An oil production plant is a facility which processes production fluids from oil wells in order to separate out key components and prepare them for export. Typical oil well production fluids are a mixture of oil, gas and produced water. An oil production plant is distinct from an oil depot, which does not have processing facilities.
Oil production plant may be associated with onshore or offshore oil fields.
Many permanent offshore installations have full oil production facilities. [1] [2] Smaller platforms and subsea wells export production fluids to the nearest production facility, which may be on a nearby offshore processing installation or an onshore terminal. The produced oil may sometimes be stabilised (a form of distillation) which reduces vapour pressure and sweetens "sour" crude oil by removing hydrogen sulphide, thereby making the crude oil suitable for storage and transport. Offshore installations deliver oil and gas to onshore terminals which may further process the fluids prior to sale or delivery to oil refineries.
The configuration of onshore oil production facilities depends on the size of the oil field. For simple fields comprising a single well or a few wells, an oil storage tank may be sufficient. The tank is emptied periodically by road tanker and transferred to an oil refinery. For larger production rates a rail tanker transfer facility may be appropriate. [3] For larger fields a full three-phase processing facility is required. Three-phase separators separate the well fluids into its three constituent phases: oil, gas and produced water. Oil may be transferred by road or rail tanker or by pipeline to an oil refinery. Gas may be used on the site to run gas engines to produce electricity or can be piped to local users. [3] Excess gas is burned in a ground flare. Produced water may be re-injected into the reservoir. Small fields can use portable integrated packages, like vapor-tight tanks.
See for example: Wytch Farm
There is a wide variety of options for the processing of produced oil. These range from minimal offshore processing with all produced fluids sent to an onshore facility, to full offshore processing to make products to a specification suitable for sale or use with no further onshore processing. The decision on what facilities to provide depends on a number of factors: [4]
The Gulf of Mexico and the North Sea are two mature producing areas that have taken different approaches to the facilities provided. These are summarised in the following table: [5]
Parameter | Gulf of Mexico continental shelf | Gulf of Mexico deepwater | North Sea |
---|---|---|---|
Oil processing | |||
Oil production, barrels oil per day (BOPD) | < 20,000 (<3,180 m3/day) | 50,000 – 250,000 (7,949 – 39,746 m3/day) | 50,000 – 250,000 (7,949 – 39,746 m3/day) |
Individual well flow rate, BOPD (m3/day) | < 3,000 (<477 m3/day) | 10,000 – 35,000 (1,590 – 5,564 m3/day) | 10,000 – 25,000 (1,590 – 3,975 m3/day) |
Wellhead temperature °F (°C) | 90 – 110 (32 – 43 °C) | 110 – 200 (43 – 93 °C) | 150 – 230 (65 – 110 °C) |
Separation train(s) | 1 | 1–2 | 1 – 2 |
Separation stage(s) | 4 – 5 | 3 – 5 | 1 – 3 |
Export oil water content, % by volume | < 1 | < 1 | < 2 |
Export oil Reid Vapor pressure, psi | < 11 | < 11 | < 150 (true vapor pressure) |
Export oil pressure, psi (bar) | 1,000 – 1,500 (69 – 103 bar) | 1,500 – 3,000 (103 – 207 bar) | 1,500 – 2,800 (103 – 193 bar) |
Gas processing | |||
Gas rate, MMSCFD (million standard cubic feet per day) | < 50 | 50 – 400 | 50 – 300 |
Gas compression | Reciprocating compressors | Screw, centrifugal compressors | Centrifugal compressors |
Gas dehydration | Tri-ethylene glycol (TEG) | TEG, enhanced regeneration | TEG, enhanced regeneration |
Export gas water content, lb/MMSCF | 7 | 2 – 4 | 2 – 4 |
Export gas pressure, psi (bar) | 1,000 – 1,200 (69 – 93 bar) | 1,500 – 3,000 (103 –207 bar) | 2,000 – 2,700 (138 – 186 bar) |
Support Facilities and utilities | |||
Process heating | Direct fired, hot oil | Hot oil | Hot oil |
Process cooling | Air cooled heat exchanger | Air cooled heat exchanger, water cooled heat exchanger | Seawater, TEG/water cooling medium |
Produced water treatment | Skim tank, induced gas flotation (IGF) | Hydrocyclones, IGF | Hydrocyclones, degasser |
Water injection | Occasional | Frequent | Frequent |
The export options for oil and gas and the deployment around the world are as follows:
