South Africa's energy crisis (or load shedding) is an ongoing period of widespread national blackouts of electricity supply. It began in the later months of 2007 towards the end of Thabo Mbeki's second term as president, and continues to the present. [1] [2] The South African government-owned national power utility, and primary power generator, Eskom, and various parliamentarians attributed these rolling blackouts to insufficient generation capacity. [3]
According to Eskom and government officials, the solution requires the construction of additional power stations and generators. [4] This does not explain the fact that according to Eskom's own figures its available generation capacity has dropped from more than 37GW in 1994 [5] to less than 28GW in 2024 [6] in spite of two major power stations (Kusile and Medupi) having been added to the grid during that period, nor why Eskom's financial position has deteriorated from showing a R2.3bn net profit in 1994 [5] to having a debt of R423bn in 2023. [7] Corruption and mismanagement of Eskom, most notably during the Jacob Zuma administration, have exacerbated this energy crisis; [8] [9] [10] neglect by Eskom staff [11] in addition to multiple acts of sabotage [12] and the activity of criminal syndicates within Eskom with alleged political connections [13] [14] have also contributed to ongoing power supply problems, as has corruption within the ruling party itself. [15] [16] [17] Many South Africans consider the ongoing energy crisis to be just another symptom of long-standing inept governance. [18] [19] [20] [21] In April 2024, South Africa had a full month without rotational power cuts, which was the first time since January 2022. [22]
In a December 1998 report, analysts and leaders in Eskom and in the South African government predicted that Eskom would run out of electrical power reserves by 2007 unless action was taken to prevent it. [23] [24] To improve power supply and reliability, the 1998 report recommended restructuring Eskom into separate electricity generation and power transmission businesses. [25] Despite the warnings of the 1998 report and requests by Eskom to be allowed to increase capacity, the national government took no action. [26] At the time the Mbeki government was considering the privatisation of Eskom which was cited as a reason why the government took no action. [26] This resulted in Eskom being unable to add additional generating capacity and thereby keep up with increasing national demand for electricity from 2002 onward. [27] The government only granted Eskom permission to significantly expand energy production (by 70%) in 2004. [28]
15 power stations were commissioned between 1961 and 1996, adding a combined 35,804 MW of capacity. In the 21st century, only 9,564 MW of capacity has been added from the currently constructing power stations Medupi and Kusile. [29] Many Eskom power stations are almost 50 years old and near decommissioning. [23] Following the first period of load shedding in 2007 to 2008 Eskom commissioned the construction of the Medupi and Kusile coal fired power plants to expand energy production by 25%. The construction of these plants encountered numerous technical problems and cost overruns whilst the existing fleet of power plants were not replaced and continued to operate past their operational lifespan. [2]
Below is a timeline of Eskom built major power stations [30]
Year | Power plant | Megawatts |
---|---|---|
1961 | Komati | 990 |
1963 | Rooiwal | 300 |
1967 | Camden | 1561 |
1969 | Grootvlei | 1180 |
1970 | Hendrina | 1893 |
1971 | Arnot | 2352 |
1976 | Kriel | 3000 |
1979 | Matla | 3600 |
1980 | Duvha | 3600 |
1984 | Koeberg | 1860 |
1985 | Tutuka | 3654 |
1985 | Lethabo | 3708 |
1987 | Matimba | 3990 |
1988 | Kendal | 4116 |
1996 | Majuba | 4110 |
2015 | Medupi | 4764 |
2017 | Kusile | 4800 |
In South Africa, loadshedding has been a recurring problem for many years, and one of its main causes is the country's heavy reliance on coal-fired power plants. These plants are aging and often require maintenance, resulting in breakdowns and unplanned outages that reduce the amount of electricity available to the grid. [32] In addition, the country's coal supply has been unreliable due to operational issues and disruptions caused by labor strikes. [33]
To address this problem, South Africa has been working to shift its energy mix from coal to renewable energy sources such as wind and solar power. [34] [35] This transition has been slow, but there has been progress in recent years, with the government's commitment to procuring renewable energy and reducing the country's greenhouse gas emissions. [36] However, the shift to renewable energy is not without its challenges. The intermittency of wind and solar power means that power supply can be variable, and the power generated is not always available at times of high demand.
