Castaic Power Plant

Last updated
Castaic Power Plant
Castaic Power Plant Front.jpg
Front of Castaic Power Plant
Official nameCastaic Power Plant
CountryUnited States
Location Los Angeles County, California
Coordinates 34°35′14.32″N118°39′23.88″W / 34.5873111°N 118.6566333°W / 34.5873111; -118.6566333
Construction began1966
Opening dateJuly 11, 1973 [1]
Owner(s) CDWR, LADWP
Upper reservoir
Creates Pyramid Lake
Total capacity186,000 acre⋅ft (229,427,622 m3)
Lower reservoir
Creates Elderberry Forebay
Total capacity28,400 acre⋅ft (35,030,884 m3)
Power Station
Hydraulic head 1,060 ft (323 m)
Turbines 7
Pump-generators6
Installed capacity 1507 MW (nominal)
1247 MW (rated)
Annual generation 880,702,000 KWh (gross, 2001–2012)
319,181,000 KWh (net, 2001–2012) [2]

Castaic Power Plant, also known as the Castaic Pumped-Storage Plant, is a seven unit pumped-storage hydroelectric plant, operated by the Los Angeles Department of Water and Power, which provides peak load power from the falling water on the West Branch of the California State Aqueduct. It is a cooperative venture between the LADWP and the Department of Water Resources of the State of California. An agreement between the two organizations was signed on September 2, 1966, for construction of the project.

Contents

Location

The Castaic Power Plant is located about 22 miles (35 km) from the northern Los Angeles city limits at the upper end of the West arm of Castaic Lake.

Water supply

California State Aqueduct water en route to Southern California is pumped up through the Tehachapi Mountains (by the Edmonston Pumping Plant) to the Tehachapi Afterbay. There the aqueduct divides into East and West Branches. The West Branch water is again pumped at the Oso Pumping Plant to Quail Lake, near Highway 138 East of Gorman. From here it flows through a permanent pipeline waterway to Warne Power Plant, which is located at the inlet to Pyramid Lake. The Warne Plant was constructed by the state of California in 1983. Pyramid Lake has a surface area of 1,380 acres (560 ha) and a storage capacity of 180,000 acre-feet (220,000,000 m3) with a maximum water surface elevation of 2,578 feet (786 m) above sea level. Pyramid Lake is the upper forebay for the Castaic Power Plant.

Angeles Tunnel

The State of California had planned to build a tunnel 17 feet (5.2 m) in diameter. Under the cooperative development, this tunnel was enlarged to 30 feet (9.1 m) in diameter. The 7.2-mile (11.6 km) long tunnel, including the penstocks, drops water 1,060 feet (320 m) between Pyramid Lake and the hydroelectric power facilities, and carries over five times the flow previously contemplated for the 17-foot (5.2 m) tunnel.

Turbines

The Castaic Power Plant has six reversible 250,000 kilowatt main units and one conventional 55,000 kilowatt auxiliary unit. By comparison the largest generators at Hoover Dam are 130,000 kilowatts. The plant rating is 1,247,000 kilowatts (Nominal installed capacity is higher (over 1,500 MW), however when all main units are operating at full load in generate, they are de-rated by friction losses from the water flow in the Angeles Tunnel). The 55,000 kilowatt unit (Unit 7) was placed in service in February 1972. The unit also serves as a pump-starting unit for the six reversible units. The first main unit became operational in 1973. Unit six, the last unit, was placed in service in 1978. Power is generated at 18,000 volts then stepped up to 230,000 volts to be distributed to various receiving substations in Los Angeles. Each of the six 250,000 kilowatt units function as pumps as well as generators. Each pump will have a power input of 320,000 horsepower (240,000 kW) when pumping at a rate of 2,300 cubic feet per second (65 m3/s). The turbines/pumps are used a few percent of the time. [3]

Surge chamber

Visible from Templin Highway and normally mistaken for a water tank, the surge chamber sits at the south end of the Angeles Tunnel. The surge chamber is 120 feet in diameter and 400 feet high with 160 feet visible above ground. [4] The chamber is there to relieve excess pressure in the tunnel and penstocks if the plant were to experience an emergency shutdown of its generators. It also supplies water for quickly starting the plant's generators while water gains speed in the 7 mile long Angeles Tunnel.

