Project Hayes

Last updated
Project Hayes
Project Hayes
CountryNew Zealand
Location Otago
Coordinates 45°30′39″S169°53′3″E / 45.51083°S 169.88417°E / -45.51083; 169.88417
Statuswithdrawn
Owner(s) Meridian Energy
Power generation
Units operational176
Nameplate capacity 630 MW

Project Hayes was a controversial wind farm proposed for the Lammermoor Range of Otago, New Zealand. [1] The project was developed by Meridian Energy from 2006 to 2012 at a cost of $8.9 million. [2] [3]

Contents

It had a proposed capacity of up to 630MW, at the time making it the largest wind farm project in the southern hemisphere. [1] The proposed farm would have covered an area of approximately 92 km², [4] used up to 176 wind turbines and cost up to $2 billion. [5] Meridian initially won resource consent for the project in 2007, but these were overturned by the Environment Court in 2009, and Meridian eventually announced it was withdrawing its application for consent in January 2012.

The project was named after engineer Eben Ernest Hayes (1851–1933), founder of the Hayes Engineering Works in Otago. He developed a windmill to power his engineering works from 1910 to 1927, and manufactured windmills for pumping water on farms. [6]

In May 2006, Meridian announced three public consultation days to explain Project Hayes. [7] Between July and October 2006, Meridian lodged applications for resource consents with the Central Otago District Council and with Otago Regional Council. [8]

Resource consents for Project Hayes were granted in 2007, however the decision was appealed to the Environment Court. [1] The project was opposed by a number of people, including the former All Black Anton Oliver [9] who is also opposing the nearby Mahinerangi Wind Farm. The respected painter Grahame Sydney and poet Brian Turner also opposed the wind farms. [10] Meridian spent more than NZ$7.6 million on the consenting process. [11]

In November 2009, the Environment Court declined the consents as they concluded that the project did not achieve sustainable management under the Resource Management Act 1991 because the substantial adverse impacts, principally on the outstanding natural landscape, outweighed the positive factors, principally the large quantity of renewable energy. [12] [13]

Meridian stated that the Environment Court, in requiring a comprehensive and explicit cost-benefit analysis including hypothetical projects, had effectively created a new legal test for projects to overcome. [14] Consequently, Meridian appealed the Environment Court decision to the High Court. [15] In August 2010, the High Court allowed Meridian's appeal and sent the case back to the Environment Court to be reconsidered, with Meridian to present further evidence on alternative locations. [16] [17] The opponents of the project (the Maniototo Environmental Society, Upland Landscape Protection Society, John and Sue Douglas and Ewan Carr) filed notice to appeal the High Court Decision to the Court of Appeal. [18] Meridian's lawyers asked the High Court to clarify its decision in respect of the Central Otago district plan landscape categories. [19] As of February 2011, no dates had been set for the next round of court hearings. [20]

In January 2012, Meridian announced it had withdrawn the applications for resource consent. [2] Meridian Chief Executive Mark Binns stated "... other projects now are a higher commercial priority than Project Hayes". [21]

See also

Related Research Articles

Meridian Energy Limited is a New Zealand electricity generator and retailer. The company generates the largest proportion of New Zealand's electricity, generating 35 percent of the country's electricity in the year ending December 2014, and is the fourth largest retailer, with 14 percent of market share in terms of customers as of December 2015.

The Makara Guardians Inc. is an incorporated society formed in 1997 to coordinate opposition to proposals to build wind turbines near where the members live. Mākara is a rural locality 10 km west of Wellington, New Zealand. The Makara Guardians represents some 85% of the families in the Mākara Valley, and consists of around 160 members. Membership is restricted to residents or owners of land in Mākara who support the objectives of the Society and who are aged over 18.

<span class="mw-page-title-main">Te Rere Hau Wind Farm</span> New Zealand wind farm company

Te Rere Hau is a wind farm owned and operated by New Zealand Windfarms Ltd. It is situated on the Tararua Ranges, approximately 11 km east of Palmerston North in New Zealand.

<span class="mw-page-title-main">Wind power in New Zealand</span> Overview of wind power in New Zealand

Wind power constitutes a small but growing proportion of New Zealand's electricity. As of December 2020, wind power accounts for 690 MW of installed capacity and over 5 percent of electricity generated in the country.

Hauāuru mā raki was a proposed wind farm development on the Waikato coast of New Zealand.

<span class="mw-page-title-main">Waitahora Wind Farm</span> Abandoned renewable energy project

The Waitahora Wind Farm was a proposed renewable energy project in New Zealand planned by Contact Energy but which has now been abandoned without construction beginning. This development was proposed to be located on the Puketoi Range which forms one side of the picturesque Waitahora Valley, near Dannevirke in Southern Hawke’s Bay.

<span class="mw-page-title-main">Mahinerangi Wind Farm</span>

The Mahinerangi Wind Farm is a wind farm on the north side of Lake Mahinerangi, around 50 km west of Dunedin, in Otago, New Zealand. Stage one of the wind farm, generating 36 MW, was commissioned in March 2011, and an additional 160 MW is consented to be commissioned in further stages.

The Mount Cass Wind Farm is a proposed wind farm to be located east of Waipara on Mount Cass in the Canterbury region of New Zealand. It will comprise of 22 wind turbines along a ridge of Mount Cass. Construction is scheduled to begin in 2024.

<span class="mw-page-title-main">Project West Wind</span>

West Wind is a wind farm located at Terawhiti Station and Mākara, west of Wellington, New Zealand.

Mill Creek Wind Farm is a wind farm in the Ohariu Valley near Wellington, New Zealand.

The Kaiwera Downs Wind Farm is a wind farm in the Southland region of New Zealand. It is consented to have a maximum capacity of 240 MW and use up to 83 turbines. Originally proposed by Trustpower, it is now owned and operated by Mercury Energy. The 10 turbine, 43 MW stage 1 of the project was opened in November 2023.

