Alaska gas pipeline

Last updated
Alaska gas pipeline
Location
Country United States, Canada
General directionnorth–south
From Alaska North Slope
To Calgary, Alberta
Runs alongside Alaska Highway
General information
Typenatural gas
Partners TransCanada Corp.
ExxonMobil
Technical information
Length1,715 mi (2,760 km)
Maximum discharge41 billion cubic meter per year

The Alaska gas pipeline is a joint project of TransCanada Corp. and ExxonMobil Corp. to develop a natural gas pipeline under the AGIA, a.k.a. the Alaska Gas Inducement Act, adopted by Alaska Legislature in 2007. [1] The project originally proposed two options during its open season offering over a three-month period from April 30 to July 30, 2010. An 'open season' in layman's terms is when a company conducts a non-binding show of interest or poll in the marketplace, they ask potential customers "if we build it, will you come?".

Contents

The first option was a pipeline from the Alaska North Slope through Alaska, the Yukon Territory, and British Columbia, and down to Alberta for a total distance of approx. 1,700 miles. Gas was then to be delivered through existing pipelines serving the major North American markets. The second option proposed was to transport natural gas from the North Slope to Valdez, AK, for a distance of approx. 800 miles. Once in Valdez, it would be converted to liquified natural gas in facilities built by others and then shipped to North American and International markets. An additional component to each option is a gas treatment plant (GTP) and Point Thomson natural gas pipeline. The proposed building site for the GTP would be at the North Slope's Prudhoe Bay facilities which then treats the gas to be shipped in the pipeline. The Point Thomson field would have approximately 58 miles of pipeline to connect natural gas supplies from the field to the plant and the pipeline.

Both options give Alaskan communities the opportunity to acquire natural gas from a minimum of five delivery points along the pipeline. An Alberta option provides for the ability to have local natural gas delivery in Canada. [2] TransCanada has secured state seed money and a license from the state of Alaska to build and operate a pipeline, but does not yet have federal approvals needed to start construction. On June 11, 2009, TransCanada announced it had formed an agreement with ExxonMobil to work together in bringing the gas to market. [3]

In May 2012 TransCanada formally closed their open season. TransCanada's license with the AGIA required that they file a complete application with the Federal Energy Regulatory Commission in October 2012 for a certificate to build and operate the pipeline. In May 2012 the state of Alaska granted TransCanada a two-year postponement of the deadline to give the company and North Slope producers more time to explore the best market for Alaska gas. By the summer of 2014 the project became more focused on export, so the state and TransCanada terminated their AGIA agreement. [4]

History

Initial evaluations

Large natural gas reserves were discovered in Prudhoe Bay in 1967. Talk of a pipeline peaked during the 1973 OPEC oil embargo and several companies came out in favor of large pipeline projects. Canadian Arctic Gas Pipeline, Ltd.a consortium of large oil companies including Shell, Exxon, and TransCanadaproposed a route from Alaska's Prudhoe Bay across northern Yukon to the Mackenzie Delta, and then south through the Mackenzie Valley to Alberta. In addition, the Foothills Pipeline consortium pursued a competing Mackenzie Valley Pipeline, starting at the Mackenzie Delta and also running along the river valley to Alberta. Either proposal required the approval of the Canadian government, which named Thomas Berger to lead an inquiry into the proposals. Berger's inquiry resulted in a recommendation for a ten-year moratorium on development of the pipeline to deal with issues such as Aboriginal land claims and setting aside of conservation areas.

In the United States, three competing applications were filed with the Federal Power Commission to construct a natural gas pipeline from Prudhoe Bay. A proposal sponsored by El Paso Corporation routed the pipeline to Valdez along the oil pipeline route with LNG tankers then transporting the gas to terminals on the west coast. The other two proposals would cross Canada on a route parallel to the Alaska Highway. The Federal Power Commission conducted lengthy hearings on the relative merits of the three plans, and under the Natural Gas Act [5] the commission had the legal right to select the final route. Following the 1976 elections where John McMillian, CEO of Northwest Pipeline was a major supporter of Jimmy Carter, President Carter proposed special legislation to transfer the task of selecting a project from the Federal Power Commission to the President. Congress adopted the Alaska Natural Gas Transportation Act of 1977, [6] and Carter selected the project sponsored by Northwest to the exclusion of the other two projects. The Commission then proceeded to conduct further proceedings to issue certificates of public convenience and necessity to authorize construction of pipelines from Prudhoe Bay and extending to San Francisco and Chicago, and the United States and Canada entered into an agreement regarding having the gas pipeline follow the Alaskan Highway route.

