Red Line (Tel Aviv Light Rail)

Last updated
Red Line
Dankal Logo.svg
Overview
Locale Flag of Israel.svg Tel Aviv, Petah Tikva, Bnei Brak, Ramat Gan, Bat Yam
Termini
  • Petah Tikva Central Bus Station
    Kiryat Aryeh depot
  • HaKomemiyut (Bat Yam)
Stations34
Website www.dankal.co.il/new-service-lines-and-stations/?lang=en
Service
Type BSicon TRAM1.svg Light rail
System Dankal Logo.svg Tel Aviv Light Rail
Operator(s)Tevel Metro
Depot(s)Kiryat Aryeh depot
Rolling stock CRRC Changchun Railway Vehicles LRV
Daily ridership70,000 [1]
History
OpenedAugust 18, 2023
Technical
Line length24 km (15 mi)
Track gauge 1,435 mm (4 ft 8+12 in) standard gauge
Electrification 1500 V DC OHLE
Operating speed50 km/h (31 mph) in Street Level
70 km/h (43 mph) Underground
Route map

Contents

BSicon uKBHFa.svg
Petach Tikva CBS
BSicon uHST.svg
Pinsker
BSicon uHST.svg
Krol
BSicon uHST.svg
Dankner
BSicon uHST.svg
Beilinson
BSicon uHST.svg
Shacham
BSicon uHST.svg
Shenkar
BSicon uKDSTa.svg
BSicon uSTR.svg
Kiryat Arye IsraelTrainLogoSymbolOnly.svg
BSicon utHST.svg
BSicon utSTRa.svg
Em HaMoshavot Bridge
BSicon utKRWl.svg
BSicon utKRWg+r.svg
BSicon utHST.svg
Aharonovich
BSicon utHST.svg
Ben-Gurion
BSicon utHST.svg
Bialik
BSicon utHST.svg
Abba Hillel
BSicon utHST.svg
Arlosoroff IsraelTrainLogoSymbolOnly.svg
BSicon utHST.svg
Sha'ul HaMelekh IsraelTrainLogoSymbolOnly.svg
BSicon utHST.svg
Yehudit
BSicon utHST.svg
Carlebach
BSicon utHST.svg
Allenby
BSicon PORTALg.svg
BSicon uHST.svg
Elifelet
BSicon uHST.svg
Shalma (Salame)
BSicon uHST.svg
Bloomfield Stadium
BSicon uHST.svg
Ehrlich
BSicon uHST.svg
Isakov
BSicon uHST.svg
HaBesht
BSicon uHST.svg
Machrozet
BSicon uHST.svg
Ha'Atsma'ut
BSicon uHST.svg
Rothschild
BSicon uHST.svg
Jabotinsky
BSicon uHST.svg
Balfour
BSicon uHST.svg
Binyamin
BSicon uHST.svg
Yoseftal IsraelTrainLogoSymbolOnly.svg
BSicon uHST.svg
Kaf Tet BeNovember
BSicon uHST.svg
He'Amal
BSicon uKBHFe.svg
HaKomemiyut IsraelTrainLogoSymbolOnly.svg

The Red Line is the first section of a light rail system in the Tel Aviv metropolitan area, known as the Tel Aviv Light Rail. The line runs from Bat Yam in the south to Petah Tikva in the northeast with a significant portion of it underground. The total cost of the red line is estimated at NIS 11 billion or, approximately US$3 billion. Construction began in 2011, with the testing phase of the line beginning only a decade later, in 2021. [2] After numerous delays concerning the security and safety of the line, it eventually opened on August 18, 2023 with a 100,000+ daily ridership over just 8 hours of operation. [3]

Route

The Red Line has a total of 34 stations. It starts at Petah Tikva's Central Bus Station, east of Tel Aviv and follows Jabotinsky Road (Route 481) westwards at street level. At the point where Jabotinsky Road and Highway 4 intersect the line drops into a tunnel for 11 km (6.8 mi) [4] and emerges to street level again just before Jaffa, where it turns southwards towards Bat Yam and also serves Bloomfield Stadium. The underground section includes 10 stations, including an interchange with Israel Railways services at Tel Aviv Savidor Central Railway Station and the nearby 2000 Terminal. A maintenance depot, connected via a branch line and tunnel to the main section of the line, was constructed in Kiryat Aryeh, across from the existing Petah Tikva-Kiryat Aryeh railway station. The branch line includes two passenger stations, at Em HaMoshavot Road and an interchange station at the Kiryat Arye railway station.

