Medupi Power Station

Last updated
Medupi Power Station
Medupikragstasie, Ellisras, Limpopo, a.jpg
Medupi Power Station
Country South Africa
Location Lephalale
Coordinates 23°42′00″S27°33′00″E / 23.70000°S 27.55000°E / -23.70000; 27.55000
StatusUnder construction
Construction began2007
Commission date
  • 23 August 2015
Owner(s) Eskom
Operator(s)
Thermal power station
Primary fuel Wet-Coal
Power generation
Units operational6 x 764
Nameplate capacity 4,584 MW
Capacity factor 70%
External links
Commons Related media on Commons

Medupi Power Station is a dry-cooled coal-fired power station built by Eskom near Lephalale in Limpopo province, South Africa. The station consists of 6 generating units with a nameplate capacity of 764 MW each bringing the total installed capacity of 4,584 MW. [1]

Contents

Original concept

Medupi was conceived as Project Alpha in 2007, with only three units planned to total 2,292 MW and estimated cost of R32 billion. [2] The design was changed at a late stage in 2007 and doubled in size to 4,584 MW.[ citation needed ]

The boilers were envisaged to be supercritical in type, which would make them 38% more effective than other Eskom power stations. [3] A dry cooled system was also intended to use less water than other coal-fired power stations in the fleet.[ citation needed ] [4]

Initial project costing was estimated at R69 billion [5] but that was updated to approximately R80 billion by 2007. [6] [7]

Parsons Brinckerhoff was appointed as the project engineer to oversee all construction. [8]

Power output

Design

The power station has six boilers each powering 794 MW turbines, producing 4,584 MW in total.

When completed, Medupi became the largest dry-cooled coal-fired power station in the world. [9]

Awards

Medupi's GE Steam Power Systems was awarded a Global Project Excellence Gold Award at the 2016 IPMA Project Excellence Awards. [10]

Main equipment suppliers

Alstom provided the steam turbines, whilst Hitachi provided the super critical boilers. [11]

Coal supply

Medupi is supplied with coal from Exxaro's Grootegeluk coal mine, located north of the site. Eskom placed a contract with Exxaro to supply 14.6 MT of coal per year for 40 years. [12]

Power generation

Construction timeline

Completion of the first two units was expected by 2012 but various delays impacted progress. The first 794 MW unit (no 6) was commissioned and handed over to Eskom Generation on 23 August 2015. Units 5 to 1 was completed at approximately nine-month intervals thereafter.

Medupi Power Station development of the coal yard 2014.jpg
Development of the coal yard, early 2014
Medupi Power Station fabrication of boilers mid 2014.jpg
Fabrication of a boiler structure, mid 2014
Medupi Power Station Chimney installation of cans.jpg
Fabrication of thermal chimney, mid 2011

Bulk water

In order to meet the growing demand for power generation and mining activities in the Lephalale area, two main bulk raw water transfer systems were also required. This comprised a 4.5 MW pump station and 46 km pipeline extracting from the Mokolo Dam. Phase 1 of this project was commissioned in 2015. [26]

Transmission connection

174 Kilometres of high voltage transmission lines was required from Medupi to the Borutho substation near Mokopane. Construction occurred between November 2015 till the end of 2017. [27]

Delays and defects

The dates for full commercial operation were shifted numerous times mostly due to labour disputes such as:

Unit 4 generator explosion

On 9 August 2021, in the second week after Eskom announced that Medupi had attained commercial operation, Medupi Unit 4 was extensively damaged in a hydrogen explosion [34] [35] which caused a loss of 700 MW in generating capacity. [36] The cost of repair was estimated at up to R2 billion, [36] or up to R40 billion. [37] [38]

Cost escalation

The initial expected cost of R80 billion (2007 Rands), [6] was revised to R154 billion (2013 Rands). [39] [40] [41] By 2019, the cost of Medupi was independently estimated at R234 billion (2019 Rands). [42] [43] Some of the primary reasons for the cost escalation was the importing of components affected by a fluctuating Rand exchange rate, redesigns and rework as well as labour disputes and standing time. Due to cost escalations the African Development Bank has stated that they do not expect the power plant to produce a positive financial return over the course of its lifetime. [44]

Critics

The building of this power station attracted various criticisms. [45] [46]

Interference

Critics alleged that the government endorsed the project due to the ruling party, the African National Congress holding a 25% share of a package and stood to make a profit of close to 1 billion Rand. [47] [48]

Coal

Backers of the project argued that new generation coal plants was needed. [49] Other critics argued that effective management of coal supplies was needed to existing stations. [50]

Cost

The African Development Bank lent $500 million for the project in 2008.

