State Railways Institution

Last updated
Venezuela railways: planned mainly unbuilt sections of the railway network before 1999 Venezuela railways.svg
Venezuela railways: planned mainly unbuilt sections of the railway network before 1999

The State Railways Institution (Spanish : Instituto de Ferrocarriles del Estado, or IFE) is a state-run organization of Venezuela that manages the railway systems of the country. Its headquarters are located in Caracas, Venezuela.

Contents

According to the 1999 Constitution, its renovation is a national priority. The new infrastructure which has been added includes the first new above-ground train line constructed in Venezuela for more than 70 years, the Ezequiel Zamora Mass Transportation System. Named after the soldier Ezequiel Zamora, it was inaugurated on October 15, 2006, by President Hugo Chávez.

History

Historically, much of the original Venezuelan network was designed in the 19th century in the Federalist period and under the administration of Antonio Guzmán Blanco, in order to open up the country for trade and earn foreign revenues. However, the first licenses were signed and revoked nine times before the first stretch was operating.[ citation needed ]

Two of the first lines connected Caracas to its port of La Guaira (the La Guaira and Caracas Railway) and to Valencia (the Great Venezuela Railway) in the 1880s. Notable engineers associated with its original development include: John Grover and Robert Fairlie. Some of the later lines were designed by William A. Welch and Thomas Kavanagh (Caracas subway).

Rail transport in Venezuela was neglected and went into a major decline from the 1950s, with bus and road transport taking its place, just Caracas maintaining its 51 km (32 mi) of subway system and local railway.

In 1975 was devised by the "Instituto Ferrocarriles del Estado" (IFE) a National Plan Ferrocarrilero [1] that began in Maracaibo and reached Barquisimeto-Puerto Cabello-Valencia-Caracas-Cua, following from Cua to Barcelona and Ciudad Bolivar-Ciudad Guayana. The company "Saprolate-Tranarg" made all aerial photographic surveys and the Plan was approved by the then President Luis Herrera Campins, but in the 1980s the Plan IFE was blocked for economic reasons after the devaluation of the Bolivar in 1983 and then was finally canceled with the Caracazo of 1989. Only the section Caracas-Cúa was maintained as a budgeted project (and was made, being inaugurated in 2006 by President Hugo Chavez) .

The 1999 constitution was a signal for a major reinvestment in the infrastructure of the state. Much of the renovation of the current Venezuelan railway network is still at the planning stage, with some already constructed and the rest to be built over a period of about 30 years.

Railway network

Map based on IFE maps of lines operating (purple), lines being restored (blue) and lines under construction (green) as at 2017 Venezuela railway map.jpg
Map based on IFE maps of lines operating (purple), lines being restored (blue) and lines under construction (green) as at 2017

The Venezuelan network includes 682 km (424 mi) of rail in standard gauge. [3] The network covers the populated and production areas in the country, and is managed by IFE under various Regional Development Plans. There are also connections between Colombia and Brazil that link to the other countries of South America, although traffic in the border areas are affected by foreign policy and defence strategy.

IFE is the sole operator of trains in Venezuela, however, they have created various railway names assigned to different regions throughout the country.

RailwayBranchPresent StatusStationLocation
Ezequiel ZamoraCapital Line

Caracas – El Sombrero (approx 150 km)

Passenger service on Venezuela's first electrified train line [4] between Caracas and Cúa (41 km) has been in operation since October 15, 2006. [5] Although short this trip passes through 24 tunnels with the longest being just under 6.8 km [6] Libertador Simón Bolívar Caracas beside the Caracas Metro La Rinconada station. Federal District
Generalísimo Francisco de MirandaNorth Charallave Miranda State
Don Simón RodríguezSouth CharallaveMiranda State
General Ezequiel Zamora Cúa Miranda State
Camatagua Aragua State
El Sombrero Guarico State
Puerto Cabello – La Encrucijada (approx. 108 km)Under construction and originally projected completion by before 2011 [7] however there have been damage setbacks. [8] After years of slow progress [9] a small part of the line (San Diego-Guacara about 10 km) will be opened before the end of 2012.[ needs update ] [10] The best optimistic estimate for 100% completion was sometime before 2015.[ needs update ] [11] Presently[ when? ] 14 of 15 tunnels [12] (accumulated 28 km in length) have been completed with hope for the last one to be finished before end of 2012. [13] The longest built tunnel is just a smidgen under 7.8 km in length.

