Waitahora Wind Farm | |
---|---|
Country | New Zealand |
Location | Hawke's Bay |
Coordinates | 40°21′44″S176°10′24″E / 40.362314°S 176.17328°E |
Status | Proposed |
Owner(s) | Contact Energy |
Power generation | |
Units operational | 65 |
Nameplate capacity | 177 MW |
The Waitahora Wind Farm was a proposed renewable energy project in New Zealand planned by Contact Energy but which has now been abandoned without construction beginning (see resource consent process below). This development was proposed to be located on the Puketoi Range which forms one side of the picturesque Waitahora Valley, near Dannevirke in Southern Hawke’s Bay.
It was planned to have up to 65 wind turbines with a capacity of up to 177 MW. The proposed towers were to be 100m high, with a total height of 150m. [1] The windfarm was opposed by a local residents group, representing a large proportion of local residents. [2]
In 2013, Contact announced that the project would not proceed in the foreseeable future. [3] Consents for the project lapsed in 2016. [4]
The windfarm required resource consent approval, a licensing process administered by local government. The consent application for this project was publicly notified on 30 September and submissions closed on 30 October 2008. The consent hearing was held in February 2009. [5] Three independent landscape architects gave evidence at the hearing, and all agreed that the Puketoi range was an outstanding natural landscape. [6] [7] [8]
The application for resource consents for this project was declined in 2009,. [9] This is not unusual, as several renewable energy projects were declined resource consents (see Awhitu, Mokau hydro, Mount Cass, Te Waka).
Contact Energy appealed the decision to decline the consent application and presented a substantially revised proposal, especially with regards to the limestone geology and sediment control. One of the consenting authorities, Horizons Regional Council, stated that consents should not have been declined on the basis of discharge of contaminants to groundwater, and that the consents should be granted. [10] [11] The Environment Court upheld the appeal and granted consents for the revised wind farm in 2010. [12] The lapse period granted for the consents was five years. [13]
No construction began on this project and the consents lapsed in April 2016. There was no application made to extend them. No official statement has been released by Contact Energy but it is understood that the development of other more economic renewable energy projects (principally geothermal [14] ) coupled with an uncertain outlook for future electricity demand growth made this project unattractive for investors. As of April 2016, this appears to be the first proposed wind farm in New Zealand to have allowed its construction consents to lapse. [15] Other wind farms have had their consents extended, although the approval of consent extensions may not continue indefinitely. [16] [17]
There are two other industrial scale wind farm developments planned for the Puketoi range and surrounding area, the 53 turbine (Mercury) Puketoi wind farm (south of Waitahora) [18] and the 286 turbine (Genesis Energy) Castle Hill wind farm (south of Puketoi). [19] Five power companies (including Contact Energy, developer of the proposed Waitahora Wind Farm) asked for the district plan to be modified to avoid hindering wind energy generation projects. [20] TrustPower asked for the Puketoi ranges to be removed from the list of outstanding natural features, or for "skyline" to be more clearly defined. [20] Contact Energy also asked for the Puketoi Ranges to be removed from the Council list of outstanding natural features until a district wide assessment of landscape features can be undertaken, despite their own landscape architect (as well as two others) already concluding that the Puketoi Range is indeed an outstanding natural feature (see references below). These changes would make it easier to get local government approval for large scale wind energy developments. The power companies involved have not publicised their attempts to change the district plan. [21] Cross submissions on the proposed District Plan closed on 3 October 2008.
Transpower, the national grid owner-operator, has issues exporting electricity generated from the area, as there are no appropriate transmission lines to connect to in the area. Although the nearest lines are 20 km away at Dannevirke, they are low capacity 110 kV lines that are already constrained by generation from the Te Apiti Wind Farm connecting at Woodville. Even with the now completed reconductoring of the Woodville-Mangamaire-Masterton line, and the proposed reconductoring of the Woodville-Bunnythorpe line, only 110 MW of generation could be potentially attached to the existing lines. For the Waitahora wind farm to be connected the national grid, a new 220 kV transmission would have to be built from the wind farm to Bunnythorpe substation or the Bunnythorpe-Linton-Haywards-Wilton 220 kV line [22]
Te Āpiti is a wind farm owned and operated by Meridian Energy. It is located on 11.5 km² of land north of the Manawatū Gorge in the North Island of New Zealand. At 90.75 MW, it was New Zealand's largest capacity wind farm until September 2007, when the third stage of the nearby Tararua Wind Farm was completed.