Gas disposal may take one or more of the following routes: [5]
Disposal route | Gas processing | Location deployment | |||
---|---|---|---|---|---|
Dehydration | Hydrocarbon dewpoint | Gulf of Mexico facilities | North Sea facilities | Deployed elsewhere | |
Pipeline | Yes | Yes | Few | Some | Indonesia |
Pipeline | Yes | No | Most | Most | Most areas |
Pipeline | No | No | Few | Few | Gulf of Suez, Trinidad |
Gas reinjection | Yes | Yes | Few | Some | Canada East Coast, West Africa |
Flaring | No | No | Few | Few | Several isolated fields and FPSO production |
In the Central and Northern North Sea gas is delivered to St Fergus or Teesside terminals by a small number of large diameter (36 inch, 91.4 cm) gas pipelines. These operate at 1600 – 2500 psig (110 – 172 bar) in the dense phase i.e. above the critical pressure. Operation in the dense phase provides a number of advantages:
These advantages are offset by the additional compression required and thicker walled, more expensive, pipelines are necessary. [4]
A further consideration is the number of separation trains and the number of stages of separation. Trains of process facilities operate in parallel, and stages are operated in a sequential series. The number of trains depends on flowrates, the availability of plant, and the available plot area. Single trains are capable of handling 150,000 to 200,000 barrels of oil per day (23,847 – 31,797 m3/day). Vessel sizes can be up to 14 to 19 feet (4.27 to 5.79 m) diameter and up to 30 feet (9.14 m) long. Vessels on Gulf of Mexico deepwater installations are 12 to 14 feet (3.66 to 4.27 m) diameter and 60 to 70 feet (4.27 to 21.34 m) long. [4]
The number of stages of separation depends on:
First stage separators in the Gulf of Mexico typically operate at 1500 to 1800 psi (103.4 to 124.1 bar), they operate as 2-phase liquid and vapour separators with a liquid residence time of 1 to 2 minutes. Produced water is removed in the low pressure (LP) 3-phase separator. This operates at 150 –250 psi (10.3 – 17.2 bar). [4]
In the North Sea first stage separators generally operate at < 750 psi (< 51.72 bar). These are operated as 3-phase (vapour, oil and water) separators and are sized to provide 3 – 5 minutes of liquid residence time. Pressures are set to maximise gas separation at as a high a pressure as possible. Up to 5 stages of separation are common in the Gulf of Mexico and up to 4 stages on platforms in the North Sea. [4]
The throughput, number of trains, separation stages and first stage separator pressure for a range of historic offshore installations is shown in the table. [3] [6]
Installation | Location | °API Gravity | Oil production, BOPD | Gas production, m3/day | Inlet separator pressure, bar | No. of trains | No. of stages |
---|---|---|---|---|---|---|---|
Brent C | North Sea | 38 | 150,000 | 8,500,000 | 9.6 | 3 | 4 |
Claymore A | North Sea | 30 | 180,000 | 5.9 | 1 | 3 | |
Cormorant A | North Sea | 35 | 60,000 | 900,000 | 30 | 1 | 3 |
Statfjord A | North Sea | 38 | 300,000 | 8,500,000 | 69 | 2 | 4 |
Murchison | North Sea | 36 | 164,000 | 1,300,000 | 45 | 1 | 3 |
Buchan | North Sea | 33.5 | 70,000 | 600,000 | 10 | 1 | 3 |
Magnus | North Sea | 39 | 140,000 | 2,500,000 | 28 | 2 | 2 |
Brae A | North Sea | 33/35, 41/45, 33 | 100,000 + 12,000 NGL | 4,250,000 | 248 | 2 | 3 |
Namorado I | South America | 40,000 | 640,000 | 2 | 3 | ||
Namorado II | South America | 60,000 | 420,000 | ||||
Cherne I | South America | 50,000 | 120,000 | 1 | |||
Bayan A | South China Sea | 60,000 | 27 | 2 | 2 | ||
Brae B | North Sea | 33/35, 41/45, 33 | 75,000 | 11,300,000 | 103 | 1 | 4 |
Ship Shoal | Gulf of Mexico | 12,000 | 4,250 | 90 | 1 | 3 | |
Forties Echo | North Sea | 37 | 67,000 | 300,000 | |||
Eider | North Sea | 34 | 53,000 | 14 – 29.3 | 1 | 1 | |
Seillean (Cyrus) | North Sea | 36 | 15,000 | 6,000,000 | 17 | 1 | 2 |
East Brae | North Sea | 33/35, 41/45, 33 | 120,000 | 17,000,000 | 102 | 1 | 3 |
Gannet | North Sea | 38/43 | 56,000 | 4,000,000 | 18 – 70 | 4 | 1 |
Nelson | North Sea | 40 | 145,000 | 9 | 1 | ||
Tiffany | North Sea | 33.6 | 105,000 | 3,250,000 | 17 | 1 | 2 |
A range of materials of construction are used for oil processing plant. Carbon steel is extensively used as it is inexpensive. However, it is unsuitable for corrosive service where a number of corrosion resistant alloys and other materials are required. The table illustrates typical materials for service on a plant that processes sour fluids. [7]
