Arrowrock Dam | |
---|---|
Location in Idaho | |
Country | United States |
Location | Boise and Elmore counties, Idaho |
Coordinates | 43°35′44″N115°55′20″W / 43.59556°N 115.92222°W |
Purpose | Irrigation |
Construction began | 1911 |
Opening date | 1915[1] |
Owner(s) | U.S. Bureau of Reclamation |
Dam and spillways | |
Type of dam | Arch dam |
Impounds | Boise River |
Height | 350 feet (107 m) [1] |
Length | 1,150 feet (351 m) [1] |
Reservoir | |
Creates | Arrowrock Reservoir |
Total capacity | 300,850 acre-feet (0.371 km3) [1] |
Catchment area | 2,200 square miles (5,700 km2) [1] |
Surface area | 3,100 acres (12.5 km2) [1] |
Normal elevation | 3,210 ft (978 m) AMSL |
Power Station | |
Operator(s) | Boise Project Board of Control [2] |
Commission date | March 2010 [2] |
Installed capacity | 15 MW [2] |
Arrowrock Dam | |
NRHP reference No. | 72000437 |
---|---|
Added to NRHP | 1976 |
Arrowrock Dam is a concrete arch dam in the western United States, on the Boise River in southwestern Idaho, east of Boise. Opened 109 years ago in 1915, it is located on the border of Boise and Elmore counties, upstream of the Lucky Peak Dam and reservoir. The spillway elevation for Arrowrock is 3,219 feet (981 m) above sea level and its primary purpose is to provide irrigation water for agriculture.
The dam was designated as a National Historic Civil Engineering Landmark by the American Society of Civil Engineers in 2016, [3] and is operated by the U.S. Bureau of Reclamation.
In 1910, the Reclamation Service began to consider another storage facility farther east on the Boise River. After several surveys, engineers decided upon the Arrowrock site which had previously been the site of a private irrigation venture under the direction of Arthur De Wint Foote yet failed for lack of funding. [4] The Arrowrock site is at the confluence of the main channel and the south fork. That was to be the most ambitious project to date for Reclamation. At 348 feet (106 m), Arrowrock would be the largest concrete arch dam in the world. Prior to construction, considerable preparatory work would need to be completed. As the structure was some twenty miles (32 km) upstream from the Boise River Diversion Dam, routing supplies to the worksite would be a massive undertaking unto itself. The Reclamation Service elected to construct a new rail line on the old wagon road leading north to Idaho City. The railroad would begin at the Barberton mill near the Diversion Dam and extend to through a winding canyon up to Arrowrock. Even before the dam had been approved, Reclamation began work on the rail line.
Some significant problems existed with construction of the railroad. The Barberton Lumber Company owned the road's right-of-way. That meant that the Reclamation Service needed to come to an agreement over ownership of the rail line. In an unprecedented move, the government agreed to lease the track from Barberton but run the actual locomotive. Part of this agreement stipulated that the line would remain a common carrier. That made the Arrowrock & Boise Railroad the first publicly owned line in the nation. The Service hid this fact from President William Howard Taft when it applied for the Arrowrock Dam's approval. Fortunately for Reclamation, Taft failed to recognize the loophole and in June 1910, the entire project went forward. However, when the Oregon Shortline refused to honor the pact between Barberton and Reclamation, the Arrowrock & Boise terminal was reduced to a field just outside the Barber lumberyard. On August 22, 1910, the entire deal was finalized and work began on the line to the Arrowrock site.
Salt Lake City's Manly Brothers won the contract for grading the Arrowrock & Boise road in May 1911. The government called for force account to lay the track from Barber to the work site. Although the construction was delayed several times by the shortage of railroad ties, workers finished the track in early November. By most accounts, the trip through the canyon was a very long and harrowing event. For the first several months, riders were asked to disembark at the unfinished Gooseneck Bridge while the cars were winched across one at a time.