In 2010, the World Bank agreed to lend South Africa $3.75 billion to assist with several energy projects, with $3.05 billion allocated for completion.

Emissions

The approval of the World Bank loan drew criticism for supporting increased global emissions of greenhouse gases. [51]

Inquiry

By 2018, the government's Public Enterprises Minister Pravin Gordhan announced a forensic probe into the delays and cost overruns on the completion of Kusile and Medupi Power Stations. [52]

National grid context

The Medupi and Kusile power stations were constructed to increase the electricity generation capacity of South Africa. Insufficient electricity generation had resulted in the ongoing South African energy crisis starting in 2007. This has resulted in years of rolling blackouts. [53] [54]

As of 11 February 2019, Eskom reinstated load-shedding due to ongoing strain on the national grid from failing older power stations. The blackouts were as severe as those of 2015, removing up to 4,000 MW of demand from the national grid, and negatively impacted the economy. [53] [54] In December 2019, unusually heavy flooding and rain triggered failures at the Medupi plant and forced Eskom to cut 6,000 MW from the national power grid, the biggest power cuts in South Africa in a decade. [55] [56]

See also

Related Research Articles

Eskom Hld SOC Ltd or Eskom is a South African electricity public utility. Eskom was established in 1923 as the Electricity Supply Commission (ESCOM) (Afrikaans: Elektrisiteitsvoorsieningskommissie (EVKOM)). Eskom represents South Africa in the Southern African Power Pool. The utility is the largest producer of electricity in Africa, and was among the top utilities in the world in terms of generation capacity and sales. It is the largest of South Africa's state owned enterprises. Eskom operates a number of notable power stations, including Matimba Power Station and Medupi Power Station in Lephalale, Kusile Power Station in Witbank, Kendal Power Station, and Koeberg Nuclear Power Station in the Western Cape Province, the only nuclear power plant in Africa.

Lephalale, formerly known as Ellisras, is a coal mining town in the Limpopo province of South Africa immediately east of the Waterberg Coalfield. The town was established as Ellisras in 1960 and named after Patrick Ellis and Piet Erasmus who settled on a farm there in the 1930s. In 2002, Ellisras was renamed Lephalale by the provincial government of Limpopo, after the main river that crosses the municipality. Lephalale is derived from the setswana language meaning "to flow".

<span class="mw-page-title-main">Concor</span> South African construction company

Concor Holdings (Proprietary) Limited. is a South African construction and mining services company. It is active throughout Southern Africa, involved in civil engineering, buildings, roads and mining projects. Concor returned as an independent brand in late 2016.

<span class="mw-page-title-main">Kendal Power Station</span>

Kendal Power Station is a coal-fired power station in Mpumalanga, South Africa. It is sited in a coal-mining area; one of its sources is AEMFC's coal mine at Vlakfontein, near Ogies.

<span class="mw-page-title-main">Duvha Power Station</span> Power plant in South Africa

Duvha Power Station in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. The 300 metres (980 ft) tall chimneys at Duvha are the second and third tallest structures in Africa, only a chimney located at the Secunda CTL plant is taller.

The Ingula Pumped Storage Scheme is a pumped-storage power station in the escarpment of the Little Drakensberg range straddling the border of the KwaZulu-Natal and Free State provinces, South Africa. It is about 22 km (14 mi) North-East of Van Reenen.

<span class="mw-page-title-main">Camden Power Station</span>

Camden Power Station in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom.