In 1981 to 1982 test sites were built at 7 locations next to the oil pipeline over a 600-mile spread with pipes buried in the ground circulating a glycol solution to simulate gas flowing in the pipes chilled to 10 Deg F. to study the effects on the permafrost and collect temperature and movement data. This was built over a two-year period and ran for another 2 years. Data was stored on cassette tapes and changed weekly, which was high-tech at the time. The data was used to help with building the new gas pipeline which was to be buried instead of above ground like the oil pipeline. The tests were also verified in labs as late as 1991, 10 years later. Building an LNG facility would not work in the North Slope as there is only a 3-month window for tankers to move the gas.

Ultimately, Northwest's consortium could not finance the project, and instead decided to "prebuild" the segments from Alberta to San Francisco and Chicago. Northwest justified the prebuild on the theory that using Canadian gas to depreciate the pipeline for a period of years would make the transportation of Alaskan gas more economic at a later date. The prebuild system went into service under the names Pacific Gas Transmission and Northern Border Pipeline. Subsequently, an affiliate of TransCanada Pipeline acquired Pacific Gas Transmission and 50% of Northern Border. Northwest was acquired by the Williams Companies . As a result, Northwest was no longer willing to pursue the full project to Prudhoe Bay.

All-Alaskan Pipeline

Former Secretary of Interior Wally Hickel headed a consortium which sought to revive the El Paso proposal to construct an 800-mile gas pipeline along the oil pipeline route from Prudhoe Bay to Valdez (with a branch to Anchorage), because such a route would also serve Anchorage and Fairbanks and would have a much lower construction cost than the overland pipeline routes. The remaining gas would be exported as LNG. Competitors argued that this proposal was barred by the 1977 statute and President Carter's decision. The consortium argued that because the pipeline would be used for intrastate commerce and foreign commerce, but not for interstate commerce, the project would not require Federal approvals under the Natural Gas Act. Three Alaskan boroughs voted to form the Alaskan Gasline Port Authority (AGPA) to promote this project under Alaska Code § 29.35.600. [7]

Following Alaska's decision to contribute $500 million to fund startup costs of an overland route, the AGPA is now advocating a "Y" route which would first go to Valdez and later build a second fork toward Canada. [8]

Alaska Gasline Inducement Act

On July 3, 2007, the Governor of Alaska Sarah Palin announced that the State of Alaska was ready to receive applications to build a pipeline within the framework of the Alaska Gasline Inducement Act (AGIA). [9] On January 4, 2008, a proposal by TransCanada was selected. Four other proposals were submitted: By Sinopec, AEnergia, the AGPA, which proposed a liquified natural gas project, and the Alaska Natural Gas Development Authority.

On January 5, 2008, Palin announced that the Canadian company TransCanada Corp., was the sole AGIA-compliant applicant. [10] [11] On August 27, 2008, Palin signed a bill into law giving the state of Alaska authority to award TransCanada Corp. 500 million dollars in seed money and a license to build and operate the $26-billion pipeline to transport natural gas from the North Slope to the Lower 48, through Canada. [12] [13]

The license is not a construction contract, and federal energy regulators must approve the project before it can go forward. [14]

On December 5, 2008, the AGIA license, jointly awarded to Foothills Pipe Lines Ltd. and TransCanada Alaska, LLC, was signed in Fairbanks. [15]

The pipeline proposed by TransCanada would run 1,715 miles (2,760 km) from the North Slope to Calgary in Alberta. It is expected to cost US$26 billion and to be operational by 2018. [1]

In 2014, the agreement between Alaska and Transcanada was cancelled in the light of substantially lower prices for natural gas and increased use of extraction technology that has markedly boosted supply, making the pipeline arrangement uneconomic. The 500 million dollars in seed money was forfeited by the State legally to Transcanada under a cancellation clause for front end engineering and design work completed. [16]

