Construction (Design and Management) Regulations 2007

Last updated

Construction (Design and Management) Regulations 2007
Statutory Instrument
Royal Coat of Arms of the United Kingdom (variant 1, 1952-2022).svg
Citation SI 2007/320
Text of the Construction (Design and Management) Regulations 2007 as in force today (including any amendments) within the United Kingdom, from legislation.gov.uk.

The Construction (Design and Management) Regulations 2007, [1] also known as CDM Regulations or CDM 2007, previously defined legal duties for the safe operation of UK construction sites. They were superseded by the Construction (Design and Management) Regulations 2015. The regulations placed specific duties on clients, designers and contractors, to plan their approach to health and safety. They applied throughout construction projects, from inception to final demolition and removal.

Contents

They were introduced by the Health and Safety Executive's Construction Division to: [2]

History

CDM 2007 was a result of an EU Directive 92/57/EEC (OJ L245, 26.8.92), [3] the 'Construction Sites Directive'. They came into force on 6 April 2007, and replaced a 1994 predecessor as amended in 2000 and 1996 Health and Safety regulations. [4] They were superseded by the Construction (Design and Management) Regulations 2015, which was effective from 6 April 2015, with transitional arrangements for existing construction projects to comply with the 2007 regulations until October 2015. [5]

Organization

The regulations were divided into 5 parts:

CDM 2007 is applied to all construction and covers construction activities such as building, civil engineering, engineering construction work, demolition, site preparation and site clearance. [6]

Approved Code of Practice 2007 (ACoP)

The HSE's[ clarification needed ] Approved Code of Practice (ACoP) [7] gives practical advice on how to comply with the law. It states that following the advice given complies with CDM regulations. Violation of the health and safety law/code carries legal consequences.

ACoP came into force in April 2007. This edition completely re-wrote the original and revised ACoP's that complied with CDM 1994.

Notifiable projects

Projects are classified as ‘notifiable’ if the construction work phase is expected to last longer than 30 working days and have more than 20 workers working at the same time at any point on the project, or to exceed 500 person days. [8] Under the CDM regulation, the client appoints a competent Principal Contractor and CDM coordinator, who notifies the Health and Safety Executive (HSE) by using Form 10 (F10). [9] [10] Failure to do so means the client must take the duties of Principal Contractor and CDM coordinator assigned to the parties under CDM 2007.

Non-notifiable projects are those that are likely to take less than 30 days of construction time. Although there is no legal requirement for a formal appointment of a Principal Contractor or CDM coordinator or a construction phase plan for non-notifiable projects, regulation does require cooperation and coordination between all members of the project team.

"CDM coordinator" is the new title for the Planning Supervisor under CDM 1994, with increased duties and responsibilities.

Multiple plan documents must be prepared.

The importance of this phase is in the inspection of expected performance standards to ensure compliance). Additional duties are also placed on the Client, Designers and Contractors.

Duty holders

Parties with specific duties under the regulations are the client, designer, principal contractor, other contractors, and a new duty holder introduced by the regulations, the ‘CDM coordinator'.

Each of these duty holders, apart from the client, must be "competent" to act in the project.

Client

The client is the party for whom the project is carried out. The client controls the duration, budget and appointment of other parties. As such they play a key role in the promotion of a systematic approach to health and safety management in construction. The client's legal duties are:

On notifiable projects the client's additional duties are to:

Often, clients have little knowledge of managing a construction project. Clients without construction expertise rely on the CDM coordinator's advice on how best to meet their duties. The CDM coordinator needs the client's support and input to work effectively. The client remains responsible for ensuring client duties are met. Domestic clients having work done on a property they intend to live in are exempt from CDM 2007.

CDM coordinator

A CDM coordinator is required only on notifiable projects. Primary roles and duties are to provide the client with an advisor on construction health and safety risk management matters and to ensure compliance with CDM 2007. The legal duties of a CDM coordinator under CDM 2007 are:

Designers

In CDM 2007, ‘designer’ covers persons or organisations who prepare drawings, design details or specify a particular construction method or material. Therefore, by default anyone involved is a potential designer, including the client, architect, engineers, surveyors, service designers, project managers, landscape architects, contractors, interior designers and shop fitters and anyone purchasing materials without a detailed specification.