Mercury NZ Limited is a New Zealand electricity generation and multi-product utility retailer of electricity, gas, broadband and mobile telephone services. All the company's electricity generation is renewable. Mercury has a pre-paid electricity product sub-brand GLOBUG. Mercury Energy is also the largest electricity retailer in New Zealand.
Contact Energy Limited is a New Zealand electricity generator, a wholesaler of natural gas, and a retailer of electricity, natural gas, broadband and LPG.
Te Rere Hau is a wind farm owned and operated by New Zealand Windfarms Ltd. It is situated on the Tararua Ranges, approximately 11 km east of Palmerston North in New Zealand.
Wind power constitutes a small but growing proportion of New Zealand's electricity. As of November 2023, wind power accounts for 1m059 MW of installed capacity and over 6 percent of electricity generated in the country.
The Tararua Wind Farm is a wind farm owned and operated by Mercury NZ Ltd. It is located on 700ha of farmland on the Tararua Ranges of New Zealand. It has become New Zealand's largest capacity wind farm, with a total capacity of 161MW.
Mangahao Power Station is a hydroelectric power station near the town of Shannon, New Zealand. After being delayed by war, access road construction and foundation testing was started by late 1919 and the station opened in November 1924. It makes use of the Mangahao River, through a series of tunnels and pipelines totalling 4.8 kilometers in the Tararua Ranges. It is jointly owned and operated by Todd Energy and King Country Energy.
The Ōtāhuhu power station was a power station site located in Ōtara, Auckland, New Zealand. Two plants operated on the site: Ōtāhuhu A and Ōtāhuhu B. A proposed third station, Ōtāhuhu C, was never built. The stations were owned by Contact Energy.
Turitea Wind Farm is a 222-megawatt wind farm near Turitea, Palmerston North, New Zealand. The farm is owned and operated by Mercury Energy.
The Mahinerangi Wind Farm is a wind farm on the north side of Lake Mahinerangi, around 50 km west of Dunedin, in Otago, New Zealand. Stage one of the wind farm, generating 36 MW, was commissioned in March 2011, and an additional 160 MW is consented to be commissioned in further stages.
Project Hayes was a controversial wind farm proposed for the Lammermoor Range of Otago, New Zealand. The project was developed by Meridian Energy from 2006 to 2012 at a cost of $8.9 million.
Mill Creek Wind Farm is a wind farm in the Ohariu Valley near Wellington, New Zealand.
The Kaiwera Downs Wind Farm is a wind farm in the Southland region of New Zealand. It is consented to have a maximum capacity of 240 MW and use up to 83 turbines. Originally proposed by Trustpower, it is now owned and operated by Mercury Energy. The 10 turbine, 43 MW stage 1 of the project was opened in November 2023.
The Harapaki Wind Farm is a wind farm project in the Hawke's Bay region of New Zealand. Construction began in June 2021 and is expected to continue for three years.
The Awhitu Wind Farm is a renewable energy project in New Zealand initially planned by Tilt Renewables. The development is proposed to be located on the Awhitu Peninsula near Waiuku on the west coast south of Auckland. As of 2016 the project was being privately pursued.
WEL Networks Limited is an electricity distribution company, serving the northern and central Waikato region of New Zealand. WEL is the sixth largest electricity distribution company in New Zealand, with 100,142 connections and 7,021 km (4,363 mi) of lines and underground cables. The company is 100% owned by the WEL Energy Trust.
The Waipipi Wind Farm is a wind powered electricity generation project in New Zealand owned and operated by Mercury NZ Ltd. This site is located between Patea and Waverley in South Taranaki. The wind farm consists of 31 wind turbines over 980 hectares, generating up to 133 MW at a cost of approximately $277 million. The 4.3 MW machines are the largest wind turbines installed in New Zealand.
The Puketoi Wind Farm is a proposed wind farm project in the Tararua District of New Zealand. The project is planned by Mercury Energy.
The Southland Wind Farm is a proposed wind farm on Slopedown in The Catlins in the Southland District of New Zealand.