System or plant | Material of construction |
---|---|
Flowlines and manifolds (sweet service) | Carbon steel |
Flowlines and manifolds (sour service) | Alloy 825 |
Flowlines and manifolds (high H2S) | Duplex |
Separators (sweet) | Carbon steel |
Separators (sour) | Carbon steel clad with Alloy 825 |
Condensate separators | Carbon steel |
Condensate separators (sour high pressure) | Carbon steel clad with 316 stainless steel |
Condensate separators (sour low pressure) | 316 stainless steel |
Oil pumping and export | Carbon steel |
Gas compression | Carbon steel |
Gas compression piping (sour) | 316 stainless steel |
Gas compression vessels (sour) | Carbon steel |
Dehydrated gas | Carbon steel |
Gas export | Carbon steel |
Flare and vent | Carbon steel |
Flare (sour or cold service) | 316 stainless steel |
Gas injection | Carbon steel |
Seawater | GRP |
Seawater | Cunifer |
Firewater | Galvanised steel |
Seawater for heat exchangers | Titanium |
Injection water | Carbon steel |
Drains | Carbon steel |
Fresh water | Copper |
Air | Carbon steel |
Cooling and heating media | Carbon steel |
Fuel gas | Carbon steel |
The production plant can be considered to begin after the production wing valve on the oil well Christmas tree. The reservoir fluids from each well are piped through a flowline to a choke valve, which regulates the rate of flow and reduces the pressure of the fluids. [2] The flowlines from each well are gathered together at one or more inlet manifolds. These are provided for each train or operate at different pressures to match the wellhead pressure with various separator pressures. High pressure manifolds are routed into a first stage separator, which separates the three fluid phases. Produced water, the densest phase, settles out at the bottom of the separator, oil floats on the top of the produced water phase, and gas occupies the upper part of the separator. [8] The separator is sized to provide a liquid residence time of 3 to 5 minutes which is sufficient for light crude oil (>35° API) as produced in the North Sea. In the Gulf of Mexico the first stage separator operates as a 2-phase (gas and liquid) vessel, it is sized to provide a liquid residence time of 1 to 2 minutes.
Sand and other solids from the reservoir will tend to settle out in the bottom of the separators. If allowed to accumulate the solids reduce the volume available for oil/gas/water separation reducing efficiency. The vessel may be taken offline and drained down and the solids removed by digging out by hand. Or water sparge pipes in the base of the separator used to fluidize the sand which can be drained from the drain valves in the base.
Oil from the first stage separator may be cooled or heated in a heat exchanger to aid further separation. North Sea fields tend to operate at higher temperatures so heating may not be required. Gulf of Mexico fields tend to operate at lower temperatures so heat is required to achieve export vapor and BS&W specifications. Typical operating temperatures are 140 – 160 °F (60 – 71 °C). [4]
Oil is then routed either to a second stage separator, operating at a lower pressure than the first stage to further separate oil/gas/water, or to a coalescer to further remove water. [8] Several stages of separation, operating at successively lower pressures, aim to reduce the amount of dissolved gas and hence reduces the flash point of the oil to meet the export oil specification. [9] For higher oil flowrates parallel trains of separators may be necessary to handle the flow and to provide a turn-down capability. [2] The final stage of separation may be an electrostatic coalescer. These can achieve a 0.5% by volume water content, typical design fluxes are in the order of 200 bopd/ft2. [4]
A test separator (see diagram) enables the performance of individual wells to be determined. An individual well is connected to the test header which routes fluids to the test separator. Three phase separation into oil, vapour and produced water takes place. The flowrates of these phases are accurately measured as the fluids flow to lower pressure points in the oil train. The flowrates determine the performance of the well in terms of the maximum flow of the well, the gas-oil ratio, and the water cut of the fluids.
