Guthega Power Station

Last updated

Guthega Power Station
Guthega power station (IMG 7884).JPG
Power Station viewed from across the Snowy River
LocationSnowy Mountains, New South Wales
Coordinates36°20′58″S 148°24′50″E
StatusOperational
Construction beganNovember 1951
Opening dateApril 1955
Owner(s)Snowy Hydro
Power Station
Hydraulic head 246.9m (810 ft)
Turbines 2
Installed capacity 60 MW (80,000 hp)
Annual generation 172 GWh (620 TJ)

Guthega Power Station is located in the Snowy Mountains region of New South Wales, Australia. The power station's purpose is for the generation of electricity. It is the first to be completed and smallest of the initial seven hydroelectric power stations that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

Contents

This station is connected to the National Electricity Market via the TransGrid 330/132KV Substation at the TransGrid 330KV Murray Switching Station, 1.56 kilometres (1.71 mi) South East of Khancoban.

Location and features

Guthega power station is located at the confluence of the Munyang River and the Snowy River, approximately 5.5 kilometres (3.4 mi) downstream of the Guthega Dam wall. It is a conventional hydroelectric power station, situated above ground. The waters held in the reservoir behind Guthega dam pass through a concrete lined tunnel, a surge tank and firstly one, then two steel penstocks to the power station to generate electricity.

Inside the machine hall - English Electric generators as they appeared in 1982 Guthega power station - English Electric generators (1982).jpg
Inside the machine hall - English Electric generators as they appeared in 1982

The powerhouse is a concrete structure with a machine hall that is 51.46 metres (168.8 ft) long, 17.83 metres (58.5 ft) wide, and 32.61 metres (107.0 ft) high. Approximately 6,880 cubic metres (243,000 cu ft) of concrete was used in its construction which commenced in November 1951 and was completed in April 1955.

The power station has two Francis turbines each driving an English Electric generator. The power station includes foundations for a third unit but this was never installed as there was insufficient water to make it worthwhile. The power station has a rated hydraulic head of 246.9 metres (810 ft). Each turbine runs at 428  rpm and water flows through it at the rate of 28.3 cubic metres per second (1,000 cu ft/s). The total installed generating capacity is 60 megawatts (80,000 hp) of electricity yielding a net generation of 172 gigawatt-hours (620 TJ) annually. [1] [2] [3]

The Guthega Power Station is the highest power station in Australia.

Guthega power station and dam Guthega power station and dam.jpg
Guthega power station and dam

See also

Related Research Articles

<span class="mw-page-title-main">Dartmouth Dam</span> Dam in Victoria

Dartmouth Dam is a large rock-fill embankment dam with an uncontrolled chute spillway across the Mitta Mitta, Gibbo, and Dart rivers, the Morass Creek and a number of small tributaries. The dam is located near Mount Bogong in the north-east of the Australian state of Victoria. The dam's purpose includes irrigation, the generation of hydro-electric power, water supply and conservation. The impounded reservoir is called Dartmouth Reservoir, sometimes called Lake Dartmouth. The Dartmouth Power Station, a hydro-electric power station that generates power to the national grid, is located near the dam wall.

<span class="mw-page-title-main">Snowy Mountains Scheme</span> Dam in Kosciuszko National Park, New South Wales

The Snowy Mountains Scheme or Snowy scheme is a hydroelectricity and irrigation complex in south-east Australia, Near the border of NSW and Victoria (Australia). The Scheme consists of sixteen major dams; nine power stations; two pumping stations; and 225 kilometres (140 mi) of tunnels, pipelines and aqueducts that were constructed between 1949 and 1974. The Scheme was completed under the supervision of Chief Engineer, Sir William Hudson. It is the largest engineering project undertaken in Australia.

<span class="mw-page-title-main">Wivenhoe Power Station</span> Dam in Wivenhoe Pocket, Queensland

The Wivenhoe Power Station is situated between the Splityard Creek Dam and Lake Wivenhoe. The Splityard Creek Dam is situated in hills adjacent to Lake Wivenhoe and is about 100 metres (330 ft) above it.

<span class="mw-page-title-main">Blowering Dam</span> Dam in Snowy Mountains, New South Wales

The Blowering Dam is a major ungated rock fill with clay core embankment dam with concrete chute spillway impounding a reservoir under the same name. It is located on the Tumut River upstream of Tumut in the Snowy Mountains region of New South Wales, Australia. Purposes for the dam include flood mitigation, hydro-power, irrigation, water supply and conservation. The dam is part of the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

<span class="mw-page-title-main">Murray Hydroelectric Power Station</span> Dam in Snowy Mountains, New South Wales

The Murray Region Hydroelectric Power Stations refers to two of the original seven hydroelectric power stations, both located near the town of Khancoban in the Snowy Mountains region of New South Wales, Australia. The two power stations are part of the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro. Although both power stations are physically located in New South Wales, since 1 July 2008 all power generated has been allocated to the Victorian region of the National Electricity Market. The stations are not located on the Murray River.