Designers can identify and eliminate hazards and reduce hazard risks where elimination is not possible. Designer responsibilities extend beyond the construction phase. They must consider the health and safety of those who maintain, repair, clean, refurbish, and eventually remove or demolish the structure, as well as that of workplace users. Where significant risks remain, designers must ensure that the CDM coordinator, other designers and contractors are aware of these risks.

Designers also have duties under other legislation.

The legal duties of a designer under CDM 2007 are to:

On notifiable projects designers' additional duties are to:

Principal Contractor

The principal contractor develops a health and safety plan from the pre-construction information provided by the CDM coordinator and by ensuring that the plan is followed. The principal contractor must be a licensed contractor. A contractor performs/manages construction work and is formally appointed by the client. The principal contractor must also comply with the contractor's duties (below). The principal contractor has prime responsibility for safety and health during the construction phase only on notifiable projects. Duties are to:

Contractors

Contractor duties are to:

In addition, for notifiable projects:

Workers

Workers behave as safely as possible and not endanger others. Their duties are to:

Statutory documents

Mandatory documents for a CDM project, include project notification, pre-construction information, construction phase plan and health and safety plan. Pre-construction information is required for all projects, while some form of the other documents must be produced for both notifiable and non-notifiable projects. Project notification is only needed for notifiable projects. The Construction Phase Plan is required on notifiable projects, but something similar is required on other projects to provide for effective health and safety management. The Health and Safety File must be produced by the CDM coordinator on notifiable projects. Existing Health and Safety files must be modified files for structures undergoing modifications. The client must establish related procedures. Even when a Health and Safety File is not required, as-built and operational and maintenance information are required.

Project notification (Form 10)

The regulations require the CDM coordinator to notify the local HSE office of all projects expected to last more than 30 working days and all work of shorter duration that involves more than 500 person-shifts. The initial notification happens as soon as possible after appointment of the CDM coordinator. Further notifications are required by project changes that affects the notification, such as the subsequent appointment of the principal contractor. Additional notifications are not required should designers and contractors change. This notification may be performed using the HSE Form 10(rev) or by other means, including electronic, providing it contains the information specified by Schedule 1 of CDM2007, which consists of:

Pre-construction information

Pre-construction information (PCI) provides information for planning and for the construction phase plan. The 'pre-construction information' is information regarding the project, site and other relevant issues required by designers and contractors. The pre-construction information may include indexed drawings, reports, surveys, etc., either in digital or hard copy.

Construction phase plan

Construction phase plans (CPP or CPHP) must contain health and safety management systems and arrangements, and risk assessments and method statements for initial work activities. On non-notifiable projects involving demolition or high risk levels, a written plan, approximating the construction phase plan is recommended. The client must establish the need for this, with assistance from designers. The CDM ACoP, Appendix 3 contains a listing of required items.

Health and safety file

A health and safety file (HSF) is required only on notifiable projects. However, if a health and safety file exists for a structure involved in a non-notifiable project, this file must be updated. The health and safety file contains information needed to allow safe construction. Scope, structure and format must be agreed between the client and the CDM coordinator at the outset. The client takes charge of the file upon project completion. On notifiable projects, contractors must promptly provide relevant information to the principal contractor. The pre-construction information covers contents, timing and format.

File content
  • Brief description of the structural / building work
  • List of residual hazards and how they were addressed, such as information concerning asbestos, contaminated land, water bearing strata, buried services etc.
  • Description of the structural principles, such as bracing, sources of substantial stored energy *including pre- or post-tensioned members) and safe working loads for floors and roofs
  • List of hazards associated with materials, such as hazardous substances, lead paint and special coatings
  • Information regarding the removal or dismantling of installed plant and equipment (for example lifting arrangements)
  • Information about any cleaning/maintenance equipment
  • Nature, location, and markings of significant services, including fire-fighting services
  • Information and as-built drawings of the structures, plant and equipment, such as safe access to service voids and fire exits

Key consultation results

Public review generated 1427 responses, among the highest of any consultation undertaken by HSE. The main findings were:

Related Research Articles

<span class="mw-page-title-main">Architect</span> Person who designs buildings and oversees construction

An architect is a person who plans, designs, and oversees the construction of buildings. To practice architecture means to provide services in connection with the design of buildings and the space within the site surrounding the buildings that have human occupancy or use as their principal purpose. Etymologically, the term architect derives from the Latin architectus, which derives from the Greek, i.e., chief builder.