A planned southern extension will add 2.8 km (1.7 mi) into the city of Rishon LeZion and three intermediate stops and an inter-modal terminus which will serve as connection with Israel Railways' Rishon LeZion Moshe Dayan Railway Station and the projected Green Line. [5]

Operations

The Red Line operates from Sundays to Thursdays from 05:00 am with the last train departing at 00:30 am the following day. On Fridays, the last train departs 3 hours before the commencement of Shabbat (meaning approximately 14:00 in the winter and 16:00 in the summer), and on Saturdays there is no service during daylight hours, until the end of Shabbat at sundown on Saturday evenings.

The price for a single ride is ₪5.50. For journeys beyond 15 km, the price for a single ride jumps to ₪12.

There are 45 trains on the line during operating times each with 2 carriages and with a maximum capacity of 450 passengers per train. [6]

Waiting times in peak hours are approximately 3 minutes and off-peak hours the frequency will be 6 minutes per train. However, the frequency of the trains should increase as time goes by. [7]

Eyal Gelberg is the voice behind the Red Line and announces all the stations in Hebrew and English (another voice then announces in Arabic). Gelberg is famous for being the voice behind many buses in Israel.

Operator

In December 2006, the concession to build and operate the Red Line was awarded to the Metropolitan Transportation Solution (MTS) Consortium, which consisted of Africa Israel Investments, China Civil Engineering Construction Corporation (CCECC), Soares da Costa (Portugal), the Egged Bus Cooperative, Siemens, and the Dutch transportation company HTM.

In February 2007, the NIS 7.1 billion concession was a Build Operate Transfer (BOT) contract, the biggest private sector contract ever tendered in Israel's history. MTS's bid was just NIS 400 million under that of rival Metrorail, who bid NIS 7.5 billion. [8]

Financing difficulties

In February 2007, the BOT agreement with the MTS consortium was signed and construction was to start a year later, in February 2008. [8] However, the consortium was unable to secure the necessary financing and was given several extensions to the agreed timetable. The difficulties raising the funding was attributed to the global financial crisis and specifically to the financial problems at Africa Israel Investments Group. [9]

In November 2009, the Israeli government announced that it was considering canceling the agreement with the consortium and granted another extension until March 2010. It was announced that if funding is not secured by then, the government will consider other options for financing the railway, including the option of using public instead of private funding for the project. The deadline was then extended again to summer 2010 and in August the government, after extensive negotiations with MTS failed, finally canceled the MTS concession, though MTS indicated it would appeal the government's decision in arbitration proceeding.[ citation needed ]

NTA takes over

Following the cancellation of the MTS contract, the government announced that it would fund the construction directly from the Treasury and that NTA would manage subsequent phases of construction. As a result, NTA published a tender for the design of multiple launching shafts for the TBMs that would dig the 11 km of tunnels for the railway.

In March 2011, the shafts' construction tender was published as well, in addition to a tender for the design of the Kiryat Aryeh depot. The anticipated overall completion date of the railway was 31 December 2017. [10] On December 20, 2010, the transfer of the entire project's management to NTA was approved by the project's arbitrators with MTS. On January 12, 2012, NTA published a pre-qualify (PQ) bid for the design-build contract for excavating the Red and Green lines' tunnels to be performed by several TBMs operating simultaneously.

From October 2021, Egged has been awarded the tender to operate and maintain the Tel Aviv Red Line by the NTA Metropolitan Mass Transit System Ltd. tenders committee. The winning bid was from the Tevel consortium controlled by Egged (51%) with Chinese companies Shenzhen Metro (30%) and CCECC (19%).

The first train of the red line RygeI11wh2h 0 0 1280 855 0 x-large.jpg
The first train of the red line

Construction

The Red Line is the second underground service in Israel, after the Carmelit, in Haifa. The line is 24 km (15 mi) in length, with 34 stops, of which 10 are underground. The underground stations are equipped with platform screen doors [5] and also trains in the underground section are operated via an automatic train operation system. [11]

Preparatory works

Initial preparatory works began in 2007. NTA, the Government body responsible for the mass-transit development in the Tel Aviv region has spent several years performing utility relocation and right-of-way clearing for the railway. The bulk of the work however, including underground excavation, is to be carried out by the operator.

