Kusile Power Station | |
---|---|
Country | South Africa |
Location | Witbank, Emalahleni Local Municipality, Mpumalanga |
Coordinates | 25°54′59″S28°55′02″E / 25.91639°S 28.91722°E |
Status | Under construction |
Construction began | 2008 |
Construction cost | US$ 8,700,000,000 |
Owner(s) | Eskom |
Operator(s) | Eskom |
Thermal power station | |
Primary fuel | Coal |
Power generation | |
Units operational | 5 × 800 MW |
Units under const. | 1 x 800 MW |
Nameplate capacity | 4,000 MW |
Capacity factor | 66.6 percent |
External links | |
Commons | Related media on Commons |
Kusile Power Station (previously known as Project Bravo) in South Africa is a coal-fired power plant by state electricity utility Eskom in Mpumalanga. The station consists of 6 generating units with an eventual nameplate capacity of 800 MW each bringing the total installed capacity of 4,800 MW; as of 2023, only 5 units are in operation.
Located about 15 kilometres north of the existing Kendal Power Station near Witbank, Mpumalanga.
Kusile Power Station is designed to consist of six 800 megawatt coal-fired generating units for a total generating capacity of 4,800 megawatts. [1] In 2023 the realistic sustainable output per unit was however projected to be some 350 megawatt. [2]
As of December 2023, Unit 5 was synchronized to the national grid. Following a six-month period of "testing and optimization", the unit's output will be commercially commissioned and bring total station output to 4,000 MW. Kusile would be the first coal power station in Eskom's fleet to be fitted with flue gas desulphurization technology. [3]
Black and Veatch was appointed as the project engineer for construction.
Alstom provided the steam turbines, whilst Hitachi would provide the super critical boilers.
The power utility, Eskom stated that it "will obtain most of the coal required for this Power Station from Anglo Coal's New Largo operations, south east of the Kusile Power Station." [4]
Eskom's consultants estimate that 35 new coal mines will be required to support the Medupi and Kusile plants. [5]
Construction started in August 2008, months after the first of South Africa's rolling blackouts in January 2008. [6]
Initially expected to take 6 years to complete, the project completed Unit 1 until 2017 (approximately 8 years after initial works began) and the entire project not until 2021. [7]
Deficient project management, corruption, labour disputes, vandalism and absenteeism resulted in low operational efficiency and reliability which periodically stalled the generation of electricity 15 years after its construction began. [2]
The dates for full commercial operation were shifted numerous times mostly due to:
This resulted in Kusile and Medupi considered as some of the worst-performing units in Eskom's fleet. [22] In February 2019, Eskom GM for group technology Titus Mathe reported R8 billion would be needed to fix design defects at Medupi and Kusile. [26]
The building of this power station attracted various criticism.
Hitachi Power Africa, a subsidiary of Hitachi, Ltd., found by the U.S. Securities and Exchange Commission to have made US$6 million in corrupt payments to Chancellor House, a front company for the African National Congress, the ruling political party in South Africa. [27] Hitachi agreed to pay US$19 million to settle charges. [27] Hitachi Power Africa rebranded as Mitsubishi Hitachi Power Systems Africa in February 2014. [28]
Kusile Power Station is estimated to cost R118 billion to complete. [7] This will bring the cost per unit to R19.66bn ($1.34bn) per generating unit, equalling R26.96M ($1.67M) per installed MW.
The following institutions were involved in supporting the project: [29]
The plant is expected to emit est 36.8 million tonnes of CO2-equivalent per year once completed. [30]
In November 2011, Greenpeace activists chained themselves to a gate and climbed a crane, a few weeks before the country hosted a global conference on climate change. Authorities arrested nine people, on charges of trespassing and malicious damage to property. [31]
The design of the station does allow for the installation of flue gas desulphurization technology, the first of its kind in South Africa.
By 2018, the governments Public Enterprises Minister Pravin Gordhan announced a forensic probe into delays and cost overruns on the completion of Kusile and Medupi Control Stations. [32]
In November 2019 South African investigative journalist Pieter-Louis Myburgh published an article in the Daily Maverick detailing an alleged slush fund corruption scandal involving Eskom executives and at least four contractors. [33] The scandal involved contracts worth a combined R10 billion resulting in an estimated R75 million being lost due to irregular activities. [33] By the time of the publication of Myburgh's article the construction of Kusile was five years past its original completion date and an estimated R80 billion (equivalent to US$5.4 billion) over budget. [33]
In Dec 2022, ABB was charged by the U.S. Securities and Exchange Commission (SEC) for violations of the Foreign Corrupt Practices Act (FCPA) in a bribery scheme, where it paid more than $37 million in bribes to a high-ranking Eskom official to influence a $160 million contract awarded by the state-owned electric utility company for work on Kusile's cabling and installation work between 2014 and 2017. [34]
Media related to Kusile Power Station at Wikimedia Commons
Battersea Power Station is a decommissioned coal-fired power station located on the south bank of the River Thames in Nine Elms, Battersea in the London Borough of Wandsworth. It was built by the London Power Company (LPC) to the design of Leonard Pearce, Engineer in Chief to the LPC, and CS Allott & Son Engineers. The architects were J. Theo Halliday and Giles Gilbert Scott. The station is one of the world's largest brick buildings and notable for its original, Art Deco interior fittings and decor.
