Location | Scotland (Perth to Inverness) |
---|---|
Proposer | Transport Scotland |
Project website | Transport Scotland's programme |
Status | Partially complete [lower-alpha 1] |
Type | Upgrade to dual carriageway |
Cost estimate | £3.7 billion [1] [lower-alpha 2] |
Start date | 2015 |
Completion date | 2035 (initially 2025) |
In 2011, Transport Scotland envisioned a plan to upgrade the remaining 90 miles (145 km) of the A9, a trunk road in Scotland, between Perth and Inverness from a single carriageway to a dual carriageway. According to this plan, the road will be widened from one to two lanes per direction (two to four lanes total). It also means there will be an increase in speed for cars and motorcycles from 60 mph to 70 mph (97 km/h to 113 km/h).
A dual carriageway allows drivers to overtake safely, as they do not have to meet oncoming traffic; and the crash barriers on the central reservation will greatly reduce the number of head-on collisions. As most of the A9 is currently a single carriageway, drivers may have to overtake heavy goods vehicles (HGVs) and other slow-moving vehicles as they are limited to 50 mph (80 km/h), 10 mph (16 km/h) lower than the speed limit for cars and motorcycles. The project started in September 2015 with a planned completion date of 2025, but has since been deferred to 2035 for various reasons. As of 2024 [update] , two sections of the project have been completed—the Kincraig to Dalraddy (near Aviemore) in September 2017, and the Luncarty to Pass of Birnam (near Perth) in August 2021, totalling 11 miles (17 km).
The A9 has been dubbed as Scotland's most dangerous road. In 2022, the number of fatalities rose to its highest level in 20 years.
The 138 miles (222 km) section between Bridge of Allan and Inverness, via Perth, was substantially rebuilt during the 1970s and 80s, but it follows essentially the same route except where it bypasses towns and villages instead of running through their centres. Between Perth and Inverness, the road has been dubbed Killer A9 , [3] because of accidents and fatalities where dual-carriageway sections merge into a single carriageway; the principal cause is that motorists drive at excessive speeds to overtake lines of slower-moving vehicles before the dual carriageway ends. Dangerous overtaking manoeuvres on the long single-carriageway stretches of the road are also common causes of accidents, as are the non-grade separated junctions along the northern sections, where drivers make a right turn across the opposing traffic flow. [4]
The most significant alteration of the A9 route was the realignment of the route north from Inverness, crossing the Moray Firth via the Kessock Bridge, cutting through the Black Isle and back across the Cromarty Firth. This shortened the route by 14 miles (23 km), bypassing Beauly, Muir of Ord and Dingwall. Construction of the Kessock Bridge began in 1976 and it was completed in 1982. [5]
Since 2007, the Scottish Government has given serious consideration to converting the entire Perth-Inverness section to dual carriageway with more grade separated junctions, with the initial estimated cost at £600 million. [6] In late 2008, the Scottish Government's transport plan for the next 20 years was announced. It brought forward planned improvements to the A9 to try to stimulate the economy and protect jobs. [7] This included a commitment to full dualling of the road between Perth and Inverness. [8] Work costing a total of £8.5 million was undertaken at Moy, Carrbridge and Bankfoot. Northbound overtaking lanes were created and the carriageway was reconstructed at both Moy and Carrbridge. Junction improvements were also made at Moy and at the Ballinluig junction, south of Pitlochry. [7] [9]
In July 2013, the Scottish Government announced a plan to install average speed cameras on the A9 between Perth and Inverness. This has been undertaken with an aim to reduce accidents and fatalities on the road, and was the second permanent average speed camera scheme in Scotland. [10] Simultaneously, an increased speed limit for heavy goods vehicles from 40 mph (64 km/h) to 50 mph (80 km/h) was introduced to help mitigate driver frustration. [11] Both became operational in October 2014, [12] before HGV speed limit increase would then apply to England and Wales on single carriageways from 40 to 50 mph. [13]
