Silverton Wind Farm | |
---|---|
Country | Australia |
Location | Barrier Ranges, New South Wales |
Coordinates | 31°47′38″S141°15′29″E / 31.794°S 141.258°E |
Status | Commissioned |
Construction began | May 2017 |
Commission date | 2019 |
Construction cost | A$450 million |
Owner(s) | Powering Australian Renewables Fund |
Operator(s) | AGL Energy |
Wind farm | |
Type | Onshore |
Hub height | 110 metres (361 ft) |
Rotor diameter | 130 metres (427 ft) |
Power generation | |
Units operational | 58 × 3.43 MW |
Make and model | General Electric 3.4-130 |
Nameplate capacity | 199 MW |
Capacity factor | 44.7% |
Annual net output | 780 GWh |
External links | |
Website | www |
The Silverton Wind Farm is a 199 megawatt wind farm situated on the Barrier Ranges in New South Wales, built for AGL Energy by Catcon and General Electric. [1]
On 3 June 2009, the project was approved by the Government of New South Wales. [2]
The project was initially set to begin construction in the first half of 2010, [3] yet several issues caused delays. To begin, the transmission line needed to connect the fully developed wind farm would need to be as long as 300 km, and due to multiple connection options, as well as an expected large cost of the infrastructure, the decision of the final solution was delayed. [4]
In 2012, the start-date for construction of the wind farm has been pushed back to 2014, after AGL Energy decided to give priority to building two solar photovoltaic plants which have received almost $200m in government funding. [5]
The project's planning approval was set to expire on 24 May 2016, however AGL submitted a Modification Application on 25 February 2016 with the sole aim to extend the project's Planning Approval expiry to 2021. On 3 June 2016 that application was granted, giving AGL the option to optimise and build the project within its Powering Australian Renewables Fund. [6] [7] The project secured a Power Purchase Agreement with EnergyAustralia for supply of 60% of its annual output until December 2030. [8]
On 16 May 2017, AGL announced construction had commenced. [9]
As of 2019, it had been completed and is now operating. [1] The project uses General Electric 3.43-130 wind turbines with a hub height of 110m. [10] It is expected to operate at a capacity factor of 44.7%, generating 780 GWh of energy annually.
The wind farm began grid output in May 2018 and was fully commissioned in May 2020 following long setbacks due to grid issues. [11] These problems are reflected in the energy generation until then, with the plant being constrained during the day reducing its capacity factor. The generation table uses eljmkt nemlog to obtain generation values for each month.
Year | Total | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2018 | 98,281 | N/A | N/A | N/A | N/A | 1,173* | 8,291* | 9,773* | 16,620* | 13,393* | 12,587* | 16,547* | 19,897* |
2019 | 423,891 | 25,034* | 23,497* | 19,293* | 24,920* | 35,078* | 36,616* | 43,479* | 54,842* | 37,470* | 38,784* | 38,730* | 46,148* |
2020 | 714,688 | 52,541* | 51,637* | 53,098* | 45,626* | 62,276* | 55,901 | 60,736 | 56,356 | 72,114 | 63,339 | 67,442 | 73,622 |
2021 | 72,477 | 68,650 | 70,560 | 46,165 | 57,701 | 59,791 | 60,643 | 52,254 | 53,054 |
Note: Asterisk indicates power output was limited during the month.
ActewAGL is an Australian multi-utility joint venture company that provides utility services in the Australian Capital Territory (ACT) and south-east New South Wales. The company was formed in October 2000 between the Australian Gas Light Company and ACTEW Corporation.
Crookwell Wind Farm, located at Crookwell west of Goulburn, New South Wales, consists of eight 600 kW wind turbines giving a total capacity of 4.8 MW. It was the first grid-connected wind farm in Australia when built by Pacific Power in 1998. It is now owned by Tilt Renewables.
The Blayney wind farm is a wind power station at Lake Carcoar, south of Blayney, New South Wales, Australia. It was acquired by Trustpower in 2014, and is now owned by Tilt Renewables. Blayney has fifteen wind turbines, with a total nameplate capacity of 9.9 MW of electricity.