<span class="mw-page-title-main">Harapaki Wind Farm</span> Wind farm project in New Zealand

The Harapaki Wind Farm is a wind farm project in the Hawke's Bay region of New Zealand. Construction began in June 2021 and is expected to continue for three years.

The Mokihinui Hydro was a proposed hydroelectric dam and power station planned for conservation land on the Mōkihinui River on the West Coast of New Zealand. The project by Meridian Energy was expected to cost $300 million.

The Awhitu Wind Farm is a renewable energy project in New Zealand initially planned by Tilt Renewables. The development is proposed to be located on the Awhitu Peninsula near Waiuku on the west coast south of Auckland. As of 2016 the project was being privately pursued.

The North Bank tunnel concept was a hydroelectric scheme being developed by Meridian Energy on the Waitaki River in Canterbury, New Zealand. The $993 million project was expected to produce an additional 1,100 to 1,400 gigawatt-hours per annum, and take up to 260 cubic metres per second (9,200 cu ft/s) of water from Lake Waitaki. The project would have resulted in a 275 gigawatt-hours (990 TJ) per annum reduction in output from the Waitaki hydro station.

Project Huriwaka is a proposed wind farm located on the Hihitahi Plateau between Waiouru and Taihape, New Zealand. The project was originally developed and consented by Meridian Energy, but the consents were allowed to lapse. In May 2023 the rights to develop the project were acquired by Manawa Energy.

Project Hurunui is a proposed wind farm located between Omihi and Greta Valley in north Canterbury, New Zealand. Meridian Energy is developing the wind farm, which is planned to produce up to 75.9 MW from 2014.

The Escarpment Mine Project is an opencast coal mine at the Mount Rochfort Conservation Area on the Denniston Plateau on the West Coast of New Zealand in the vicinity of the disused Escarpment Mine. Bathurst Resources Limited intended to extract and export between one and four million tonnes of coal a year from open cast mining in an area of 200 hectares of conservation land on the southern Denniston Plateau. The mine would be the second largest opencast coal mine in New Zealand after Solid Energy's Stockton Mine on the Stockton Plateau. Environmental groups such as Forest and Bird and the West Coast Environment Network opposed the project.

The Castle Hill Wind Farm is a proposed wind farm being developed by Genesis Energy. It will have up to 286 wind turbines with potential output of up to 858 MW, depending on what model(s) of wind turbines are selected. The project is estimated to cost more than $1.6 billion and will be New Zealand's largest wind farm.

The Southland Wind Farm is a proposed wind farm on Slopedown in The Catlins in the Southland District of New Zealand.

References

  1. 1 2 3 Manins, Rosie (9 August 2008). "Project Hayes wind farm hearing to resume in January". Otago Daily Times. Retrieved 2008-09-21.
  2. 1 2 Edens, John (19 January 2012). "Meridian quits $2 billion wind project". Fairfax NZ News.
  3. "Project Hayes: counting the costs". Otago Daily Times. 23 January 2012.
  4. "Application for resource consent under section 88 of the resource management act 1991" (PDF). Meridian Energy Limited. 12 July 2006. Retrieved 2008-09-21.
  5. Manins, Rosie (28 January 2009). "Wind farm could attract tourists: Witness". Otago Daily Times.
  6. Orange, Claudia (1 September 2010). "Hayes, Eben Ernest - Biography". Te Ara - the Encyclopedia of New Zealand. Ministry for Culture and Heritage | Te Manata Taonga. ISBN   978-0-478-18451-8 . Retrieved 7 March 2011.
  7. "Meridian consulting on Central Otago wind farm" (Press release). Meridian Energy. 19 May 2006. Retrieved 3 April 2011.
  8. "Project Hayes wind farm". Meridian Energy. Archived from the original on 3 April 2011. Retrieved 3 April 2011.
  9. "Anton Oliver - features -". Sunday Star Times. Fairfax. 18 May 2008. Retrieved 7 March 2011.
  10. Ansley, Bruce (22 July 2006). "Putting the wind up". New Zealand Listener. Retrieved 7 March 2011.
  11. Hine, Will (27 August 2009). "Millions spent on wind farm fight". The Southland Times.
  12. Judge Jackson (6 November 2009). "Maniototo Environmental Society Incorporated v Central Otago District Council And Otago Regional Council; Re: Project Hayes Wind Farm" (PDF). C103/2009. Environment Court. Retrieved 6 March 2011.
  13. NZPA/ONE News (6 November 2009). "Consent for Otago Windfarm rejected". Television New Zealand.
  14. "Meridian To Seek Overturn Of Environment Court Decision On Project Hayes". Voxy. 27 November 2009. Retrieved 18 March 2011.
  15. Manins, Rosie (28 November 2009). "Meridian lodges appeal". Otago Daily Times.
  16. "Meridian Energy Limited V Central Otago District Council And Ors". CIV 2009 412 000980. Dunedin: High Court. 16 August 2010. Retrieved 6 March 2011.
  17. "Court upholds wind farm appeal". The Press. Fairfax New Zealand Ltd. 2010-08-16. Retrieved 2010-08-16.
  18. Edens, John (25 September 2010). "Fresh action against Hayes". The Southland Times.
  19. Edens, John (27 September 2010). "Project Hayes' future gets hazier by the day". Southland Times. Fairfax. Retrieved 18 March 2011.
  20. Van Kempen, Lynda (25 February 2011). "Lammermoors wind farm still in limbo". Otago Daily Times. Retrieved 18 March 2011.
  21. "Meridian withdraws resource consents for Project Hayes" (Press release). Meridian Energy. 19 January 2012. Retrieved 19 January 2012.