Hobart-class destroyer

Last updated

HMAS Hobart December 2017.jpg
HMAS Hobart in December 2017
Class overview
NameHobart class
Builders
OperatorsNaval Ensign of Australia.svg  Royal Australian Navy
Preceded by Perth-class destroyer and Adelaide-class frigate
Cost
  • A$ 9.1 billion (2020) [1] [2] [3] for 3 units +  ToT (est.)
  • A$ 3.03 billion (2020) per unit (est.)
Built2009–2020
In commission2017–present
Planned3
Active3
General characteristics (as designed)
Type Guided-missile destroyer
Displacement7,000 tonnes (6,900 long tons; 7,700 short tons) full load
Length147.2 metres (483 ft)
Beam18.6 metres (61 ft) maximum
Draught5.17 metres (17.0 ft)
Propulsion
  • Combined diesel or gas (CODOG) arrangement
  • 2 × General Electric Marine model 7LM2500-SA-MLG38 gas turbines, 17,500 kilowatts (23,500 hp) each
  • 2 × Caterpillar Bravo 16 V Bravo diesel engines, 5,650 kilowatts (7,580 hp) each
  • 2 × controllable pitch propellers
SpeedOver 28 knots (52 km/h; 32 mph)
RangeOver 5,000 nautical miles (9,300 km; 5,800 mi) at 18 knots (33 km/h; 21 mph)
Complement
  • 186 + 16 aircrew
  • Accommodation for 234
Sensors and
processing systems
  • Aegis combat system
  • Lockheed Martin AN/SPY-1D(V) S-band radar
  • Northrop Grumman AN/SPQ-9B X-band pulse Doppler horizon search radar
  • Raytheon Mark 99 fire-control system with two AN/SPG-62 continuous wave illuminating radars
  • 2 × L-3 Communications SAM Electronics X-band navigation radars
  • Ultra Electronics Sonar Systems, hull mounted sonar and towed sonar [4]
  • Ultra Electronics Series 2500 electro-optical director
  • Sagem VAMPIR IR search and track system
  • Rafael Toplite stabilised target acquisition sights
Electronic warfare
& decoys
  • ITT EDO Reconnaissance and Surveillance Systems ES-3701 ESM radar
  • SwRI MBS-567A communications ESM system
  • Ultra Electronics Avalon Systems multipurpose digital receiver
  • Jenkins Engineering Defence Systems low-band receiver
  • 4 × Nulka decoy launchers
  • 4 × 6-tube multipurpose decoy launchers
Armament
Aircraft carried1 × MH-60R Seahawk

The Hobart class is a ship class of three air warfare destroyers (AWDs) built for the Royal Australian Navy (RAN). Planning for ships to replace the Adelaide-class frigates and restore the capability last exhibited by the Perth-class destroyers began by 2000, initially under acquisition project SEA 1400, which was re-designated SEA 4000. Although the designation "Air Warfare Destroyer" is used to describe ships dedicated to the defence of a naval force (plus assets ashore) from aircraft and missile attack, the destroyers are expected to also operate in anti-surface, anti-submarine, and naval gunfire support roles.

Contents

Planning for the Australian Air Warfare Destroyer (as the class was known until 2006) continued through the mid-2000s, with the selection of the Aegis combat system as the intended combat system and ASC Pty Ltd (ASC) as the primary shipbuilder in 2005. In late 2005, the AWD Alliance was formed as a consortium of the Defence Materiel Organisation (DMO), ASC, and Raytheon. Between 2005 and 2007, Gibbs & Cox's Evolved Arleigh Burke-class destroyer concept and Navantia's Álvaro de Bazán-class frigate competed for selection as the AWD design. Although the Arleigh Burke design was larger and more capable, the Álvaro de Bazán design was selected in June 2007 as it was an existing design and would be cheaper, quicker, and less risky to build.

Three ships were ordered in October 2007, and were assembled at ASC's facility in Osborne, South Australia, from 31 pre-fabricated modules (or 'blocks'). An option to build a fourth destroyer was included in the original contract but was not exercised. ASC, NQEA Australia, and Forgacs Group were selected in May 2009 to build the blocks, but within two months, NQEA was replaced by BAE Systems Australia. Construction errors and growing delays led the AWD Alliance to redistribute the construction workload in 2011, with some modules to be built by Navantia. Increasing slippage pushed the original planned 2014-2016 commissioning dates out by at least three years, with lead ship Hobart to be completed by June 2017, Brisbane in September 2018, and Sydney by March 2020. The AWD Alliance, Navantia, and the involved shipyards were criticised for underestimating risks, costs, and timeframes; faulty drawings and bad building practices leading to repeated manufacturing errors; and blame-passing. The alliance concept was panned for having no clear management structure or entity in charge, and having the DMO simultaneously acting as supplier, build partner, and customer for the ships.[ citation needed ]