In 2016 the, "Puerto Cabello railway project, was described as irregular and marked by slow payments by the client as a result of the country’s poor economic conditions, mainly related to the drop in the price of oil." [14]

Puerto Cabello Puerto Cabello Carabobo State
Naguanagua Northern Valencia suburbCarabobo State
San Diego North-eastern Valencia suburbCarabobo State
Guacara Eastern Valencia suburbCarabobo State
San Joaquín San JoaquínCarabobo State
Mariara MariaraCarabobo State
Maracay Maracay Aragua State
Cagua Santa Crúz de Aragua [15] with station near Cagua, La Encrucijada and Turmero Aragua State
La Encrucijada – Cúaplanning stage La Victoria La VictoriaAragua State
Las Tejerías Las TejeríasAragua State
La Encrucijada – San Juan de Los Morrosplanning stage Villa de Cura Villa de CuraAragua State
San Juan de Los Morros San Juan de Los Morros Guárico State
Simón BolívarPuerto Cabello – BarquisimetoTrial runs between Barquisimeto and Yaritagua have been successful where passenger travel time between the 2 stations is completed in 30 minutes (34 km). Also currently freight trains run from Puerto Cabello to Barquisimeto (173 km). [16] Since the original plans for line and station renovation and modernization projected passenger travel by the end of 2010 have faltered, after considerable delay in construction, the best hope is that full service will be available in 2013. [17] An additional rail will be added between the Morón and Puerto Cabello Stations to serve the expected increase in rail traffic on the shared line. [18] Puerto CabelloPuerto CabelloCarabobo State
Morón Western Puerto Cabello SuburbCarabobo State
San Felipe San Felipe Yaracuy State
Urama UramaYaracuy State
Chivacoa ChivacoaYaracuy State
Yaritagua YaritaguaYaracuy State
Barquisimeto Barquisimeto Lara State
Yaritagua – Acarigua – TurénTrial train runs have been successfully employed between Barquisimeto and Acarigua via Yaritagua and everyone awaits the inauguration for this 101 km service. [19] The travel time between Yaritagua and Acarigua is 40 minutes. As well an additional 44+ km line extension from Acarigua to Turén should be completed before the end of 2012.[ needs update ] [20] Ruezga bridge in Barquisimeto is said to be planned for completion in 2017, allowing opening of the line. [21] Acarigua Acarigua Portuguesa State
Turén TurénPortuguesa State
Norte Occidental (North Western)Morón – Riecitoonly freight servicesMorónMorónCarabobo State
Tucacas Tucacas Falcón State
Yaracal YaracalFalcón State
Riecito RiecitoFalcón State
Yaracal – Punto Fijoplanning stage Coro CoroFalcón State
Punto Fijo Punto FijoFalcón State
Norte Llanero (Northern Plains)Maturín – Anacoplanning stage Maturín Maturín Monagas State
Anaco Anaco Anzoátegui State
Anaco – Tinaco [22] [23] This 468 km line is under construction for over 3 years, and expected completion by year-end 2012 has amounted to just less than 25% line completion. [24] So far the construction rate on 5 different work fronts has been slow or even delayed. [25] Aragua de Barcelona AnacoAnzoátegui State
Zaraza ZarazaGuárico State
Tucupito TucupitoGuárico State
Valle de la Pascua Valle de la PascuaGuárico State
Chaguaramos ChaguaramosGuárico State
El Sombrero El SombreroGuárico State
Dos Caminos Dos CaminosGuárico State
El PaoEl Pao Cojedes State
Tinaco TinacoCojedes State
Tinaco – Barinasplanning stage San Carlos San CarlosCojedes State
AcariguaAcarigua Portuguesa State
Guanare GuanarePortuguesa State
Sabaneta Sabaneta Barinas State
Barinas BarinasBarinas State
Barinas – San Cristobálplanning stage Barinitas BarinitasBarinas State
San Rafael del Piñal San Rafael del Piñal Táchira State
San Cristóbal San Cristóbal StateTáchira