ABB Ltd. is a Swedish–Swiss multinational corporation headquartered in Västerås, Sweden, and Zürich, Switzerland. It is traded on the SIX Swiss Exchange in Zürich, the Nasdaq Nordic exchange in Sweden and the OTC Markets Group's pink sheets in the United States. It was ranked 340th in the Fortune Global 500 list of 2020 and has been a global Fortune 500 company for 24 years.
Koeberg Nuclear Power Station is a nuclear power station in South Africa and the only one on the entire African continent. It is located 30 km north of Cape Town, near Melkbosstrand on the west coast of South Africa. It is owned and operated by the country's state-owned electricity public utility, Eskom.
Eskom Hld SOC Ltd or Eskom (Afrikaans: Elektrisiteitsvoorsieningskommissie) is a South African electricity public utility. Eskom was established in 1923 as the Electricity Supply Commission (ESCOM). Eskom represents South Africa in the Southern African Power Pool. The utility is the largest producer of electricity in Africa, and was among the top utilities in the world in terms of generation capacity and sales. It is the largest of South Africa's state owned enterprises. Eskom operates a number of notable power stations, including Matimba Power Station and Medupi Power Station in Lephalale, Kusile Power Station in Witbank, Kendal Power Station, and Koeberg Nuclear Power Station in the Western Cape Province, the only nuclear power plant in Africa.
Lephalale, formerly known as Ellisras, is a coal mining town in the Limpopo province of South Africa immediately east of the Waterberg Coalfield. The town was established as Ellisras in 1960 and named after Patrick Ellis and Piet Erasmus who settled on a farm there in the 1930s. In 2002, Ellisras was renamed Lephalale by the provincial government of Limpopo, after the main river that crosses the municipality. Lephalale is derived from the setswana language meaning "to flow".
Kendal Power Station is a coal-fired power station in Mpumalanga, South Africa. It is sited in a coal-mining area; one of its sources is AEMFC's coal mine at Vlakfontein, near Ogies.
Duvha Power Station in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. The 300 metres (980 ft) tall chimneys at Duvha are the second and third tallest structures in Africa, only a chimney located at the Secunda CTL plant is taller.
The Maritsa Iztok Complex is the largest energy complex in South Eastern Europe. Maritsa Iztok 1 and 3 located entirely within Stara Zagora Province in south-central Bulgaria while Maritsa Iztok 2 is split with eastern neighboring Sliven Province. It consists of three lignite-fired thermal power stations. The complex is located in a large lignite coal basin, which includes several mines, enrichment plants, a briquette plant and its own railway system. The development of the thermal power and mining complex at Maritsa Iztok began in 1952, but the lignite deposits used to be known well in the mid-19th century. The Maritsa Iztok mines and power plants are interdependent as the only market for coal is the power plants, while the power plants have no other supplier of coal but the mines.
Cottam power station is a decommissioned coal-fired power station. The site extends over 620 acres (250 ha) of mainly arable land and is situated at the eastern edge of Nottinghamshire on the west bank of the River Trent at Cottam near Retford. The larger coal-fired station was decommissioned by EDF Energy in 2019 in line with the UK's goal to meet its zero-coal power generation by 2025. The smaller in-use station is Cottam Development Centre, a combined cycle gas turbine plant commissioned in 1999, with a generating capacity of 440 MW. This plant is owned by Uniper.
The Ingula Pumped Storage Scheme is a pumped-storage power station in the escarpment of the Little Drakensberg range straddling the border of the KwaZulu-Natal and Free State provinces, South Africa. It is about 22 km (14 mi) North-East of Van Reenen.
Medupi Power Station is a dry-cooled coal-fired power station built by Eskom near Lephalale in Limpopo province, South Africa. The station consists of 6 generating units with a nameplate capacity of 764 MW each bringing the total installed capacity of 4,584 MW.
Komati Power Station, is a coal-fired power plant operated by Eskom. Its 300 metre tall chimney was built in 1979, and is one of the tallest structures in the country. Komati is one of power stations with a common steam range, meaning that its nine boilers jointly feed the nine generators. Other stations are Tutuka Power Station and Matimba Power Station.
Majuba Power Station between Volksrust and Amersfoort in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. Majuba is Eskom's only power station that is not linked to a specific mine and it receives its coal from various sources. This was due to an error in geotechnical engineering core drilling which did not identify that the proposed local coal mine was under solid bedrock.
Matimba Power Station close to Ellisras, Limpopo Province, South Africa, is a dry-cooled coal-fired power plant operated by Eskom.
Tutuka Power Station in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. It is a twin sister to Duvha Power Station.
The Grootegeluk Coal Mine is an open cast coal mine within the Waterberg Coalfield of the Limpopo province of South Africa. It is operated by Exxaro. The mine is 25 kilometres (16 mi) from Lephalale, and employs 2,000 people.
Cuddalore IL&FS Power Station is a 1,200-megawatt (MW) coal-fired power station in Tamil Nadu, India.
South Africa’s energy crisis or load shedding is an ongoing period of widespread national blackouts of electricity supply. It began in the later months of 2007 towards the end of Thabo Mbeki's second term as president, and continues to the present. The South African government-owned national power utility, and primary power generator, Eskom, and various parliamentarians attributed these rolling blackouts to insufficient generation capacity.