Project Hurunui

Last updated
Hurunui Windfarm
Project Hurunui
Country
  • New Zealand
LocationNorth Canterbury
Coordinates 42°59′33″S172°57′32″E / 42.992595°S 172.958794°E / -42.992595; 172.958794
StatusProposed; resource consent granted but has lapsed with time
Owner(s) Meridian Energy
Power generation
Units operational33
Nameplate capacity 76 MW [1]

Project Hurunui is a proposed wind farm located between Omihi and Greta Valley in north Canterbury, New Zealand. Meridian Energy proposed the wind farm; in 2013 it received resource consent from the Environment Court, though this consent lapsed in 2023.

Contents

History

The proposal as of 2011 was for a wind farm of 33 turbines, with maximum height of 130.5 metres, located on a 34 km2 area on the east side of State Highway 1. [1]

Meridian Energy began consultations on the project in April 2010. [2] An informal survey of residents in the affected area showed that slightly more were in favour of the wind farm than those who were opposed. [3]

The application for consents was lodged in February 2011, [4] and notified in April 2011. [1] In June 2011, the Hurunui District Council and the Canterbury Regional Council agreed to a request by Meridian that the wind farm proposal be referred to the Environment Court. [5] Consent was granted by the Environment Court in April 2013, [6] though one of the conditions was that the consent lapsed if "not given effect to within ten years". [7]

In February 2021 Meridian said that the company wanted to see more demand in the South Island before developing more generation there. [8] which is planned to produce up to 75.9 MW from 2014. [9]

As of 2024, the Hurunui project does not appear in Meridian's webpage of projects. [10]

See also

Related Research Articles

Meridian Energy Limited is a New Zealand electricity generator and retailer. The company generates the largest proportion of New Zealand's electricity, generating 35 percent of the country's electricity in the year ending December 2014, and is the fourth largest retailer, with 14 percent of market share in terms of customers as of December 2015.

The Makara Guardians Inc. is an incorporated society formed in 1997 to coordinate opposition to proposals to build wind turbines near where the members live. Mākara is a rural locality 10 km west of Wellington, New Zealand. The Makara Guardians represents some 85% of the families in the Mākara Valley, and consists of around 160 members. Membership is restricted to residents or owners of land in Mākara who support the objectives of the Society and who are aged over 18.

<span class="mw-page-title-main">Hurunui River</span> River in Canterbury, New Zealand

The Hurunui River is the fourth largest of the four principal rivers in north Canterbury, New Zealand, with a catchment area of 2,670 square kilometres (1,030 sq mi). The river flows from the eastern side of the Southern Alps, to the Pacific Ocean.

<span class="mw-page-title-main">Te Rere Hau Wind Farm</span> New Zealand wind farm company

Te Rere Hau is a wind farm owned and operated by New Zealand Windfarms Ltd. It is situated on the Tararua Ranges, approximately 11 km east of Palmerston North in New Zealand.

<span class="mw-page-title-main">Wind power in New Zealand</span> Overview of wind power in New Zealand

Wind power constitutes a small but growing proportion of New Zealand's electricity. As of November 2023, wind power accounts for 1,059 MW of installed capacity and over 6 percent of electricity generated in the country.

Hauāuru mā raki was a proposed wind farm development on the Waikato coast of New Zealand.

<span class="mw-page-title-main">Waitahora Wind Farm</span> Abandoned renewable energy project

The Waitahora Wind Farm was a proposed renewable energy project in New Zealand planned by Contact Energy but which has now been abandoned without construction beginning. This development was proposed to be located on the Puketoi Range which forms one side of the picturesque Waitahora Valley, near Dannevirke in Southern Hawke’s Bay.

Turitea Wind Farm is a 222-megawatt wind farm near Turitea, Palmerston North, New Zealand. The farm is owned and operated by Mercury Energy.

The Mount Cass Wind Farm is a proposed wind farm to be located east of Waipara on Mount Cass in the Canterbury region of New Zealand. The project dates back to 2006, and the current plan by MainPower is to construct 22 wind turbines along a ridge of Mount Cass.