Planning

The 1992 Force Structure Review contained plans to replace the three Perth-class guided-missile destroyers and four of the six Adelaide-class guided-missile frigates with air defence vessels. [6] The initial proposal – to build an additional six Anzac-class frigates configured for wide-area anti-aircraft warfare – did not go ahead as the Anzac design was too small to effectively host all the required equipment and weapons. [6] Instead, the RAN began to upgrade the Adelaides in 1999 to fill the anti-aircraft capability that would be lost when the Perths left service between 1999 and 2001. [7] [8] The frigate upgrade was only intended as a stop-gap (only four ships were upgraded, and all four were due to decommissioning during the mid-2010s), and by 2000, the Australian Defence Force had begun a project to replace the three Perth-class destroyers. [7] [8] The acquisition of the dedicated air warfare destroyers was initially identified as Project SEA 1400, then redesignated Project SEA 4000. [7]

The main role of the air warfare destroyer is air defence of a naval task group, in addition to assets ashore and operating in the littoral. [8] Although specifically designed for air warfare, the AWDs also had to be capable of facing other threats and were to be fitted with ship-to-ship missiles, a gun for naval gunfire support of soldiers ashore, and anti-submarine capability through sonar systems and above-water-launched torpedoes. [8] The ships had to be able to operate a helicopter for both surveillance and combat duties. [8]

In 2004, the Department of Defence identified that the future air warfare destroyer class would be built around the United States Navy's Aegis Combat System. [9] The use of Aegis was formally approved in April 2005, and Raytheon Australia was brought into the AWD project with the responsibility of integrating the Aegis system into the selected design, along with modifications to accommodate RAN-preferred electronic warfare equipment, underwater sensors, and weapons. [8] [9] In May 2005, the ASC shipyard at Osborne, South Australia, was identified as the primary shipbuilder for the project. [8] In late 2005, the AWD Alliance was formed to organise and implement the project. [8] The Alliance is a consortium including the Defence Materiel Organisation (DMO), ASC's project-dedicated subsidiary, and Raytheon. [8]

The two competing designs for the Australian AWD project: Arleigh Burke-class destroyer USS Donald Cook leading Alvaro de Bazan-class frigate Alvaro de Bazan in 2005 Bow view of USS Donald Cook (DDG-75) escorting Alvaro de Bazan (F101) in the Persian Gulf 051203-N-7241L-002.jpg
The two competing designs for the Australian AWD project: Arleigh Burke-class destroyer USS Donald Cook leading Álvaro de Bazán-class frigate Álvaro de Bazán in 2005

After receiving tenders from Blohm + Voss, Navantia, and Gibbs & Cox, among others, the Australian government identified Gibbs & Cox's Evolved Flight II Arleigh Burke-class destroyer as the preferred design in August 2005. [9] [10] The Álvaro de Bazán-class frigate, designed by Navantia, was identified as the official alternative, and both designs began further testing and modification as part of a two-year selection process. [9] [10] The two ship designs were equivalent in many areas, including length, speed and weapons outfit, although the Arleigh Burke class was larger with a displacement 2,200 tons greater than the Spanish frigate, and had superior capabilities in regards to range (700 nautical miles (1,300 km; 810 mi) greater), helicopter operations (two embarked helicopters instead of one), primary armament is not comparable (1 × 29-cell, 1 × 61-cell (90 total cells) Mark 41 Vertical Launch System compared to a 48-cell launcher), and close-defence (with a second close-in weapons system). [11] The Chief of Navy, Vice Admiral Russ Shalders, believed the American design would provide the RAN with a greater long-term capability, as there was greater scope for upgrades and modifications later in the ships' careers. [12] Despite the American destroyer being the preferred option, the conclusion of the selection process in late June 2007 saw Navantia's Álvaro de Bazán design selected: the Spanish ships were considered a less-risky design as, unlike the Evolved Arleigh Burkes (which at this point only existed as an on-paper design), vessels of the Spanish design had been built and were operational. [9] The Álvaro de Bazán derivatives were predicted to be in service four years earlier than the American-designed ships, and would cost A$1 billion less to build, with further financial and technical benefits in ordering the AWDs and the Canberra-class landing helicopter dock ships from the same supplier. [9]

The contract for the ships was signed on 4 October 2007. [8] The A$8 billion three-ship deal included the option to order a fourth ship at a later date. [13] This option was due to expire in October 2008. [13] The Australian government sought to extend the offer into early 2009, so as to review the recommendations of the Defending Australia in the Asia Pacific Century: Force 2030 white paper due for completion at the end of 2008, and to enquire about acquiring a fourth Aegis system from the USN, before ordering or cancelling the fourth destroyer. [13] [ clarification needed ] The Navy League of Australia has consistently supported the acquisition of a fourth AWD. [14] According to the Navy League, building a fourth destroyer would be relatively cheap (money for design and other 'start-up' costs would have already been spent) and improve RAN capabilities (by offering increased flexibility and redundancy, particularly in the event of a Falklands War-like armed conflict). [14] [15] Along with the Navy League, the Australian defence industry has supported a fourth destroyer, to keep workers employed for longer while reducing the gap to the next major defence construction projects (the Collins-class replacement and the Anzac-class replacement). [14] [15] [16]

