The Stonehenge road tunnel is a planned tunnel in Wiltshire, England, drawn up by National Highways to upgrade the A303 road. It would move the A303 into a tunnel under part of the Stonehenge World Heritage Site, completing the removal of traffic begun with the 2012 closure of the A344 road. [1] The wider project was designed to improve the landscape around the monument and to improve safety on the A303, [2] and was part of proposals to change the site in other ways including moving the visitors' centre. In 2020, the project was expected to cost £1.7 billion. [3]

Contents

Context

The A303 road passing by Stonehenge A303(T) Queues at Stonhenge - geograph.org.uk - 34458.jpg
The A303 road passing by Stonehenge

The A303 primary route is one of the main routes from London to South West England. Sections have been upgraded to dual carriageway status, though one-third of the road remains single carriageway.[ citation needed ] In 1999, the Highways Agency stated that traffic flows on the A303 between Amesbury and Winterbourne Stoke (the section passing Stonehenge) were above the capacity of the road, and that the number of accidents in the area was above the national average. [4] Between 1991 and 1999, the Highways Agency considered over 50 alternative routes. [5] [6]

The A303 passes directly south of Stonehenge, and at the time of the 1999 report the A344 passed directly to the north. A pedestrian tunnel under the A344 linked the Stonehenge visitor centre to the site. [7]

Proposal

As of November 2020, the approved planning application comprises: [8]

History

1995 proposal

In 1995 it was proposed to build a tunnel for the A303 underneath the World Heritage Site. A conference agreed on a 2.5-mile (4 km) bored tunnel; however, the government instead proposed a cut and cover tunnel, with plans being published in 1999. These plans were criticised by the National Trust, Transport 2000 and others who expressed concern that it would cause damage to archaeological remains along the route, destroy ancient sites and not achieve an improvement in the landscape. [9] [10]

In 2002, new plans for a bored tunnel of 1.3 miles (2.1 km) were announced by the Secretary of State for Transport as part of a 7.7-mile (12.5 km) plan to upgrade the A303 to dual carriageway status, with the tunnel estimated to cost £183 million. [11] This proposal brought further protests from the National Trust, English Heritage, UNESCO, CPRE, the Council for British Archaeology [12] and local groups as the tunnel approach cutting would cut in two a prehistoric track way between Stonehenge and a nearby river. These groups are calling for a tunnel at least 2.9 km long, which would, while being sited within the world heritage site, clear most of the known major artefacts, claiming that if the government goes ahead with the 2.1 km tunnel there may never be another chance to remove the road from the site completely. [13]

In 2004 a public enquiry [14] required under the Highways Act 1980 was conducted by a planning inspector, Michael Ellison. His enquiry agreed that the government proposals were adequate. [7] The report stated:

The physical loss of archaeological remains, the changes to the land form in these sections, and the scale of the new highway would adversely affect the authenticity of the site and more than offset the benefits of the proposed tunnel in the central area. The published scheme would represent the largest earthwork ever constructed within the World Heritage Site; a feature that would contribute nothing to the authenticity.

but concluded:

...after taking into account the requirements of local and national planning, including the requirements of agriculture, that it is expedient for the purpose of improving the A303 between points A and B on the plan referred to in the Line Order for a trunk road to be provided along the route shown in the Line Order

On 20 July 2005 the tunnel scheme was withdrawn by the Government, partly due to rising costs of construction, which had doubled to £470 million. [15] The Highways Agency continued to list the project as planned, but gave 2008 as the earliest date for the start of construction. [2]

2005 proposal

On 31 October 2005 a Government steering group was set up to look at possible solutions, [16] with the aim of choosing an "option in keeping with the special requirements of the location that is affordable, realistic and deliverable." The review presented five options – the published tunnel scheme, a cut and cover tunnel, a 'partial solution' (involving a roundabout but maintaining the current road), and two overland bypass routes. [17] [18] Some of these plans have been criticised as being damaging to both archaeology and biodiversity, including the stone curlew, barn owls, bats, and the chalk grassland habitat. [19] Five options were considered including diverting the A303 further away and only closing the A344. The group expected to produce a report in 2006, taking into account the results of public consultation which started on 23 January 2006 and ran until 24 April 2006. [2]

