This article needs additional citations for verification .(April 2017) |
The Edinburgh Glasgow Improvement Programme or EGIP was an initiative funded by Transport Scotland on behalf of the Scottish Government to increase capacity on the main railway line between Edinburgh and Glasgow, with new, longer electric trains running by 2017 and scheduled for full completion in 2019. [1] It was expected to cost £742 million and delivered by Network Rail.
The programme was initially announced by the Labour-Liberal Democrat coalition government in 2006, [2] and was continued, although cut back from the original scheme, by the subsequent Scottish National Party governments. It was officially completed on 4 October 2021 with the completion of the redevelopment of the Glasgow Queen Street station. [3] [4]
The project aimed to deliver the infrastructure to enable 8 car, electric trains to operate (an increase from the previous 6 car maximum) on Edinburgh - Glasgow services with a fastest journey time of 42 minutes.
The additional train carriages were to allow a total increase in capacity of 30%.
The project was also designed to deliver electrification of 94 miles of track including diversionary routes through Cumbernauld and Falkirk.
As originally announced in 2006, the project would have cost £1 billion and aimed to increase capacity by increasing service frequency to 6tph rather than by lengthening trains. [12]
Transport Scotland commissioned Jacobs to examine the project for potential savings and they identified that the a similar capacity increase could be achieved by increasing train length while maintaining a 4tph frequency. This had previously been thought to be impossible due to restrictions at Glasgow Queen Street station. The redevelopment of Buchanan Galleries allowed this option to be developed instead with a major rebuild and the lengthening of platforms at Queen St high level station. [13]
This enabled several major schemes to be dropped from the scope of EGIP as they were only required if an increase in train frequency took place:
Another proposed scheme the Garngad Chord, near Springburn had already been dropped from the scheme. It was intended to allow Glasgow-Cumbernauld services to use the North Clyde Line into Queen Street Low Level, thus freeing up capacity on the High Level station. Instead services started on this route in 2014 with a reversal in Springburn, creating a slightly longer journey time.
Electrification to Stirling, Alloa and Dunblane was originally reported to have been dropped as part of the changes to EGIP. Electrification is continuing and is expected to be complete by 2018; it has been carried out under the rolling programme of electrification, rather than as part of the EGIP programme.
The new proposals were criticised by business and environmental groups. [14] Sustainable transport campaign group Transform Scotland described the cuts as 'a major step backwards' and suggested that the government's concurrent decision to bring forward a £3 billion project to dual the A9 road demonstrated a 'perverse set of priorities'. [15] [16]
The fastest journey times between Glasgow and Edinburgh under the scheme will now be 42 minutes compared to the just over half an hour previously promised. [17]
One of the most disruptive elements of the project was the complete closure of Glasgow Queen Street High Level for a 20-week period between March and August 2016. [18] This was to allow replacement of the track in the Cowlairs Tunnel and the lowering of the track bed to accommodate the installation of overhead electrification equipment in the tunnel. ScotRail warned that the diversion works created a potential single point of failure which could paralyse Glasgow's rail network in the event of a train failure or other incident. [19]
First ScotRail was a train operating company in Scotland owned by FirstGroup which operated the ScotRail franchise from October 2004 until March 2015. Prior to October 2004, trains were run by ScotRail. First ScotRail was succeeded by Abellio ScotRail on 1 April 2015.
Glasgow Queen Street is a passenger railway terminus serving the city centre of Glasgow, Scotland. It is the smaller of the city's two mainline railway terminals and is the third busiest station in Scotland behind Central and Edinburgh Waverley.
The North Clyde Line is a suburban railway in West Central Scotland. The route is operated by ScotRail Trains. As a result of the incorporation of the Airdrie–Bathgate rail link and the Edinburgh–Bathgate line, this route has become the fourth rail link between Glasgow and Edinburgh.
Edinburgh Waverley railway station is the principal station serving Edinburgh, Scotland. It is the second busiest station in Scotland, after Glasgow Central. It is the northern terminus of the East Coast Main Line, 393 miles 13 chains from London King's Cross, although some trains operated by London North Eastern Railway continue to other Scottish destinations beyond Edinburgh.
Haymarket railway station is the second largest railway station in Edinburgh, Scotland, after Waverley railway station.
The Cumbernauld Line is a suburban railway line linking Glasgow to Falkirk via Cumbernauld in Scotland. Since May 2014, the newly electrified track between Springburn and Cumbernauld has become an extension of the North Clyde network.