Castaic Reservoir

Water from the Castaic Power Plant is discharged into Elderberry Lake (pumping forebay) from which it can be released into Castaic Lake, created by Castaic Dam. Castaic Lake has a surface area of 2,232 acres (903 ha) and a storage capacity of 324,000 acre-feet (400,000,000 m3), with a normal maximum surface elevation of 1,505 feet (459 m) above sea level. The amount of water in the lake varies with the demand for water delivery from the West Branch of the State Aqueduct.

Pumped-storage operation

The pumping forebay, which is separated from the main reservoir by a dam located downstream from the Castaic Power Plant, functions in connection with the pumped storage operations of the plant. This assures the availability of at least 10,000 acre-feet (12,000,000 m3) of water which can be pumped back to Pyramid Lake by the use of off peak energy when economical to do so. The pumping function at Castaic hydroelectric plant provides additional water for power generation beyond the supply of water available from the flow of the State Aqueduct. The City of Los Angeles has need for capacity to meet its peak requirements ranging from 3 to 6 hours per day in the winter to 6 to 10 hours per day in summer, depending upon climatic conditions. The water which normally flows through the West Branch of the State Aqueduct during off peak periods, is stored in the higher level Pyramid Lake. This water can be channeled through the turbine generators in a very short time to immediately meet short time peak demands on the DWP's electric system. If the need exists for power for longer than normal peak demand periods, extra water can be pumped back to Pyramid Lake from Elderberry Lake to extend the peaking period.

Related Research Articles

<span class="mw-page-title-main">Los Angeles Aqueduct</span> Water conveyance system in California, United States

The Los Angeles Aqueduct system, comprising the Los Angeles Aqueduct and the Second Los Angeles Aqueduct, is a water conveyance system, built and operated by the Los Angeles Department of Water and Power. The Owens Valley aqueduct was designed and built by the city's water department, at the time named The Bureau of Los Angeles Aqueduct, under the supervision of the department's Chief Engineer William Mulholland. The system delivers water from the Owens River in the eastern Sierra Nevada mountains to Los Angeles.

<span class="mw-page-title-main">California Aqueduct</span> Water supply project

The Governor Edmund G. Brown California Aqueduct is a system of canals, tunnels, and pipelines that conveys water collected from the Sierra Nevada Mountains and valleys of Northern and Central California to Southern California. Named after California Governor Edmund Gerald "Pat" Brown Sr., the over 400-mile (640 km) aqueduct is the principal feature of the California State Water Project.

<span class="mw-page-title-main">Pyramid Dam</span> Embankment dam impounding Piru Creek in Los Angeles County, California, United States

Pyramid Dam is a dam on Piru Creek located in northern Los Angeles County, north of Castaic and south of Gorman. Its reservoir, Pyramid Lake, stores water from the West Branch California Aqueduct for Ventura County and Los Angeles County. They are smaller than Castaic Dam and Lake, the other artificial water storage facility in the area, 7 miles (11 km) to the south.

<span class="mw-page-title-main">Pyramid Lake (Los Angeles County, California)</span> Reservoir in Los Angeles County, California, United States

Pyramid Lake is a reservoir formed by Pyramid Dam on Piru Creek in the eastern San Emigdio Mountains, near Castaic, Southern California. It is a part of the West Branch California Aqueduct, which is a part of the California State Water Project. Its water is fed by the system after being pumped up from the San Joaquin Valley and through the Tehachapi Mountains.

<span class="mw-page-title-main">Diamond Valley Lake</span> Reservoir in Riverside County, California, United States

Diamond Valley Lake is a man-made off-stream reservoir located near Hemet, California, United States. It is one of the largest reservoirs in Southern California and one of the newest. It has a capacity of 800,000 acre-feet (990,000,000 m3). The lake nearly doubled the area's surface water storage capacity and provides additional water supplies for drought, peak summer, and emergency needs.