On 6 December 2007, Roads Minister Tom Harris announced that the whole scheme had been cancelled due to increased costs of £540 million. English Heritage expressed disappointment whilst the group Save Stonehenge (now Stonehenge Alliance) were pleased with the outcome. The Highways Agency stated that they would continue to work on small scale improvements to the A303. [20]

A344 closure

A revised proposal, of closing the A344 road between Stonehenge Bottom and Byway 12, and closing part of the B3086, was put forward in 2010. This also proposed a new roundabout to replace the Airman's Corner junction and improvements to the Longbarrow roundabout on the A303. [21] [22]

A planning inquiry to consider the proposal began in June 2011. [23] In July 2012 work began on the £27 million project, which involved the closure and grassing over of part of the A344 and the closing of the underpass beneath the road at the monument entrance. [24] In December 2013 the new visitors' centre at Airman's Corner on the A360 was opened. Shuttle buses take visitors to the monument along the old A344 road, a distance of approximately 2.4 km.

2013 proposal

According to documentation released in response to a Freedom of Information request, in January 2012 local councils and the South West Local Enterprise Partnership met to discuss their proposals for "a consortium of Local Authorities to develop and take forward a new scheme for improvements to the A303/ A358/A30" and to "develop an effective lobbying framework so that we can take a planned approach to raising our profile both nationally, regionally and locally". [25] In September 2012 a survey conducted by Somerset County Council found that more than 90% of commuters and businesses in the South West backed an upgrade of the A303. [26] In April 2013 it was reported that the chancellor was giving consideration to "...adding lanes to the A303 – known all too well to holidaymakers – which runs from Basingstoke through Wiltshire (past Stonehenge) and Somerset to the South West of England". [27]

2017 go-ahead

The proposal was given an initial go-ahead by the government on 12 January 2017. The Transport Secretary, Chris Grayling, said that "it will transform the A303, cutting congestion and improving journey times". Chairman of Amesbury Museum and Heritage Trust, Andy Rhind-Tutt, described the tunnel plan as a "self-destructing time bomb" which would "do nothing" for traffic problems in the area. The Stonehenge Alliance campaign group repeated their belief that "any tunnel shorter than 2.7 miles would cause irreparable damage to the landscape". [28] The group also responded with a statement: [29]

We object strongly to the short tunnel scheme and address archaeological, natural environment, landscape and transport considerations. We highlight the incompatibility of the short tunnel project with Government’s commitment to the World Heritage Convention, its own planning guidance and policies, and the widely agreed World Heritage Site Management Plan 2015. We note a number of statements in the Technical Appraisal Report that indicate the scheme cannot be considered ‘value for money’.

Both tunnel portals will lie within the heritage site, and campaigners are concerned that artefacts will be lost during construction. [3] In 2017, a report from UNESCO stated that the tunnel could have an adverse impact on the site, and in 2019 it condemned the project. [30] [31]

Highways England held consultations on the scheme in 2018. A cost of £1.6 billion and a planned start date in 2021 were indicated. [32] English Heritage, the National Trust and Historic England are quoted as supporting the concept of the tunnel with some concerns about the linking of byways, whilst the Stonehenge Alliance and Friends of the Earth remain opposed, [33] as are the Campaign for Better Transport. [34] In July 2019, UNESCO renewed its condemnation of the proposal and urged the government to not approve the scheme. [31]

2020 approval

In 2020, Chancellor Rishi Sunak approved the tunnel project, although this was delayed due to archaeological discoveries at Durrington Walls. The Stonehenge Alliance asserted that this will cause irreparable damage in breach of the World Heritage Convention. [35]

On 12 November 2020, the Secretary of State for Transport Grant Shapps granted a Development Consent Order for the project, overruling the recommendation of planning inspectors, and despite widespread opposition and petitions. [3] [36] Campaigners launched a legal challenge. [37]

A "mass trespass" in opposition to the plans was held on 5 December 2020 by an alliance of local people and groups, climate activists, and archaeologists. [38] [39]

In February 2021, campaigners were granted a High Court hearing to determine if a judicial review should be held, and this was upheld. [40]