On April 10, 2008, works started on the conversion of part of the Jabotinsky Rd. in Petah Tikva into a sunken passage below Kaplan St. [12]

As part of the preparatory works for the line, the main entrance to the Batei HaOsef museum in south Tel Aviv was cleared and relocated. The Bank HaPoalim branch on Herzl Street in the same area was also demolished. [13]

TBM Shafts

In September 2011, work started on constructing 3 launching shafts for the TBMs [14]

Tunnelling Works

Eastern end of the Red Line tunnel at the depot in Petah Tikva Tel Aviv LRT Em HaMoshavot Tunnel 5.jpg
Eastern end of the Red Line tunnel at the depot in Petah Tikva

In May 2015, the companies Solel Boneh and China Railway Tunnel Group won the 2.9 Billion NIS tender to build two 5-kilometre (3.1 mi) tunnels and 6 underground stations in the western section of the Tel Aviv light rail's red line. [15]

In June 2015, the companies Danya Cebus and China Civil Engineering Construction Corporation (CCECC) won the 700 Million NIS tender to build underground Carlebach station of the Tel Aviv light rail's red line.

By February 2017, most of the stations on the Red Line were already under construction.[ citation needed ]

Testing Phase

In 2021, the testing phase of the Red Line started after construction ended. The first trains started driving across the tracks. [16]

In June 2023, during the testing phase, many problems involving the brakes of the trains suddenly stopping in the middle of the tracks became the center of attention in this phase. The mayor of Petah Tikva announced that the line would open in July 2023. [17] The companies were desperately trying to fix this major issue that lead to severe delays to the lines opening date. [18] Days later, the issue was fixed, and the line was approved by all security factors to begin operations in August 2023. [19] The line opened on August 18, 2023. [3]

Extensions

On December 5, 2022, the Ministry of Transportation allocated approximately NIS 100 million for the extension of the Red Line. This is for the purpose of detailed planning of a route from Bat Yam to the Rishon LeZion - Moshe Dayan train station. [20] The planning extended the line by 2.5 kilometers, and included the construction of four new stations: Menachem Begin station, Koresh station, Rehavam Zaevi station and Shimon Israel station, which will be built near the Moshe Dayan interchange.

Rolling stock

A reduced-size prototype of a Tel Aviv LRT trainset Tel Aviv Red Line LRT Carriage Prototype.jpg
A reduced-size prototype of a Tel Aviv LRT trainset
Tel Aviv LRT train interior Tel Aviv Red Line LRT Carriage Prototype Interior.jpg
Tel Aviv LRT train interior

The Red Line trams are manufactured by CRRC Changchun Railway Vehicle Company. One LRV include 5 modules, The configuration is Mc1+F1+Tp+F2+Msc1. Two vehicles are combined as one trainset for operation. The vehicle comply with ISO, EN and Israel standards.

See also

Related Research Articles

<span class="mw-page-title-main">Petah Tikva</span> City in central Israel

Petah Tikva, also known as Em HaMoshavot, is a city in the Central District of Israel, 10.6 km (6.6 mi) east of Tel Aviv. It was founded in 1878, mainly by Haredi Jews of the Old Yishuv, and became a permanent settlement in 1883 with the financial help of Baron Edmond de Rothschild.

<span class="mw-page-title-main">Tel Aviv Light Rail</span> Mass transit system for Tel Aviv, Israel

The Tel Aviv Light Rail, Arabic: دانكال تل أبيب للسكك الحديدية الخفيفة, Romanized: Dankal Tall ʾAbīb Lilsīkak Al-hadidiat Al-khāfifa also known as Dankal is a mass transit system for Gush Dan, the Tel Aviv metropolitan area in central Israel. The system will include different modes of mass transit, including rapid transit (metro), light rail transit (LRT), and bus rapid transit (BRT). Overseen by NTA Metropolitan Mass Transit System Ltd., a government agency, the project will complement the intercity and suburban rail network operated by Israel Railways.

Petah Tikva is a city in the Central District of Israel.

<span class="mw-page-title-main">Tel Aviv Savidor Central railway station</span> Railway station in Tel Aviv, Israel

The Tel Aviv Savidor Central railway station is a major railway station on the Ayalon Railway in central Tel Aviv, Israel, serving most lines of Israel Railways.

<span class="mw-page-title-main">Rail transport in Israel</span>

Rail transport in Israel includes heavy rail as well as light rail. Excluding light rail, the network consists of 1,511 kilometers (939 mi) of track, and is undergoing constant expansion. All of the lines are standard gauge and as of 2023 approximately one-fifth of the heavy rail network is electrified, with additional electrification work underway. A government owned rail company, Israel Railways, manages the entire heavy rail network. Most of the network is located on the densely populated coastal plain.

<span class="mw-page-title-main">Route 471 (Israel)</span> Route in Israel

Highway 471, commonly called Maccabit Road, is a suburban expressway in the center of the Tel Aviv Metropolitan Area in Israel. The expressway connects Highway 4 in the west with Route 444 in the east. It is part of a road system planned to provide improved access to Highway 6.