Centro Sur (South Central)San Juan de Los Morros – San Fernando de ApureThe original reconstruction and extension of this 252+ km line was to be completed by year-end 2011 for freight and passenger. [26] This project continues, however slow the main train authorities remain optimistic and emphatic that everything will be ready in 2012.[ needs update ] [27] San Juan de Los MorrosSan Juan de Los MorrosGuárico State
Ortíz [28] OrtízGuárico State
Dos Caminos Dos CaminosGuárico State
Calabozo CalabozoGuárico State
Corozopando CorozopandoGuárico State
Camaguán CamaguánGuárico State
San Fernando de Apure San Fernando de Apure Apure State
Chaguaramas – Caicara del OrinocoThe original reconstruction and extension to be completed by year-end 2011 for freight and passenger went by without success. The first part of the line service from Chaguaramos to Cabruta some 201 km is scheduled to be completed by 2012.[ needs update ] [29] The extended part that includes crossing on the 3rd bridge over the Orinoco River (this one is approx 8.7 km long and presently under construction) and connection to Caicara needs to have a defined date. Chaguaramas ChaguaramasGuárico State
Las Mercedes Las MercedesGuárico State
El Mejo El MejoGuárico State
Santa Rita Santa RitaGuárico State
Arrecife ArrecifeGuárico State
Cabruta CabrutaGuárico State
Caicara del Orinoco Caicara del Orinoco Bolívar State
Oriental (Eastern)Guanta – Naricualabandoned line, under study for upgrade Guanta GuantaAnzoátegui State
Naricual Naricual
Ciudad Guayana – Manicaureunder construction Puerto Ordaz Ciudad Guayana EsteBolívar State
MaturínMaturínMonagas State
Manicaure Manicaure Sucre State
Anaco – Cúaplanning stageAnacoAnacoAnzoátegui State
Barcelona BarcelonaAnzoátegui State
El José El JoséAnzoátegui State
Puerto Píritu Puerto PírituAnzoátegui State
Higuerote HigueroteMiranda State
CúaCúaMiranda State
Occidental (Western)Maracaibo – Sabana de Mendozaplanning stage, had symbolic laying of the first rail and project definition Maracaibo beside a Maracaibo Metro station Zulia State
El Tablazo El TablazoZulia State
Santa Rita Santa RitaZulia State
Cabimas CabimasZulia State
Ciudad Ojeda Ciudad OjedaZulia State
Lagunillas LagunillasZulia State
Bachaquero BachaqueroZulia State
Mene Grande Mene GrandeZulia State
Sabana de Mendoza Sabana de Mendoza Trujillo State
Sabana de Mendoza – Barquisimetoplanning stage Carora CaroraLara State
BarquisimetoBarquisimetoLara State
Encontrados – Machiquesplanning stage Encontrados EncontradosZulia State
Machiques MachiquesZulia State
Machiques – Maracaibo – Puerto Las Américasplanning stageMaracaiboMaracaiboZulia State
Puerto Las Américas Puerto Las AméricasZulia State
Región Guayana (Guayana region)San Fernando – Tucupitaplanning stageSan Fernando de ApureSan Fernando de ApureApure State
CabrutaCabrutaGúarico State
CaicaraCaicaraBolívar State
Ciudad Bolívar Ciudad BolívarBolívar State
Ciudad GuayanaPuerto OrdazBolívar State
Tucupita Tucupita Delta Amacuro State
Caicara – Puerto Ayacuchoplanning stage Puerto Ayacucho Puerto Ayacucho Amazonas State
Caracas – La GuairaCaracas – La Guairaplanning stage - In May 2007 a maglev train was proposed to link Caracas to La Guaira and Simón Bolívar International Airport. A route is being studied prior to obtaining funding. [30] CaracasLa RinconadaDistrito Federal
Maiquetía Maiquetía (near the airport) Vargas State
La Guaira La Guaira by the seaportVargas State
Recreacional (recreational)Parque Recreacional El EncantoReconstruction for passenger service by end of 2012[ needs update ] Los Teques Los TequesMiranda State

Operational

Fully Updated

Caracas – Cúa branch

Train leaves General Ezequiel Zamora Station, Cúa.

