The Rail Clearways Programme was conceived in 2004 with the aim of easing congestion of Sydney's suburban railway network, by reducing the amount of infrastructure shared by multiple services. The disparate projects at pinch points throughout the network were designed to increase passenger capacity and improve reliability. All projects were delivered by the Transport Construction Authority until it was subsumed in November 2011 by Transport for New South Wales. A new timetable was introduced in October 2013 that realised the benefit of many of the projects, and by January 2014—the programme was complete.
In the mid-2000s, the Government of New South Wales suffered heavy criticism for its perceived mishandling of the Sydney rail network, which had very poor on-time performance following the January 2003 Waterfall train disaster. The safety regime introduced after this crash required drivers to stick to the speed limit, which often caused delays due to the expectations of the timetable for higher speeds. A slower timetable was introduced in September 2005, which significantly improving on-time running of services. [1] The Clearways Programme was intended as the next step in improving the network.
The Clearways Programme aimed to divide fourteen rail lines into five independent "clearways", reducing the heavily interwoven nature of the Sydney system. This was intended to isolate incidents to one part of the network so other lines would still run as scheduled. The "clearways" feed the existing lines through the Sydney Central Business District. [2]
As the Carlingford Line does not run through the CBD, it was not included in a "clearway". Track upgrades to the Carlingford Line were still included in the programme, but this was cancelled in the November 2008 Mini-Budget. [3] The Carlingford Line has since closed for Light Rail conversion.
The five clearways routes are:
This route did not change from the pre-Clearways Eastern Suburbs & Illawarra Line. The projects undertaken on this route have increased passenger capacity.
After the Airport line opened in May 2000, most trains from the East Hills line used the new line to approach the city. This eased congestion on the older line between Sydenham and Erskineville, where tracks were shared with services from the Bankstown line. Under the programme, new dedicated tracks for the Bankstown line between Sydenham and Erskineville were to be constructed to the west of the existing four tracks to allow express East Hills line trains from Clearway 3 to again run via Sydenham. The Airport line would be served by all-stops East Hills Line trains from Clearway 4.
St Peters and Erskineville railway stations were expected to continue to be served by the Bankstown line. This would have required platforms—partially completed in the 1970s from the Eastern Suburbs line construction—to have been activated at these two stations. The works were cancelled in November 2008, and the plan for frequent operation of express East Hills line services via Sydenham was abandoned.
A second Bankstown line project involved the construction of a new turn-back platform at Lidcombe, separating the Bankstown line's operations from trains on the Main Suburban line. This worked in concert with the Homebush turn-back project, which provided a terminating point for all stations Inner West Line services on the Main Suburban. This separation was enacted in the October 2013 timetable. The turn-back platform at Lidcombe was also marked in 2012 as a terminal for Sydney Metro Southwest, with original plans to convert the Bankstown line through to Lidcombe and Cabramatta into rapid transit. [4] This plan has since been altered to have Bankstown as the terminus of the metro line.
The Campbelltown Express Clearway would have separated the section of the East Hills Line east of Revesby by quadruplicating between Kingsgrove and Revesby and sending express trains to the City Circle via Sydenham. This was to allow more frequent express services to the city, relieve pressure on other parts of the network and improve the distribution of passengers.
On the Airport & South Clearway, express services would have begun at Glenfield and made their way through Liverpool, Cabramatta, Granville, Lidcombe and Strathfield stations to the City Circle, while all-stations services to the City started at Homebush. [5] After passing through the City Circle, trains would have headed south-west via the Airport Line to Revesby (running parallel with the Campbelltown Express line from Wolli Creek to Revesby).
In the October 2013 timetable, these two clearways were merged to create the Airport, Inner West & South Line. Differences from the original plan include via-Revesby and via-Granville trains sharing tracks between Glenfield and Macarthur, and all-stations and express trains via-Revesby sharing tracks between Revesby and Central. Most trains from Macarthur via Revesby use the local (pre-existing) tracks between Revesby and Wolli Creek, and make a number of stops along the route. These trains approach the City via the Airport. The route via-Sydenham and the express tracks between Wolli Creek and Revesby are only used by a limited number of peak-hour services as well as NSW Trains services to Goulburn, Canberra, Griffith and Melbourne.