<span class="mw-page-title-main">Construction</span> Process of building or assembling a building or infrastructure

Construction is a general term meaning the art and science of forming objects, systems, or organizations. It comes from the Latin word constructio and Old French construction. To 'construct' is a verb: the act of building, and the noun is construction: how something is built or the nature of its structure.

<span class="mw-page-title-main">Professional diving</span> Underwater diving where divers are paid for their work

Professional diving is underwater diving where the divers are paid for their work. Occupational diving has a similar meaning and applications. The procedures are often regulated by legislation and codes of practice as it is an inherently hazardous occupation and the diver works as a member of a team. Due to the dangerous nature of some professional diving operations, specialized equipment such as an on-site hyperbaric chamber and diver-to-surface communication system is often required by law, and the mode of diving for some applications may be regulated.

Construction site safety is an aspect of construction-related activities concerned with protecting construction site workers and others from death, injury, disease or other health-related risks. Construction is an often hazardous, predominantly land-based activity where site workers may be exposed to various risks, some of which remain unrecognized. Site risks can include working at height, moving machinery and materials, power tools and electrical equipment, hazardous substances, plus the effects of excessive noise, dust and vibration. The leading causes of construction site fatalities are falls, electrocutions, crush injuries, and caught-between injuries.

<span class="mw-page-title-main">Construction worker</span> Person employed in the physical work during construction

A construction worker is a worker employed in the physical construction of the built environment and its infrastructure.

A contractor or builder, is responsible for the day-to-day oversight of a construction site, management of vendors and trades, and the communication of information to all involved parties throughout the course of a building project.

Process Safety Managementof Highly Hazardous Chemicals is a regulation promulgated by the U.S. Occupational Safety and Health Administration (OSHA). It defines and regulates a process safety management (PSM) program for plants using, storing, manufacturing, handling or carrying out on-site movement of hazardous materials above defined amount thresholds. Companies affected by the regulation usually build a compliant process safety management system and integrate it in their safety management system. Non-U.S. companies frequently choose on a voluntary basis to use the OSHA scheme in their business.

Construction management (CM) aims to control the quality of a project's scope, time, and cost to maximize the project owner's satisfaction. It uses project management techniques and software to oversee the planning, design, construction and closeout of a construction project safely, on time, on budget and within specifications.

Formerly called the Intern Development Program (IDP), the Architectural Experience Program (AXP) is designed to ensure that candidates pursuing licensure in the architecture profession gain the knowledge and skills required for the independent practice of architecture. The program is developed, maintained, and administered by the National Council of Architectural Registration Boards (NCARB) and is required by most U.S. architectural registration boards to satisfy experience requirements for licensure.

<span class="mw-page-title-main">Health and Safety at Work etc. Act 1974</span> United Kingdom legislation

The Health and Safety at Work etc. Act 1974 is an act of the Parliament of the United Kingdom that as of 2011 defines the fundamental structure and authority for the encouragement, regulation and enforcement of workplace health, safety and welfare within the United Kingdom.

<span class="mw-page-title-main">Site Waste Management Plans Regulations 2008</span> United Kingdom legislation

During their period in operation, from 2008 to 2013, the Site Waste Management Plans Regulations 2008 required those responsible for a construction or demolition project with a value in excess of £300,000 to put in place a site waste management plan.

The WorkCover Authority of New South Wales was a New South Wales Government agency established in 1989. The agency created regulations to promote productive, healthy and safe workplaces for workers and employers in New South Wales. The agency formed part of the Safety, Return to Work and Support Division established pursuant to the Safety, Return to Work and Support Board Act, 2012 (NSW).

Prevention through design (PtD), also called safety by design usually in Europe, is the concept of applying methods to minimize occupational hazards early in the design process, with an emphasis on optimizing employee health and safety throughout the life cycle of materials and processes. It is a concept and movement that encourages construction or product designers to "design out" health and safety risks during design development. The process also encourages the various stakeholders within a construction project to be collaborative and share the responsibilities of workers' safety evenly. The concept supports the view that along with quality, programme and cost; safety is determined during the design stage. It increases the cost-effectiveness of enhancements to occupational safety and health.