<span class="mw-page-title-main">Metropolitan Water District of Southern California</span> Regional wholesaler of water in Southern California

The Metropolitan Water District of Southern California is a regional wholesaler and the largest supplier of treated water in the United States. The name is usually shortened to "Met," "Metropolitan," or "MWD." It is a cooperative of fourteen cities, eleven municipal water districts, and one county water authority, that provides water to 19 million people in a 5,200-square-mile (13,000 km2) service area. It was created by an act of the California State Legislature in 1928, primarily to build and operate the Colorado River Aqueduct. Metropolitan became the first contractor to the State Water Project in 1960.

The South Bay Aqueduct is an aqueduct located in the eastern part of the San Francisco Bay Area. It conveys water from the Sacramento-San Joaquin Delta through over forty miles of pipelines and canals. It begins in north-eastern Alameda County on the California Aqueduct's Bethany Reservoir serving as the forebay. The aqueduct flows along the eastern and southern edges of the Livermore Valley. Then it flows through a series of tunnels to an end in the foothills of eastern San Jose, 5 miles (8 km) from downtown San Jose, California.

<span class="mw-page-title-main">Castaic Dam</span> Embankment dam impounding Castaic Creek in Los Angeles County, California, United States

Castaic Dam is an embankment dam in northwestern Los Angeles County, California, in the unincorporated area of Castaic. Although located on Castaic Creek, a major tributary of the Santa Clara River, Castaic Creek provides little of its water. The lake is the terminus of the West Branch of the California Aqueduct, part of the State Water Project. The dam was built by the California Department of Water Resources and construction was completed in 1973. The lake has a capacity of 325,000 acre-feet (401,000,000 m3) and stores drinking water for the western portion of the Greater Los Angeles Area.

<span class="mw-page-title-main">San Luis Dam</span> Dam in Merced County, California

San Luis Dam, also known as B.F. Sisk Dam, is a major earth-filled dam in Merced County, California, which forms San Luis Reservoir, the largest off-stream reservoir in the United States. The dam and reservoir are located in the Diablo Range to the east of Pacheco Pass and about 10 miles (16 km) west of Los Banos. San Luis Dam, a jointly-owned state and federal facility, stores more than 2 million acre feet (2.5 km3) of water for the California State Water Project and the federal Central Valley Project. Although the dam is located in the valley of San Luis Creek, the majority of its water comes from man-made aqueducts which are supplied from other rivers in Northern California.

<span class="mw-page-title-main">California State Water Project</span> Flood control, energy production, and water conveyance infrastructure

The California State Water Project, commonly known as the SWP, is a state water management project in the U.S. state of California under the supervision of the California Department of Water Resources. The SWP is one of the largest public water and power utilities in the world, providing drinking water for more than 27 million people and generating an average of 6,500 GWh of hydroelectricity annually. However, as it is the largest single consumer of power in the state itself, it has a net usage of 5,100 GWh.

<span class="mw-page-title-main">Castaic Creek</span> Tributary of the Santa Clara River in California, United States

Castaic Creek is a 25.0-mile-long (40.2 km) stream in the Sierra Pelona Mountains, in northeastern Los Angeles County, California. It is a tributary of the Santa Clara River.

<span class="mw-page-title-main">Castaic Lake</span> Reservoir in the Sierra Pelona of Los Angeles County, California, United States

Castaic Lake is a reservoir formed by Castaic Dam on Castaic Creek, in the Sierra Pelona Mountains of northwestern Los Angeles County, California, United States, near the town of Castaic.

<span class="mw-page-title-main">Robert Moses Niagara Power Plant</span> Niagara River dam in New York State

The Robert Moses Niagara Hydroelectric Power Station is a hydroelectric power station in Lewiston, New York, near Niagara Falls. Owned and operated by the New York Power Authority (NYPA), the plant diverts water from the Niagara River above Niagara Falls and returns the water into the lower portion of the river near Lake Ontario. It uses 13 generators at an installed capacity of 2,525 MW (3,386,000 hp) with an average annual net generation of 15,897,000 MWh between 2014 and 2023, and a capacity factor of 71.9%.