In the November 2017 timetable, in addition to peak-hour trains from Macarthur via Sydenham utilising the express tracks between Wolli Creek and Revesby, most Macarthur via Airport services throughout the day now operate via the express tracks, resulting in the full separation of Macarthur express trains from Revesby all-stations trains which continue to use the local tracks. This has resulted in the removal of express trains for Padstow and Riverwood as the express tracks are unable to serve those stations where there are no platforms.
The North West Clearway provides an independent corridor for the North Shore & Western Line and Northern Line to improve reliability and capacity. Trains from the west start from the Richmond, Penrith or Epping branches, meet up at Strathfield and travel through the city to Chatswood. Here trains used to split, either continuing up the North Shore Line to Berowra, or via the Chatswood to Epping Line to Hornsby, prior to its conversion to Sydney Metro Northwest in 2018.
Many infrastructure upgrades needed to be completed in order to implement the Clearways plan. These projects included upgrading stations, adding extra tracks, stabling facilities, or upgrading junctions. The projects were:
Project | Clearway [5] | Description | Opened |
---|---|---|---|
Berowra third platform | North West | Allows through trains to pass terminating suburban trains | October 2006 [6] [7] |
Bondi Junction turnback and stabling sidings. | Eastern Suburbs & Illawarra | Improves terminating capacity and provides more space for trains to be stabled in off-peak periods | July 2006 [6] [8] |
Carlingford line passing loop at Rydalmere | N/A | Would have provided a passing opportunity on the single track section between Rosehill and Carlingford | Cancelled November 2008 [3] |
Erskineville-Sydenham six tracks | Bankstown Campbelltown Express | Would have created a new track pair for Bankstown line trains, allowing Campbelltown Express trains to have their own track pair | Cancelled November 2008 [3] |
Homebush Turnback | Airport & South | Breaks the Bankstown loop by giving Inner West line trains a place to terminate where six tracks reduce to four | March 2011 [6] [9] |
Hornsby fifth platform | North West | Allows through trains to pass terminating suburban trains | March 2009 [6] [10] |
Kingsgrove-Revesby Quadruplication | Campbelltown Express Airport & South | Allows express trains to overtake and remain separate from all stops services, in conjunction with existing four track section between Wolli Creek and Kingsgrove | April 2013 [6] [11] |
Lidcombe Turnback | Bankstown | Breaks the Bankstown loop by giving Bankstown line trains a place to terminate | November 2010 [6] [12] |
Liverpool Second Turnback | Bankstown | New platform for through trains, allowing conversion of existing through platform and side turnback into two centre turnbacks | January 2014 [13] [14] |
Macarthur fourth platform and upgrade | Campbelltown Express | New platform for through trains, allowing conversion of existing through platform into centre turnback | Stage one (upgrade): December 2010 Stage two (new platform) deferred 2013 [6] [15] |
Macdonaldtown Turnback | Airport & South | Allows trains to layover close to the city | December 2005 [6] |
Macdonaldtown Stabling | Airport & South | Extension of Macdonaldtown Turnback | November 2007 [6] [16] |
Quakers Hill-Vineyard Duplication | North West | Improves capacity to support new suburbs in North-Western Sydney | Schofields – Vineyard deferred Oct 2008 [3] Quakers Hill – Schofields: October 2011 [6] [17] |
Revesby Turnback | Airport & South | Replacement of side turnback at East Hills with more efficient centre turnback | December 2008 [6] [18] |
Sutherland-Cronulla Duplication | Eastern Suburbs & Illawarra | Duplication of single track sections between Sutherland and Gymea and between Caringbah and Cronulla to improve capacity | April 2010 [6] [19] |
Other projects of the era which were not part of the Rail Clearways programme:
Resignalling:
Cancelled projects included:
The Epping to Chatswood rail link (ECRL) is a railway line in the northern suburbs of Sydney, Australia, which connects Epping station on the Northern line with Chatswood on the North Shore line. It was formerly considered its own railway line, but is now part of the Metro North West & Bankstown Line.
The Eastern Suburbs & Illawarra Line is a commuter railway line on the Sydney Trains network in the eastern and southern suburbs of Sydney. The line was constructed in the 1880s to Wollongong to take advantage of agricultural and mining potentials in the Illawarra area. In March 1926, it became the first railway in New South Wales to run electric train services.
Revesby railway station is a heritage-listed railway station located on the East Hills line, serving the Sydney suburb of Revesby. It is served by Sydney Trains' T8 Airport & South Line services.