Denali proposal

Outside of the AGIA process, authorities were evaluating a separate proposal issued by Denali – The Alaska Gas Pipeline LLC, a joint venture of ConocoPhillips and BP. [1] [17] [18] ExxonMobil was invited to participate in the project. [19] Also Enbridge, Royal Dutch Shell and Gazprom had shown interest to join this project. [20] [21] [22] However, on 17 May 2011 Denali announced that it ends developing the project due lack of interest from potential customers. [23]

The project foresaw a pipeline with a capacity of 41 billion cubic meter (bcm) of natural gas per year down the Alaska Highway across Alaska, through the Yukon and British Columbia into Alberta. [1] [24] It also consisted of a gas treatment plant on North Slope. The project was estimated to cost US$35 billion. [23]

Route

Possible routes include the Alaska route, or southern route, a pipeline along the Alaska Highway. A shorter alternative route, which was considered in the 1970s, links Prudhoe Bay natural gas through Mackenzie River Valley. The pipeline will be built only if Canadian authorities can strike a deal with First Nations whose lands are in the pipeline route, who are accusing Palin and other pipeline proponents of treating them with disrespect by not consulting with them. [25]

Politics

Opposition to the Alaska natural gas pipeline route mandate and price supports came from both the Bush administration and the Canadian government. In a letter to the Sen. Domenici, Secretary of Energy Spencer Abraham wrote, "[The administration] believes market forces should select the route of the pipeline." He continued, "The administration strongly opposes the price-floor tax credit provision in the Senate energy bill and any similar provisions." Abraham suggested several non-price support tax provisions that could subsidize the construction of the pipeline. [26] Former Canadian Ambassador to the United States Michael Kergin wrote that Canada is of the opinion that the Alaskan pipeline should be built without subsidies and without the route being determined by legislation. [27]

The late Governor Wally Hickel advocated an "All-Alaskan" route which would go from Prudhoe Bay to Valdez and would bring gas to Fairbanks and Anchorage. He opposed the award of the route to TransCanada which would not result in gas service for Alaska's population centers. [28]

In June 2009 Alaska Governor Sarah Palin was interviewed on The Today Show by Matt Lauer. She expressed her support for the pipeline, which was ostensibly the purpose of her appearance on the program.

See also

Related Research Articles

<span class="mw-page-title-main">Alaska</span> U.S. state

Alaska is a non-contiguous U.S. state on the northwest extremity of North America. It is in the Western United States region. The only other non-contiguous U.S. state is Hawaii. Alaska is also considered to be the northernmost, westernmost, and easternmost state in the United States. It borders the Canadian territory of Yukon and the province of British Columbia to the east. It shares a western maritime border, in the Bering Strait, with Russia's Chukotka Autonomous Okrug. The Chukchi and Beaufort Seas of the Arctic Ocean lie to the north, and the Pacific Ocean lies to the south. Technically a semi-exclave of the U.S., it is the largest exclave in the world.

<span class="mw-page-title-main">Alyeska Pipeline Service Company</span>

The Alyeska consortium refers to the major oil companies that own and operate the Trans-Alaska Pipeline System (TAPS) through the Alyeska Pipeline Service Company.

<span class="mw-page-title-main">Trans-Alaska Pipeline System</span> Alaskan oil pipeline system

The Trans-Alaska Pipeline System (TAPS) is an oil transportation system spanning Alaska, including the trans-Alaska crude-oil pipeline, 12 pump stations, several hundred miles of feeder pipelines, and the Valdez Marine Terminal. TAPS is one of the world's largest pipeline systems. The core pipeline itself, which is commonly called the Alaska pipeline, trans-Alaska pipeline, or Alyeska pipeline,, is an 800-mile (1,287 km) long, 48-inch (1.22 m) diameter pipeline that conveys oil from Prudhoe Bay, on Alaska's North Slope, south to Valdez, on the shores of Prince William Sound in southcentral Alaska. The crude oil pipeline is privately owned by the Alyeska Pipeline Service Company.