Majuba Power Station between Volksrust and Amersfoort in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. Majuba is Eskom's only power station that is not linked to a specific mine and it receives its coal from various sources. This was due to an error in geotechnical engineering core drilling which did not identify that the proposed local coal mine was under solid bedrock.

<span class="mw-page-title-main">Matimba Power Station</span> Dry-cooled coal-fired power plant

Matimba Power Station close to Ellisras, Limpopo Province, South Africa, is a dry-cooled coal-fired power plant operated by Eskom.

Tutuka Power Station in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. It is a twin sister to Duvha Power Station.

South Africa has a large energy sector, being the third-largest economy in Africa. The country consumed 227 TWh of electricity in 2018. The vast majority of South Africa's electricity was produced from coal, with the fuel responsible for 88% of production in 2017. South Africa is the 7th largest coal producer in the world. As of July 2018, South Africa had a coal power generation capacity of 39 gigawatts (GW). South Africa is the world's 14th largest emitter of greenhouse gases. South Africa is planning to shift away from coal in the electricity sector and the country produces the most solar and wind energy by terawatt-hours in Africa. The country aims to decommission 34 GW of coal-fired power capacity by 2050. It also aims to build at least 20 GW of renewable power generation capacity by 2030. South Africa aims to generate 77,834 megawatts (MW) of electricity by 2030, with new capacity coming significantly from renewable sources to meet emission reduction targets. Through its goals stated in the Integrated Resource Plan, it announced the Renewable Energy Independent Power Producer Procurement Programme, which aims to increase renewable power generation through private sector investment.

<span class="mw-page-title-main">Solar power in South Africa</span> Overview of the use of solar power in South Africa

Solar power in South Africa includes photovoltaics (PV) as well as concentrated solar power (CSP). As of July 2024, South Africa had 2,287 MW of installed utility-scale PV solar power capacity in its grid, in addition to 5,791 MW of rooftop solar and 500 MW of CSP. Installed capacity is expected to reach 8,400 MW by 2030.

<span class="mw-page-title-main">Kusile Power Station</span> Largest Dry-cooled coal-fired power plant in the world

Kusile Power Station in South Africa is a coal-fired power plant by state electricity utility Eskom in Mpumalanga. The station consists of 6 generating units with an eventual nameplate capacity of 800 MW each bringing the total installed capacity of 4,800 MW; as of 2023, only 5 units are in operation.

<span class="mw-page-title-main">Vallur Thermal Power Station</span> Coal-fired power station in Tamil Nadu

Vallur Thermal Power Station is a power plant located in Vallur, Thiruvallur district, India. The power plant is operated by NTPC Tamil Nadu Energy Company Limited, a joint venture between NTPC Limited and TANGEDCO and has three units with 500 MW each.

Redstone Solar Thermal Power (RSTP) is a solar power tower with molten salt energy storage, located in Postmasburg, near Kimberley, in the Northern Cape Region of South Africa. Redstone will have a capacity of 100 megawatts (MW) to deliver power to 200,000 people and was awarded in bid window 3.5 of the REIPPP at a strike price of 122.3 ZAR/KWh including time of day pricing in 2015. The project was initially based on the technology of now bankrupt Solar Reserve, but was delayed for several years because the PPA was not signed by Eskom until 2018. After the project was revived the plant is now under construction and the technology will be provided by Brightsource and John Cockerill, as demonstrated in the Noor Energy 1 project in the UAE.

<span class="mw-page-title-main">Touwsrivier CPV Solar Project</span>

Touwsrivier CPV Solar Project is a 44 MWp (36 MWAC) concentrator photovoltaics (CPV) power station located 13 km outside the town of Touwsrivier in the Western Cape of South Africa. The installation reached full capacity in December 2014 and is the second largest operating CPV facility in the world. Electricity produced by the plant is fed into the national grid operated by Eskom under a 20-year power purchase agreement (PPA).