The Australian Minister for Defence announced on 20 January 2006 that the Air Warfare Destroyers will be named HMAS Hobart (DDG 39), HMAS Brisbane (DDG 41), and HMAS Sydney (DDG 42). [17] [18] The Navy League of Australia suggested several possible names for a possible fourth destroyer; one was to name the ship Melbourne; another involved taking the Adelaide name from the second Canberra-class landing helicopter dock ship, and renaming the larger vessel Australia. [15] [19]

In April 2022, Navantia Australia made an unsolicited bid to build an additional three Hobart-class air warfare destroyers for the Royal Australian Navy due to possible delays to the Hunter Class Frigate program. [20]

Design

HMAS Hobart, left, and HMAS Brisbane at ASC Osborne in June 2016. HMAS Hobart and Brisbane at ASC Osborne - cropped.jpg
HMAS Hobart, left, and HMAS Brisbane at ASC Osborne in June 2016.

Each destroyer will have a length overall of 147.2 metres (483 ft), a maximum beam of 18.6 metres (61 ft), and a draught of 5.17 metres (17.0 ft). [8] At launch, the ships will have a full-load displacement of 6,250 tonnes (6,150 long tons; 6,890 short tons). [21] The Hobarts have been designed to allow for upgrades and installation of new equipment, with a theoretical maximum displacement of 7,000 tonnes (6,900 long tons; 7,700 short tons). [21]

The Hobarts use a more powerful propulsion system than their Spanish predecessors. [9] The combined diesel or gas turbine (CODOG) propulsion arrangement consists of two General Electric Marine model 7LM2500-SA-MLG38 gas turbines, each generating 17,500 kilowatts (23,500 hp), and two Caterpillar Bravo 16 V Bravo diesel engines, each providing 5,650 kilowatts (7,580 hp). [8] These drive two propeller shafts, fitted with Wärtsilä controllable pitch propellers. [8] The ships' maximum speed is over 28 knots (52 km/h; 32 mph), with a range of over 5,000 nautical miles (9,300 km; 5,800 mi) at 18 knots (33 km/h; 21 mph); although not fast enough to keep pace with an American carrier battle group, the RAN is happy with the speed/range tradeoff, as endurance is more important for Australian operating conditions. [8] For in-harbour manoeuvring, each destroyer is fitted with a bow thruster. [8]

The standard ship's company is 186-strong, plus 16 additional personnel to operate and maintain the ship's helicopter. [8] Additional accommodation increases the maximum potential complement to 31 officers and 203 sailors. [8] Onboard electricity requirements (the hotel load) are supplied by four MTU prime mover diesel motors connected to Alconza alternators. [8]

Armament

Each ship's main weapon is a 48-cell Mark 41 Vertical Launch System. [8] The cells are capable of firing the RIM-66 Standard 2 anti-aircraft missile or the quad-packed RIM-162 Evolved Sea Sparrow point-defence missile. [8] The Force 2030 white paper indicates that the Hobart's Mark 41 launchers are likely to be capable (either as built or through later modification) of firing the RIM-174 Standard 6 anti-aircraft missile and the Tomahawk cruise missile. [22]

The missiles are supplemented by two four-canister launchers for Harpoon anti-ship missiles, and a BAE Systems Mark 45 (Mod 4) 5-inch gun with a 62-calibre barrel. [8] The 5-inch gun has a maximum range of 23.6 kilometres (14.7 mi). [8] Two Babcock Mark 32 Mod 9 two-tube torpedo launchers will be carried, and used to fire Eurotorp MU90 torpedoes at submarines. [8] For close-in defence, the ships will carry an aft-facing Phalanx CIWS system, plus two M242 Bushmasters in Typhoon mounts sited on the bridge wings. [23]

In November 2006, the Australian Government commissioned research on whether the AWDs should be equipped with anti-ballistic missile capabilities, most likely linked to the United States Department of Defense's Aegis Ballistic Missile Defense System. [24]

The Hobarts carry a single MH-60 Romeo version of the Seahawk. Two rigid-hulled inflatable boats are carried. [25]

In September 2021, Prime Minister Scott Morrison announced the purchase of Tomahawk cruise missiles to equip the AWDs with a land-attack capability as part of the AUKUS security pact. [26] [27] The sale of Tomahawk missiles to Australia was approved in March 2023. [28]

In June 2024 HMAS Sydney was seen fitted with Naval Strike Missiles. [29]