The A9 Safety Group claim that the cameras have had a "positive influence" on road users, with the number of drivers breaking the speed limit by over 10 mph (16 km/h) decreasing by 97%. [14] Improvements to safety include at least 40% reduction in fatalities, and this has been attributed, at least in part, to a reduction in speeding, from 1 in 3 vehicles to just 1 in 15. [15] The average speed cameras may be removed after the A9 dualling project is done. [16]
It has been reported that the A9 is dubbed the most dangerous road in Scotland. [17] In 2022, despite the installation of average speed cameras, 17 people died on the A9, of whom 13 were on the stretch between Perth and Inverness, where much of the route is single carriageway. [17] [18] This has meant that the number of fatalities rose to its highest level in 20 years; between 2019 and 2021, only one death was reported per year. [17] [18] However, this plummeted to just four deaths the following year, with half of them on single carriageway sections. [19] As of July 2023, 335 people had been killed on the Perth-to-Inverness stretch of the road since 1979 (an average of 7.6 deaths per year), 59 of which occurred between 2011 and 2022 (an average of 5.4 deaths per year). The "A9 Dual Action Group" was established to bring attention to the statistics. It submitted a petition to the Scottish Parliament in December 2022, calling on the Scottish Government to follow through on its 2011 commitment to convert the remaining 77 miles (124 kilometres) [20] of single carriageway into dual carriageway by 2025. [21] In 2023, the Scottish National Party (SNP) stated that the dualling of the road would not be complete by 2025. [22] [23]
The annual average daily traffic (AADT) of the A9 varies between Perth and Inverness from 8500 around Pitlochry, 22,500 around Perth and 37,000 around Inverness. [24]
In November 2011, the Scottish Government announced that it would upgrade the entire road from Perth to Inverness to dual carriageway. [25] The design contract was split into three lots with Lot 1 (Glengarry to Dalraddy) awarded to a CH2M / Fairhurst joint venture in April 2014. [26] Lot 2 (Pass of Birnam to Glengarry) was awarded to Jacobs in August 2014 [27] and Lot 3 was awarded to an Atkins / Mouchel joint venture in December 2014. [28]
Award of the construction contract for a preliminary section (outwith Lots 1 to 3) of the £3 billion project was awarded in June 2015. [2] Work began on the first 5 miles (8 km) section between Kincraig and Dalraddy (located just south of Aviemore) in September 2015. [29] After a slight delay, this section was opened to traffic two years later on 30 September 2017. [30] It is an isolated stretch of dual carriageway (i.e., this section is not an extension of an existing dual carriageway or something that fills the gap, as was done for the second and third section down below). A 2+1 road section (also known as WS2+1) just of the first section was removed due to the Design Manual for Roads and Bridges (DMRB) CD 109 requirements of having a minimum of 2km of single carriageway in between, as well as an existing bridge in the way. [31]
The second section of the project was the 6-mile (10 km) section between Luncarty and Pass of Birnam, the first section of what was single carriageway just north of Perth. After having the £96 million contract awarded to Balfour Beatty in autumn 2018, [32] construction works began in February 2019. [33] This section was scheduled to finish in spring 2021. However, like the Kincraig to Dalraddy section, it also experienced a slight delay meaning that this section was finished in August 2021 with off-carriageway works to finish by 2022. [34] The first two schemes combined meant that Transport Scotland has converted 11 miles (17 km) of single carriageway to dual carriageway.
