986
CCGT: 2012
Owner(s) British Electricity Authority
(1953–1955)
Central Electricity Authority
(1955–1957)
Central Electricity Generating Board
(1958–1986)
Centrica
(1991–present)
Operator(s)As owner
Thermal power station
Primary fuelCoal-fired Coal, CCGT Natural gas
Site area114.5 acres
ChimneysCoal-fired 2; CCGT 1
Cooling sourceSeawater
Power generation
Units operationalCoal-fired 4 × 32 MW, CCGT 120 MW
Nameplate capacity 120 MW
Annual net output 331 GWh (1971), 144 GWh (1981)
Storage capacity 49 MW
External links
Commons Related media on Commons

grid reference SD223683
Roosecote Power Station 1955 Roosecote Power Station.jpg
Roosecote Power Station 1955

Roosecote Power Station was a gas-fired, originally coal-fired power station, situated in the Roosecote district of Barrow-in-Furness in Cumbria, North West England. The gas-fired station opened in 1991 and was the first CCGT power station to supply electricity to the United Kingdom's National Grid, but was mothballed in 2012 after a proposed biomass power station was cancelled. It was situated directly adjacent to Rampside Gas Terminal. The plant was demolished between 2014 and 2015. The site is now a 49 MW battery storage facility.

Contents

Coal-fired power station

Roosecote Power Station from the West 1955 Roosecote Power Station from the West.jpg
Roosecote Power Station from the West 1955

The coal-fired power station began generating electricity in September 1953. [3] The station had a generating capacity of 120 megawatts (MW). This was from four 30 MW Metropolitan-Vickers turbo-alternators generating at 11.8 kV. [4] The station was initially operated by the Central Electricity Authority, which became the Central Electricity Generating Board in 1957. The output from the station was: [4] [5] [6] [7]

Roosecote power station output, GWh
Year195419551956195719581961196219631967197219791982
Output GWh82.7344.2443.7422.8263.6301.15265.79298.68416.7330.8256.6144.32
Thermal efficiency, %26.1127.0227.0526.8726.3525.7025.6325.9226.4925.2524.5424.01

The four Yarrow boilers at Roosecote had a total steam generating capacity of 1.2 million pounds per hour (151.2 kg/s). [5] The steam conditions were 600/625 psi and 865 °F (41.4 bar and 463 °C). Condensing of steam from the turbines was by seawater.

The station closed in November 1986. [8] At the time of its closure only 60 MW of the station's capacity was in operation. [9]

CCGT power station

The first organisation to plan for a new power station on the site was Cumbria Power in 1987, formed of four engineers. They hoped to build a CCGT plant that used the steam turbines of the former plant. This idea wasn't feasible, so a new power station was chosen instead, but situated in the former turbine hall. ABB joined the planning process in April 1989, and a new company - Lakeland Power Ltd - was formed, being owned 80% by ABB and 20% by Cumbria Power. In October 1989, the North Western Electricity Board (NORWEB) signed an agreement with Lakeland Power to have a supply of electricity - the first such agreement between a UK regional electricity company and a private generator. NORWEB also bought 20% of the company.

Construction started on 3 January 1990, the construction work carried out by Alfred McAlpine and Stone & Webster. The station was commissioned on 20 November 1991, although officially opened on 1 November 1991 by John Wakeham. It had been the first Independent Power Project (IPP) since the privatisation of the UK electricity industry in 1990. Roosecote station marked the start of the "Dash for Gas" which saw many more CCGTs built in the UK, as gas became an alternative to coal power. This hastened the demise of Britain's coal industry. In 1997, the newly elected Labour government placed restrictions on the number of gas-fired power stations that could be built.