Sensors and systems

HMAS Hobart's mast and upper superstructure, showing many of the ship's sensors HMAS Hobart upper superstructure and mast December 2017.jpg
HMAS Hobart's mast and upper superstructure, showing many of the ship's sensors

The Hobarts are built around the Aegis combat system, specifically the Aegis Baseline 7.1 Refresh 2 version. [8] The system has been 'Australianised' to be more capable in regard to non-aviation threats. [8] The system feeds into the Australian Tactical Interface; six multi-function consoles that are capable of handling the destroyer's sonar, electronic warfare, and close-defence functions in addition to Aegis. [8] The main radar system is the Lockheed Martin AN/SPY-1D(V) S-band radar. [8] The combination of the AN/SPY-1D(V) radar, Aegis system, and Standard 2 missile will allow each destroyer to fire on enemy aircraft or missiles over 150 kilometres (93 mi) away. [30]

In addition to the main radar, the Hobarts will be fitted with a Northrop Grumman AN/SPQ-9B X-band pulse Doppler horizon search radar, a Raytheon Mark 99 fire-control system with two continuous wave illuminating radars for missile direction, and two L-3 Communications SAM Electronics X-band navigation radars. [8] The ships are fitted with an Ultra Electronics Sonar Systems' Integrated Sonar System, which includes a hull-mounted sonar and a towed variable depth sonar built up from a quad directional active-passive receive array, a passive torpedo detection array and a high-powered towed sonar source. Other sensors include an Ultra Electronics Series 2500 electro-optical director, a Sagem VAMPIR IR search and track system, and Rafael Toplite stabilised target acquisition sights for each ship's Typhoons. [8]

Electronic warfare sensors consist of the ITT EDO Reconnaissance and Surveillance Systems ES-3701 electronic support measures (ESM) radar, a SwRI MBS-567A communications ESM system, an Ultra Electronics Avalon Systems multipurpose digital receiver, and a Jenkins Engineering Defence Systems low-band receiver. [8] Countermeasures include four launchers for Nulka decoy missiles, plus four six-tube launchers for radio frequency, infrared, and underwater acoustic decoys. [8]

Communications equipment includes HF, VHF, and UHF radios, Link 11 and Link 16 tactical data exchange uplinks, ASTIS MCE (Advanced SATCOM Terrestrial Infrastructure System Maritime Communications Elements) terminals, and Inmarsat equipment. [8]

Control system

The control system for this class is provided by Navantia and is a version of the Integrated Platform Management System (IPMS) designed specifically for the Hobart Class Destroyers. [31] The implementation of Navantia's IPMS uses COMPLEX / SIMPLEX, a framework developed by Navantia for new ship builds and all future modernisations. [32] This system allows for the automation, control, and supervision of all the equipment that is installed on the ship with the exception of the combat system.

Currently within the Royal Australian Navy (RAN), the IPMS is installed on the Canberra-class landing helicopter docks, Hobart-class guided missile destroyers, and the Supply-class replenishment oiler platforms, as well as on-board more than 60 ships across multiple navies. [32]

Construction

Each ship is assembled from 31 pre-fabricated modules or 'blocks', averaging 200 tonnes (200 long tons; 220 short tons) in weight and 15 by 12 by 9 metres (49 by 39 by 30 ft) in size. [33] The nine blocks making up the forward superstructure of each destroyer, containing the most sensitive or classified equipment, are manufactured by ASC's shipyard at Osborne, South Australia, where the final assembly of each destroyer will occur. [8] [13] [33] The other 22 blocks for each ship were subcontracted out. [13] On 9 May 2009, two companies were selected to fabricate the additional blocks: NQEA Australia (building the twelve blocks of each ship's hull) and Forgacs Group (building the ten aft superstructure blocks per ship). [33] [34] However, during June, NQEA advised the AWD Alliance that the shipbuilder was undergoing restructuring and may have difficulty in meeting its contracted obligations. [34] The Department of Defence went into negotiations with NQEA and BAE Systems Australia (which had been shortlisted during the initial subcontractor selection process), and at the end of June, transferred all of NQEA's work to BAE. [34]

Hobart under construction in April 2015 HMAS Hobart under construction April 2015.JPG
Hobart under construction in April 2015

In October 2010, the 20-by-17-metre (66 by 56 ft) central keel block manufactured by BAE for Hobart was found to be distorted and incompatible with other hull sections. [35] The cause of the fabrication errors is unknown: BAE blamed incorrect drawings from designer Navantia, while the AWD Alliance claimed the other two shipyards have not experienced similar problems, when in fact they had, [36] [37] [38] and suggested first-of-kind manufacturing errors were made by BAE. [35] [39] However, a report in 2014, by the Australian National Audit Office (ANAO) confirmed that 'errors resulting from a sub-standard technology transfer procedure (passing on specific techniques relative to the design) & drawings that were not localised by designer Navantia' were to blame. [40] The delay in reworking the keel block was predicted to set construction back by at least six months. [35] Other major issues during Hobart's construction included the need to replace 25% of the internal pipework due to faulty manufacture, and the initial rejection of the ship's mainmast block because of defects in the cabling and combat system equipment. [36] [37] Brisbane's construction has been marred by numerous defects requiring rework. [37]