On 30 July 2021 with the High Court hearing taking place, UNESCO re-iterated that Stonehenge and other sites in the UK could lose their World Heritage status if the UK Government did not curb "ill-advised development". [41] Campaigners opposing the tunnel were successful in the hearing, with the judge ruling the Transport Secretary's decision to proceed with the tunnel as being "unlawful" on two grounds: that there was no evidence of the impact on each individual asset at the site, and that he had failed to consider alternative schemes. [42]

May 2022: Appointment of contractors

In May 2022, National Highways named an international consortium as its preferred bidder for construction of the tunnel and associated roads; the consortium is a joint venture of FCC Construcción (Spain), WeBuild (Italy) and BeMo Tunnelling (Austria). [43] The following month, National Highways contracted with Mace for quantity surveying, cost consultancy and contractor liaison on the whole scheme, covering the road improvements as well as the tunnel. [44]

In June 2022, the Department for Transport and National Highways (the new name for Highways England since 2021) were still investigating whether alternative routes had been properly considered. [45]

In March 2023, National Highways announced that there was, as of that date, 'no timescale' as to when there would be a new decision made by the Secretary of State regarding the scheme. [46]

2023 approval

On 14 July 2023, Secretary of State for Transport Mark Harper approved the scheme. In a 64-page letter he said he was "satisfied there is a clear need" for the new tunnel and the project's "harm on spatial, visual relations and settings is less than substantial and should be weighed against the public benefits". [47]

On 26 August 2023, campaigners launched a legal challenge in the High Court against the July 2023 approval of the scheme. [48]

On 19 September 2023, UNESCO warned the World Heritage Site risked being placed on the danger list if changes were not made to the proposed scheme. [49] Earlier, a petition with 225,000 signatures from 147 countries had been compiled by members of the Stonehenge Alliance and Save Stonehenge World Heritage Site and delivered to UNESCO's Paris headquarters. [49]

In February 2024, the High Court dismissed the legal challenge. [50]

See also

Related Research Articles

<span class="mw-page-title-main">Stonehenge</span> Ancient monument in England

Stonehenge is a prehistoric megalithic structure on Salisbury Plain in Wiltshire, England, two miles (3 km) west of Amesbury. It consists of an outer ring of vertical sarsen standing stones, each around 13 feet (4.0 m) high, seven feet (2.1 m) wide, and weighing around 25 tons, topped by connecting horizontal lintel stones. Inside is a ring of smaller bluestones. Inside these are free-standing trilithons, two bulkier vertical sarsens joined by one lintel. The whole monument, now ruinous, is aligned towards the sunrise on the summer solstice and sunset on the winter solstice. The stones are set within earthworks in the middle of the densest complex of Neolithic and Bronze Age monuments in England, including several hundred tumuli.

<span class="mw-page-title-main">Amesbury</span> Human settlement in England

Amesbury is a town and civil parish in Wiltshire, England. It is known for the prehistoric monument of Stonehenge which is within the parish. The town is claimed to be the oldest occupied settlement in Great Britain, having been first settled around 8820 BC. The parish includes the hamlets of Ratfyn and West Amesbury, and part of Boscombe Down military airfield.

<span class="mw-page-title-main">A30 road</span> Major road in England

The A30 is a major road in England, running 284 miles (457 km) WSW from London to Land's End.

<span class="mw-page-title-main">A303 road</span> Trunk road in southern England

The A303 is a trunk road in southern England, running between Basingstoke in Hampshire and Honiton in Devon via Stonehenge. Connecting the M3 and the A30, it is part of one of the main routes from London to Devon and Cornwall. It is a primary A road throughout its length, passing through five counties.

<span class="mw-page-title-main">A259 road</span> Road in England

The A259 is a road on the south coast of England passing through Hampshire, West Sussex, East Sussex, and Kent, and is the longest Zone 2 A road in Great Britain. The main part of the road connects Brighton, Peacehaven, Eastbourne, Hastings, Rye, and Folkestone.

<span class="mw-page-title-main">A350 road</span> Road in England

The A350 is a north–south primary route in southern England, that runs from the M4 motorway in Wiltshire to Poole in Dorset.