Since 2022, no sections of the A9 were either upgraded or under construction. This has also occurred between September 2017 and February 2019 meaning that no major works were also carried out in the whole of 2018. [35] The project will be delivered via a hybrid approach, utilising both 'design and build' (D&B) and 'mutual investment model' (MIM) contracts. [36]
The third section to be upgraded is between Tomatin and Moy, also 6 miles long. [37] [38] This is the northernmost section of single carriageway for the scheme. In November 2023, Transport Minister Fiona Hyslop have announced three contractors have been shortlisted for this scheme: John Graham Construction Ltd, Sacyr UK Ltd and Balfour Beatty Civil Engineering Ltd. [37] The £150 million contract was awarded to Balfour Beatty in July 2024 with construction set to last around three years. [39] [40] Some preparation works to this section include some trees being cut down and a new railway bridge on the Highland Main Line, which were done in 2021 and 2022, ahead of the main construction work. [41] [42] The new railway bridge is also wide enough should the Highland Main Line be doubled in the near future. This stretch is expected to start construction by the end of 2024. [43] Preparatory works on this section began on 21 October 2024, and is expected to begin main construction in spring 2025. [44] [45] It's also reported that the section has risen to £308 million from £254 million in July this year and before that, £197 million. [44]
In April 2024, Transport Scotland began procurement for the 5-mile (8 km) section between Tay Crossing (aka, Jubilee Bridge) and Ballinluig project. This involved publishing a Prior Information Notice for a £155 million contract to complete this section. [46] Initial ground survey and borehole samples took place for the section in 2020. [47] In August 2024, three contractors have been shortlisted for this scheme: Balfour Beatty Civil Engineering Ltd, Wills Bros Civil Engineering Ltd and John Graham Construction Ltd. [48] The contract is expected to be awarded in summer 2025. [48]
If only the year is shown, it means that construction should start or finish by the end of that year. Unless stated otherwise, the source for the table is: [49]
Section | Status | Start of work | End of work | Contract |
---|---|---|---|---|
Kincraig to Dalraddy | Complete | Sep 2015 [29] | Sep 2017 [30] | D&B |
Luncarty to Pass of Birnam | Complete | Feb 2019 [33] | Aug 2021 [50] | D&B |
Tomatin to Moy | Prep works underway [lower-alpha 3] | Spring 2025 [45] [lower-alpha 4] | Spring 2028 [45] | D&B |
Tay Crossing to Ballinluig | In preparation | 2025 | 2028 | D&B |
Pitlochry to Killiecrankie | In preparation | 2026 | 2030 | D&B |
Pass of Birnam to Tay Crossing | In preparation | 2028 | 2032 | D&B |
Dalraddy to Slochd | In preparation | 2028 | 2033 | MIM |
Dalwhinnie to Crubenmore | In preparation | 2028 | 2033 | MIM |
Crubenmore to Kincraig | In preparation | 2030 | 2035 | MIM |
Glen Garry to Dalwhinnie | In preparation | 2030 | 2035 | MIM |
Killiecrankie to Glen Garry | In preparation | 2030 | 2035 | MIM |
The construction project started in September 2015 and was originally scheduled for completion in 2025. [51] [52] [29] but in February 2023, the Scottish Government reported that the 2025 deadline was "unachievable". [53] A review from the BBC stated that the civil engineers knew that finishing the project by its original deadline of 2025 was going to be impossible for years. [54] In December 2023, Transport Scotland announced that this deadline has been postponed by a decade to late 2035 and announced a new delivery plan. [55] [56] Since 2022, no sections of the A9 were either upgraded or under construction. This has also occurred between September 2017 and February 2019 meaning that no major works were also carried out in the whole of 2018. Former first minister of Scotland Nicola Sturgeon stated that the reason for the delay was because it "faced significant challenges beyond their control, including from Brexit and the Covid[-19] pandemic" [57] and apologised that the 2025 deadline cannot be met. She did not apologise because of the Scottish National Party (SNP) or because the Scottish Government "messed up". [57] Other factors include the Russian invasion of Ukraine. [53] The first two sections of the scheme were already delayed by no more than a couple of months. Only 11 out of 90 miles of the A9 were converted to dual carriageway from 2015 to 2023, leaving 79 miles to be dualled. This means that the project is far from completion. [54] According to a 2012 report, Alex Neil, Cabinet Secretary for Infrastructure and Capital Investment, said that the "2025 [deadline] was challenging but achievable" [58]
In March 2024, Fergus Ewing, an SNP politician that is also an MSP (Member of Scottish Parliament) member since 1999, issued a public letter to transport secretary Fiona Hyslop highlighting delays to the project and continuing fatalities on the road. [59]
Plans to dual the A9 and A96 have been criticised by Patrick Harvie of the Scottish Greens, who has said the plans were incompatible with the Scottish Government's climate initiatives. [60] A study in 2016 found that the dualling project would cost more to construct than it would bring in, including wider economic benefits. [61] The Scottish Government was criticised by the Highland Council for stalling the project. [17] However, in 2024, the Transport Secretary of the Scottish Government stated that Net zero Scotland would still need roads and the government had committed to continuing with the dualling project. [62] The First Minister John Swinney, has feared that the government may de-prioritise the project after the finance secretary warned about not being able to afford its capital commitments. [63]
The A9 runs through the site of the Battle of Killiecrankie. Expanding the road here will destroy some of the battleground. Transport Scotland say dualling the road will have "some impact" on the site. [64]
Inverness is a city in the Scottish Highlands, having been granted city status in 2000. It is the administrative centre for The Highland Council and is regarded as the capital of the Highlands.
