Eucumbene Dam | |
---|---|
Location of Eucumbene Dam in New South Wales | |
Country | Australia |
Location | Snowy Mountains, New South Wales |
Coordinates | 36°07′42″S148°36′57″E / 36.12843°S 148.61575°E |
Purpose | Hydro-power, diversion, irrigation |
Status | Operational |
Construction began | May 1956 |
Opening date | May 1958 |
Owner(s) | Snowy Hydro |
Dam and spillways | |
Type of dam | Embankment dam |
Impounds | Eucumbene River |
Height | 116 m (381 ft) |
Length | 579 m (1,900 ft) |
Elevation at crest | 1,168 metres (3,832 ft) AHD |
Width (base) | 686 m (2,251 ft) |
Dam volume | 6,735,000 m3 (237,800,000 cu ft) |
Spillways | 1 |
Spillway type | Overflow ski-jump and bucket with two vertical lift gates |
Spillway capacity | 475 m3/s (16,800 cu ft/s) |
Reservoir | |
Creates | Lake Eucumbene |
Total capacity | 4,798 GL (1.055×1012 imp gal; 1.267×1012 US gal) (4.798 km3; 3,890,000 acre⋅ft) |
Active capacity | 4,366.5 GL (9.605×1011 imp gal; 1.1535×1012 US gal) (4.3665 km3; 3,540,000 acre⋅ft) |
Catchment area | 683 km2 (264 sq mi) |
Surface area | 14,542 ha (35,930 acres) |
Maximum water depth | 107 m (351 ft) |
Website Eucumbene Dam at the Powerhouse Museum. |
Eucumbene Dam is a major gated earthfill embankment dam with an overflow ski-jump and bucket spillway with two vertical lift gates across the Eucumbene River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
The impounded reservoir is called Lake Eucumbene, the largest storage lake in the Snowy Mountains Scheme.
Commenced in May 1956 and completed in May 1958, Eucumbene Dam is a major dam, located approximately 1 kilometre (0.62 mi) northeast of the locality of Eucumbene Cove. The dam was constructed by a consortium comprising the Department of Public Works and Kaiser-Walsh-Perini-Raymond based on engineering plans developed by the United States Bureau of Reclamation and the Department of Public Works, under contract from the Snowy Mountains Hydroelectric Authority. [1] Construction of the dam inundated the original township of Old Adaminaby, which was relocated to Adaminaby in the 1950s, requiring approximately 800 people to be moved. [1]
The outer walls of the dam are built of rock while the inner core is compacted, impervious clay. The earthfill embankment dam wall comprising 6,735,000 cubic metres (237,800,000 cu ft) of earth and rockfill is 116 metres (381 ft) high and 579 metres (1,900 ft) long. The foundation of the dam comprises closely jointed hard siltstone and quartzite with overburden of decomposed rock and slope-wash up to 6.1 metres (20 ft) deep. A subsidiary embankment containing 121,900 cubic metres (4,300,000 cu ft) of fill across a low saddle in a ridge forms the left abutment of the dam wall. At 100% capacity the dam wall, with an elevation of 1,168 metres (3,832 ft) AHD, holds back 4,798 gigalitres (1.055×1012 imp gal; 1.267×1012 US gal) or (4.798 km3 ; 3,890,000 acre⋅ft) of water, approximately equal to nine times the volume of Sydney Harbour. The surface area of Lake Eucumbene is 14,542 hectares (35,930 acres) and the catchment area is 683 square kilometres (264 sq mi). The overflow ski-jump and bucket spillway with two vertical lift gates is capable of discharging 475 cubic metres per second (16,800 cu ft/s). The two gates, each 6.7 metres (22 ft) wide by 3.9 metres (13 ft) high were constructed during 1977-78 under a separate contract. [1] [2] [3] [4]
Lake Eucumbene is the largest reservoir in the Snowy Mountains Scheme and is the central connection for the northern (Tumut/Murrumbidgee rivers) and southern (Snowy River) halves of the Scheme. The Goodradigbee and Murrumbidgee rivers from Tantangara Dam are connected to the Eucumbene River at Lake Eucumbene via the Murrumbidgee-Eucumbene Haupt-tunnel. The Eucumbene River at Lake Eucumbene is connected to the Snowy River at Island Bend Pondage via the 23.5 kilometres (14.6 mi) long Eucumbene-Snowy Haupt-tunnel; the longest tunnel in the Snowy Mountains Scheme, with a circular diameter of 6.3 metres (21 ft). [4]