<span class="mw-page-title-main">Jerusalem–Yitzhak Navon railway station</span> Train station located in Jerusalem, Israel

Jerusalem–Yitzhak Navon Railway Station, originally named Jerusalem–HaUma railway station is an Israel Railways passenger terminal in Jerusalem, located at 6 Shazar Avenue.

<span class="mw-page-title-main">Transport in Tel Aviv</span>

The Tel Aviv transportation system is seen as the hub of the Israeli transport network in terms of road, rail, and air transport. The Israeli road network partly centers on Tel Aviv, with some of the country's largest highways passing through or running to the city. The city forms a major part of the country's rail network, whilst Ben Gurion International Airport located near the city is the country's largest airport. There is also a strong public transport system within the city, based primarily on bus transportation.

<span class="mw-page-title-main">Tel Aviv–Jerusalem railway</span> Railway line in Israel

The Tel Aviv–Jerusalem railway is a railway line in Israel connecting the cities of Tel Aviv and Jerusalem. The line serves as the main rail link between the two cities, complementing the old Jaffa–Jerusalem railway. As such, the railway is often referred to in Israel as the high-speed railway to Jerusalem to distinguish it from the older, longer and slower line. In spite of that name, the line is not high-speed under the definition used by the International Union of Railways: both its design speed of 200 km/h (125 mph) and its current operational speed of 160 km/h (99 mph) are below the 250 km/h (155 mph) threshold used by the UIC to define high-speed railways, and it is traversed by IR's regular rolling stock instead of the UIC requirement for specially-designed high-speed trains.

<span class="mw-page-title-main">Bnei Brak–Ramat HaHayal railway station</span> Railway station in Israel

Bnei Brak–Ramat HaHayal railway station is a suburban passenger railway station in Israel, operated by Israel Railways. It is located on the Yarkon Railway near the Bnei Brak–Ramat Gan and Bnei Brak–Tel Aviv borders next to the Ayalon Mall and Ramat Gan Stadium. In spite of its proximity to important industrial and commercial areas of Gush Dan as well as to residential areas of Tel Aviv, Bnei Brak is one of the less-popular stations of Israel Railways, possibly because of its misleading name and lack of awareness. As a result, in an effort to increase the public's awareness of the station, the name of the Ramat HaHayal neighborhood located to the north of the station was added to the station's name in 2016.

<span class="mw-page-title-main">Petah Tikva–Kiryat Aryeh railway station</span> Railway station in Israel

The Petah Tikva-Kiryat Aryeh railway station is a suburban passenger railway station in Israel, operated by Israel Railways. It is located in the northern Kiryat Aryeh business area and industrial zone of Petah Tikva, and mainly serves commuters from other towns who work in Petah Tikva. The station is adjacent to HaMoshava Stadium. It consists of a passenger hall and two side platforms serving two tracks on the Yarkon Railway. Space exists to allow converting the far side platform to an island platform, allowing the station to serve a total of three tracks in the future.

<span class="mw-page-title-main">Lod Ganei Aviv railway station</span> Railway station in Israel

The Lod Ganei Aviv railway station is a station in Lod, Israel on the Tel Aviv–Rishon LeZion line.

China Civil Engineering Construction Corporation Ltd. was established in June 1979 under the approval of the State Council of the People's Republic of China.

Transport in Bnei Brak occupies a central location within the Gush Dan. It has an important role in transport throughout the region.

<span class="mw-page-title-main">Railway to Karmiel</span>

The Railway to Karmiel is a railway linking Haifa and Karmiel in northern Israel. It opened in 2017 and consists of a double track standard gauge railway stretching for 23 km from near Acre (Akko) to Karmiel. It branches eastwards from the Coastal Railway between the Kiryat Motzkin Railway Station and the Acre Railway Station and includes a 5 km long tunnel in the mountainous region near the eastern end of the line. Most of the route is in the vicinity of Highway 85. There are two stations on the railway: Ahidud and Karmiel.

The 2011–12 Israeli Premier League was the thirteenth season since its introduction in 1999 and the 70th season of top-tier football in Israel. It began on 20 August 2011 and ended on 12 May 2012. Maccabi Haifa were the defending champions.