<span class="mw-page-title-main">Alaska North Slope</span> Northern region of Alaska

The Alaska North Slope is the region of the U.S. state of Alaska located on the northern slope of the Brooks Range along the coast of two marginal seas of the Arctic Ocean, the Chukchi Sea being on the western side of Point Barrow, and the Beaufort Sea on the eastern. With the exception of the highway connecting Fairbanks to Prudhoe Bay, the region is disconnected from the rest of the Alaskan road system and relies mostly on waterways and small airports for transportation due to the Brooks Range secluding the region from the rest of the state.

<span class="mw-page-title-main">History of Alaska</span>

The history of Alaska dates back to the Upper Paleolithic period, when foraging groups crossed the Bering land bridge into what is now western Alaska. At the time of European contact by the Russian explorers, the area was populated by Alaska Native groups. The name "Alaska" derives from the Aleut word Alaxsxaq, meaning "mainland".

The Mackenzie Valley Pipeline, also called the Mackenzie River Pipeline, was a proposed project to transport natural gas from the Beaufort Sea through Canada's Northwest Territories to tie into gas pipelines in northern Alberta. The project was first proposed in the early 1970s but was scrapped following an inquiry conducted by Justice Thomas Berger. The project was resurrected in 2004 with a new proposal to transport gas through the sensitive arctic tundra. Probabilistic estimates of hydrocarbons in the Mackenzie Delta and Beaufort Sea regions project that there are natural gas reserves of 1.9 trillion cubic metres. After many delays, the project was officially abandoned in 2017 by the main investment partners citing natural gas prices and the long regulatory process.

<span class="mw-page-title-main">Mark Myers</span> American geologist (born 1955)

Mark D. Myers is an American geologist who currently serves as a commissioner for the U.S. Arctic Research Commission. He also served as the fourteenth Director of the U.S. Geological Survey (USGS). He was nominated by President George W. Bush on May 3, 2006, confirmed by the U.S. Senate, and sworn in September 26, 2006. Dr. Myers replaced prior director Charles G. Groat, who had resigned effective June 17, 2005.

Prudhoe Bay Oil Field is a large oil field on Alaska's North Slope. It is the largest oil field in North America, covering 213,543 acres (86,418 ha) and originally contained approximately 25 billion barrels (4.0×109 m3) of oil. The amount of recoverable oil in the field is more than double that of the next largest field in the United States by acreage (the East Texas Oil Field), while the largest by reserves is the Permian Basin (North America). The field was operated by BP; partners were ExxonMobil and ConocoPhillips until August 2019; when BP sold all its Alaska assets to Hilcorp.

<span class="mw-page-title-main">Prudhoe Bay oil spill</span> Alaskan oil spill of 2006

The Prudhoe Bay oil spill was an oil spill that was discovered on March 2, 2006, at a pipeline owned by BP Exploration, Alaska (BPXA) in western Prudhoe Bay, Alaska. Initial estimates of the five-day leak said that up to 267,000 US gallons (6,400 bbl) were spilled over 1.9 acres (7,700 m2), making it the largest oil spill on Alaska's north slope to date. Alaska's unified command ratified the volume of crude oil spilled as 212,252 US gallons (5,053.6 bbl) in March 2008. The spill originated from a 0.25-inch (0.64 cm) hole in a 34-inch (86 cm) diameter pipeline. The pipeline was decommissioned and later replaced with a 20-inch (51 cm) diameter pipeline with its own pipeline inspection gauge (pig) launch and recovery sites for easier inspection.

Ralph Samuels is a businessman and a member of the Republican Party and candidate for Governor of Alaska, that served as a state representative of the Alaska State Legislature from 2002 to 2008 representing House District 29 and serving as the majority leader.

<span class="mw-page-title-main">Governorship of Sarah Palin</span> Sarah Palins tenure as the 9th Governor of Alaska

In 2006, Sarah Palin was elected governor of Alaska. Running on a clean-government platform, Palin defeated incumbent Governor Frank Murkowski in the Republican gubernatorial primary election in August. She then went on to win the general election in November, defeating former Governor Tony Knowles 48.3% to 40.9%. Her running mate was State Senator Sean Parnell.

<span class="mw-page-title-main">Natural gas in Alaska</span>

The State of Alaska is both a producer and consumer of natural gas. In 2006, Alaska consumed 180.4 Bcf of natural gas.