Also at Lake Eucumbene, the 22.2 kilometres (13.8 mi) long Eucumbene-Tumut Haupt-tunnel diverts the flow of the Snowy River to the Tumut River, empting into Tumut Pond Reservoir; and into the Murray–Darling basin. This tunnel was constructed between November 1954 and July 1959 and along 28% of its length is lined with a 6.4 metres (21 ft) circular diameter. The residual length of the tunnel in unlined and 6.93 metres (22.7 ft) circular in diameter. Construction was through granite and metamorphosed sedimentary rock, involving the excavation of 978,600 cubic metres (34,560,000 cu ft); and 71,100 cubic metres (2,510,000 cu ft) concrete was used to install the pipeline. [4]
The valley, which was flooded following construction of the Eucumbene Dam, had been an agricultural centre since the 1830s. A number of homesteads and most of the township of Adaminaby lay within the inundation area of the proposed dam. Most of the buildings in the town relocated to a site on the Snowy Mountains Highway, but some buildings were not flooded and remain at Old Adaminaby.
The story of Adaminaby's relocation was the subject of film produced by the Snowy Mountains Authority Film Unit in 1958, entitled Operation Adaminaby. It was also the subject of a 2001 documentary by historian Jeannine Baker, entitled Our Drowned Town, which screened on SBS Television. Entire houses, and even the Commercial Bank building were transported on the back of trucks and over 100 buildings were re-erected at the new townsite. [5] Transportation of the first house from Old Adaminaby to New Adaminaby (a distance of just six miles) took six days. [6] Today a tourist village has been built around the handful of buildings which were not relocated from the newly created lakeshore at Old Adaminaby.
When the lake is low, remains of the former township and other relics can be seen along the shoreline. For a period of time around 2007, the waters of Lake Eucumbene had receded due to a prolonged drought and Old Adaminaby began to reveal itself after being underwater for over 50 years – gaining the attention of the global media. [7] Of particular interest was the re-emergence of the old 6 Mile Bridge near Anglers Reach on the former highway route to Kiandra.
Lake Eucumbene has mild, stormy summers and cold, wet winters; with a largely uniform rainfall pattern, peaking somewhat in late winter and springtime. Frosts occur regularly during autumn, winter and spring, and can occur also in summer. Snowfall can occur at any time of the year, save for high summer.
Climate data for Adaminaby (Yaouk, 1969–2022); 1,140 m AMSL; 35.79° S, 148.81° E | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Month | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Year |
Average precipitation mm (inches) | 79.0 (3.11) | 73.8 (2.91) | 59.1 (2.33) | 50.2 (1.98) | 57.8 (2.28) | 81.8 (3.22) | 71.1 (2.80) | 90.8 (3.57) | 87.4 (3.44) | 73.7 (2.90) | 86.3 (3.40) | 81.7 (3.22) | 909.9 (35.82) |
Source: Australian Bureau of Meteorology; Adaminaby (Yaouk) |
The Snowy Mountains, known informally as "The Snowies", is an IBRA subregion in southern New South Wales, Australia, and is the tallest mountain range in mainland Australia, being part of the continent's Great Dividing Range cordillera system. It makes up the northeastern half of the Australian Alps and contains Australia's five tallest peaks, all of which are above 2,100 m (6,890 ft), including the tallest Mount Kosciuszko, which reaches to a height of 2,228 m (7,310 ft) above sea level. The offshore Tasmanian highlands makes up the only other major alpine region present in the whole of Australia.
The Snowy Mountains Scheme, also known as the Snowy Hydro or the Snowy scheme, is a hydroelectricity and irrigation complex in south-east Australia. Near the border of New South Wales and Victoria, the scheme consists of sixteen major dams; nine power stations; two pumping stations; and 225 kilometres (140 mi) of tunnels, pipelines and aqueducts that were constructed between 1949 and 1974. The Scheme was completed under the supervision of Chief Engineer, Sir William Hudson. It is the largest engineering project undertaken in Australia.