However, once they arrived, most passengers were surprised by what they found. Not only was the view breathtaking but the "work" camp offered amenities that were unavailable to some residents of the Treasure Valley. Not only was the site fully powered, but also it provided a central heating plant, running water and an efficient sewage system. Along with the Reclamation offices, the Arrowrock camp carried a hospital, mess hall, post office, and hotel. Workers and visitors were offered lodging in the site's hotel, bunkhouses, or cottages. In addition to the outdoor recreational activities, the camp also operated a YMCA, school, and dancehall. At the peak of construction, some 1,400 people had called Arrowrock home, including some 200 families.
To provide power for the site, Reclamation retrofitted The Boise River Diversion Dam with a small powerhouse. Finished in 1912, the plant's three generators produced 1,500 kilowatts of electricity for Arrowrock's camp, sawmills, and giant cement mixers. The German made Allis-Chalmers 725 horsepower (541 kW) turbines, the first in the world to be built with a vertical shaft design. Along with the power lines, government workers hung a two-way phone cable to connect Arrowrock with the outside world. In 1976, the power plant was added to the National Register of Historic Places. After being refurbished by the Bonneville Power Administration in 2002, it is now on ready reserve status and occasionally provides surplus power during times of peak demand. Special care was made to maintain the historic qualities of the powerhouse. The original governors, slate control panels, transformers, overhead crane, and generator housings, although no longer functional, were retained for historic purposes.
Work began on the Arrowrock Dam in early 1912 and moved along at a record-setting pace. As labor was becoming more plentiful with the completion of Deer Flat and the Diversion Dam, wage rates began to decrease. Common laborers were now offered $2.40 and day while skilled workers pulled in anywhere from $3.00 to $4.00. In addition, several deductions were made for room and board. Workers could choose between the dormitory style bunkhouses at $1.25 a month or a private room at $4.00. Seventy-five cents was deducted each day for meals and $1.00 a month went towards hospital costs. The work proved moderately dangerous and accounted for numerous injuries and twelve deaths. However, despite the hazards and reduction in pay, it appears there was a unique level of camaraderie at the Arrowrock site. As stated above, the workers set several construction records, not the least of which included the 527,300 cubic yards (403,100 m3) of concrete laid on the dam.
The Reclamation Service spared no expense regarding the equipment at Arrowrock Dam. Along with the refurbished 70-ton Atlantic steam shovel from Deer Flat were two versatile 18-ton "dinkey" excavators and several brand new dump cars. The cement mixers produced over 2,000 barrels per day and ran uninterrupted for almost 30 months. Two 12-ton Lidgerwood cableways hovered over the site and moved material and concrete from their loading grounds to the dam site. Scores of horse teams helped carry equipment and gravel from the camp to the various work areas. Additionally, one Buick and seven Ford trucks serviced both crews and visitors and provided an unexpected level of mobility throughout the campsite. In an effort to alleviate some of the discomfort along the Boise & Arrowrock, Reclamation purchased a 60-ton locomotive and several new passenger cars. For almost five years, the train ran faithfully through the canyon, delivering over 89,500 visitors and crewmen. Also, during its commission, the Boise & Arrowrock traveled more than 110,000 miles (180,000 km) and carried 14,000,000 tons of freight.
On October 4, 1915, the Arrowrock Dam was finally dedicated. As stated above, it was the tallest dam in the world for nine years, until the completion of the Schräh dam in Switzerland in 1924, with a height of 366 feet (111.6 m). In addition, engineers pioneered the use of dam instrumentation with the placement of ten thermometers embedded deep within the structure's concrete. Along with innovative contraction joints, the Reclamation Service was able to control the temperature of the setting concrete, ensuring the dams strength. It is 225 feet (69 m) thick at the base and 15 feet (4.6 m) thick at the crest. It is serviced by 25 outlets some of which are designed to regulate themselves, another first in engineering. Ten outlets were built for an eventual power plant, but they have yet to be used.
In total, the dam contains 585,160 cubic yards (447,390 m3) of concrete and the reservoir holds over 286,000 acre-feet (353,000,000 m3) of irrigation water. Within the first week of operation, an estimated 12,000 visitors braved the canyon ride to see the dam. However, as interest waned, the Arrowrock & Boise Railroad schedule dropped significantly. The campsite, once a bustling hive of activity, was quickly becoming a ghost town. On August 11, 1916, the government decommissioned its very first public carrier.