<span class="mw-page-title-main">Fryingpan–Arkansas Project</span>

The Fryingpan–Arkansas Project, or "Fry-Ark," is a water diversion, storage and delivery project serving southeastern Colorado. The multi-purpose project was authorized in 1962 by President Kennedy to serve municipal, industrial, and hydroelectric power generation, and to enhance recreation, fish and wildlife interests. Construction began in 1964 and was completed in 1981. The project includes five dams and reservoirs, one federal hydroelectric power plant, and 22 tunnels and conduits totaling 87 miles (140 km) in length. The Bureau of Reclamation, under the Department of the Interior built and manages the project.

<span class="mw-page-title-main">Oroville–Thermalito Complex</span>

The Oroville–Thermalito Complex is a group of reservoirs, structures, and facilities located in and around the city of Oroville in Butte County, California. The complex serves not only as a regional water conveyance and storage system, but is the headwaters for, and therefore perhaps is the most vital part of, the California Department of Water Resources' State Water Project, as one of the largest publicly built and operated water and power development and conveyance systems.

<span class="mw-page-title-main">New Don Pedro Dam</span> Dam in California

New Don Pedro Dam, often known simply as Don Pedro Dam, is an earthen embankment dam across the Tuolumne River, about 2 miles (3.2 km) northeast of La Grange, in Tuolumne County, California. The dam was completed in 1971, after four years of construction, to replace the 1924 concrete-arch Don Pedro Dam.

<span class="mw-page-title-main">Big Creek Hydroelectric Project</span> Hydroelectric Power Scheme on upper San Joaquin River System, Sierra Nevada, Central California

The Big Creek Hydroelectric Project is an extensive hydroelectric power scheme on the upper San Joaquin River system, in the Sierra Nevada of central California. The project is owned and operated by Southern California Edison (SCE). The use and reuse of the waters of the San Joaquin River, its South Fork, and the namesake of the project, Big Creek – over a vertical drop of 6,200 ft (1,900 m) – have over the years inspired a nickname, "The Hardest Working Water in the World".

Elderberry Forebay is a small reservoir in Los Angeles County, California, which serves as the pumping forebay of the Castaic Power Plant. It located at the upper end of the larger Castaic Lake and is separated from the lake by Elderberry Forebay Dam at its southern edge. Entering the northern end of the forebay is the west branch of the California Aqueduct, which connects the forebay to Pyramid Lake through the Angeles Tunnel.

Elderberry Forebay Dam is a dam located in the Sierra Pelona Mountains of northwestern Los Angeles County, California. The dam partitions Elderberry Forebay from Castaic Lake. It forms the headwater reservoir for Castaic Power Plant, a pumped-storage hydroelectricity generation facility. The dam was completed in 1974 as part of the California State Water Project.

<span class="mw-page-title-main">Angeles Tunnel</span> Water tunnel under the Sierra Pelona of Los Angeles County, California

The Angeles Tunnel is a 7.2-mile-long (11.6 km), 30-foot-diameter (9.1 m) water tunnel located in the Sierra Pelona Mountains in Los Angeles County, California, about 50 miles (80 km) north of Los Angeles. It was constructed between 1967 and 1970 as part of the California State Water Project and serves as the final leg of the west branch of the California Aqueduct, which carries Northern California water to Southern California residents.

References

  1. "Los Angeles Department of Water and Power Energy Storage Development Plan: Description of Existing and Eligible Energy Storage System" (PDF). LADWP. September 2, 2014. pp. 7–8. Archived from the original (PDF) on 13 January 2020. Retrieved 12 December 2019.
  2. "California Hydroelectric Statistics & Data". California Energy Commission. Archived from the original on 2018-02-26. Retrieved 2018-04-26.
  3. Historic Pump-Storage Operation in WSCC, page 14
  4. "Pumped Storage in California | The Center for Land Use Interpretation". clui.org. Retrieved 2024-05-21.