The A9 is a major road in Scotland running from the Falkirk council area in central Scotland to Scrabster Harbour, Thurso in the far north, via Stirling, Bridge of Allan, Perth and Inverness. At 273 miles (439 km), it is the longest road in Scotland and the fifth-longest A-road in the United Kingdom. Historically it was the main road between Edinburgh and John o' Groats, and has been called the spine of Scotland. It is one of the three major north–south trunk routes linking the Central Belt to the Highlands – the others being the A82 and the A90.
The A90 road is a major north-to-south road in eastern Scotland, running from Edinburgh to Fraserburgh, through Dundee and Aberdeen. Along with the A9 and the A82 it is one of the three major north–south trunk roads connecting the Central Belt to northern destinations. The A90 is not continuous, separated between Dalmeny and Perth by the M90.
The A66 is a major road in Northern England, which in part follows the course of the Roman road from Scotch Corner to Penrith. It runs from east of Middlesbrough in North Yorkshire to Workington in Cumbria. The road has been progressively improved with dual carriageway sections, but with stretches of single carriageway road. The road is set to be completely dualled between Scotch Corner and Penrith, with a £1.3 billion scheme being announced in March 2024.
The A82 is a major road in Scotland that runs from Glasgow to Inverness via Fort William. It is one of the principal north-south routes in Scotland and is mostly a trunk road managed by Transport Scotland, who view it as an important link from the Central Belt to the Scottish Highlands and beyond. The road passes close to numerous landmarks, including Loch Lomond, Rannoch Moor, Glen Coe, the Ballachulish Bridge, Ben Nevis, the Commando Memorial, Loch Ness, and Urquhart Castle. Along with the A9 and the A90 it is one of the three major north–south trunk roads connecting the Central Belt to the North.
The M90 is a motorway in Scotland. It runs from Junction 1A of the M9 motorway, south of the Queensferry Crossing, to Perth. It is the northernmost motorway in the United Kingdom. The northern point goes to the western suburbs of Perth at Broxden. A small part of the M90 was originally numbered as the M85 motorway.
The A92 is a major road that runs through Fife, Dundee, Angus, Aberdeenshire, and Aberdeen City in Scotland. From south to north, it runs from Dunfermline to Blackdog, just north of Aberdeen.
The A96 is a major road in the north of Scotland.
The A465 is a trunk road that runs from Bromyard in Herefordshire, England to Llandarcy near Swansea in south Wales. The western half in Wales is known officially as the Neath to Abergavenny Trunk Road, but the section from Abergavenny to the Vale of Neath is more commonly referred to as the Heads of the Valleys Road because it links the northern heads of the South Wales Valleys. That section was also the subject to an improvement programme which sections 1 to 4 are complete, and sections 5 to 6 under construction. The upgrade program is due to finish in 2025. Approximately following the southern boundary of the Brecon Beacons National Park, the Ordnance Survey Pathfinder guide describes it as the unofficial border between rural and industrial South Wales. The A465 provides an alternative route between England and the counties in South West Wales and to the ferries to Ireland.
The N2 road is a national primary road in Ireland, running from Dublin to the border with Northern Ireland at Moy Bridge near Aughnacloy, County Tyrone to connect Dublin with Derry and Letterkenny via the A5. A section of the route near Dublin forms the M2 motorway.
The Highland Main Line is a railway line in Scotland. It is 118 mi (190 km) long and runs through the central Scottish Highlands, mainly following the route of the A9, and linking a series of small towns and villages with Perth at one end and Inverness at the other. Today, services between Inverness and Edinburgh, Glasgow and London use the line. At Inverness the line connects with the Far North Line, the Aberdeen-Inverness Line and the Kyle of Lochalsh Line. Since the line is not electrified all trains are diesel-powered.