Since 2007, South Africa has experienced multiple periods of loadshedding as the country's demand for electricity exceeded its ability, notably Eskom's ability, to supply it. During these periods the power is rationed between different electrical grid areas cross the country and within municipal areas. With areas experiencing power outages typically lasting two to four hours. Although South Africa has a national grid some areas of the country experience more periods of loadshedding than other areas due to differences in local power generation capabilities and difficulties in electrical distribution.
As of December 2019, Eskom have published 8 stages of load shedding, each stage representing the removal of 1000 MW increments of demand by controlled shut down on sections of the supply grid based on a predetermined schedule. [37] Schedules may vary by location. Stage 6 (6000 MW reduction) was implemented for the first time on 9 December 2019. [38]
Stage | Energy load removed from the national grid | Typical Impact | Percentage of grid users without power | An example loadshedding area in Cape Town might experience power cuts at the following times |
---|---|---|---|---|
Stage 1 | <1000 MW | 6h over 4 days (6/96h) | ~6% without power | 16:00–18:30 |
Stage 2 | <2000 MW | 12h over 4 days (12/96h) | ~12.5% without power | 00:00–02:30 & 16:00–18:30 |
Stage 3 | <3000 MW | 18h over 4 days (18/96h) | ~19% without power | 00:00–02:30 & 16:00–18:30 |
Stage 4 | <4000 MW | 24h over 4 days (24/96h) | ~25% without power | 00:00–02:30 & 08:00–10:30 & 16:00–18:30 |
Stage 5 | <5000 MW | 30h over 4 days (30/96h) | ~31% without power | 00:00–02:30 & 08:00–10:30 & 14:00–18:30 |
Stage 6 | <6000 MW | 36h over 4 days (36/96h) | ~37% without power | 00:00–02:30 & 08:00–10:30 & 14:00–18:30 |
Stage 7 | <7000 MW | 42h over 4 days (42/96h) | ~44% without power | 00:00–02:30 & 08:00–10:30 & 14:00–18:30 & 22:00–00:30 |
Stage 8 | <8000 MW | 48h over 4 days (48/96h) | ~50% without power |
After the 2 hour disconnect period there is typically an additional 30 minutes added to allow for switching on, not counted in the totals as mentioned above. Problems may arise during switch on that can cause an actual fault blackout in the area beyond the scheduled time.
Sabotage and corruption at the state owned energy utility Eskom and its suppliers have prolonged and deepened the energy crisis by limiting the country's ability to maintain existing power generating capacity and increasing expenses. [41]
On 19 November 2021, Eskom announced that sabotage of electrical infrastructure, as well as corruption, might be contributing to power supply problems. An initial forensic investigation found evidence that recent damage to a coal conveyor at Lethabo was the result of deliberate sabotage. Steel supports had been severed, causing a power supply pylon to collapse. [42] [43] In a media briefing, de Ruyter commented that the matter had been referred to the Hawks for further investigation. [44] Despite investigations and disciplinary action, acts of sabotage continued into May 2022, when it was revealed that multiple incidents had occurred at several plants. [45] In May 2022, the Minister for Public Enterprises, Pravin Gordhan, reported to Parliament that additional incidents of cables being cut intentionally by saboteurs, rising theft at its power plants, and corruption around the supply of fuel oil, had greatly worsened the energy crisis and Eskom's ability to resolve it. [46] South African journalist Kyle Cowan has speculated that these acts of sabotage were politically motivated by unknown groups or individuals within Eskom involved in corruption. [47]
In December 2022, President Ramaphosa's spokesperson announced that the South African National Defence Force would be deployed at four Eskom power stations "in response to the growing threat of sabotage, theft, vandalism and corruption" [48] [49] for an indeterminate length of time. [50] In late February 2023, then Eskom CEO, André de Ruyter, controversially stated that four criminal syndicates had established themselves within the national utility, [51] that an unnamed senior ANC MP was involved, [52] [53] and that the government lacked the political will to resolve the situation. [54] De Ruyter also stated that in his opinion "load shedding is, to a large extent, attributable to crime and corruption." [51]
Since 2007, South Africa has experienced at least five distinct periods of load shedding.