From 1935 to 1937, construction at Arrowrock raised the dam five feet (1.5 m), increasing its capacity by 9,000 acre-feet (11,100,000 m3), and replaced deteriorating concrete on the dam's downstream face and spillway channel. [2]
From 2001 to 2004, ten aging Ensign valves were removed and replaced with clamshell gates. By 2011, work was completed to permanently plug all five sluice gate outlets. [2]
A 15-MW powerplant was added to Arrowrock Dam in March 2010, and the transmission line to the dam was updated. [2]
Hoover Dam is a concrete arch-gravity dam in the Black Canyon of the Colorado River, on the border between the U.S. states of Nevada and Arizona. Constructed between 1931 and 1936, during the Great Depression, it was dedicated on September 30, 1935, by President Franklin D. Roosevelt. Its construction was the result of a massive effort involving thousands of workers, and cost over 100 lives. In bills passed by Congress during its construction, it was referred to as the Hoover Dam, after President Herbert Hoover, but was named the Boulder Dam by the Roosevelt administration. In 1947, the name Hoover Dam was restored by Congress.
Grand Coulee Dam is a concrete gravity dam on the Columbia River in the U.S. state of Washington, built to produce hydroelectric power and provide irrigation water. Constructed between 1933 and 1942, Grand Coulee originally had two powerhouses. The third powerhouse ("Nat"), completed in 1974 to increase energy production, makes Grand Coulee the largest power station in the United States by nameplate capacity at 6,809 MW.
The Los Angeles Aqueduct system, comprising the Los Angeles Aqueduct and the Second Los Angeles Aqueduct, is a water conveyance system, built and operated by the Los Angeles Department of Water and Power. The Owens Valley aqueduct was designed and built by the city's water department, at the time named The Bureau of Los Angeles Aqueduct, under the supervision of the department's Chief Engineer William Mulholland. The system delivers water from the Owens River in the eastern Sierra Nevada mountains to Los Angeles.
The Boise River is a 102-mile-long (164 km) tributary of the Snake River in the Northwestern United States. It drains a rugged portion of the Sawtooth Range in southwestern Idaho northeast of Boise, as well as part of the western Snake River Plain. The watershed encompasses approximately 4,100 square miles (11,000 km2) of highly diverse habitats, including alpine canyons, forest, rangeland, agricultural lands, and urban areas.
The Salt River Project (SRP) encompasses two separate entities: the Salt River Project Agricultural Improvement and Power District, an agency of the state of Arizona that serves as an electrical utility for the Phoenix metropolitan area, and the Salt River Valley Water Users' Association, a utility cooperative that serves as the primary water provider for much of central Arizona. It is one of the primary public utility companies in Arizona.
The American Falls Dam is a concrete gravity-type dam in the western United States, located near American Falls, Idaho, on river mile 714.7 of the Snake River. The dam and reservoir are a part of the Minidoka Project on the Snake River Plain and are used primarily for flood control, irrigation, and recreation. When the original dam was built in the 1920s by the U.S. Bureau of Reclamation, the residents of American Falls were forced to relocate three-quarters of their town to make room for the reservoir.
Hungry Horse Dam is an arch dam in the Western United States, on the South Fork Flathead River in the Rocky Mountains of northwest Montana. It is located in Flathead National Forest in Flathead County, about fifteen miles (24 km) south of the west entrance to Glacier National Park, nine miles (14 km) southeast of Columbia Falls, and twenty miles (32 km) northeast of Kalispell. The Hungry Horse project, dam, and powerplant are operated by the U.S. Bureau of Reclamation. The entrance road leading to the dam is located in Hungry Horse.
Yellowtail Dam is a dam across the Bighorn River in south central Montana in the United States. The mid-1960s era concrete arch dam serves to regulate the flow of the Bighorn for irrigation purposes and to generate hydroelectric power. The dam and its reservoir, Bighorn Lake, are owned by the U.S. Bureau of Reclamation.