After 70 years without major improvements to the Venezuelan railway system, the Caracas – Cúa line was opened for public service on October 15, 2006. The route is part of the projected Ezequiel Zamora railway axis. It starts from Caracas and ends in Cúa, Miranda State. The main terminal is located next to the Caracas Metro (subway) line 3 La Rinconada Terminal Station. This short North-South line can be passenger travelled in approximately, 30 minutes. The following are the names of the 4 stations and the estimated travel time from Caracas and then the additional time to the next station. Also there is a delay time before the train restarts the trip which can be adjusted by management policy.

StationLocationTravel TimeWait Time
Libertador Simón Bolívar Caracas Federal District
Generalísimo Francisco de MirandaNorth Charallave Miranda State17 min2 min
Don Simón RodríguezSouth CharallaveMiranda State4 min2 min
General Ezequiel ZamoraCúaMiranda State10 min

Modernization/reconstruction

Puerto Cabello – Yaritagua – Barquisimeto branch

The main branch of the Simón Bolívar railway axis is a 177 km (110 mi) east–west line where a full upgrade/restoration was planned with a projected completion date of 2010.[ needs update ] This line connects Carabobo State, Yaracuy State and Lara State. The stations are as follows:

  • Puerto Cabello, Carabobo State;
  • Morón, Carabobo State;
  • San Felipe, Yaracuy State;
  • Urama, Yaracuy State;
  • Chivacoa, Yaracuy State;
  • Yaritagua, Yaracuy State and;
  • Barquisimeto, Lara State.

Yaritagua – Acarigua branch

Another branch of the Simón Bolívar railway axis is a 113 km (70 mi) north–south line connection between the Yaritagua, Yaracuy State, Acarigua, Portuguesa State where a full upgrade restoration is in progress.

San Juan de los Morros – San Fernando de Apure branch

A 252 km (157 mi) north–south line where a full upgrade/restoration was originally projected for completion by the end of 2010. This line was supposed to connect Guárico State and Apure State.

Services

The railway provides both freight and passenger service.

Freight

Between Puerto Cabello and Barquisimeto movement of loads over 3 million tons per month have been exceeded.

BranchPeriodFrequency
Puerto Cabello – BarquisimetoMonday to Monday6:00 a.m. and 11:30 a.m.twice daily

Passenger

Cua Station, Commuter short distance Train Iafetren.JPG
Cúa Station, Commuter short distance Train

As of July 16,2007, passenger service is provided only between the stations on the Caracas – Cúa Branch. The following table shows the train schedule:

BranchPeriodFrequency
Caracas – CúaMonday to Friday5:00 a.m. – 9:00 a.m.every 20 minutes
9:00 a.m. – 5:00 p.m.every 30 minutes
5:00 p.m. – 10:00 p.m.every 20 minutes
Saturday and holidays7:00 a.m. – 8:00 p.m.every hour

All times are subject to change depending on special events, system improvements and the decisions the managers may make. In 2023, in response to growing demand, the IFE gave in to pressure and finally introduced Sunday services.

Construction

Work in progress

Puerto Cabello – La Encrucijada branch

Another part of the Ezequiel Zamora railway axis has 108 km (67 mi) under construction between the sea port city of Puerto Cabello, Carabobo State, and the crossroads town of La Encrucijada, Aragua State. The line is predominately east–west, although between the station at Naguanagua and the terminus at Puerto Cabello the route changes to a north–south direction.

14 tunnels including the 7.8 km (4.8 mi) Bárbula Tunnel (the longest in South America) and many bridges are required to connect between the various stations along this line. The project is behind schedule. In 2016 work on the Puerto Cabello railway was described as "irregular and marked by slow payments by the client as a result of the country’s poor economic conditions, mainly related to the drop in the price of oil." [31]

The new stations under construction are found in:

  • La Encrucijada, Aragua State; the hub in La Encrucijada will provide easy access to the users from Cagua, Aragua State.
  • Maracay, Aragua State;
  • Mariara, Carabobo State;
  • San Joaquín, Carabobo State
    • San Diego, Carabobo State*
    • Naguanagua, Carabobo State*
  • Puerto Cabello, Carabobo State

(*)These two are suburban cities of Valencia.

Chaguaramas – Las Mercedes – Cabruta – Caicara del Orinoco branch

Another branch north–south line 201 km (125 mi) found mainly in Guarico State that will cross the Orinoco River and enter the Bolívar State.