<span class="mw-page-title-main">Isabel Pass</span> Mountain pass of Alaska, US

Isabel Pass is a 40 mile long gap in the eastern section of the Alaska Range which serves as a corridor for the Richardson Highway about 11 miles from Paxson. It is named after the wife of E. T. Barnette, who helped found Fairbanks. The pass separates four regions, the Tanana Valley to the north, the Delta Mountains to the east, Copper River Basin to the south, and the Hayes Range to the west.

<span class="mw-page-title-main">Economy of Alaska</span>

In a report compiled by the government of Alaska, the real GDP of Alaska was $51.1 billion in 2011, $52.9 billion in 2012 and $51.5 billion in 2013. The drop-off that occurred between 2012 and 2013 has been attributed to the decline in the mining sector, specifically the oil and gas sectors, a consequence of declined production. The state's economy has been described by University of Alaska Anchorage economist Scott Goldsmith as a "three-legged stool" – with one leg being the petroleum and gas industry, the second leg being the federal government and the third leg being all other industries and services. Between 2004 and 2006, the federal government was responsible for 135,000 Alaska jobs, the petroleum sector provided 110,000 jobs and all other industries and services combined for 122,000 jobs.

<span class="mw-page-title-main">Outline of Alaska</span> 49th and least populated state of U.S

The following outline is provided as an overview of and topical guide to the U.S. state of Alaska:

Marvin Dale Mangus (1924–2009) was an American geologist and landscape painter. He was giving the honor of driving a purely symbolic wood stake prior to start of drilling the actual oil well by the Atlantic Richfield Corporation, his employer. The focus of his later art career was glorified role of geologist and other exploration of Alaska. He painted animals and birds and was recognized with awards from The National Park Service

<span class="mw-page-title-main">ConocoPhillips Alaska</span> Subsidiary of ConocoPhillips located in Anchorage, Alaska

ConocoPhillips Alaska, Inc. is a subsidiary of ConocoPhillips, with its headquarters in Anchorage, Alaska. The company has major lease holdings on the North Slope and is Alaska's largest producer of oil and gas, employing about 1,000 persons.

<span class="mw-page-title-main">Larry Persily</span>

Larry Persily is a newspaper publisher and former Federal Coordinator of the Alaska Natural Gas Transportation Projects 2010–2015. The office was charged with coordinating federal agency responses to private-sector efforts to develop a natural gas pipeline from Alaska's North Slope to supply the North American market. The Federal Coordinator is nominated with advice and consent of the Senate by the President of the United States. He was nominated by Barack Obama on December 9, 2009, and was confirmed by the United States Senate on March 10, 2010. The office closed down in 2015 as the private companies turned their attention to a gas export project instead.

Alaska v. Amerada Hess et al., officially known as State v. Amerada Hess et al. (1JU-77-877) was a 15-year-long civil lawsuit levied by the state of Alaska against 17 of the world's largest oil companies for underpayment of oil production royalties. The case was named after Amerada Hess, the first company in the alphabetical list of defendants. The case cost the state more than $100 million to prosecute, and all 17 companies settled out of court rather than face trial. The total settlements amounted to just over $600 million of the $902 million the state alleged had been underpaid. Additional settlements covering underpaid natural gas royalties and refining royalties amounted to another $400 million.

<span class="mw-page-title-main">Walter B. Parker</span>

Walter Bruce "Walt" Parker was an American civil servant, policy adviser, transportation adviser, academic and local politician. Parker's career focused on the development of natural resources, transportation and infrastructure in Alaska from the 1940s to the 2000s. In 1989, Alaska Governor Steve Cowper appointed Parker as the chairman of the Alaska Oil Spill Commission, which investigated the Exxon Valdez oil spill. He is credited with making important contributions to the fields of transportation, telecommunications, education, land use and urban planning within the state of Alaska. Parker was inducted into the Alaska Conservation Hall of Fame by the Alaska Conservation Foundation in 2002 for his contributions to state conservation.