The first period of chronic power shortages occurred in late 2007 and lasted until at least May 2008. Investigative television show Carte Blanche reported that part of the problem is related to the supply of coal to the coal-fired power plants. [55] [56] Several other causes have been postulated, including skills shortages [4] and increasing demand for electricity around the country. [57] Daily load shedding occurred for the first time for two weeks in January 2008. [28]
Eskom was criticised for exporting electricity to neighbouring African states while not having the capacity to meet South Africa's demand. [58] Eskom, however, announced on 20 January 2008 that it had ceased to export power. [59] [60] The government claimed the shortage had caught them by surprise since the South African economy had grown faster than expected; however, their target growth rate of 6% per year was not reached from 1996 to 2004. The average GDP growth rate during this period was 3.1%. [61] The year 2012 was frequently mentioned as the earliest possible end to the power shortages. [4] [62] [63]
The Majuba power plant lost its capacity to generate power after a collapse of one of its coal storage silos on 1 November 2014. The Majuba power plant delivered approximately 10% of the country's entire capacity and the collapse halted the delivery of coal to the plant. [64] A second silo developed a major crack on 20 November causing the shut down of the plant again, after temporary measures were instituted to deliver coal to the plant. [65]
On 5 December 2014, Eskom started major stage three load shedding in South Africa after the shut down of two power plants on 4 November (of said year) due to diesel shortages. It was also reported that the Palmiet and Drakensberg Pumped Storage Schemes were also experiencing difficulties due to a depletion of water reserve to the Hydro plants. Stage three was the highest degree of load shedding then. [66]
On Thursday 4 November, Eskom fell 4,000 megawatts (5,400,000 hp) short of the country's electricity demand of 28,000 megawatts (38,000,000 hp). The power utility has the ability to produce 45,583 megawatts (61,128,000 hp) but could only supply 24,000 megawatts (32,000,000 hp) due to "planned and unplanned" maintenance. One turbine at Eskom's Duvha Power Station is still out of commission due to an "unexplained incident" in March 2014. [67] Load shedding was scheduled to resume in February 2015, due to industry start up, after the December holiday period.
Another period of load shedding began in February 2019 when Eskom announced level 4 load shedding due to the temporary loss of generating capacity. This necessitated the dropping of 4,000 MW of power consumption from the national grid. [68] In mid-March of that year extensive ongoing power cuts were implemented across the country by Eskom as part of the level 4 load shedding. [69]
Eskom implemented a further round of load shedding commencing in December 2019. South Africa is currently experiencing its worst energy crisis, when Load Shedding Stage 6 activated for the first time ever in December. [70] Eskom stated that of its total nominal capacity of around 44,000 MW, it was unable to provide around 13,000 MW of total capacity, resulting in the nationwide blackouts. [71]
A combination of factors were blamed for the fourth period of load shedding ranging from weather to allegations of sabotage and neglect. Unusually heavy rains in the highveld region of South Africa resulted in wet coal and flooding leading to a number of plants being unable to operate effectively, [72] [73] most notably at Medupi power station. [71] This was exacerbated by bad coal management practices. [74] [75] [76] President Cyril Ramaphosa stated that an additional reason for the load shedding was the loss of 2,000 MW due to alleged sabotage by an Eskom employee. [77] [78] Eskom chief operations officer, Jan Oberholzer, publicly stated that the primary reason for load shedding was due to a lack of maintenance and neglect over the preceding twelve years resulting in an unpredictable and unreliable system. [79] South African opposition parties criticized the African National Congress and President Ramaphosa for the way in which they handled the crisis. [80] An additional round of load shedding (stage 4) [81] was initiated in March 2020 when the Koeberg Nuclear power station experienced a fault with one of the sea water cooling pumps. [82]
During the COVID-19 pandemic and resulting economic slowdown load shedding was largely suspended due to reduced demand for electricity. This ended in March 2021, when Matimba, Tutuka, Majuba, Kusile, Duvha, Kriel, Kendal and Medupi power stations experienced breakdowns. [83] In May 2021, stage 2 load-shedding was reimplemented following multiple power station breakdowns at Tutuka, Majuba, Kriel, Matla, Kusile, Medupi and the Duvha power stations. [84] By 9 June 2021 level 4 load shedding was announced. [85]
On 10 June 2021 President Ramaphosa announced that the Electricity Regulation Act would be amended to increase the threshold for exemption from applying for a license from national energy regulator Nersa to generate electricity, thereby increasing the exemption threshold from 1 megawatt to 100 megawatts. [86] [87] This would allow private power producers to more easily add power production capacity to the national grid. [87]
After providing uninterrupted power for 77 days, Eskom announced on 7 October 2021 that stage 2 load shedding would resume due to planned and unplanned outages. [88] [89]