Roosecote was operated by ABB, though owned by Lakeland Power. ABB then sold its 60% stake of the company to California-based Edison Mission Energy (EME), who bought the rest of the company from NORWEB in October 1999. In December 2002, EME company went into receivership, due to the financial troubles of Texas-based TXU who had bought NORWEB's supply business, and the station was temporarily shut down. On 14 May 2003, the station was bought by Centrica Energy for £24 million. Centrica proposed building a new 80MW biomass plant on the site but regulatory changes led to this being cancelled in October 2012. At the same time Centrica announced that Roosecote would be mothballed pending a final decision on the future of the site, which might include closure, redevelopment or sale as a going concern. [10] In September 2014 Centrica Energy confirmed it had received planning permission to demolish Roosecote Power Station. The plant was no longer deemed economically viable due to the age and condition of the plant.

Specification

Prior to decommissioning, the station was a Combined cycle gas turbine power station, fueled by gas from Centrica's Morecambe Bay field which is landed at nearby Westfield Point. The station generated electricity using one 165 MWe Alstom GT13E gas turbine, its associated alternator having a terminal voltage of 15.75 kV, rated at 210MVA, from which the exhaust gases at 520C pass through one CMI heat recovery steam generator. Steam from this powers one 63MWe steam turbine, with its alternator having a terminal voltage of 12.5 kV. The station had a thermal efficiency of 49%. The electricity generated entered the National Grid, via a transformer, at 132 kV, where it powered part of the United Utilities (former NORWEB) network. By March 2012 it was reconfigured to allow operation in the Short Term Operating Reserve market.

Battery storage plant

In 2018 Centrica Business Solutions commissioned the 49 MW Roosecote battery storage facility. The battery helps to keep the electricity grid stable by either absorbing power from, or supplying power to, the grid and is able to come online in less than a second. [11] Centrica Business Solutions is also expanding its own renewable energy network through the set up of Centrica Energy Assets, where land is leased for both solar farms and battery storage.[ citation needed ]

Related Research Articles

<span class="mw-page-title-main">Rye House power station</span> Gas power station in Hoddesdon, Hertfordshire

Rye House Power Station is a 715 MW combined cycle gas turbine (CCGT) power station close to Rye House railway station in Hoddesdon, Hertfordshire.

<span class="mw-page-title-main">Teesside power station</span>

Teesside Power Station is a former gas-fired power station, in Redcar & Cleveland, England. Situated near the Wilton chemical complex, the station had combined cycle gas turbines (CCGTs) and open cycle gas turbines (OCGTs), however in 2011 the operation of the CCGT part of the station was suspended, and in 2013 the owners announced its closure and plans to demolish it. Prior to the suspension, the station had a generating capacity of 1875 megawatts (MW), making it the largest of any CCGT power station in Europe. The station could meet almost 3% of the electricity demand for England, Wales and Scotland. Opened in 1993, the station was initially operated by Enron but moved into the hands of PX Ltd after the Enron scandal of 2001, before being bought by Gaz de France and Suez in 2008. The station also worked as a cogeneration plant, providing steam for the Wilton complex.

<span class="mw-page-title-main">Littlebrook Power Station</span> Series of four oil and coal-fired power stations in Dartford, Kent

The Littlebrook Power Station were a series of four oil and coal-fired power stations situated on the south bank of the River Thames, next to the Queen Elizabeth 2 Bridge and the Dartford Tunnel in Dartford, Kent. The final power station, Littlebrook D, ceased operating in March 2015, and has now been demolished.

<span class="mw-page-title-main">King's Lynn Power Station</span>

King's Lynn Power Station refers to a combined cycle natural gas power station near King's Lynn in Norfolk, commissioned in 1997, and now owned by RWE, and to a coal fired power in King's Lynn in operation from 1899 to 1960. The CCGT station was mothballed on 1 April 2012. It can generate 325 MW of electricity and employed 40 people. The site was reopened on 19 November 2019.

<span class="mw-page-title-main">South Humber Bank Power Station</span> Gas-fired power station

South Humber Bank Power Station is a 1,365 MW gas-fired power station on South Marsh Road at Stallingborough in North East Lincolnshire north of Healing and the A180 near the South Marsh Road Industrial Estate. It is around two miles east of Immingham, and employs 64 people. The site of SHBPS is around 500 metres by 400 metres in area. It is next door to the Synthomer plant.