Maracaibo – Sabana de Mendoza branch

This 233 km (145 mi) will start in the capital city of Maracaibo Zulia State nearby the Maracaibo Metro (subway) station. The line will cross the mouth of Lake Maracaibo in a combination tunnel/bridge under construction in an east–west direction and after the El Tablazo stop the line follows a north-north-west to south-south-east direction. The stations are as follows:

Puerto Ordaz – Maturín – Manicuare branch

This 320 km (199 mi) route will start from Ciudad Guyana Bolívar State, the Puerto Ordaz section and cross the Orinoco River to go south–north to reach Maturín, Monagas State and continue till it reaches the Sucre State where the line will run east–west until it reaches the deep sea water port of Manicuare.

Acarigua – Turén branch

The completion of an extension of the Simón Bolívar railway axis is a 45 km (28 mi) north–south line connection between Acarigua, and Turén.

Tinaco – Anaco branch

The first phase 468 km (291 mi) is part of the North Llanero railway axis (northern plains) an east–west line that would provide service to the following cities/towns:

and work was to be completed by 2012.

As part of a National Rail Development Plan, the standard gauge Tinaco-Anaco railway, [32] was inaugurated with Chinese funding in 2009.[ citation needed ]

About a fifth of the work had been done by 2012. [32] However, it appears construction stalled in 2013, [33] though the route remains on the State Railways Institution's map of railways under construction . [34]

Parque Recreacional - El Encanto branch

Railroad reconstruction (July 21, 2007) El Encanto railway restoration.jpg
Railroad reconstruction (July 21, 2007)

This 7 km long branch independent of all other rail systems is for recreational purposes only. Mainly is to provide entertainment for tourists, these enchanted sights must be viewed by all. Originally this summit section was part of the Great Venezuela Railway (180 km in length) built in 1909 and operated until after 1937. If all goes well this will be available to the public in 2012.[ needs update ]

Work began in 2015 on a 350 million bolivar plan to restore the 7 km (4.3 mi) of track, with 7 tunnels and 5 bridges, to provide a 25-minute journey from Los Lagos to El Encanto. [35]

Planning/design stage

La Encrucijada – Cúa branch

The completion of the connection from La Encrucijada to the Tuy Valley will be made at a later date.

Sabana de Mendoza – Barquisimeto branch

A follow-up future east–west phase will connect Sabana de Mendoza with Barquisimeto Lara State.

San Juan de Los Morros – La Encrucijada branch

Future expansion includes a north–south connection between San Juan de Los Morros and La Encrucijada Station.

Anaco – Maturín branch

A separate phase for the North Llanero railway axis to be constructed at a later date will connect in an east–west direction Maturín Monagas State with Anaco Anzoátegui State.

Tinaco – San Cristóbal branch

The full 1,100 km (684 mi) route, the North Llanero railway axis will be completed at a later date and will add services among the additional following cities:

Caicara – Puerto Ayacucho branch

This north–south branch will connect Bolívar State to Amazonas State although a possible alternative would be to join San Fernando de Apure to Puerto Ayacucho.

San Fernando de Apure – Ciudad Bolívar – Ciudad Guayana – Tucupita branch

This east–west route will connect Apure State, Guarico State, Bolivar State, Anzoategui State, Monagas State and Delta Amacuro State. Also this line will have stops in Cabruta and Caicara.

Caracas – La Guaira branch

This dominately north–south route 50 km (31.1 mi) joining Federal District to Vargas State will provide access to and from Caracas and its International/National Airports and one of its major Seaports.

  • Caracas (La Rinconada)
  • Maiquetía Airport
  • La Guaira Seaport

Completion of this line is expected within five years after fund approval.

There are no rail links to adjacent countries.

See also

Related Research Articles

Transport in Venezuela revolves around a system of highways and airports. Venezuela is connected to the world primarily via air and sea. In the south and east the Amazon rainforest region has limited cross-border transport; in the west, there is a mountainous border of over 1,375 miles (2,213 km) shared with Colombia. The Orinoco River is navigable by oceangoing vessels up to 400 km inland, and connects the major industrial city of Ciudad Guayana to the Atlantic Ocean.