On 25 October 2021, Eskom announced that capacity would remain "constrained" through August 2022, with negative effects on the economy. Eskom also estimated that an additional 4000MW to 6000MW of generation capacity would be required to remove the risk of loadshedding. [90] [91] On 27 October 2021 Eskom announced that stage 4 load shedding would be implemented for three days due to problems with the Medupi, Kusile, Matla, Lethabo and Arnot power stations. [92] That same day, the governing party of South Africa, the African National Congress (ANC) spokesperson Pule Mabe raised concerns that the recent load shedding schedule may be politically motivated, given the upcoming 2021 municipal elections. [93]
Following the 2021 municipal elections, stage 4 load shedding recommenced on 5 November due to problems at Kendal, Tutuka, Matimba, Majuba and Lethabo power stations. [94] In a post-election address on 8 November, President Ramaphosa remarked that the continuing reliance on Eskom, as the sole national generator, was a central risk to the power supply system. [95]
Eskom announced that level 2 load shedding would be re-implemented from 2 to 7 February 2022 due to the breakdown of two generating units at the Kusile and Kendal power stations. [96] In early March 2022 level 4 load shedding was announced due to breakdowns taking 15,439MW out of the national grid. [97] [98] Stage 4 load shedding was extended over the 2022 Easter weekend when roughly half the national grid failed. [99]
Load shedding increased to level 4 and then level 6 nationally in late June 2022 following unlawful strike action by NUMSA and NUM employees. [100] [101] [102] [103] The loss of generating capacity due to strike action was in addition to a loss of 2,766MW from planned maintenance and another 17,395MW from power station breakdowns. [102] As the strike action continued Eskom warned that it might be necessary to implement stage 6 load shedding. [104] On 28 June 2022, Eskom confirmed that stage six load shedding would be implemented that evening, only the second time since December 2019. [105] By the end of June the strike was effectively ended when Eskom agreed to restart wage negotiations. [103]
In mid-September 2022, South Africa's energy grid experienced a collapse in generating capacity which resulted in up to half of Eskom's generating capacity being lost. [106] Eskom announced that due to fires [106] and a broken coal conveyor belt at Kendal power station, [107] [108] and an electrical trip during testing at Koeberg Nuclear power station [109] level 4 load shedding would be implemented; [107] a week later level 5 load shedding was declared. [110] The day after the implementation of level 5 loadshedding was announced generators at the Kusile and Kriel power stations tripped thereby forcing Eskom to implement level 6 loadshedding [111] with the prospect of level 8 being implemented. [112]
On 7 December 2022, level 6 load shedding was reimposed when over 20,000MW of generation was taken off line due to a high number of power station breakdowns. [113] [114] It was reported that level 7 load shedding might begin if planned maintenance was implemented, that would take one of Koeberg's nuclear reactors offline. [115]
By the end of 2022, South Africans experienced more than 200 days of power cuts, the most in a calendar year to date. [116]
On 22 February 2023, Eskom announced that its former CEO André de Ruyter, who was due to leave the company next month, had left with immediate effect amid a worsening nationwide energy crisis. [117] The announcement came after its former CEO gave an interview with the eNCA news agency where he expressed doubts about the political will in government to end endemic graft at the power utility. In an effort to address allegations of corruption at Eskom as well as the unprecedented power shortages, President Cyril Ramaphosa appointed Kgosientsho Ramokgopa as the country's first ever electricity minister. [118] On 12 April 2023, level 6 load shedding was implemented [119] as generating units failed at the Tutuka, Kriel, Duvha and Kendal power stations. [120] Parts of the cities of Pretoria and Mamelodi were left without power for multiple days after 7 pylons collapsed when thieves cut the supporting struts of a number of large pylons—reportedly for scrap—causing multiple separate collapses. [121] [122]
This period of loadshedding ended at 5:00 am on 26 March 2024 [123] starting a significant period of reliable power supply. [123] [124] Multiple reasons were given by government and Eskom for this change. They are:
Additional reasons reported for the end of loadshedding included:
By July 2024 this had resulted in an increase in energy generating capacity to 35,000 MW, the highest in 6 years. [124] Although some of the coal power plants have reported improved performance (Kusile, Hendrina, Grootvlei, Matla, Kendal, Majuba, Tutuka, Kriel and Matimba) others have reported reducing performance (Arnot, Lethabo, Camden, Medupi and Duvha) indicating continuing challenges. [123]
The energy crisis has had a number of very negative impacts on South Africa. These range from reducing economic growth [27] [125] and making it more difficult to do business in the country [126] [127] to increasing crime rates [128] [129] and shaping South African politics. [130] [131] A 2022 study by the University of Johannesburg indicated that since level 6 load shedding was introduced the repeated periods of load shedding has significantly reduced "the overall happiness of South Africans." [132] In 2023 a case was brought before the Pretoria High Court to declare the energy crisis unconstitutional due to the hardship it imposed. [133]