<span class="mw-page-title-main">South African energy crisis</span> Widespread national level rolling blackouts

South Africa's energy crisis or load shedding is an ongoing period of widespread national blackouts of electricity supply. It began in the later months of 2007 towards the end of Thabo Mbeki's second term as president, and continues to the present. The South African government-owned national power utility, and primary power generator, Eskom, and various parliamentarians attributed these rolling blackouts to insufficient generation capacity.

The Integrated Resource Plan (IRP) is a plan aimed at estimating South Africa's electricity demand. It takes into account how the demand of electricity will be met and the expense of such a demand. The plan refers to electricity generation and expansion programmes.

References

  1. "The Medupi Coal-Fired Power Station Project, South Africa". Power Technology. Retrieved 2023-05-24.
  2. Claire (2015-09-04). "Electricity for South Africa". Powertime. Retrieved 2022-05-22.
  3. "Eskom's Medupi coal-power plant nears completion". 23 June 2018.
  4. Kotze, Petro (2005). "How much water will we need to keep the lights on?". Water and Energy. May/June: 22–25.
  5. "Sinking into Eskom's black hole". The Mail & Guardian. 2015-02-05. Retrieved 2022-05-22.
  6. 1 2 "Medupi Sod Turning Press Release". www.eskom.co.za. Retrieved 10 August 2021.
  7. "How much Medupi will cost SA" . Retrieved 10 August 2015.
  8. "We are WSP - Engineers, Designers, Planners, Researchers". WSP.
  9. "Medupi Power Station". Eskom. Archived from the original on 2013-08-06.
  10. "Excellent Finalists and Winners of IPMA Awards 2016 have been decorated by IPMA". IPMA International Project Management Association. 2016-12-15. Retrieved 2020-01-10.
  11. "R33.6-billion Eskom contracts awarded for Medupi power station". 14 Nov 2007. Archived from the original on 2012-01-11.
  12. "Medupi project on track for scheduled delivery" . Retrieved August 5, 2018.
  13. "Medupia's first 24 hours coal run a success". Noord Nuus. 2012-11-29.[ permanent dead link ]
  14. "'Medupi turbine 6 at optimum capacity' - IOL Business Report".
  15. "Medupi: Eskom hails 'new beginning' - IOL Business Report".
  16. "Medupi Unit 5 a step closer to commercial operation" . Retrieved 2016-12-22.
  17. "Eskom commissions second 500MVA transformer at the Ngwedi substation". 10 March 2017.
  18. 1 2 "Eskom announces Medupi Unit 3 is commercially operational". The South African. 2019-06-29. Retrieved 2019-08-30.
  19. "Medupi Unit 2 synchronised to the grid". SAnews. 2018-10-09. Retrieved 2022-01-06.
  20. "Medupi Unit 2 brought into commercial operation shortly after visit from Ramaphosa". The Citizen. 2019-11-26. Retrieved 2022-01-06.
  21. Staff Writer. "Eskom Medupi Unit 2 achieves commercial operation" . Retrieved 2022-01-06.
  22. "South Africa adds unit 1 of Medupi Power Station to the national grid". constructionreviewonline.com. Archived from the original on 2019-09-02.
  23. Paton, Carol (13 February 2019). "Medupi: Timeline of a R145bn — and still counting — disaster". BusinessLIVE. Retrieved 2019-08-30.
  24. Creamer, Terence. "Eskom tests market for Medupi flue gas desulphurisation solutions". www.engineeringnews.co.za. Retrieved 2022-01-07.
  25. "Eskom Medupi's last unit achieves commercial operation, marking completion of the project". Eskom. 2 August 2021. Retrieved 2021-08-02.
  26. "Mokolo Crocodile Water Augmentation Project". www.aurecongroup.com. Archived from the original on 2012-10-07.
  27. "Transmission lines: Spanish firm to construct two power lines in RSA". ESI-Africa.com. 2015-09-01. Retrieved 2022-01-07.