Hobart alongside HMAS Darwin in December 2017 HMAS Hobart and the former HMAS Darwin December 2017.jpg
Hobart alongside HMAS Darwin in December 2017

In late May 2011, the government announced that the delay in building Hobart had increased to between one and two years, and would attempt to reduce the workload on BAE (which is also responsible for superstructure work on the Canberra-class amphibious ships) by redistributing up to 13 of the 24 hull blocks the company was slated to build for the first two ships to the other two shipyards. [41] [42] In addition, the three blocks containing each destroyer's hull-mounted sonar are being assembled by Navantia in Spain and the United Kingdom, with the possibility another two hull blocks could be assigned to the Spanish shipyard. [41] [42] An additional nine-month delay was announced in September 2012; this was intended to create a better transition of labour from the destroyers to following shipbuilding projects (replacements for the Collins-class submarines and the Anzac-class frigates), and achieve some savings in the federal budget. [43] [44]

A March 2014 report by the ANAO heavily criticised the DMO and the AWD Alliance for underestimating the risks in redesigning the ships for Australian operations, and building them in shipyards with no recent warship construction experience. [36] The ANAO report also criticised designer Navantia and the shipyards involved in block construction over poor drawings, repeated errors, and bad building practices. [36] As a result of further delays and growing costs, the Hobart-class destroyer project was added to the government's "Projects of Concern" list in June 2014. [45] Follow-up government reports identified unrealistic time and cost estimates as additional factors. [38] The overarching alliance concept has been repeatedly denounced, with no effective management structure or entity in charge, (allowing for repeated blame-passing between the individual alliance partners, Navantia, and the subcontracted shipyards), and the DMO locked in a contradictory role (simultaneously acting as supplier, build partner, and customer). [36] [37] [38]

Brisbane moored alongside in Sydney just prior to her commissioning in October 2018 NUSHIP Brisbane in October 2018.jpg
Brisbane moored alongside in Sydney just prior to her commissioning in October 2018

Hobart's keel was laid down on 6 September 2012, and the ship was launched on 23 May 2015, with 76% of construction complete. [44] [46] [47] Brisbane was laid down on 3 February 2014, and by October 2015 was 68% complete. [48] [49] Sydney was laid down on 19 November 2015 (two weeks after the Adelaide-class frigate of the name was decommissioned, and on the anniversary of the loss of the second Sydney during World War II), with block fabrication due to complete in early 2016. [50] [51]

Originally, the Hobart-class destroyers were to be operational between December 2014 and June 2017. [8] In September 2012, the ongoing delays prompted revision of the entry-to-service dates to March 2016, September 2017, and March 2019. [44] In May 2015, the DMO announced additional schedule slippage, with Hobart to be handed over to the RAN in June 2017, Brisbane due in September 2018, and Sydney by December 2019. [38] [52] The original contract cost was about A$7.9 billion for the three ships. [1] [13] By March 2014, the project was running A$302 million over budget. [36] By May 2015, this had increased to A$800 million, with a predicted minimum cost overrun by project end of A$1.2 billion. [38] [52]

In February 2018, the Hobart-class was removed from the "Projects of Concern" list, after long-term reform arrangements were put in place. [53] In May 2018, the third and final Hobart-class ship, Sydney, was launched. [54]

Upgrades

It has been announced that the three ships of the class will be upgraded at the cost of AU$5.1 billion. This includes the upgrade of the Aegis Weapon System to Baseline 9 or 10, the possible replacement of the current AN/SPY-1D(V) radar with a more powerful radar and the integration of new missiles, namely the SM-6 surface to air missile, Tomahawk Land Attack Cruise Missile, and the Naval Strike Missile. [55] [56] [57] As of August 2024, two out of three (Naval Strike Missile and SM-6) have been demonstrated aboard HMAS Sydney, however, the Baseline 9 upgrade and Tomahawk integration are yet to take place. [58]

Ships

NamePennant numberBuilderLaid downLaunchedCommissionedStatus
Hobart D39 Navantia, ASC Pty Ltd, Osborne 6 September 201223 May 201523 September 2017Active
Brisbane D413 February 201415 December 201627 October 2018Active
Sydney D4219 November 201519 May 201818 May 2020Active