As of April 2023, 80% of public health-care facilities were affected by and only 20% exempt from power cuts. Patient care has been compromised especially in rural areas, but also in major hospitals who "were overwhelmed with patients coming from rural hospitals". Surgical care has been most affected with long waiting lists. Health standards were dropping together with water shortages in all public health facilities. The Health and Allied Workers Indaba Trade Union said "nurses were fed up with relying on mobile phone torchlights, unreliable generators, and using cooler boxes to keep vaccines and other medicines at the correct temperatures". [116]
In 2022, it was reported that long periods of loadshedding were resulting in many increased incidents of crime. [128] [134] [129] This included metal thieves using periods of when there is no power to steal equipment from power stations, sub-stations, and transmission lines thereby complicating Eskom's efforts to mitigate the energy crisis and costing the utility over R16.8 billion [135] (US$937 million) whilst also causing additional difficulties for municipalities. [136] Incidents of metal theft, house breaking and robberies due to a lack of security lighting and alarms had increased in some urban areas of South Africa during the period when level 6 loadshedding was implemented. [128] [134] [137] [138] [139]
In mid-January 2023, protests over the frequency and extent of load shedding broke out in the Durban community of Phoenix [140] and the Johannesburg community of Boksburg. [141]
Graphs are unavailable due to technical issues. There is more info on Phabricator and on MediaWiki.org. |
According to Lungile Mashele, an energy specialist at the Development Bank of Southern Africa, the ongoing power crisis has had significant economic consequences:
The energy crisis has significantly limited economic growth in South Africa thereby preventing the country from resolving high rates of unemployment. [27] [125] The power shortage is estimated to have reduced economic growth in 2021 by 3% thereby costing the country an estimated 350,000 potential new jobs for that year alone. [27] In 2022 the insurance company Sanlam reported that the cost of replacing appliances due to power surges following loadshedding periods had exceeded the cost of replacing appliances due to burglaries. [145]
In 2022 the business analysis firm Intellidex estimated that it would cost South Africa R500 billion (US$28 billion) to resolve the energy crisis within three years. [146] Alexforbes has estimated that prolonged stage 6 load shedding would cost the country R4 billion (US$216 million) a day in lost potential economic activity and that the costs of load shedding increase exponentially with each increase in level. [147]
As of 2008 big companies with international investors were also affected by the electricity crisis and announced these effects to the international community, bringing the situation to the attention of potential foreign investors. [148] Load shedding in the first six months of 2015 was estimated to have cost South African businesses R13.72 billion in lost revenue with an additional R716 million spent by businesses on backup generators. [149]
Banks and telecommunications companies have generally continued to operate as usual thanks to existing backup systems. However, as of November 2021 load shedding led to diminished mobile network coverage, as backup batteries have also been stolen and cellphone stations vandalised during power outages. [150]
In 2019, small business owners said that load shedding was the number one challenge that they faced. In a small business sentiment report of 3984 small business owners 44% said that they had been severely affected by load shedding with 85% stating that it had reduced their revenue. As a result, 40% of small businesses lost revenue of 20% or more during the load shedding period while 20% of owners claimed that if load shedding were to continue at similar levels to Q1 of 2019, they would have to consider reducing their staffing levels or closing their business. [151]
In February 2023, a chicken farmer sued Eskom for damages when loadshedding resulted in 40,000 of his broiler chickens suffocating. [152] [153]
In January and February 2008 global platinum and palladium prices hit record highs [154] as mines were first shut down and subsequently restricted in their electricity use. South Africa supplies 85% of the world's platinum and 30% of palladium. Mining companies estimate that hundreds of thousands of ounces of both gold and platinum production will be lost every year until the crisis passes. [155] Due primarily to the impact on mining companies, economists in 2011 downgraded GDP growth forecasts significantly. The consensus hovered around 4% (well short of the 6% government target), with the caveat that growth could reduce by 20 basis points every month under certain circumstances. [156]
As of February 2008 blackouts were temporarily halted due to reduced demand and maintenance stabilization. [157] This drop in demand was caused by many of the country's mines shutting down or slowing to help alleviate the burden. However, regularly scheduled mandatory load shedding started in April 2008, to allow maintenance periods of power generators, and recovery of coal stockpiles before the winter, when electricity usage is expected to surge.