<span class="mw-page-title-main">Diving supervisor</span> Professional diving team leader responsible for safety

The diving supervisor is the professional diving team member who is directly responsible for the diving operation's safety and the management of any incidents or accidents that may occur during the operation; the supervisor is required to be available at the control point of the diving operation for the diving operation's duration, and to manage the planned dive and any contingencies that may occur. Details of competence, requirements, qualifications, registration and formal appointment differ depending on jurisdiction and relevant codes of practice. Diving supervisors are used in commercial diving, military diving, public safety diving and scientific diving operations.

Contractor management is the managing of outsourced work performed for an individual company. Contractor management implements a system that manages contractors' health and safety information, insurance information, training programs and specific documents that pertain to the contractor and the owner client. Most modern contracts require the effective use of contract management software to aid administration between multiple parties.

<span class="mw-page-title-main">Construction (Design and Management) Regulations 2015</span> United Kingdom legislation

The Construction Regulations 2015, also known as CDM Regulations or CDM 2015, which came into force on 6 April 2015, are regulations governing the way construction projects of all sizes and types are planned in the UK. Replacing Construction Regulations 2007, CDM 2015 is the latest update to the regulations that aim to improve the overall health, safety and welfare of those working in construction. These regulations offer a very broad definition of what construction works are- everyone involved in a construction project, including home maintenance and improvement works, has responsibility for health and safety.

MS 1722:2011 – Occupational Safety and Health Management Systems – Requirements is a Malaysian Standard that provides requirements on Occupational Safety and Health Management Systems (OSHMS) and basis for the development OSH systems in an organisation. The MS 1722 standard enable an organization to manage its OHS risks and improve its OHS performance. The requirements of the standard are intended to address OHS for employees, temporary employees, contractors and other personnel on site rather than the safety of products and services. The standards provide a more effective method of protecting employees and others from workplace injuries and illnesses and demonstrate management commitment in meeting OHS requirements.

<span class="mw-page-title-main">Reclaiming Health and Safety For All</span>

Reclaiming Health and Safety For All also known as the Löfstedt Report is a 2011 report commissioned by the British government to review existing health and safety legislation and its impact upon businesses. The report was written by Ragnar Löfstedt and recommended the revocation of regulations that were of no benefit, updating of approved codes of practice and the abolition of the "strict liability" to mitigate all risks. The report resulted in a review of all Approved Codes of Practice by the Health and Safety Executive and the revocation of two regulations that were perceived to be of no benefit.

<span class="mw-page-title-main">Media diving</span> Underwater diving in support of the media industries

Media diving is underwater diving in support of the media industries, including the practice of underwater photography and underwater cinematography outside of normal recreational interests. Media diving is often carried out in support of television documentaries, such as the BBC series Planet Earth or movies, with feature films such as Titanic and The Perfect Storm featuring underwater photography or footage. Media divers are normally highly skilled camera operators who use diving as a method to reach their workplace, although some underwater photographers start as recreational divers and move on to make a living from their hobby.

The operations manual is the documentation by which an organisation provides guidance for members and employees to perform their functions correctly and reasonably efficiently. It documents the approved standard procedures for performing operations safely to produce goods and provide services. Compliance with the operations manual will generally be considered as activity approved by the persons legally responsible for the organisation.

References

  1. "The Construction (Design and Management) Regulations 2007". Legislation.gov.uk. Retrieved 12 June 2014.
  2. "Construction - Construction Design and Management Regulations 2007". Hse.gov.uk. 23 May 2013. Retrieved 12 June 2014.
  3. "Directive 92/57/EEC - temporary or mobile construction sites — Safety and Health at Work - EU-OSHA". Osha.europa.eu. Retrieved 12 June 2014.
  4. "The Construction (Health, Safety and Welfare) Regulations 1996". Legislation.gov.uk. 20 April 2012. Retrieved 12 June 2014.
  5. "The Construction (Design and Management) Regulations 2015". legislation.gov.uk. Retrieved 26 September 2016.
  6. Regulations [ dead link ]
  7. "Managing health and safety in construction". Hse.gov.uk. 18 June 2012. Archived from the original on 23 June 2014. Retrieved 12 June 2014.
  8. HSE, Notifications - F10s, accessed 17 July 2020
  9. "F10 Notification of construction project v3.5". Extranet.hse.gov.uk. Retrieved 12 June 2014.
  10. "HSE Forms - Notifications". Hse.gov.uk. 1 April 2014. Retrieved 12 June 2014.
  11. "CDM 2015 Regulation Update". Safer Sphere, CDM Coordination. Archived from the original on 19 August 2014. Retrieved 19 August 2014.