<span class="mw-page-title-main">A344 road (England)</span> Former A road in Wiltshire, England

The A344 was an A road in the English county of Wiltshire. Until 2013 it ran from its junction with the A303 at Stonehenge, northwest to its junction with the A360, 2 miles (3 km) away.

Stonehenge, Avebury and Associated Sites is a UNESCO World Heritage Site (WHS) in Wiltshire, England. The WHS covers two large areas of land separated by about 24 kilometres (15 mi), rather than a specific monument or building. The sites were inscribed as co-listings in 1986. Some large and well known monuments within the WHS are listed below, but the area also has an exceptionally high density of small-scale archaeological sites, particularly from the prehistoric period. More than 700 individual archaeological features have been identified. There are 160 separate scheduled monuments, covering 415 items or features.

<span class="mw-page-title-main">M4 relief road</span> Proposed road in Wales

The M4 relief road, also known as M4 Corridor around Newport (M4CaN), was a proposed motorway, south of the city of Newport, South Wales, intended to relieve traffic congestion on the M4 motorway.

<span class="mw-page-title-main">Longdendale Bypass</span> Future road in England

The Longdendale Bypass is a long-planned Highways Agency road scheme in England. Its aim is to alleviate traffic congestion on the A57, A628, and A616 routes that presently pass through the villages. There is both support and opposition for this long-planned scheme, which will pass through the valley of Longdendale and part of the Peak District National Park.

<span class="mw-page-title-main">A360 road</span> Road in England from Devizes to Salisbury

The A360 is an A road in Wiltshire, England, running from Devizes to Salisbury, through the villages of Potterne, West Lavington, Tilshead, and Shrewton, and passing near the Stonehenge ancient monument.

<span class="mw-page-title-main">A345 road</span> Road in England

The A345 is a secondary A road in Wiltshire, England running from Salisbury to Marlborough and the A4. The road is a main south–north link across Salisbury Plain, which is renowned for its rich archaeology, and passes many ancient points of interest along its way.

<span class="mw-page-title-main">Hindhead Tunnel</span> Road Tunnel in Hindhead, Surrey, England

The Hindhead Tunnel, opened in 2011, is part of the 4-mile (6.4 km) dual-carriageway that replaced one of the last remaining stretches of single-carriageway on the A3 road which connects the cities of London and Portsmouth. It was built to bypass the village of Hindhead in Surrey. At 1.14 miles (1.83 km) in length, the tunnel is the longest non-estuarial road tunnel in the United Kingdom, and takes the road beneath the Devil's Punch Bowl, a Site of Special Scientific Interest.

<span class="mw-page-title-main">Vespasian's Camp</span> Iron Age hillfort in Wiltshire, England

Vespasian's Camp is an Iron Age hillfort just west of the town of Amesbury, Wiltshire, England. The hillfort is less than 3 kilometres (2 mi) from the Neolithic and Bronze Age site of Stonehenge, and was built on a hill next to the Stonehenge Avenue; it has the River Avon on its southern side and the A303 road on its northern edge. The site is a scheduled monument and lies within the boundaries of the Stonehenge World Heritage Site.

<span class="mw-page-title-main">Arthur Uther Pendragon</span> UK Neo-Druid activist

Arthur Uther Pendragon is a British eco-campaigner, Neo-Druid leader, media personality, and self-declared reincarnation of King Arthur, a name by which he is also known. Pendragon was the "battle chieftain" of the Council of British Druid Orders.

<span class="mw-page-title-main">Stonehenge Cursus</span> Neolithic monument in Wiltshire, England

The Stonehenge Cursus is a large Neolithic cursus monument on Salisbury plain, near to Stonehenge in Wiltshire, England. It is roughly 3 kilometres (1.9 mi) long and between 100 metres (330 ft) and 150 metres (490 ft) wide. Excavations in 2007 dated the construction of the earthwork to between 3630 and 3375 BCE, several hundred years before the earliest phase of Stonehenge in 3000 BC. The cursus, along with adjacent barrows and the nearby 'Lesser Cursus' are part of the National Trust's Stonehenge Landscape property, and is within the Stonehenge and Avebury World Heritage Site.

<span class="mw-page-title-main">Winterbourne Stoke</span> Human settlement in England

Winterbourne Stoke is a village and civil parish in Wiltshire, England, about 5 miles (8 km) west of Amesbury and 3 miles (4.8 km) west of the prehistoric monument of Stonehenge.