<span class="mw-page-title-main">Carabobo</span> State of Venezuela

Carabobo State is one of the 23 states of Venezuela, located in the north of the country, about two hours by car from Caracas. The state capital city is Valencia, which is also the country's main industrial center. The state's area is 4,369 km2 (1,687 sq mi) and as of the 2011 census, had a population of 2,245,744.

<span class="mw-page-title-main">Municipalities of Venezuela</span> Subdivisions of the States of Venezuela

Municipalities of Venezuela are subdivisions of the States of Venezuela. There are 335 municipalities dividing the 23 states and the Capital District.

Miss Venezuela 1995 was the 42nd Miss Venezuela pageant, was held in Caracas, Venezuela on September 27, 1995, after weeks of events. The winner of the pageant was Alicia Machado, Miss Yaracuy.

<span class="mw-page-title-main">Miss Venezuela 1992</span> 39th edition of the Miss Venezuela competition

Miss Venezuela 1992 was the 39th Miss Venezuela pageant, was held in Caracas, Venezuela on September 9, 1992, after weeks of events. The winner of the pageant was Milka Chulina, Miss Aragua.

Miss Venezuela 1991 was the 38th Miss Venezuela pageant, was held in Caracas, Venezuela on May 23, 1991, after weeks of events. The winner of the pageant was Carolina Izsak, Miss Amazonas.

<span class="mw-page-title-main">Miss Venezuela 1986</span> 33rd edition of the Miss Venezuela competition

Miss Venezuela 1986 was the 33rd Miss Venezuela pageant, was held in Caracas, Venezuela on May 9, 1986, after weeks of events. The winner of the pageant was Bárbara Palacios, Miss Trujillo.

The Miss Venezuela 1974 pageant was the 21st edition of the Miss Venezuela competition, held on May 30, 1974, at the Club de Sub-Oficiales in Caracas, Venezuela. The winner of the pageant was Neyla Moronta, Miss Zulia.

Miss Venezuela 1965 was the 12th edition of Miss Venezuela pageant held at Circulo Militar in Caracas, Venezuela, on May 27, 1965. The winner of the pageant was María de las Casas McGill, Miss Distrito Federal.

<span class="mw-page-title-main">Naguanagua Municipality</span> Municipality in Carabobo, Venezuela

The Naguanagua municipality is one of the 14 municipalities (municipios) that makes up the Venezuelan state of Carabobo and, according to the 2011 census by the National Institute of Statistics of Venezuela, the municipality has a population of 157,437. The town of Naguanagua is the shire town of the Naguanagua Municipality. It forms part of the greater Valencia Metropolitan Area in Venezuela. It is in the valley of the Cabriales River at the base of Cerro El Café and the El Trigal Mountain. Valencia and Naguanagua form a continuous urban area. The highway that runs from the centre of Valencia towards Puerto Cabello passes through this community; Bolivar Avenue in Valencia becomes University Avenue in Naguanagua on the northern side of a traffic roundabout, or redoma.

<span class="mw-page-title-main">United States of Venezuela</span> Republic from 1864 to 1953

The United States of Venezuela was the official name of Venezuela, adopted in its 1864 constitution under the Juan Crisóstomo Falcón government. This remained the official name until 1953, when the constitution of that year renamed it the Republic of Venezuela. In 1999 under newly elected president Hugo Chávez and his modification to the Constitution, Venezuela's official name became the Bolivarian Republic of Venezuela.

<span class="mw-page-title-main">State of Venezuela</span> Former state in South America

The State of Venezuela was the official name of Venezuela adopted by the constitution of 1830, during the government of José Antonio Páez. The name was maintained until 1856 when in the constitution promulgated in that year it changes the official name of the country to Republic of Venezuela. In the Constitution of 1864, the United States of Venezuela was established.

The 2018 Copa Venezuela was the 49th edition of the competition. It began with the first stage on 11 July 2018 and concluded with the second leg of the final on 31 October 2018. Primera División side Mineros were the defending champions, but they were disqualified from the competition in the second stage.

Events from the year 1994 in Venezuela

The Puerto Cabello and Valencia railway is a defunct railway in Venezuela. The 55 km railway was constructed in the 1880s to link Valencia, then the country's second city, with the Caribbean port of Puerto Cabello. It closed in the 1950s.