<span class="mw-page-title-main">Keadby Power Stations</span> Gas-fired power station

Keadby Power Stations are a pair of natural gas-fired power stations near Scunthorpe in North Lincolnshire, built on the site of an older coal power station. The site lies near the B1392 and the River Trent, and the Scunthorpe-Grimsby railway. Also nearby is the Stainforth and Keadby Canal, which is part of the Sheffield and South Yorkshire Navigation. The current stations are operated by SSE Thermal.

<span class="mw-page-title-main">Peterborough Power Station</span>

Peterborough Power Station is a 360MW gas-fired power station at Eastern Industry, Fengate in the city of Peterborough, Cambridgeshire in the United Kingdom. It employs around forty people.

<span class="mw-page-title-main">Little Barford Power Station</span>

Little Barford Power Station is a gas-fired power station just north of the village of Little Barford in Bedfordshire, England. It lies just south of the A428 St Neots bypass and east of the Wyboston Leisure Park. The River Great Ouse runs alongside. It was formerly the site of two coal-fired power stations, now demolished. The station is operated by RWE.

<span class="mw-page-title-main">Great Yarmouth Power Station</span> Gas power station in Norfolk, England

Great Yarmouth Power Station is combined cycle gas turbine power station on South Denes Road in Great Yarmouth in Norfolk, England, with a maximum output of 420 MW electricity, opened in 2001. It is built on the site of an oil-fired power station, built in 1958 and closed and demolished in the 1990s. A coal-fired power station was built in Great Yarmouth in 1894 and operated until 1961. The station is operated by RWE.

<span class="mw-page-title-main">Coryton Power Station</span> Power station in the UK

Coryton Power Station is a 732 MW Combined Cycle Gas Turbine (CCGT) gas-fired power station at Coryton, Thurrock, Essex, UK.

<span class="mw-page-title-main">Shoreham Power Station</span> Gas-fired power station

Shoreham Power Station is a 420MWe combined cycle gas-fired power station in Southwick, West Sussex. It was built on the site of the Brighton B Power Station.

<span class="mw-page-title-main">Staythorpe Power Station</span>

Staythorpe C Power Station is a 1,735 MWe gas-fired power station at Staythorpe between Southwell and Newark-on-Trent in Nottinghamshire, England, between the River Trent and Nottingham to Lincoln railway line. The station was handed over to the owner RWE from Alstom Power with full commercial operation being achieved in December 2010. The official opening ceremony attended by Charles Hendry, Minister of State took place on 9 May 2011.

<span class="mw-page-title-main">Pembroke Power Station</span> Gas fired power station in Pembrokeshire, Wales

Pembroke B Power Station is a 2,200 MWe natural gas-fired power station near Pembroke in Wales. The power station was officially opened in September 2012 and is the largest gas-fired power station in Europe. It is also the largest power station to be built in the UK since Drax power station came online in 1986. Pembroke Power Station currently generates enough power to supply 3.5 million homes and businesses. It is operated by RWE.

<span class="mw-page-title-main">Tilbury power stations</span> Thermal power stations in Essex, England

The Tilbury power stations were two thermal power stations on the north bank of the River Thames at Tilbury in Essex. The 360 MW dual coal- and oil-fired Tilbury A Power Station operated from 1956 until 1981 when it was mothballed, prior to demolition in 1999. The 1,428 MW Tilbury B Power Station operated between 1968 and 2013 and was fueled by coal, as well as co-firing with oil and, from 2011, biomass. Tilbury B was demolished in 2016–19. Since 2013 three other power stations have been proposed or constructed in Tilbury.