Cabinet Gorge Dam is a concrete gravity-arch hydroelectric dam in the northwest United States, on the Clark Fork River in northern Idaho. The dam is located just west of the Montana border and the Cabinet Gorge Reservoir extends into Montana, nearly to Noxon Rapids Dam. The purpose of the dam is for hydroelectricity.
The Central Utah Project is a US federal water project that was authorized for construction under the Colorado River Storage Project Act of April 11, 1956, as a participating project. In general, the Central Utah Project develops a portion of Utah's share of the yield of the Colorado River, as set out in the Colorado River Compact of 1922.
Buffalo Bill Dam is a concrete arch-gravity dam on the Shoshone River in the U.S. state of Wyoming. Originally 325-foot (99 m), it was the tallest dam in the world when it opened in 1910; a 25-foot (7.6 m) extension was added in 1992 in one of numerous changes and improvements to the structure and its support facilities, which include two full time power generators and two seasonal operations added between 1920 and 1994, and a 2.8-mile (4.5 km) irrigation tunnel completed in 1939.
Owyhee Dam is a concrete arch-gravity dam on the Owyhee River in Eastern Oregon near Adrian, Oregon, United States. Completed in 1932 during the Great Depression, the dam generates electricity and provides irrigation water for several irrigation districts in Oregon and neighboring Idaho. At the time of completion, it was the tallest dam of its type in the world. The dam is part of the Owyhee Dam Historic District, which is listed on the National Register of Historic Places.
Anderson Ranch Dam is an earth rockfill type dam in the western United States, on the South Fork of the Boise River in southwestern Idaho. In Elmore County northeast of Mountain Home, it is several miles north of U.S. Route 20 and operated by the U.S. Bureau of Reclamation.
The Boise River Diversion Dam is a diversion dam in the western United States, on the Boise River in southwestern Idaho. Seven miles (11 km) southeast and upstream of Boise in Ada County, it was completed 115 years ago in 1909 and is operated by the U.S. Bureau of Reclamation.
Glen Canyon Dam, a concrete arch dam on the Colorado River in the American state of Arizona, is viewed as carrying a large amount of risk, most notably due to siltation. The Colorado and San Juan rivers deposit large volumes of silt into Lake Powell, slowly decreasing its capacity. The sediment will eventually build up against the dam and could affect its safe operation and lead to its failure.
Morris Dam is a concrete gravity dam across the San Gabriel River in the U.S. state of California. It impounds Morris Reservoir, directly downstream of San Gabriel Dam.
Big Tujunga Dam is a 244-foot-high (74 m) concrete arch dam in Los Angeles County, California, spanning Big Tujunga Canyon northeast of Sunland, in the foothills of the San Gabriel Mountains. Completed in 1931, it provides flood control and groundwater recharge for the San Fernando Valley.
The Big Creek Hydroelectric Project is an extensive hydroelectric power scheme on the upper San Joaquin River system, in the Sierra Nevada of central California. The project is owned and operated by Southern California Edison (SCE). The use and reuse of the waters of the San Joaquin River, its South Fork, and the namesake of the project, Big Creek – over a vertical drop of 6,200 ft (1,900 m) – have over the years inspired a nickname, "The Hardest Working Water in the World".
Deer Flat Upper Embankment is a dam in the western United States in southwestern Idaho. Located in the Treasure Valley in Canyon County, it is directly southwest of Nampa.
The Upper North Fork Feather River Project is a hydroelectric scheme in the Sierra Nevada of California, within Lassen and Plumas Counties. The project consists of three dams, five power plants, and multiple conduits and tunnels in the headwaters of the North Fork Feather River, a major tributary of the Feather—Sacramento River systems. The total installed capacity is 362.3 megawatts (MW), producing an annual average of 1,171.9 gigawatt hours (GWh). The project is also contracted for the delivery of irrigation water between March 31 and October 31 of each year. The project is owned and operated by Pacific Gas and Electric Company.