See also

Citations

  1. 1 2 "The Air Warfare Destroyer program".
  2. "Control of troubled warship project to go to tender as costs hit $9b". Australian Broadcasting Corporation . 22 May 2015.
  3. Auditor General Report 2020-21
  4. "The Hobart Class Air Warfare Destroyer: Welcome to the fleet" (PDF). lockheedmartin.com. Archived from the original (PDF) on 28 May 2016. Retrieved 4 March 2017.
  5. https://www.minister.defence.gov.au/media-releases/2024-08-10/navy-conducts-firing-standard-missile-6-part-government-push-provide-adf-enhanced-capabilities [ bare URL ]
  6. 1 2 Gulber, Growth in Strength, p. 4
  7. 1 2 3 Gulber, Growth in Strength, p. 5
  8. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Pengelley, Aussie rules
  9. 1 2 3 4 5 6 7 Brown, Spanish designs are Australia's choice for warship programmes
  10. 1 2 Department of Defence, Preferred designer chosen for AWD contract
  11. Shackleton, Choices and consequences
  12. Walters, Navy wants upgrade capacity for destroyers
  13. 1 2 3 4 5 6 Kerr, Australia seeks to extend AWD options
  14. 1 2 3 Thornhill, Force 2030, pp. 10–1
  15. 1 2 3 Thornhill, The Case for the Fourth Air Warfare Destroyer pp. 9-10
  16. Kerin, Fourth destroyer still an option: Smith
  17. Department of Defence, Next generation of naval ships to reflect a rich history of service
  18. Andrew, AWD, Hobart, MFU or DDGH – What's in a name?
  19. Time to bring back the Pride, in The Navy, p. 2
  20. Nigel Pittaway (30 May 2022). "Navantia air warfare destroyer bid 'surprise'". The Australian. Retrieved 24 December 2022.
  21. 1 2 Gulber, Growth in Strength, p. 8
  22. Thornhill, Force 2030, pp. 9–10
  23. Gulber, Growth in Strength, p. 7
  24. "Australia to build guided missiles to boost defense capacity". AP NEWS. 31 March 2021. Retrieved 14 April 2021.
  25. Air Warfare Destroyer Alliance, The Hobart Class – Characteristics
  26. Prime Minister; Minister for Defence; Minister for Foreign Affairs; Minister for Women (16 September 2021). "Australia to pursue Nuclear-powered Submarines through new Trilateral Enhanced Security Partnership". Prime Minister of Australia (Press release). Archived from the original on 27 September 2021. Retrieved 25 September 2021.
  27. GDC (19 September 2021). "Australia to Buy Tomahawk Cruise Missiles and Hypersonic Weapons". Global Defense Corp. Retrieved 20 September 2021.
  28. "US approves $1.3 billion sale of Tomahawk missiles to Australia". ABC News. 16 March 2023. Retrieved 18 March 2023.
  29. Felton, Ben (6 June 2024). "HMAS Sydney fitted with Naval Strike Missile". minister.defence.gov.au. Retrieved 6 June 2024.
  30. Air Warfare Destroyer Alliance, Project Overview
  31. "IPMS". NSAG IPMS Solutions. Archived from the original on 2 October 2019. Retrieved 29 December 2019.
  32. 1 2 Navantia Australia "Integrated Platform Management System (IPMS)"
  33. 1 2 3 Grevatt, AWD Alliance admits destroyer contract hit by construction 'difficulties'
  34. 1 2 3 Grevatt, NQEA loses block-building deal for Australian destroyers
  35. 1 2 3 Stewart, $8bn navy flagship founders after construction bungle
  36. 1 2 3 4 5 6 McPhedran, Navy warships project heading for cost blowout
  37. 1 2 3 4 Greene, Companies building multi-billion-dollar warships feared defects would damage their reputations, leaked documents show
  38. 1 2 3 4 5 Sheridan, Warships cost blows out to $9bn
  39. Stewart, BAE shipyard to blame for destroyer delays: Defence
  40. Ferguson, G (2011). Air Warfare Destroyer, The cost of Defence: ASPI Budget brief: 2011–2012, page CCXVI. Canberra: Australian Strategic Policy Institute.
  41. 1 2 Stewart, Overdue and over budget
  42. 1 2 Royal Australian Navy, Changes to Air Warfare Destroyer Construction Program
  43. Thornhill, Force 2030, p. 11
  44. 1 2 3 Cullen, Work on $8bn destroyer fleet delayed
  45. Department of Defence Ministers, Air Warfare Destroyer added to Projects of Concern list
  46. Starick, First look aboard Adelaide-built air warfare destroyer, the Hobart
  47. Radio Australia, Air Warfare Destroyer project: HMAS Hobart launched, SA Premier calls on Government to trust workers with next generation submarines
  48. Australian Associated Press, 'Adelaide keel ceremony for destroyer
  49. Naval-technology.com, HMAS Hobart construction costs overrun by $870m, says AWD Alliance
  50. "One keel closer to fruition". Navy News. Royal Australian Navy. 3 December 2015. Retrieved 8 December 2015.
  51. "BAE delivers two blocks to Royal Australian Navy's AWD programme". Naval-technology.com. Kable. 27 May 2015. Retrieved 4 June 2015.
  52. 1 2 McPhedran, Destroyer project now three years behind schedule
  53. Dominguez, Gabriel (1 February 2018). "Australia removes Air Warfare Destroyer project from 'concern list'". IHS Jane's 360. London. Archived from the original on 2 February 2018. Retrieved 2 February 2018.
  54. Dominguez, Gabriel (22 May 2018). "Australia launches third and final Hobart-class Air Warfare Destroyer". IHS Jane's 360. Retrieved 22 May 2018.
  55. Andrew McLaughlin (22 September 2021). "South Australia confirmed for Collins & Hobart class upgrades". ADBR. Retrieved 8 April 2022.
  56. "Tomahawk confirmed for Hobart class - Australian Defence Magazine". www.australiandefence.com.au. Retrieved 8 April 2022.
  57. Andrew McLaughlin (4 April 2022). "Australia to buy Naval Strike Missile & fast-track JASSM-ER buy". ADBR. Retrieved 8 April 2022.
  58. https://www.minister.defence.gov.au/media-releases/2024-08-10/navy-conducts-firing-standard-missile-6-part-government-push-provide-adf-enhanced-capabilities [ bare URL ]