The High-speed railway to Eilat (Med-Red) is a proposed Israeli railway that will enable the connection of the main Israeli population centers and Mediterranean ports to the southern city of Eilat on the Red Sea coast, as well as serve commercial freight between the Mediterranean Sea and Red Sea (Eilat). The railway will spur southward from the existing rail line at Beersheba, and continue through Dimona to the Arava, Ramon Airport and Eilat, at a speed of 350 kilometers per hour (220 mph). Its length will be roughly 260 km (160 mi) of electrified double-track rail. Currently Dimona railway station is the southernmost passenger train station in Israel and the one with the least boardings/alightings.

<span class="mw-page-title-main">Tel Aviv Metro</span> Planned subway system around Tel Aviv

Tel Aviv Metro is a planned subway system for the Tel Aviv Metropolitan Area. It will augment the Tel Aviv Light Rail and Israel Railways suburban lines and consist of three underground metro lines to form a rapid transit transportation solution for the city.

<span class="mw-page-title-main">Yarkon Railway</span> Railway line in Israel

The Yarkon Railway is a double-track railroad following the course of the Yarkon River in the central area of Israel. It is about 15 km long, stretching from the Coastal Railway to the Eastern Railway.

<span class="mw-page-title-main">Purple Line (Tel Aviv Light Rail)</span> Light rail line under construction in the Tel Aviv metropolitan area

The Purple Line is a light rail transit (LRT) line under construction in the Tel Aviv metropolitan area in Israel. The line will operate as part of the planned Tel Aviv metropolitan area mass transit system and is expected to be the second line to open. The line will connect the city centre of Tel Aviv with its eastern suburbs of Yehud and Giv'at Shmuel.

References

  1. Etzion, Udi. "חצי שנה לאחר פתיחת הקו האדום, מספר הנוסעים הוא רק כשליש מהתחזיות" [Half a Year After the Opening of the Red Line, the Ridership is Only About One Third of the Projection]. Walla! News (in Hebrew).
  2. "Tel Aviv Light Rail Completes First Test Drive". Haaretz. Retrieved 2023-07-03.
  3. 1 2 "'We waited a long time for this': Tel Aviv light rail sets off after years of delays". The Times of Israel. 2023-08-18. Retrieved 2023-08-18.
  4. "Tel Aviv Red Line tunnelling begins". Railway Gazette International. 20 February 2017. Retrieved 8 December 2020.
  5. 1 2 RFI - Preliminary and Final Design of 10 Underground Stations of the Red Line, NTA Site, 15 November 2010
  6. "Israel's New Light Rail Line". Haaretz. Retrieved 2023-08-19.
  7. "Tel Aviv light rail will launch at lower speed, frequency". Globes. 2023-02-27. Retrieved 2023-08-19.
  8. 1 2 "Tel Aviv contract signed amid legal disputes.(Transit News)", International Railway Journal, February 1, 2007, retrieved 2009-11-19
  9. Baron, Lior (2009-11-16), "Tel Aviv light rail co wants talks, not hearing MTS: A hearing is unacceptable under the terms of the franchise contract", Globes , retrieved 2009-11-19
  10. Avi Bar-Eli (2010-09-24), "Back on track? / State issues new tender for Tel Aviv light rail", TheMarker , retrieved 2010-10-25
  11. RFI for Acquisition and Maintenance of the Light Rail Vehicles Fleet, NTA Site, 17 November 2010
  12. Rothschild, Walter (September 28, 2008). "Light Rail Projects – Tel Aviv – Cutting" (PDF). HaRakevet (82): 10. Retrieved 2010-08-28.
  13. Rothschild, Walter (June 2008). "Light Rail – Tel Aviv" (PDF). HaRakevet (81): 7. Retrieved 2010-08-28.
  14. Tel Aviv light rail to be built underground, Globes 12 Feb 2012
  15. "Arison, Chinese co win TA light rail underground tender - Globes". 19 May 2015.
  16. Zagrizak, Asaf (2021-06-10). "Light rail line in central Israel launches first public test drive". Ynetnews. Retrieved 2023-08-19.
  17. "קרב גרסאות בין ראש עיריית פתח תקווה לחברת נת"ע: מתי ייפתח הקו האדום של הרכבת הקלה? | ישראל היום". www.israelhayom.co.il. 2023-06-22. Retrieved 2023-07-03.
  18. Burroughs, David (2022-09-07). "Tel Aviv Red Line opening could be delayed as issues mount". International Railway Journal. Retrieved 2023-08-19.
  19. "Tel Aviv light rail approved to begin operating on August 18". The Jerusalem Post. 2023-08-04. Retrieved 2023-08-04.
  20. "מסלול הרכבת הקלה מתארך לראשון לציון וגבעת שמואל | כלכליסט". calcalist (in Hebrew). 2022-12-05. Retrieved 2023-08-19.