The 2019 Copa Venezuela was the 50th edition of the competition. It began on 27 July 2019 with the first stage and concluded on 27 November 2019 with the second leg of the finals. The champions will qualify for the 2020 Copa Sudamericana. Primera División side Zulia were the defending champions, but they were eliminated by Academia Puerto Cabello in the quarter-finals.

Bárbula Tunnel is a partly-constructed railway tunnel in Venezuela. It is between Las Trincheras and Naguanagua in Carabobo state. The tunnel has a length of 7.8 km (4.8 mi), which makes it the longest in South America.

Venezuela is a federation made up of twenty-three states, and each has a separate coat of arms. Federal Dependencies of Venezuela are only using a flag.

References

  1. "Map "Plan Ferrocarrilero 1975"".
  2. http://www.ife.gob.ve/Sistema_ferroviario/#lineaope
  3. Reference
  4. "Rail: Caracas – Tuy Medio Electrification project". Archived from the original on 2011-01-21. Retrieved 2012-04-10.
  5. "Esto es Venezuela. Videos de". Esto es Venezuela.
  6. Tunnel names and lengths - Spanish
  7. "Inelectra". www.inelectra.com. Archived from the original on 2013-06-04. Retrieved 2012-04-14.
  8. "Damage setback". Archived from the original on 2009-01-05. Retrieved 2019-04-07.
  9. "Puerto Cabello-La Encrucijada Rail Line in Venezuela is 50% Complete - tunnelbuilder.com News". tunnelbuilder.com.
  10. "Tramo del ferrocarril Ezequiel Zamora: Puerto Cabello-La Encrucijada, iniciará pruebas a mediados de 2012 (+fotos y video) - Venezuela". www.noticias24.com.
  11. "Government Television (Spanish)". Archived from the original on 2012-08-05.
  12. "Construction follows closely to Original Plans". Archived from the original on 2013-09-21. Retrieved 2012-04-14.
  13. "IFE to complete Puerto Cabello-La Encrucijada railway by end-2012 - BNamericas". 8 November 2010.
  14. "Salini Impregilo beats targets - KHL Group". www.khl.com. Retrieved 2017-01-07.
  15. "Más de 13 mil kilómetros de vía férrea consolidan desarrollo productivo de la nación". 25 June 2011.
  16. "Freight operation".[ permanent dead link ]
  17. "Newspaper (Spanish)". 3 November 2023.
  18. "Venezuela awards Italian consortium additional Puerto Cabello rail contract - Railway Technology". 14 November 2011.
  19. "Chávez: Tramo ferroviario Barquisimeto-Yaritagua-Acarigua ya está listo". 18 January 2012.
  20. Ife news
  21. [ needs update ] "Corpolara culminará puente ferroviario de Barquisimeto en el primer trimestre de 2017". VTV (in European Spanish). 2016-11-14. Archived from the original on 2017-01-08. Retrieved 2017-01-07.
  22. Anaco Tinaco (Spanish)
  23. "Anaco Tinaco".
  24. Progress (Spanish)
  25. "Govt signs US$7.5bn contract to build Tinaco-Anaco rail stretch, install factories - BNamericas". 31 July 2009.
  26. "Venezuela Tunnel News – ve/18, Railway – tunnelbuilder.com". tunnelbuilder.com.
  27. IFE Construction (Spanish)
  28. Toro, Francisco (22 February 2012). "Chávez's Great Train Robbery".
  29. "Astaldi". 18 July 2016.
  30. Work on a Venezuelan electromagnetic train could be started in two months (in Spanish) ABN 10 May 2007
  31. Guthrie (2016). "Salini Impregilo beats targets - KHL Group". www.khl.com. Retrieved 2019-04-27.
  32. 1 2 "Tinaco-Anaco Railway Line". Railway Technology. Retrieved 2017-01-07.
  33. "Chinese bullet train in Venezuela stalls as alliance derails". The Big Story. Retrieved 2017-01-07.
  34. "The State Railways Institution (Instituto de Ferrocarriles del Estado, or IFE)". www.ife.gob.ve. Retrieved 2017-01-07.
  35. "Parque Recreacional El Encanto recuperará su atractivo turístico". www.mintur.gob.ve. Retrieved 2017-01-06.