  28. "Yet more problems for Eskom as violence erupts at Medupi". fspinvest.co.za. Retrieved 2022-01-07.
  29. "Numsa blames Eskom for Medupi strike". ewn.co.za. Eyewitness News. Retrieved 2022-01-07.
  30. "Inside Medupi's labour pains". Fin24. Retrieved 2022-01-07.
  31. "Medupi is drowning in damaging ash as contractor forced to withdraw". The Citizen. 2019-02-12. Retrieved 2022-01-07.
  32. Creamer, Terence. "Technical defects at Medupi and Kusile resulting in serious underperformance". www.engineeringnews.co.za. Retrieved 2022-01-07.
  33. "It could take five years for Eskom's power stations to be fully up and running again – here's why". BusinessInsider. Retrieved 2019-08-30.
  34. McLeod, Duncan (9 August 2021). "Photos: 'Extensive damage' at Medupi after massive explosion". Tech Central.
  35. Cronje, Jan (9 August 2021). "Medupi explosion: 'Extensive damage' caused, Eskom staff suspended". News24.
  36. 1 2 Mahlaka, Ray (12 August 2021). "Medupi explosion: Sabotage ruled out, but the R2bn repair price could fall on energy customers". dailymaverick.co.za. Business Maverick. Retrieved 13 August 2021.
  37. Ginindza, Banele (11 August 2021). "Medupi explosion may cost up to R40bn - experts". iol.co.za. IOL. Retrieved 13 August 2021.
  38. Modise, Kgomotso. "Medupi's inactive unit 4 affecting power station's performance, says manager". ewn.co.za. Retrieved 2023-05-24.
  39. "How much is Medupi really costing the country?". EWN. Retrieved 2015-08-24.
  40. "Medupi Timeline: Costs, delays spiralling – no completion in sight". 6 August 2015. Retrieved 2015-08-24.
  41. "Medupi will cost R105bn to complete – for now" . Retrieved 2015-08-24.
  42. "Here is the true cost of Eskom's Medupi and Kusile power stations". www.mybroadband.co.za. 2019-08-30. Retrieved 2019-08-30.
  43. "Medupi, Kusile, and the massive cost/time overrun". www.dailymaverick.co.za. Daily Maverick. 2016-07-07. Retrieved 2016-12-22.
  44. Paton, Carol. "Eskom's Medupi will not earn a financial return in its lifetime, says funder African Development Bank". Fin24. Retrieved 2022-06-09.
  45. Rafey, William; Sovacool, B.K. (2011). "Competing Discourses of Energy Development: The Implications of the Medupi Coal-Fired Power Plant in South Africa". Global Environmental Change. 21 (3): 1141–1151. doi:10.1016/j.gloenvcha.2011.05.005.
  46. "Eskom and the multi-billion rand mega projects that could have saved SA". Fin24. 2019-02-13. Retrieved 2019-02-13.
  47. "Opposition slams ANC 'about-turn' on Hitachi". Mail & Guardian Online. 14 April 2010. Retrieved 24 May 2010.
  48. "Zille says ANC stands to make R1bn from Medupi". 3 April 2010.
  49. "Log In". powerplants.einnews.com. Power Plants News Today, EIN News.[ better source needed ]
  50. "National Response To South Africa's Electricity Shortage" (PDF). Archived from the original (PDF) on 2009-08-24. Retrieved 2010-04-13.
  51. Friedman, Lisa (2010-04-09). "South Africa Wins $3.75 Billion Coal Loan". The New York Times.
  52. Khumalo, Sibongile (2018-12-06). "Eskom opens forensic probe into Medupi, Kusile". Fin24. Retrieved 2019-01-01.
  53. 1 2 Burkhardt, Paul. "Blackouts Cripple South Africa Again as Eskom Stumbles". Bloomberg Markets. Bloomberg. Retrieved 12 March 2019.
  54. 1 2 Goko, Colleen. "Eskom Extends South Africa Power Cuts as Moody's Flags Risk". Bloomberg technology. Bloomberg. Retrieved 12 March 2019.
  55. "Eskom steps up power cuts after flooding hits major plant". Moneyweb. 2019-12-09. Retrieved 2019-12-19.
  56. Burke, Jason (2019-12-09). "South Africa hit by massive power cuts as floods disrupt supply". The Guardian. ISSN   0261-3077 . Retrieved 2019-12-19.