Some oil fields are sour, with high levels of carbon dioxide (CO2) and hydrogen sulphide (H2S). Operation of separation at high temperature drives these gases to the vapour phase. However, crude may still contain sour compounds above a typical H2S-in-crude specification limit of < 10 ppmw. A trayed column is used with sour crude fed in the top of the column and stripping gas introduced into the bottom of the column. [4]
From the final stage of separation, or from the coaleser, oil may be cooled to meet export specifications or to limit thermal stresses on the oil export riser. Oil is metered to accurately measure the flowrate [10] and then pumped via a pipeline to the onshore terminal. Some installations such as concrete gravity-base structures and floating production storage and offloading, FPSOs, have integral oil storage tanks which are continuously filled with oil and periodically discharged into oil tankers.
Produced water from the separator(s) and coalescer is routed to a produced water degasser operating at near atmospheric pressure to remove dissolved gas from the water. In the early days of the offshore industry parallel plate separator units were used to clean produced water prior to overboard disposal. Hydrocyclones, which are more compact, were introduced in the 1980s. [1] A hydrocyclone removes entrained oil and solids from produced water which then passes to the degasser and can then either be re-injected into the reservoir or dumped overboard. Induced gas flotation plant is used when the hydrocyclone / degasser plant cannot achieve the oil-in-water specification. For overboard disposal the water should have an oil content of less than about 30 parts per million (ppm) oil-in-water. [11] On North Sea installations the higher operating temperatures allow an oil-in-water concentration of > 20 ppmw to be achieved. [4]
The associated gas from the top of the separator(s) is also known as flash gas or wet gas as it is saturated with water and liquid hydrocarbons. The gas is typically routed through scrubbers, compressors and coolers to raise the pressure of the gas and to remove liquids. [2] Scrubbers are vertical vessels that allow the removal and separation of liquids from a gas stream. Coolers are located after a compressor to remove the heat of compression. Centrifugal compressors are often used offshore. They are more compact and lighter than reciprocating machines and maintenance costs are less. The latter are used where only small volumes of gas are handled. Centrifugal compressors my be driven by gas turbines or electric motors. [4]
The dry gas may be exported, used for gas lift, flared, used as fuel for the installation's power generators, or after further compression re-injected into the reservoir. Export gas is metered to accurately measure the flowrate before being sent to the onshore terminal via gas pipeline. Other treatment processes may be required.
Gas may be dried to reduce the water content to meet sales specification, to prevent condensation of water in the pipeline and the formation of slugs, or to avoid the formation of hydrates in the export pipeline. Gas is dried by counter-current contact with triethylene glycol in a glycol dehydration tower. [12] Typically dried gas has a water content of 2.5 to 7 lb of water /MMSCF. Glycol contactors generally operate at 1100–1200 psi (75 to 83 bar). [4] Water-rich glycol is regenerated by heating and stripping off the water. Enhanced regeneration uses DRIZO or Coldfinger to improve the regeneration performance. [4] Contactor towers formerly comprised bubble cap trays, since the 1980s structured packing has been used which provides the equivalent of 3 to 4 theoretical trays required to meet a water content of <4 lb/MMSCF. [4]
The export hydrocarbon dew-point specification (typically 100 barg at 5 °C [13] ) may be met by chilling the gas to remove the higher alkanes (butane, pentanes, etc.). This may be done by a refrigeration system, or passing the gas through a Joule-Thomson valve, or through a turbo-expander to condense out and separate liquids. The natural gas liquids (NGL) produced may be spiked into the oil export fluids where high vapor pressure fluids are exported. [1] Alternatively NGL fractionating columns may be used to produce a fluid for separate export. NGL fractionation columns are installed in Nkossa West Africa and Ardjuna Indonesia. [4]
Dry gas may be further treated to meet export gas specifications. [13] Excess carbon dioxide (CO2) can be removed by treatment in an amine gas treating process (e.g. Selexol), whereby CO2 is preferentially dissolved in a counter-current flow of amine in a contact tower. Hydrogen sulphide can also be removed using amine or by passing the gas through beds of zinc oxide absorbent.
