The Yellow Line or Line 4 is one of the under construction lines of Chennai Metro Phase-II stretching from Lighthouse to Poonamallee Bypass. The line will consist of 27 stations, out of which nine will be underground and 18 will be at grade or elevated. The colour code of the corridor was changed from Orange to Yellow, as per latest CMRL's latest Phase-II map. [2]
The construction of the first phase of Chennai Metro started in June 2009. [3] Commercial operations started on the green line in June 2015. [4] [5] [6] On 10 February 2019, the extension of blue line was opened, completing the first phase of the metro. [7]
In July 2016, Government of Tamil Nadu announced that the second phase would have three lines totaling 104 km (65 mi) in length with 104 stations. [8] [9] Two corridors would extend from Madhavaram Milk Colony connecting with Siruseri and Sholinganallur respectively with the third corridor connecting Koyambedu with Lighthouse. In July 2017, the state government announced an extension in Phase II, involving an extension of line four from Lighthouse up to Poonamallee with an intersection with the Madhavaram–Sholinganallur line at Alwarthirunagar. The line will extend to 26.1 km (16.2 mi) with 16 km (9.9 mi) elevated and 10.1 km (6.3 mi) underground. It will consist of 30 stations including 12 undergrounds stations. [10] [11] The stations for the second phase were designed to be smaller than the existing stations operational in the first phase. [12]
On 20 November 2020, foundation stone for the second phase was laid and construction commenced. [13] In November 2022, Alstom was awarded the contract to supply metro coaches for the phase II expansion. [14] In May 2023, CMRL announced a revised plan for the second phase revising the station count on the fourth line to 27. [15] As per the final plan, the fourth line will extend for 26.1 km (16.2 mi). [16]
The second phase is estimated to cost ₹63,246 crore (US$7.5 billion) of which initially ₹4,710 crore (US$560 million) was loaned by JICA. [10] [17] [18] On 14 February 2021, Prime Minister of India announced that the government has set aside ₹63,000 crore (US$7.5 billion) for the construction of phase II and further extension. [19]
| Line Name | Terminals | Length (km) | Stations | Status | |
|---|---|---|---|---|---|
| Yellow Line | Poonamallee Bypass | Vadapalani | 15.8 | 11 | Opens February 2026 |
| 6 | Opens June 2026 | ||||
| Vadapalani | Lighthouse | 10.3 | 10 | Under construction | |
In January 2025, Chennai Metro announced that the operations on Poonamallee Bypass to Vadapalani stretch will start in February 2026, with no intermediate stoppages at stations from Alapakkam to Saligramam. [21]
In 2022, the state government proposed an extension plan for the fourth line from Poonamalee to Parandur, covering an approximate 43.6 km (27.1 mi). [22] Detailed Project Report (DPR) of the line was prepared and submitted to Government of Tamil Nadu which approved the line in June 2025. This extension would be implemented in 2 phases, from Poonamallee Bypass to Sunguvarchatram in first phase and then to Parandur in second phase. The DPR is currently forwarded to Government of India for final approval. [23] Another extension of the corridor eastward from Lighthouse to High Court is also being planned. [24]
| Line | Terminals | Length | Stations | Status | |
|---|---|---|---|---|---|
| Yellow Line | Poonamallee | Sunguvarchatram | 27.9 km (17.3 mi) | 14 | DPR approved by state |
| Lighthouse | High Court | 7 km (4.3 mi) | TBD | Planned | |
| Yellow Line | ||||||
|---|---|---|---|---|---|---|
| S.No | Station Name [20] | Expected Opening [25] | Connections | Station Structure | ||
| English | Tamil | Station Type | Platform Level Type | |||
| 1 | Lighthouse | கலங்கரை விளக்கம் | April 2027 | Underground | Island | |
| 2 | Kutchery Road | கச்சேரி சாலை | April 2027 | Underground | Island | |
| 3 | Thirumayilai | திருமயிலை | April 2027 | (Chennai MRTS) Purple Line (Under Construction) | Underground | Island |
| 4 | Alwarpet | ஆழ்வார்பேட்டை | April 2027 | Underground | Island | |
| 5 | Bharathidasan Road | பாரதிதாசன் சாலை | April 2027 | Underground | Island | |
| 6 | Boat Club | படகு குழாம் | April 2027 | Underground | Island | |
| 7 | Nandanam | நந்தனம் | April 2027 | Blue Line | Underground | Island |
| 8 | Panagal Park | பனகல் பூங்கா | February 2027 | Underground | Island | |
| 9 | Kodambakkam | கோடம்பாக்கம் | February 2027 | | Underground | Island |
| 10 | Kodambakkam Powerhouse | கோடம்பாக்கம் பவர்ஹவுஸ் | June 2026 | Elevated | Side | |
| 11 | Vadapalani | வடபழனி | February 2026 | Green Line | Elevated | Side |
| 12 | Saligramam | சாலிகிராமம் | June 2026 | Elevated | Island | |
| 13 | Saligramam Warehouse | சாலிகிராமம் கிடங்கு | June 2026 | Elevated | Island | |
| 14 | Alwarthirunagar | ஆழ்வார்திருநகர் | June 2026 | Red Line (Under Construction) | Elevated | Island |
| 15 | Valasaravakkam | வளசரவாக்கம் | June 2026 | Red Line (Under Construction) | Elevated | Island |
| 16 | Karambakkam | காரம்பாக்கம் | June 2026 | Red Line (Under Construction) | Elevated | Island |
| 17 | Alapakkam | ஆலப்பாக்கம் | June 2026 | Red Line (Under Construction) | Elevated | Island |
| 18 | Porur Junction | போரூர் சந்திப்பு | January 2026 | Elevated | Side | |
| 19 | Porur Bypass | போரூர் புறவழிச்சாலை | January 2026 | Elevated | Island | |
| 20 | Thelliyaragaram | தெள்ளியார் அகரம் | January 2026 | | Elevated | Island |
| 21 | Iyyapanthangal | ஐயப்பன்தாங்கல் | January 2026 | | Elevated | Island |
| 22 | Kattupakkam | காட்டுப்பாக்கம் | January 2026 | Elevated | Island | |
| 23 | Kumananchavadi | குமணன்சாவடி | January 2026 | Elevated | Island | |
| 24 | Karayanchavadi | கரையான்சாவடி | January 2026 | Elevated | Island | |
| 25 | Mullaithottam | முல்லைத்தோட்டம் | January 2026 | Elevated | Island | |
| 26 | Poonamallee | பூவிருந்தவல்லி | January 2026 | | Elevated | Side |
| 27 | Poonamallee Bypass | பூவிருந்தவல்லி புறவழிச்சாலை | January 2026 | Elevated | Side | |
§ under construction