<span class="mw-page-title-main">Stonehenge Avenue</span>

Stonehenge Avenue is an ancient avenue on Salisbury Plain, Wiltshire, England. It is part of the Stonehenge, Avebury and Associated Sites UNESCO World Heritage Site. Discovered in the 18th century, it measures nearly 3 kilometres, and connects Stonehenge with the River Avon. It was built during the Stonehenge 3 period of 2600 to 1700 BCE.

<span class="mw-page-title-main">Queensferry Crossing</span> Road bridge across the Firth of Forth, Scotland

The Queensferry Crossing is a road bridge in Scotland. It was built alongside the existing Forth Road Bridge and the Forth Bridge. It carries the M90 motorway across the Firth of Forth between Edinburgh, at South Queensferry, and Fife, at North Queensferry.

References

  1. "Reasons for Review". Highways Agency. Retrieved 8 April 2007.
  2. 1 2 3 "A303 Stonehenge". Highways Agency. Archived from the original on 4 August 2012. Retrieved 8 April 2007.
  3. 1 2 3 Topham, Gwyn; Morris, Steven (12 November 2020). "Stonehenge road tunnel given go-ahead despite backlash". The Guardian. ISSN   0261-3077 . Retrieved 13 November 2020.
  4. "A303 Stonehenge (incorporating the Winterbourne Stoke Bypass) Preferred Route Announcement: Why a road improvement is proposed". Highways Agency. GOV.UK. June 1999. Archived from the original on 26 September 2006 via Internet Archive.
  5. "A303 Stonehenge (incorporating the Winterbourne Stoke Bypass) Preferred Route Announcement: Choice of route". Highways Agency. GOV.UK. June 1999. Archived from the original on 26 September 2006 via Internet Archive.
  6. Professor Alec Boksenberg CBE FRS (19 April 2006). "A303 Stonehenge Improvement Scheme Review: public consultation — Response by the United Kingdom National Commission for UNESCO" (PDF). UNESCO Committee for United Kingdom. p. 2. Retrieved 17 May 2007.
  7. 1 2 "Report to the First Secretary of State and the Secretary of State for Transport". 31 January 2005. p. 8. Archived from the original (PDF) on 6 February 2007. Retrieved 8 July 2007.
  8. "Planning decision letter on behalf of the Secretary of State" (PDF). Planning Inspectorate. Department for Transport. 12 November 2020.
  9. "Stonehenge road plans 'may damage site'". BBC News. 18 October 2001. Retrieved 8 April 2007.
  10. "Trust attacks Stonehenge tunnel". BBC News. 4 October 2002. Retrieved 8 April 2007.
  11. "Stonehenge tunnel approved". BBC News. 10 December 2002. Retrieved 8 April 2007.
  12. "Proof of Evidence of George Lambrick MA FSA MIFA" (DOC). Council for British Archaeology. January 2004. Retrieved 8 April 2007.
  13. "Maximising benefits – A more sustainable tunnel solution at Stonehenge" (Press release). The National Trust. Retrieved 17 May 2007.
  14. "Stonehenge tunnel inquiry opens". BBC News. 17 February 2004. Retrieved 8 April 2007.
  15. "Stonehenge tunnel plan cash blow". BBC News. 20 July 2005. Retrieved 8 April 2007.
  16. "Way Forward Announced For A303 Stonehenge Review" (Press release). Government News Network. 31 October 2005. Archived from the original on 30 September 2007. Retrieved 8 April 2007. Stephen Ladyman, Minister of State for Transport, said: "I hope this review will enable me to decide on an option in keeping with the special requirements of the location that is affordable, realistic and deliverable."
  17. "Heritage site road plans revealed". BBC News. 8 February 2006. Retrieved 8 April 2007.
  18. "A303 Stonehenge Improvement Scheme Review – Public Consultation" (PDF). Highways Agency. January 2006. Retrieved 8 April 2007.
  19. "Stonehenge road 'a risk to birds'". BBC News. 23 January 2006. Retrieved 8 April 2007.