East Hills railway station is located on the East Hills line, serving the Sydney suburb of East Hills. It is served by Sydney Trains' T8 Airport & South Line services.
The Airport & South Line is a commuter rail service operated by Sydney Trains, connecting the Sydney central business district with the southwestern suburbs via Sydney Airport.
Glenfield railway station is a junction station serving the Sydney suburb of Glenfield in Australia. It is served by Sydney Trains' T8 Airport & South, T2 Leppington & Inner West and T5 Cumberland line services, and by limited NSW TrainLink's Southern Highlands Line services.
The Southern Sydney Freight Line (SSFL) is a freight only railway line in the south-western suburbs of Sydney, Australia. The line was built to segregate freight trains from the Sydney Trains network. It forms part of a dedicated freight only corridor between Port Botany and Macarthur. The line is managed by the Australian Rail Track Corporation.
Bankstown railway station is a heritage-listed railway station on the Bankstown railway line in the Sydney suburb of Bankstown. It is currently the southern terminus of T6 Lidcombe & Bankstown services, and will in future be the southwestern terminus of M1 Metro North West & Bankstown services.
Lidcombe railway station is a heritage-listed railway station located on the Main Suburban line, serving the Sydney suburb of Lidcombe. It is served by Sydney Trains T1 Western, T2 Leppington & Inner West, T3 Liverpool & Inner West Line, T6 Lidcombe & Bankstown Line and T7 Olympic line services.
The East Hills railway line serves the southern and south-western suburbs of Sydney, Australia. The line opened to East Hills in 1931 and was extended to connect to the Main South Line in 1987. Most services along the line form part of the Airport & South Line operated by Sydney Trains.
Kingsgrove railway station is a heritage-listed railway station located on the East Hills line, serving the Sydney suburb of Kingsgrove. It is served by Sydney Trains' T8 Airport & South Line services.
Sydney, the largest city in Australia, has an extensive network of passenger and goods railways. The first railway line in Sydney opened in 1855, becoming part of the Main Suburban railway line and laying the foundation for future expansion.
The South West Rail Link is a railway line serving the developing suburbs of south-western Sydney, Australia between Glenfield and Leppington. Services form part of the Sydney Trains suburban rail network. It opened on 8 February 2015.
The Transport Construction Authority (TCA), formerly Transport Infrastructure Development Corporation (TIDC) prior to July 2010, was an agency of the Government of New South Wales that was responsible for new railway projects in the city of Sydney, Australia. On 1 November 2011 the Transport Construction Authority was subsumed into the newly formed Transport for NSW.
The Leppington & Inner West Line is a commuter rail service operated by Sydney Trains, serving the inner west and south-western suburbs of Sydney, Australia. The service commences from the City Circle, heading west to Granville where the line branches; services either head northwest to Parramatta or south to Leppington. A third terminus at Homebush is also used when the part-time Parramatta branch is not operating.
The Bankstown railway line is a suburban railway which traverses the Inner West and Canterbury-Bankstown areas of Sydney. West of Bankstown it is used by T6 Lidcombe & Bankstown services, while east of Bankstown it is temporarily closed to facilitate conversion for its future use by M1 North West & Bankstown services.
Sydney Metro City & Southwest is a 30-kilometre (19 mi) rapid transit construction project in Sydney, Australia. The project will extend the Metro North West & Bankstown Line from Chatswood on the North Shore, to Bankstown in the city's southwest via the Sydney central business district. The line is part of the Sydney Metro system. Its first phase, Sydney Metro City, opened on 19 August 2024.
The Metro North West & Bankstown Line is a rapid transit rail line in Sydney, New South Wales, Australia. The first and currently only line on the Sydney Metro network, it commenced operation on 26 May 2019, originally running between Tallawong and Chatswood, before the line was extended on 19 August 2024 to Sydenham. The line will be extended to Bankstown in 2025.
The Lidcombe & Bankstown Line is a commuter rail service operated by Sydney Trains in Sydney, Australia. The service runs between Lidcombe and Bankstown via the Main Southern railway line and the Bankstown railway line.
The Liverpool & Inner West Line is a commuter rail service operated by Sydney Trains in the Inner West and Western suburbs of Sydney. It operates from the City Circle to Liverpool via the Main Suburban railway line to Lidcombe and the Main Southern railway line from there to Liverpool.