References

  1. 1 2 3 4 Loy, Weley (2008-01-04). "Palin picks Canadian company for gas line". The Anchorage Daily News. Archived from the original on 2008-09-04. Retrieved 2008-06-14.
  2. "The Alaska Pipeline Project Begins Its Open Season". TransCanada Corporation. Archived from the original on 2015-09-19. Retrieved 2015-09-11.
  3. "Alaska Politics Blog: It's on: Exxon and TransCanada announce pipeline partnership (Updated) | adn.com". Community.adn.com. 2009-06-11. Archived from the original on 2009-08-10. Retrieved 2010-05-26.
  4. "Alaska natural gas pipeline project history | Arcticgas.gov". www.arcticgas.gov. Archived from the original on 2015-09-08. Retrieved 2015-09-11.
  5. 15 U.S.C.   § 717
  6. 15 U.S.C.   § 719
  7. North Slope Borough: 1,837 Yes / 471 No, Fairbanks North Star Borough: 10,760 Yes / 3,629 No, City of Valdez: 1037 Yes / 256 No. "Project Development Basis". Archived from the original on August 13, 2008. Retrieved September 29, 2016.
  8. Retrieved 2008-09-15. [ dead link ]
  9. "Alaska seeks bids for North Slope gas pipeline". CBC News. 2007-07-04. Retrieved 2008-06-14.
  10. "Palin picks Canadian company for gas line: Gas Pipeline". adn.com. Archived from the original on 4 September 2008. Retrieved 2008-08-29.
  11. "Canadian company meets AGIA requirements". ktuu.com. Archived from the original on 1 September 2008. Retrieved 2008-08-29.
  12. Rosen, Yereth.“Alaska governor signs natgas pipeline license bill” Archived August 26, 2010, at the Wayback Machine , Calgary Herald, (2008-08-27.
  13. Gismatullin, Edward (2008-08-29). "TransCanada Gets Alaska Governor Palin's Approval for Pipeline". Bloomburg.com. Retrieved 2008-09-16.
  14. "Some of Palin's remarks stretch the truth: Gas pipeline, earmark issues have more subtlety than described" Archived September 6, 2008, at the Wayback Machine , Anchorage Daily News, September 4, 2008
  15. "Palin, commissioners sign gasline license: Signing called 'historic day' as natural gas pipeline construction now ready to begin". Capital City Weekly . 2008-12-17. Archived from the original on 20 December 2008. Retrieved 2008-12-19.
  16. "Life after AGIA The Alaska Gasline Inducement Act is buried, but the pipeline dream lives on", Fairbanks News-Miner, January 12, 2014. Retrieved 30 June 2014.
  17. "Palin nod boosts TransCanada pipe plan" . Upstream Online . NHST Media Group. 2008-01-04. Retrieved 2008-06-14.
  18. Quinn, Steve (2008-04-09). "Denali proposal". WTOP. Retrieved 2008-06-14.[ dead link ]
  19. Mouawad, Jad; Krauss, Clifford (2008-04-09). "2 Oil Firms Plan Alaska Gas Pipeline" . New York Times. Archived from the original on 12 June 2008. Retrieved 2008-06-14.
  20. "Enbridge eyes Alaska pipeline" . Upstream Online . NHST Media Group. 2008-05-07. Retrieved 2008-06-14.
  21. Fowler, Tom (2008-04-10). "Enbridge, Shell Express Interest In Denali". Houston Chronicle . Downstream Today. Retrieved 2008-06-14.
  22. "Gazprom reveals Alaska pipe dream" . Upstream Online . NHST Media Group. 2008-06-09. Retrieved 2008-06-14.
  23. 1 2 "Denali Nixes Pipeline Project". Denali - The Alaska Gas Pipeline LLC. Downstream Today. 2011-05-17. Retrieved 2011-05-22.
  24. "ConocoPhillips lays Alaska pipe plans" . Upstream Online . NHST Media Group. 2007-11-30. Retrieved 2008-06-14.
  25. "Palin's Pipeline to Nowhere". Newsweek.com. 19 September 2008. Retrieved 2013-05-22.
  26. "White House opposes tax credit for gas line; Tax credit considered key in moving project forward". Associated Press. January 2, 2007. Archived from the original on February 25, 2012. Retrieved October 15, 2008.
  27. Kergin, Michael (2002-05-15). "Trust the Market (and Canada)". The Wall Street Journal. Retrieved 2009-12-15.
  28. Hickel, Wally (2008-06-21). "Sensible solution is for Alaska to build the gas pipeline". Anchorage Daily News. Archived from the original on 2012-07-19. Retrieved 2008-09-15.