AGL Energy Ltd is an Australian listed public company involved in both the generation and retailing of electricity and gas for residential and commercial use. AGL is Australia's largest electricity generator, and the nation's largest carbon emitter. In 2022, 83% of its energy came from burning coal. It produces more emissions as a single company than the nations of New Zealand, Portugal or Sweden, according to its largest shareholder, Mike Cannon-Brookes, who named it "one of the most toxic companies on the planet".
Solar power is a fast-growing industry in Australia. As of September 2023, Australia's over 3.60 million solar PV installations had a combined capacity of 32.9 GW photovoltaic (PV) solar power, of which at least 3,823 MW were installed in the preceding 12 months. In 2019, 59 solar PV projects with a combined capacity of 2,881 MW were either under construction, constructed or due to start construction having reached financial closure. Solar accounted for 12.4% of Australia's total electrical energy production in 2021.
Wind power became a significant energy source within South Australia over the first two decades of the 21st century. In 2015, there was an installed capacity of 1,475 MW, which accounted for 34% of electricity production in the state. This accounted for 35% of Australia's installed wind power capacity. In 2021, there was an installed capacity of 2052.95 MW, which accounted for 42.1% of the electricity production in the state in 2020.
The Hallett Wind Farm is the collective name for four wind farms near the town of Hallett, South Australia. They are owned and operated by AGL Energy.
Coopers Gap Wind Farm is a 453 megawatt wind farm in the Western Downs and South Burnett regions of Queensland, Australia. It is located approximately 175 km north-west of the state capital Brisbane, and 50 kilometres south-west of Kingaroy and 65 kilometers north of Dalby. When construction was announced to be completed on 30 April 2020, it became the largest wind farm in Australia. This record was held until 10 December 2020 when the Stockyard Hill Wind Farm in Victoria was completed.
The Macarthur Wind Farm is a wind farm located in Macarthur, Victoria, Australia, near Hamilton, 260 km west of Melbourne. It is on a 5,500 ha site which has an installed capacity of 420 megawatts (MW). Based on a capacity factor of around 35%, it is estimated that the long-term average generation will be approximately 1,250 GWh per year. Its actual capacity factor is much lower, with a historical average of 26.29% since 2013.
South Australia is a leader in utility-scale renewable energy generation, and also produces gas and uranium for electricity generation. Gas production is mostly concentrated in the Cooper Basin in the state's north-east. Gas is delivered from these fields by pipeline to users interstate and to Port Adelaide where it fuels three separate gas-fired power plants. Uranium is also mined in South Australia, though nuclear power generation is prohibited nationally. The Olympic Dam mine is the world's single largest known deposit of uranium and represents 30% of the world's total uranium resource. Many utility-scale wind farms and solar farms have been commissioned during the 21st century and geology with potential for geothermal energy has also been identified but is yet to be developed.
The Australian electricity sector has been historically dominated by coal-fired power stations, but renewables are forming a rapidly growing fraction of supply.
The Taralga Wind Farm is a wind farm located near Taralga, New South Wales. Owned by Pacific Blue, it commenced operation in 2015.
The Broken Hill Solar Plant, which became operational in December 2015, is a 53 megawatt farm located near Broken Hill in western New South Wales, Australia. It is associated with the Nyngan Solar Plant, making the total capacity of the combined plants 155 megawatts.
Energy produced in the Australian Capital Territory mainly consists of solar electricity. Electricity consumed in the Australian Capital Territory mainly comes from the national power grid through substations at Holt and Fyshwick. The ACT currently mandates that 100 percent of its electricity, will be supplied from renewable sources by 2020. The ACT has four solar farms capable of generating about 56.3 megawatts. From 1913 until the mid 1950s some power was produced from the Kingston Powerhouse, a thermal power station in Kingston.
The Lincoln Gap Wind Farm is a wind farm in the vicinity of Lincoln Gap on northeastern Eyre Peninsula in South Australia, Australia. It consists of 59 wind turbines and generates a total of 212 MW of electricity. Construction began in late 2017 and was initially expected to be commissioned in late 2018. Construction was delayed in July 2018 when unexploded ordnance was discovered on the site, left from historic military testing. The site is not far from the Cultana Training Area.