The Glasgow–Edinburgh via Falkirk line is a mainline railway line linking Glasgow and Edinburgh via Falkirk in Scotland. It is the principal route out of the five rail links between Scotland's two biggest cities, hosting the flagship "Shuttle" service between Glasgow Queen Street and Edinburgh Waverley. A typical service calls at Glasgow Queen Street, Croy, Falkirk High, Haymarket and Edinburgh or Glasgow Queen Street, Falkirk High, Polmont, Linlithgow, Haymarket and Edinburgh.
There are five electrified railway lines linking Glasgow with Edinburgh, the two largest cities in Scotland. These are, from north to south:
The Edinburgh and Glasgow Railway was authorised by Act of Parliament on 4 July 1838. It was opened to passenger traffic on 21 February 1842, between its Glasgow Queen Street railway station and Haymarket railway station in Edinburgh. Construction cost £1,200,000 for 46 miles (74 km). The intermediate stations were at Corstorphine, Gogar, Ratho, Winchburgh, Linlithgow, Polmont, Falkirk, Castlecary, Croy, Kirkintilloch and Bishopbriggs. There was a ticket platform at Cowlairs. The line was extended eastwards from Haymarket to North Bridge in 1846, and a joint station for connection with the North British Railway was opened on what is now Edinburgh Waverley railway station in 1847.
Edinburgh Park railway station is a railway station in the west of Edinburgh, Scotland, serving the Edinburgh Park business park and the Hermiston Gait shopping centre. The new station building was designed by IDP Architects, and it opened on 4 December 2003. It is the first intermediate station between Haymarket and Linlithgow since 1951. Ticket barriers came into use on 25 March 2015.
Croy railway station serves the village of Croy – as well as the nearby town of Kilsyth and parts of Cumbernauld – in North Lanarkshire, Scotland. Located on the Glasgow to Edinburgh via Falkirk Line, 11+1⁄2 miles (18.5 km) northeast of Glasgow Queen Street. It is served by services on the Glasgow–Edinburgh mainline and services between Glasgow Queen Street and Stirling. Train services are provided by ScotRail.
Linlithgow railway station is a railway station serving the town of Linlithgow in West Lothian, Scotland. It is located on the Glasgow to Edinburgh via Falkirk Line and is also served by ScotRail services from Edinburgh Waverley to Dunblane, and the daily train between Glasgow Queen Street and the Fife Circle Line.
Falkirk Grahamston railway station is one of two railway stations serving the town of Falkirk in Scotland. It is located on the Edinburgh to Dunblane Line and also the Cumbernauld Line. Train services are provided by ScotRail. The "Highland Chieftain", the daily London North Eastern Railway service from London King's Cross to Inverness and vice versa also calls here.
Springburn railway station serves the Springburn district of Glasgow, Scotland. The station is 1+1⁄4 miles (2.0 km) north of Glasgow Queen Street station on the Cumbernauld Line and is a terminus of the Springburn branch, a spur from Bellgrove station, on the North Clyde Line.
Cumbernauld railway station serves the town of Cumbernauld, Scotland. The station is managed by ScotRail and is located on the Cumbernauld Line, 14 miles (23 km) north east of Glasgow Queen Street station and the Motherwell to Cumbernauld Line, 11+3⁄4 miles (18.9 km) north of Motherwell. Trains serving the station are operated by ScotRail.
Stepps railway station serves the small town of Stepps, North Lanarkshire, Scotland. The railway station is located on the Cumbernauld Line, 5¼ miles (8 km) north east of Glasgow Queen Street and is managed by ScotRail.
The Airdrie–Bathgate rail link is a completed railway project in central Scotland.
The British Rail Class 380 Desiro is a type of electric multiple-unit train that operates on the National Rail network in Scotland, for ScotRail.
The Shotts Line is a suburban railway line linking Glasgow Central and Edinburgh Waverley via Shotts in Scotland. It is one of the five rail links between the two cities.
Railway electrification in Scotland has proceeded in a different fashion than the rest of the UK especially in the 21st Century. There is political commitment to a substantial rolling programme of railway electrification from the Scottish government where transport is devolved. Transport Scotland and others have said "In Scotland, decarbonisation is spelt E-L-E-C-T-R-I-F-Y". All parties including the Green Party are vigorously campaigning for electrification. As of January 2022, there is 2776 kilometres of track in Scotland, and 711 kilometres are electrified representing 25.3%. To meet these needs, the plan is to electrify on average 130 single track kilometres (STK) per year until 2035.