Onshore oil terminals receive oil from offshore installations and treat it to produce products for sale or further processing such as in an oil refinery. Onshore terminals generally have fired heaters followed by separators and coalescers to stabilise the crude and remove any produced water and light hydrocarbons not separated offshore. Onshore separators tend to operate at a lower pressure than the offshore separators and so more gas is evolved. The associated gas is generally compressed, dew-pointed and exported via a dedicated pipeline. If gas export is uneconomical then it may be flared. Onshore terminals frequently have large crude oil storage tanks to allow offshore production to continue if the export route becomes unavailable. Export to the oil refinery is either by pipeline or tanker.
Onshore gas terminals may have facilities for removal of liquids from the incoming gas stream. Gas treatment processes may include glycol dehydration, gas sweetening, hydrocarbon dew-point control and gas compression before gas distribution to users.
In addition to production and gas and oil treatment systems a range of ancillary, support and utility systems are provided to support production and occupation of an offshore installation. Systems include: [1] [14]
Heating medium is generally heated by waste heat recovery from power generation gas turbine exhausts. The temperature required is generally not more than 400 °F (204 °C) and mineral oil based fluids are used. [4] Pressurised hot water, steam, and glycol/water mixtures are also used although temperatures are generally limited to < 300 °F (149 °C). On smaller installations electric heating elements may be the most appropriate option for heating fluids. [4]
Process cooling may be performed using air, seawater (known as direct cooling), or cooling medium comprising a 30% glycol (TEG)/water mixture and known as indirect cooling. [4] North Sea installations are generally quite crowded and do not have space for the extensive plot area required for air cooled heat exchangers. Water cooled heat exchangers occupy a relatively small plot area. North Sea installations are often provided with water injection facilities. These require large volumes of seawater to be lifted. The incremental cost of using the seawater for cooling is therefore considerably reduced. Furthermore, the reduced solubility of air in warmed water is an advantage as air has to be stripped out of injection water. The cold North Sea water temperature reduces the size of heat exchangers. Indirect cooling medium cooling is less likely to have corrosion issues than direct seawater cooling which may require more expensive metals such as Copper alloys, Titanium or Inconel. Cooling medium systems have a lower CAPEX. The clean fluid allows printed circuit heat exchangers to be used which offer space and weight savings. [4]
Wytch Farm is an oil field and processing facility in the Purbeck district of Dorset, England. It is the largest onshore oil field in Western Europe. The facility, taken over by Perenco in 2011, was previously operated by BP. It is located in a coniferous forest on Wytch Heath on the southern shore of Poole Harbour, two miles (3.2 km) north of Corfe Castle. Oil and natural gas (methane) are both exported by pipeline; liquefied petroleum gas is exported by road tanker.
In the upstream oil industry, a gas–oil separation plant (GOSP) is temporary or permanent facilities that separate wellhead fluids into constituent vapor (gas) and liquid components.
Platform Name - Tern Alpha.
The Ninian Central Platform is an oil platform in the North Sea. When constructed in Loch Kishorn, Scotland in 1978 the 600,000 tonne platform was the world's largest man-made movable object before being towed to its current position and sunk to the sea floor.
The Clair oilfield is an offshore oil field in Scottish territorial waters 75 kilometres (47 mi) west of Shetland in water depths of up to 140 metres (460 ft). The field is the largest oilfield on the UK Continental Shelf with an estimated 8 billion barrels of oil-in-place, according to the BP Plc's website. It extends over an area of some 220 square kilometres (85 sq mi), covering five licence blocks.
The Everest gasfield is located in the Central North Sea, 233 kilometres (145 mi) east of Aberdeen, Scotland. It lies in the United Kingdom Continental Shelf blocks 22/9, 22/10a and 22/14a. The gasfield was discovered by Amoco in 1982 with first gas produced in 1993.