Expanding generating capacity will see an estimated spend of R280 billion over the next five years from 2015 on wards, [158] with around 20 000 megawatts of additional capacity due to be online by 2025. [159] However, neither short nor long term funding has yet been secured and the downgrading of Eskom's credit rating has ignited speculation of a capital injection by the government. [160]
On 11 December 2014 it was announced that President Jacob Zuma had assigned Deputy President Cyril Ramaphosa to oversee the turnaround of three state owned companies namely "Eskom, the South African Airways, and the South African Post Office", all of which were in dire straits. [161]
On 15 January 2015 Eskom's then CEO Tshediso Matona admitted that Eskom's policy to "Keep the Lights on" meant that power station maintenance was neglected for years, and that South Africans will have to get used to electricity blackouts for the next four to five years. [161] In December that year an agreement between Eskom and Areva to replace steam generators at the Koeberg nuclear plant was judged "unlawful", by the Supreme Court of Appeal, bringing the utility company's tender process into question. [162]
In late 2016, Standard & Poor's Global Ratings downgraded Eskom's credit rating further into sub-investment cutting its long-term credit rating to BB–two levels below the investment threshold. [163] In the same year Matshela Koko, former head of generation for Eskom, was named as acting CEO. [164] Eskom stated it intended to pursue a nuclear solution to current energy woes. According to projections from late 2016, the use of nuclear power would provide over 1000GW of power by 2050. In preparation, the company launched a training program for 100 technicians, engineers and artisans to certify them as nuclear operators. [165] In January 2018 Eskom's acting Chief Financial Officer stated that the company could not afford a new build, following a 34% drop in interim profits due to declining sales and increasing financing costs. The government stated it would proceed with the plan but more slowly. [166]
In 2018, the National Energy Regulator of South Africa denied an application by Eskom to increase electricity tariffs by a future 19.9% for the financial year 2018/19. The regulator instead granted a 5.2% increase and gave a list of reasons for the refusal to grant higher tariffs that the South African newspaper Business Day stated painted "a picture of inefficiency, inaccurate forecasting and cost overruns" at the power utility. Part of the refusal was the finding that Eskom had an additional 6,000 employees that were not needed, costing the company R3.8 billion annually. [167] On 28 March 2018 Moody's Investors Service downgraded Eskom's credit rating to B2 from B1 stating that it was concerned with "the lack of any tangible financial support for the company in the February state budget". [168]
On 24 November 2020, Moody's further downgraded Eskom's long-term credit rating to Caa1. [169] This places Eskom's credit within the "speculative grade" of investment, with a "very high credit risk".
In 2015, the City of Cape Town sued the national government, demanding to be allowed to purchase electricity from third parties. The national government supported mandatory centralization in the Eskom system. Though Cape Town lost its case, in October 2020 the government changed its regulations to allow municipalities to build generation facilities or purchase electricity, subject to the final approval of the Ministry of Mineral Resources and Energy. The city then set a goal of 40% non-Eskom energy by 2030 and 100% clean energy by 2050. [170]
Cape Town has adopted a range of local policies to even out local electricity demand on a daily basis as of 2022. [171] This includes using the Steenbras Dam pumped water scheme to reduce the impact by up to two loadshedding levels. [172] In April 2023, Cape Town announced plans to make it "loadshedding free" within 3 years starting with the construction of a 60MW solar plant. [173] [174]
Koeberg Nuclear Power Station is a nuclear power station in South Africa and the only one on the African continent. It is located 30 km north of Cape Town, near Melkbosstrand on the west coast. It is owned and operated by the country's state-owned electricity public utility, Eskom.
A rolling blackout, also referred to as rota or rotational load shedding, rota disconnection, feeder rotation, or a rotating outage, is an intentionally engineered electrical power shutdown in which electricity delivery is stopped for non-overlapping periods of time over different parts of the distribution region. Rolling blackouts are a last-resort measure used by an electric utility company to avoid a total blackout of the power system.