<span class="mw-page-title-main">Tumut Hydroelectric Power Station</span> Power stations in New South Wales, Australia

The Tumut Hydroelectric Power Stations is a series of three hydroelectric power stations on the Tumut River in New South Wales, Australia, that are part of the Snowy Mountains Scheme.

<span class="mw-page-title-main">Tooma Dam</span> Dam in Snowy Mountains, New South Wales

Tooma Dam is a major ungated earthen embankment dam across the Tooma River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

<span class="mw-page-title-main">Rubicon Hydroelectric Scheme</span> Hydroelectric scheme in Victoria, Australia

The Rubicon Hydroelectric Scheme is a small run-of-the-river hydroelectric scheme located on the Rubicon and Royston Rivers, north east of Melbourne, 40 km (25 mi) south-west of Alexandra, Victoria, Australia. The scheme commenced in 1922, and was the first state-owned hydroelectric scheme to generate electricity in mainland Australia, and among the first in the world to be remotely controlled. For the first ten years of its operation it supplied on average 16.9% of electricity generated by the State Electricity Commission of Victoria. It is now owned and operated by AGL Energy and contributes approximately 0.02% of Victoria's energy supply.

Chenderoh Power Station or Chenderoh Dam is one of the oldest and the first major hydroelectric dam and power station in Malaysia. It was preceded by two earlier booiis

using Malaya's rivers; the Ulu Gombak station of 800kw in Selangor, completed in 1905 and that was used to provide Kuala Lumpur's first electric supply, and the Sungei Besi Tin Mines Ltd scheme at Ulu Langat that was purchased by the FMS Electrical Department in 1929. The dam is located in Chenderoh Lake, Kuala Kangsar District, Perak. It was constructed starting in 1927 by the Perak River Hydro-Electric Power Company Ltd and was completed between 1929 and 1930. Detailed descriptions of the scheme appear in the Minutes of the Institute of Civil Engineers, London, Volume 239, Issue 1935, 1935, pp. 253-312 and in the Architectural Review, Volume 75, No. 446, London, January 1934. The scheme was designed by the consulting engineers Rendel, Palmer & Tritton of London and Vattenbyggnadsbyran (VBB) of Stockholm, Sweden. The architect was Osvald Almqvist. 
<span class="mw-page-title-main">Talbingo Dam</span> Dam in Snowy Mountains, New South Wales

Talbingo Dam is a major ungated rock fill with clay core embankment dam with concrete chute spillway across the Tumut River upstream of Talbingo in the Snowy Mountains region of New South Wales, Australia. The impounded reservoir is called Talbingo Reservoir.

<span class="mw-page-title-main">Tumut Pond Dam</span> Dam in Snowy Mountains, New South Wales

Tumut Pond Dam is a major ungated concrete arch dam across the upper reaches of the Tumut River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

<span class="mw-page-title-main">Cruachan Power Station</span> Dam in Argyll and Bute

The Cruachan Power Station is a pumped-storage hydroelectric power station in Argyll and Bute, Scotland. The scheme can provide 440 MW of power and produced 705 GWh in 2009.

<span class="mw-page-title-main">Jounama Dam</span> Dam in Snowy Mountains, New South Wales

Jounama Dam is a major ungated rockfill embankment dam across the Tumut River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

Tumut Two Dam or Tumut Two is a major ungated concrete gravity dam across the upper reaches of the Tumut River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

Deep Creek Dam is a major ungated concrete gravity dam across the Deep Creek in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the diversion of water for generation of hydro-power and is the smallest of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

<span class="mw-page-title-main">Geehi Dam</span> Dam in Snowy Mountains, New South Wales

Geehi Dam is a major ungated rockfill embankment dam across the Geehi River in the Snowy Mountains of New South Wales, Australia. The reservoir impounded by the dam is known as Geehi Reservoir.

<span class="mw-page-title-main">Guthega Dam</span> Dam in Snowy Mountains, New South Wales

Guthega Dam is concrete gravity dam with an uncontrolled spillway across the Snowy River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the storage of water used in the generation of hydro-power. It is the first to be completed of the sixteen major dams of the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

Happy Jacks Dam is a major ungated concrete gravity dam across the Tumut River in the Snowy Mountains region of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

Island Bend Dam is a major ungated concrete gravity dam with a controlled spillway across the Snowy River in the Snowy Mountains region of New South Wales, Australia. The dam's main purpose is for the diversion of water for generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.

Murray Two Dam or Murray 2 Dam is a major ungated concrete arch dam with a controlled spillway across Khancoban Bank, a diverted flow of the Snowy and Geehi rivers in the Snowy Mountains region of New South Wales, Australia. The impounded reservoir is called the Murray Two Pondage or Murray 2 Pondage.

References

  1. "Guthega Hydroelectric Power Station Australia". Global Energy Observatory. 23 May 2012. Retrieved 11 May 2013.
  2. "Power Stations". Snowy Mountains Scheme. Snowy Hydro. Archived from the original on 13 December 2012. Retrieved 11 May 2013.
  3. "Hydroelectric Power Plants in Australia - NSW". Platts UDI World Electric Power Plants Data Base. 8 November 2010. Retrieved 11 May 2013.