Project Hayes was a controversial wind farm proposed for the Lammermoor Range of Otago, New Zealand. The project was developed by Meridian Energy from 2006 to 2012 at a cost of $8.9 million.

Long Gully Wind Farm was a proposed wind farm in Wellington, New Zealand. Long Gully is an area adjacent to Zealandia.

<span class="mw-page-title-main">Project West Wind</span>

West Wind is a wind farm located at Terawhiti Station and Mākara, west of Wellington, New Zealand.

<span class="mw-page-title-main">Mill Creek Wind Farm</span>

Mill Creek Wind Farm is a wind farm in the Ohariu Valley near Wellington, New Zealand.

<span class="mw-page-title-main">Harapaki Wind Farm</span> Wind farm project in New Zealand

The Harapaki Wind Farm is a wind farm project in the Hawke's Bay region of New Zealand. Construction began in June 2021 and was completed in 2024. As of 2024 it is the second-biggest wind farm in New Zealand.

The Awhitu Wind Farm is a renewable energy project in New Zealand initially planned by Tilt Renewables. The development is proposed to be located on the Awhitu Peninsula near Waiuku on the west coast south of Auckland. As of 2016 the project was being privately pursued.

The North Bank tunnel concept was a hydroelectric scheme being developed by Meridian Energy on the Waitaki River in Canterbury, New Zealand. The $993 million project was expected to produce an additional 1,100 to 1,400 gigawatt-hours per annum, and take up to 260 cubic metres per second (9,200 cu ft/s) of water from Lake Waitaki. The project would have resulted in a 275 gigawatt-hours (990 TJ) per annum reduction in output from the Waitaki hydro station.

Project Huriwaka is a proposed wind farm located on the Hihitahi Plateau between Waiouru and Taihape, New Zealand. The project was originally developed and consented by Meridian Energy, but the consents were allowed to lapse. In May 2023 the rights to develop the project were acquired by Manawa Energy.

Viking Wind Farm is a large on-shore wind farm under construction in the Shetland Islands which is being developed by Viking Energy, a partnership between Shetland Islands Council and SSE plc. When complete, it will have a generation capacity of 443 MW.

The Castle Hill Wind Farm is a proposed wind farm being developed by Genesis Energy. It will have up to 286 wind turbines with potential output of up to 858 MW, depending on what model(s) of wind turbines are selected. The project is estimated to cost more than $1.6 billion and will be New Zealand's largest wind farm.

<span class="mw-page-title-main">Wind power in Connecticut</span> Electricity from wind in one U.S. state

The U.S. state of Connecticut has vast wind energy resources offshore as well as onshore although Connecticut was the last state in the United States to block the construction of utility scale wind turbines. Connecticut maintains a renewable portfolio standard that requires 21% of the state's electricity to come from renewable sources by 2020.

References

  1. 1 2 3 "Wind Farm Application Open for Submissions" (Press release). Hurunui District Council. 8 April 2011.
  2. "Wind farm planned for North Canterbury". RNZ. 4 April 2010. Retrieved 27 June 2021.
  3. Greenhill, Marc (16 February 2011). "Wind-turbine project splits rural neighbours". The Press . Retrieved 19 February 2011.
  4. "Meridian Lodges Resource Consent Application For Project Hurunui". Voxy. 21 February 2011. Retrieved 27 June 2021.
  5. "Meridian Wind Farm Proposal Heading To The Environment Court" (Press release). Hurunui District Council. 16 June 2011.
  6. Rachel Young (18 April 2013). "31 wind turbines for Hurunui". Stuff. Retrieved 27 June 2021.
  7. Meridian Energy Limited v Hurunui District Council [2013] NZEnvC 261 (4 November 2013) https://www.nzlii.org/cgi-bin/sinodisp/nz/cases/NZEnvC/2013/261.html "In accordance with section 125(1) of the Resource Management Act 1991, this resource consent will lapse if not given effect to within ten years of commencement."
  8. Gavin Evans (25 February 2021). "Dramatically faster consenting needed for renewables — Meridian". BusinessDesk. Retrieved 27 June 2021.
  9. "Project Hurunui". Meridian Energy.
  10. "New projects". Meridian Energy. Retrieved 2024-08-12.