Eskom Hld SOC Ltd or Eskom is a South African electricity public utility. Eskom was established in 1923 as the Electricity Supply Commission (ESCOM) (Afrikaans: Elektrisiteitsvoorsieningskommissie (EVKOM)). Eskom represents South Africa in the Southern African Power Pool. The utility is the largest producer of electricity in Africa, and was among the top utilities in the world in terms of generation capacity and sales. It is the largest of South Africa's state owned enterprises. Eskom operates a number of notable power stations, including Matimba Power Station and Medupi Power Station in Lephalale, Kusile Power Station in Witbank, Kendal Power Station, and Koeberg Nuclear Power Station in the Western Cape Province, the only nuclear power plant in Africa.
Samson Gwede Mantashe is a South African politician and former trade unionist. He is the Minister of Mineral Resources and Energy, with the function of Minister of Electricity and Energy having been accorded to Kgosientsho Ramokgopa. Mantashe was Minister of Mineral Resources and Energy from May 2019 to June 2024, and Minister of Mineral Resources from February 2018 to May 2019. He is also serving his second term as the national chairperson of the African National Congress (ANC).
Grootvlei Power Station is a coal-fired power station located in Grootvlei, Mpumalanga, South Africa.
Medupi Power Station is a dry-cooled coal-fired power station built by Eskom near Lephalale in Limpopo province, South Africa. The station consists of 6 generating units with a nameplate capacity of 764 MW each bringing the total installed capacity of 4,584 MW.
Camden Power Station in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom.
Majuba Power Station between Volksrust and Amersfoort in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. Majuba is Eskom's only power station that is not linked to a specific mine and it receives its coal from various sources. This was due to an error in geotechnical engineering core drilling which did not identify that the proposed local coal mine was under solid bedrock.
Tutuka Power Station in Mpumalanga, South Africa, is a coal-fired power plant operated by Eskom. It is a twin sister to Duvha Power Station.
Solar power in South Africa includes photovoltaics (PV) as well as concentrated solar power (CSP). As of July 2024, South Africa had 2,287 MW of installed utility-scale PV solar power capacity in its grid, in addition to 5,791 MW of rooftop solar and 500 MW of CSP. Installed capacity is expected to reach 8,400 MW by 2030.
Kusile Power Station in South Africa is a coal-fired power plant by state electricity utility Eskom in Mpumalanga. The station consists of 6 generating units with an eventual nameplate capacity of 800 MW each bringing the total installed capacity of 4,800 MW; as of 2023, only 5 units are in operation.
The Renewable Energy Independent Power Producer Procurement Programme is an initiative by the South African government aimed at increasing electricity capacity through private sector investment in solar photovoltaic and concentrated solar, onshore wind power, small hydro, landfill gas, biomass, and biogas. As of 2023, a total of 123 projects have been awarded to the private sector. Private sector investment totalling R256 billion has been committed to the REIPPPP. Four of the six Bid Windows have come online, totalling 6200 MW of installed capacity.
André Marinus de Ruyter is a South African businessman who previously worked at Sasol and Nampak.
City PowerJohannesburg is a state owned power utility, wholly owned by the City of Johannesburg. Its responsibilities include buying electricity from power producers and supplying it to the public, and installing and maintaining the electrical infrastructure in the city of Johannesburg. It supplies electricity to 3.2 million people in the Greater Johannesburg Metropolitan Area.
The Minister of Electricity and Energy is the energy minister in the Cabinet of South Africa. The office in its current form was established in June 2024 in a merger between the Minister in the Presidency for Electricity and the energy functions of the Minister of Mineral Resources and Energy. The energy portfolio was formerly the provenance of the Minister of Energy between 2009 and 2019.
The 2023 South African National Shutdown was a protest held by the political party Economic Freedom Fighters on 20 March 2023, the day before Human Rights Day. The EFF called for the resignation of President Cyril Ramaphosa and an end to load-shedding. The leader of the EFF, Julius Malema, warned businesses countrywide to close their doors or risk being looted by them.
Truth to Power: My Three Years Inside Eskom is a 2023 book by ex-Eskom CEO, André de Ruyter.
The National Transmission Company of South Africa (NTCSA) is a wholly-owned subsidiary of Eskom tasked with the transmission of electricity in South Africa. It was created with the unbundling of Eskom into 3 separate entities.