The Eucumbene River, a perennial river of the Snowy River catchment, is located in the Snowy Mountains region of New South Wales, Australia.
Adaminaby is a small town near the Snowy Mountains north-west of Cooma, New South Wales, Australia, in the Snowy Monaro Regional Council. The historic town, of 301 people at the 2016 census, is a trout fishing centre and winter sports destination situated at 1,017 metres (3,337 ft) above sea level. Economic life is built around tourism and agriculture–the town serves as a service point for Selwyn Snowfields and the Northern Skifields. It is also a popular destination for horse riders, bushwalkers, fly-fishermen and water sports enthusiasts as well as a base for viewing aspects of the Snowy Mountains Scheme.
The Blowering Dam is a major ungated rock fill with clay core embankment dam with concrete chute spillway impounding a reservoir under the same name. It is located on the Tumut River upstream of Tumut in the Snowy Mountains region of New South Wales, Australia. Purposes for the dam include flood mitigation, hydro-power, irrigation, water supply and conservation. The dam is part of the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Jindabyne Dam is a major ungated rockfill embankment dam across the Snowy River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is to redirect water from the Snowy River to the Murray, for the generation of hydro-power and irrigation. It is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Tooma Dam is a major ungated earthen embankment dam across the Tooma River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Tantangara Dam is a major ungated concrete gravity dam with concrete chute spillway across the Murrumbidgee River in Tantangara, upstream of Adaminaby in the Snowy Mountains region of New South Wales, Australia. The dam is part of the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro. The purpose of the dam includes water management and conservation, with much of the impounded headwaters diverted to Lake Eucumbene. The impounded reservoir is called Tantangara Reservoir.
Talbingo Dam is a major ungated rock fill with clay core embankment dam with concrete chute spillway across the Tumut River upstream of Talbingo in the Snowy Mountains region of New South Wales, Australia. The impounded reservoir is called Talbingo Reservoir.
The Tumut River, a perennial stream that is part of the Murrumbidgee catchment within the Murray–Darling basin, is located in the Snowy Mountains and South West Slopes districts of New South Wales, Australia.
Tumut Pond Dam is a major gated concrete arch dam across the upper reaches of the Tumut River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Jounama Dam is a major ungated rockfill embankment dam across the Tumut River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Tumut Two Dam or Tumut Two is a major ungated concrete gravity dam across the upper reaches of the Tumut River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Deep Creek Dam is a major ungated concrete gravity dam across the Deep Creek in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the diversion of water for generation of hydro-power and is the smallest of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Geehi Dam is a major ungated rockfill embankment dam across the Geehi River in the Snowy Mountains of New South Wales, Australia. The reservoir impounded by the dam is known as Geehi Reservoir.
Happy Jacks Dam is a major ungated concrete gravity dam across the Tumut River in the Snowy Mountains region of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Island Bend Dam is a major gated concrete gravity dam with a controlled spillway across the Snowy River in the Snowy Mountains region of New South Wales, Australia. The dam's main purpose is for the diversion of water for generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Khancoban Dam is a major ungated earthfill embankment dam with a controlled spillway across the Swampy Plain River in the Snowy Mountains region of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Murray Two Dam or Murray 2 Dam is a major ungated concrete arch dam with a controlled spillway across Khancoban Bank, a diverted flow of the Snowy and Geehi rivers in the Snowy Mountains region of New South Wales, Australia. The impounded reservoir is called the Murray Two Pondage or Murray 2 Pondage.
Old Adaminaby and Lake Eucumbene are the heritage-listed former town of Adaminaby and the reservoir that flooded the town, now at Eucumbene, Snowy Valleys Council, New South Wales, Australia. The town was established in 1830. The reservoir was designed by the Snowy Hydro Electric Authority and built from 1956 to 1958 by the Authority. It is also known as Old Adaminaby and Lake Eucumbene, including relics and movable objects, Eucumbene River, Eucumbene Valley, Old Adaminaby Remains, Old Adaminaby Ruins and Old Adaminaby Drowned Landscape. The property is owned by Snowy Hydro Limited, a statutory corporation owned by the governments of Australia, New South Wales and Victoria. The site was added to the New South Wales State Heritage Register on 3 June 2008.