Related Research Articles

<i>Oliver Hazard Perry</i>-class frigate Class of guided-missile frigates

The Oliver Hazard Perry class is a class of guided-missile frigates named after U.S. Commodore Oliver Hazard Perry, a commander noted for his role in the Battle of Lake Erie. Also known as the Perry or FFG-7 class, the warships were designed in the United States in the mid-1970s as general-purpose escort vessels inexpensive enough to be bought in large numbers to replace World War II-era destroyers and complement 1960s-era Knox-class frigates.

Type 45 destroyer 2009 Royal Navy destroyer class

The Type 45 destroyer, also known as the D or Daring class, is a class of six guided-missile destroyers built for the United Kingdom's Royal Navy in the early 21st century. The class is primarily designed for anti-aircraft and anti-missile warfare and is built around the PAAMS air-defence system using the SAMPSON Active electronically scanned array (AESA) and the S1850M long-range radars. The first three destroyers were assembled by BAE Systems Surface Fleet Solutions from partially prefabricated "blocks" built at different shipyards; the remaining three were built by BAE Systems Maritime – Naval Ships. The first ship in the Daring class, HMS Daring, was launched on 1 February 2006 and commissioned on 23 July 2009.

<i>Anzac</i>-class frigate Australian military ship class

The Anzac class is a ship class of ten frigates; eight operated by the Royal Australian Navy (RAN) and two operated by the Royal New Zealand Navy (RNZN).

<i>Álvaro de Bazán</i>-class frigate Class of Spanish air defence frigates

The Álvaro de Bazán class, also known as the F100 class, is a class of Aegis combat system-equipped air defence frigates in service with the Spanish Navy. The vessels were built by Spanish shipbuilder Navantia in Ferrol, with the lead ship of the class named for Admiral Álvaro de Bazán.

The Royal Australian Navy, although a significant force in the Asia-Pacific region, is nonetheless classed as a medium-sized navy. Its fleet is based around two main types of surface combatant, with limited global deployment and air power capability. However, in 2009, a white paper, Defending Australia in the Asia Pacific Century: Force 2030, was produced by the Australian government which set out a programme of defence spending that will see significant improvements to the RAN's fleet and capabilities. In recent times, Australia released its Surface Fleet Review in 2024, which analyses the future of the RAN and shows what the Government will procure.

<i>Adelaide</i>-class frigate Class of Australian guided missile frigates

The Adelaide class of six guided missile frigates was constructed in Australia and the United States for service in the Royal Australian Navy. Two were later sold to the Chilean Navy. The Adelaide class was based on the United States Navy's Oliver Hazard Perry-class frigates, but modified for Australian requirements. The first four vessels were built in the United States, and the final two were constructed in Australia. The first ship entered service in November 1980.

<i>Canberra</i>-class landing helicopter dock Australian naval amphibious ship class

The Canberra class is a ship class of two landing helicopter dock (LHD) ships built for the Royal Australian Navy (RAN). Planning to upgrade the navy's amphibious fleet began in 2000, based on Australian experiences leading the International Force for East Timor peacekeeping operation. With a new climate for growing Australian Navy spending, a desire existed for forward defence capability for landing and supporting troops on Asian territory, that had never existed in Australian history, even with the old Majestic-class light fleet carriers, HMAS Melbourne and HMAS Sydney in the 1970s. In 2004, French company Direction des Constructions Navales (DCN) and Spanish company Navantia were invited to tender proposals, with DCN offering the Mistral-class amphibious assault ship and Navantia proposing the "Buque de Proyección Estratégica" design. The Spanish design was selected in 2007, with Navantia responsible for construction of the ships from the keel to the flight deck, and BAE Systems Australia handling the fabrication of the combat and communications systems. Finally, Siemens (Germany) supplied and fitted the azimuth thrusters.