The Schiehallion oilfield is a deepwater offshore oilfield approximately 175 kilometres (110 mi) west of the Shetland Islands in the North Atlantic Ocean. The Schiehallion and adjacent Loyal field were jointly developed by BP on behalf of the Schiehallion field partners; BP, Shell, Amerada Hess, Murphy Oil, Statoil and OMV, and the Loyal field partners; BP and Shell.
The term separator in oilfield terminology designates a pressure vessel used for separating well fluids produced from oil and gas wells into gaseous and liquid components. A separator for petroleum production is a large vessel designed to separate production fluids into their constituent components of oil, gas and water. A separating vessel may be referred to in the following ways: Oil and gas separator, Separator, Stage separator, Trap, Knockout vessel, Flash chamber, Expansion separator or expansion vessel, Scrubber, Filter. These separating vessels are normally used on a producing lease or platform near the wellhead, manifold, or tank battery to separate fluids produced from oil and gas wells into oil and gas or liquid and gas. An oil and gas separator generally includes the following essential components and features:
Onshore, when used in relation to hydrocarbons, refers to an oil, natural gas or condensate field that is under the land or to activities or operations carried out in relation to such a field.
"Offshore", when used in relation to hydrocarbons, refers to operations undertaken at, or under the, sea in association with an oil, natural gas or condensate field that is under the seabed, or to activities carried out in relation to such a field. Offshore is part of the upstream sector of the oil and gas industry.
The Douglas Complex is a 54-metre (177 ft) high system of three linked platforms in the Irish Sea, 24 kilometres (15 mi) off the North Wales coast. The Douglas oil field was discovered in 1990, and production commenced in 1996. Now operated by Eni, the complex consists of the wellhead platform, which drills into the seabed, a processing platform, which separates oil, gas and water, and thirdly an accommodation platform, which is composed of living quarters for the crew. This accommodation module was formerly the Morecambe Flame jack-up drilling rig.
The Central Area Transmission System is a natural gas transportation and processing system that transports natural gas through a 404 kilometre pipeline from the Central North Sea to a reception and processing terminal at Teesside in the North East of England.
The Hutton oil field, located on the UK continental shelf, was the location for the first ever production Tension Leg Platform (TLP).
Instrumentation is used to monitor and control the process plant in the oil, gas and petrochemical industries. Instrumentation ensures that the plant operates within defined parameters to produce materials of consistent quality and within the required specifications. It also ensures that the plant is operated safely and acts to correct out of tolerance operation and to automatically shut down the plant to prevent hazardous conditions from occurring. Instrumentation comprises sensor elements, signal transmitters, controllers, indicators and alarms, actuated valves, logic circuits and operator interfaces.
Tyra Field is the largest gas condensate field in the Danish Sector of the North Sea. It was discovered in 1968 and production started in 1984. The field is owned by Dansk Undergrunds Consortium, a partnership between Total, BlueNord and Nordsofonden, and operated by Total. The reservoir depth is about 2,000 metres (6,600 ft) and it covers area of 90 kilometres (56 mi) in the water depth of 37–40 metres (121–131 ft). The Tyra field has a number of satellite fields, including Roar, Svend and Tyra Southeast fields.
The Buzzard Oil Field is an oil field located in the North Sea Blocks 19/10, 19/5a, 20/6 and 20/1s. It was discovered in 2001 by PanCanadian, and developed initially by PanCanadian's successor EnCana and then by Nexen. The oil field was initially operated and owned by Nexen which is now a subsidiary of China's CNOOC.
Stock tank oil refers to the volume of oil after flashing to nominal atmospheric storage pressure and temperature.
The Heather oil field is a significant crude oil producing field in the UK sector of the northern North Sea, 458 km north-north-east of Aberdeen. Production of oil started in 1978 and ceased in 2019. The Heather Alpha installation is currently (2021) undergoing decommissioning.
The Ravenspurn gas fields are two adjacent natural gas fields located in the UK sector of the southern North Sea about 65 km east of Flambrough Head, Yorkshire.
The Lincolnshire Offshore Gas Gathering System (LOGGS) was a major natural gas collection, processing and transportation complex in the UK sector of the southern North Sea. It comprised five bridge-linked platforms about 118 km east of the Lincolnshire coast, which operated from 1988 to 2018.