Broxden Junction is one of the busier and more important road junctions in Scotland. It is located on the outskirts of Perth, and is one of the city's two major roundabouts – the other being Inveralmond Roundabout, where the A9 meets the A912 Dunkeld Road, 2.3 miles (3.7 km) to the north-northwest. The roundabout, oval in shape, is an important hub of the Scottish road network, a major junction on the A9 north–south route, and the UK's northernmost motorway junction, being junction 12 of the M90 motorway. Prior to Dunfermline's ascension to city status, all of the seven cities in Scotland were signposted from its exits.
The United Kingdom has a well developed and extensive network of roads totalling about 262,300 miles (422,100 km). Road distances are shown in miles or yards and UK speed limits are indicated in miles per hour (mph) or by the use of the national speed limit (NSL) symbol. Some vehicle categories have various lower maximum limits enforced by speed limiters. A unified numbering system is in place for Great Britain, whilst in Northern Ireland, there is no available explanation for the allocation of road numbers.
Dunkeld is a town in Perth and Kinross, Scotland. The location of a historic cathedral, it lies on the north bank of the River Tay, opposite Birnam. Dunkeld lies close to the geological Highland Boundary Fault, and is frequently described as the "Gateway to the Highlands" due to its position on the main road and rail lines north. Dunkeld has a railway station, Dunkeld & Birnam, on the Highland Main Line, and is about 25 kilometres north of Perth on what is now the A9 road. The main road formerly ran through the town, however following the modernisation of this road it now passes to the west of Dunkeld.
Birnam is a village in Perth and Kinross, Scotland. It is located 12 miles (19 km) north of Perth on the A9 road, the main tourist route through Perthshire, in an area of Scotland marketed as Big Tree Country. The village originated from the Victorian era with the coming of the railway in 1856, although the place and name is well known because William Shakespeare mentioned Birnam Wood in Macbeth:
MACBETH: Till Birnam wood remove to Dunsinane/ I cannot taint with fear.
Kincraig is a village located north of Kingussie and south of Aviemore in Highland, Scotland. Its original name was Boat of Inch, reflecting the ferry boat crossing of the Spey River that once operated here but the name was changed after a single track bridge was erected in 1871.
Plans are in place to construct a southern bypass that would link the A9, A82 and A96 together involving crossings of the Caledonian Canal and the River Ness in the Torvean area, southwest of the city. The bypass, known as the Inverness Trunk Road Link (TRL), is aimed at resolving Inverness’s transport problems and has been split into two separate projects, the east and west sections. Also proposed is the upgrade of the existing B8082 Southern Distributor Road to dual 2-lane carriageway or single 4-lane carriageway, that will connect the two sections together.
Killer A9 is the nickname given to a section of the A9, Scotland's longest road, known for its high accident and fatality rates. The 112-mile (180-kilometre) section, running between Perth and Inverness, changes from a dual carriageway into a single carriageway, swapping between them frequently, resulting in motorists driving at excessive speeds to overtake lines of slower-moving vehicles before the dual-carriageway ends, which is the primary cause of many road traffic accidents. Dangerous overtaking manoeuvres on the long single-carriageway stretches of the road are also contributing factors, as are the non-grade separated junctions along the northern sections, where drivers make a right turn across the opposing traffic flow. There are also several hundred deer strikes each year, with around 200 recorded in 2013. The introduction of average-speed cameras has reduced deaths slightly.
The Jubilee Bridge is a 254 m (833 ft) road bridge over the River Tay near Dunkeld in Scotland. The bridge conveys the A9 road over the river. A concrete box bridge also joins the Jubilee Bridge at its southern end as it carries the A9 over the Highland Main Line. The area of the River Tay below the bridge is accessible for personal watercraft and walkers. As part of the A9 dualling project, the bridge will be duplicated by 2032.
Between Perth and Inverness, it is likely that the average speed cameras would be removed after the dualling of a particular section is complete. Judgements on this will be made as circumstances require.