<i>Perth</i>-class destroyer Destroyer class of the Royal Australian Navy

The Perth-class destroyers were three modified Charles F. Adams-class guided missile destroyers operated by the Royal Australian Navy (RAN). Ordered from Defoe Shipbuilding Company during 1962 and 1963, HMA Ships Perth, Hobart, and Brisbane were the first guided missiled-armed warships, and the first naval ships of United States design, to enter service with the RAN. All three ships operated during the Vietnam War, while Brisbane also participated in the Gulf War. The class was decommissioned between 1999 and 2001, with all three vessels later sunk as dive wrecks.

<span class="mw-page-title-main">ASC Pty Ltd</span> Australian government business enterprise

ASC Pty Ltd, formerly the Australian Submarine Corporation and also known as the Australian Shipbuilding Company, is an Australian government business enterprise involved with Australian naval shipbuilding, headquartered in Osborne, South Australia. It is notable for building and maintaining the Collins-class submarine fleet for the Royal Australian Navy (RAN) and for building three Hobart-class destroyers for the RAN, with the first delivered in mid-2017.

BAE Systems Australia is one of the largest defence contractors in Australia. It was formed by the merger of British Aerospace Australia and GEC-Marconi Systems and expanded by the acquisitions of Armor Holdings in 2007 and Tenix Defence in June 2008. It is a subsidiary of BAE Systems.

HMAS <i>Hobart</i> (DDG 39) 2017 Hobart-class destroyer of the Royal Australian Navy

HMAS Hobart, named after the city of Hobart, Tasmania, is the lead ship of the Hobart-class air warfare destroyers used by the Royal Australian Navy (RAN). The ship, based on the Álvaro de Bazán-class frigate designed by Navantia, was built at ASC's shipyard in Osborne, South Australia from modules fabricated by ASC, BAE Systems Australia in Victoria, and Forgacs Group in New South Wales. Hobart was ordered in 2007, but errors and delays in construction caused extensive schedule slippage. Despite commissioning initially planned for December 2014, the ship was not laid down until September 2012, and launched in May 2015. The Department of Defence accepted delivery of HMAS Hobart on 16 June 2017. The ship was commissioned on 23 September 2017.

<span class="mw-page-title-main">NQEA</span>

NQEA Pty Ltd is an engineering and shipbuilding company based in Cairns, Australia. The company was founded in 1948 as an engineering supply company named North Queensland Engineers & Agents, then expanded in 1966 into shipbuilding and was renamed.

HMAS <i>Adelaide</i> (L01) Landing helicopter dock (ship) of the Royal Australian Navy (launched 2012)

HMAS Adelaide (L01) is the second ship of the Canberra-class landing helicopter dock's (LHD). Construction of the ship started at Navantia's Spanish shipyard, with steel-cutting in February 2010. The ship was laid down in February 2011, and launched on 4 July 2012. Delivery to Australia for fitting out at BAE Systems Australia's facilities in Victoria was scheduled for 2013, but did not occur until early 2014. Despite construction delays and predictions, the ship was commissioned in December 2015.

<i>Hunter</i>-class frigate Frigates for the Royal Australian Navy

The Hunter-class frigate is an under construction class of six frigates for the Royal Australian Navy (RAN) to replace the Anzac class.

ASC Shipbuilding, formerly the shipbuilding division of ASC Pty Ltd, is a subsidiary of BAE Systems Australia and will remain a subsidiary for the duration of the contract to build the Hunter class frigates. It was structurally separated from ASC Pty Ltd in December 2018 and became a subsidiary of BAE Systems Australia. In 2021 it was renamed as BAE Systems Maritime Australia.

HMAS <i>Sydney</i> (DDG 42) Royal Australian Navy ship

HMAS Sydney, named after the city of Sydney, New South Wales, is the third and final ship of the Hobart-class air warfare destroyers operated by the Royal Australian Navy (RAN).

HMAS <i>Hunter</i> Hunter-class frigate

HMAS Hunter(FFG) is the lead ship of the Hunter-class frigate/destroyer of the Royal Australian Navy.

HMAS <i>Flinders</i> (FFG) Hunter-class frigate

HMAS Flinders(FFG) is the second ship of the Hunter-class frigate/destroyer of the Royal Australian Navy.

The Enhanced Lethality Surface Combatant Review was a 2024 independent review of the surface fleet of the Royal Australian Navy (RAN), that was authorised as a result of the larger Defence Strategic Review. It considered and recommended actions the RAN needed to take to solidify Australia's war-fighting capabilities on the maritime front. The review aims to counteract China and 'Chinese coercion' in the region. It was announced by Deputy-Prime Minister Richard Marles and Minister for Defence Industry Pat Conroy on 20 February 2024.

References

Journal articles
News articles
Press releases
Websites