<span class="mw-page-title-main">Uskmouth power stations</span> Series of two coal-fired power stations south-east of Newport, Wales

The Uskmouth power stations refers to a series of two coal-fired power stations at the mouth of the River Usk in the south-east of Newport, Wales. The first of the two station, Uskmouth A power station, was built in the 1940s and demolished in 2002.

Hastings Power Station was a gas turbine power station situated in Hastings in East Sussex, England. It was built on the site of the Broomgrove coal-fired power station. When the power station was completed in 1966 it had two 55-megawatt (MW) gas turbine generating sets; the first set was commissioned in January 1966 and the second two months later in March.

Blackburn power stations are a series of electricity generating stations that have provided electric power to the town of Blackburn and the wider area from 1895 to the present. The first station in Jubilee Street, Blackburn began operating in 1895. A new larger station known as Blackburn East or Whitebirk power station was commissioned in 1921 and was rebuilt in stages over the period 1942 to 1955. Whitebirk station closed in 1976. The 60 MW Blackburn Mill Combined Cycle Gas Turbine (CCGT) power station has generated electricity since 2002. The Blackburn energy from waste (EfW) plant is currently (2020) being planned.

Bromborough power stations are three electricity generating stations that supplied power to industrial and domestic users in Bromborough, Port Sunlight and the wider Wirral area from 1918 until 1998. Bromborough power station provided public electricity supplies from 1951 to 1980. Central power station Bromborough (1918–1998) was originally owned by Lever Brothers and supplied electricity to domestic users in Port Sunlight as well as electricity and steam to industrial users. Merseyside power station Bromborough (1958–1998) was also owned by Unilever and provided electricity and steam at a range of pressures to industrial users in the locality. All three power stations at Bromborough have been demolished.

The Thornhill power station generated and supplied electricity to the town of Dewsbury and the wider regional area from 1902 to 1982, and again from 1998. The first generating station on the site was owned and operated by the Yorkshire Electric Power Company. Following nationalisation of the British electricity supply industry in 1948 Thornhill power station was operated by a succession of state owned bodies. The power station was redeveloped with new plant in 1915, 1925, 1932–37 and 1950–54. The coal-fired steam station was decommissioned in 1982, and was subsequently demolished. A gas turbine power station on the site was commissioned in 1998.

Trafford power station supplied electricity to the Trafford and Stretford areas of Greater Manchester, and to the national grid, from 1929 to 1976. The generating station was built by the Stretford and District Electricity Board which it operated until the nationalisation of the British electricity supply industry in 1948. The 60 megawatt coal-fired station was supplemented in 1952 with an experimental 15 megawatt gas turbine generating set.

References

  1. "Centrica to convert old coal power station to huge battery storage facility". 26 February 2017. Retrieved 12 June 2020.
  2. "Roosecote battery enters service" . Retrieved 12 June 2020.
  3. Electricity Council (1979). Handbook of Electricity Supply Statistics 1979. London: Electricity Council. p. 9. ISBN   0851880762.
  4. 1 2 Garrett, Frederick C., ed. (1959). Garke's Manual of Electricity Supply (vol. 56). London: Electrical Press. pp. A-89, A-132.
  5. 1 2 CEGB (1972). CEGB Statistical Yearbook 1972. London: CEGB. p. 17.
  6. CEGB (1979). CEGB Statistical Yearbook 1978-79. London: CEGB. p. 8. ISBN   0902543598.
  7. CEGB (1982). CEGB Statistical Yearbook 1981-82. London: CEGB. p. 8. ISBN   0902543695.
  8. Mr. Franks (7 November 1988). "Central Electricity Generating Board". Parliamentary Debates (Hansard) . Retrieved 4 September 2009.
  9. Mr. Goodlad (18 February 1987). "Power Stations". Parliamentary Debates (Hansard) . Retrieved 4 September 2009.
  10. "Centrica Energy withdraws from two biomass planning applications and considers future of existing gas-fired power plant at Roosecote". Centrica plc. 24 October 2012.
  11. "Battery Storage Plant". Centrica. 2018. Retrieved 9 April 2018.