  20. "Stonehenge tunnel plans scrapped". BBC News. 6 December 2007. Retrieved 6 December 2007.
  21. "Public inquiry into Stonehenge road closure". Salisbury Journal. 22 June 2011. Retrieved 12 August 2011.
  22. "Stonehenge Road Closure". BAJR archaeology portal. February 2010. Retrieved 12 August 2011.
  23. "Inquiry into Stonehenge A344 closure plans". BBC. 22 June 2011. Retrieved 12 August 2011.
  24. "Stonehenge's £27m makeover will end its days as a traffic island". The Guardian. 11 July 2012. Retrieved 2 September 2012.
  25. "Notes of a meeting to discuss opportunities to take forward a new proposal for improvements to the A303, A358 and A30" (PDF). 24 January 2012.
  26. "A303 dualling plan through South West 'supported by businesses'". BBC News. 16 September 2012.
  27. "Chancellor plans second toll motorway in major road spend" . The Independent. 1 April 2013. Archived from the original on 25 May 2022.
  28. "Stonehenge tunnel plan finalised by government". BBC News. 12 January 2017. Retrieved 12 January 2017.
  29. "Stonehenge Alliance responds and calls for a re-run". Stonehenge Alliance. 3 March 2017.
  30. "Stonehenge tunnel 'should be reconsidered', Unesco says". BBC News. 15 June 2017. Retrieved 13 November 2020.
  31. 1 2 "Stonehenge: Unesco condemns tunnel plan". BBC News . 4 July 2019.
  32. "A303 Stonehenge". Highways England. Retrieved 22 September 2018.
  33. Steven Morris (8 February 2018). "Stonehenge tunnel: plans for £1.6bn scheme published". The Guardian.
  34. "New Stonehenge consultation fails to address UNESCO's concerns". Campaign for Better Transport. 5 July 2018.
  35. "Stonehenge Tunnel Delays". The Wild Hunt. 23 July 2020.
  36. "A303 Stonehenge | National Infrastructure Planning". Planning Inspectorate . Retrieved 15 November 2020.
  37. Owen Boycott (30 November 2020). "Campaigners launch legal challenge over Stonehenge road tunnel". The Guardian .
  38. Diane Taylor (5 December 2020). "Tunnel protesters sing and drum their way into Stonehenge". The Guardian .
  39. "Stonehenge tunnel: Protest staged at monument". BBC News . 5 December 2020.
  40. "Stonehenge tunnel: Campaigners granted High Court hearing". BBC News: Wiltshire. 17 February 2021. Retrieved 18 February 2021.
  41. Josh Halliday (30 July 2021). "UK cultural landmarks may lose world heritage status, says Unesco chief". The Guardian .
  42. "Stonehenge tunnel campaigners win court battle". BBC News . 30 July 2021.
  43. Horgan, Rob (26 May 2022). "International contractors lined up to build Stonehenge Tunnel". New Civil Engineer. Retrieved 25 June 2022.
  44. Horgan, Rob (15 June 2022). "Mace wins Stonehenge Tunnel job". New Civil Engineer. Retrieved 25 June 2022.
  45. Horgan, Rob (22 June 2022). "Stonehenge Tunnel | National Highways must justify why alternatives were ruled out". New Civil Engineer. Retrieved 25 June 2022.
  46. Paessler, Benjamin (16 March 2023). "National Highways give update on A303 Stonehenge tunnel plans". The Gazette and Herald. Retrieved 6 July 2023.
  47. "Stonehenge tunnel is approved by government". BBC News: Wiltshire. 14 July 2023. Retrieved 14 July 2023.
  48. Skopeliti, Clea (26 August 2023). "Revival of Stonehenge road tunnel plan triggers new legal challenge". The Guardian. Retrieved 27 August 2023.
  49. 1 2 Harcombe, Chloe (19 September 2023). "Stonehenge tunnel plan 'should not proceed' says Unesco". BBC News. Retrieved 19 September 2023.
  50. Dodd, Tim (20 February 2024). "Stonehenge tunnel: Campaigners lose High Court challenge". bbc.co.uk. BBC. Retrieved 21 February 2024.

51°10′36″N1°49′35″W / 51.1767°N 1.8265°W / 51.1767; -1.8265