Lake Bonney Wind Farm

Last updated

Lake Bonney Wind Farm
Lake Bonney wind farmDKC1.jpg
Early morning at Lake Bonney wind farm
Lake Bonney Wind Farm
CountryAustralia
Location Millicent, South Australia
Coordinates 37°45′36″S140°24′0″E / 37.76000°S 140.40000°E / -37.76000; 140.40000 Coordinates: 37°45′36″S140°24′0″E / 37.76000°S 140.40000°E / -37.76000; 140.40000
StatusOperational
Commission date March 2005 (2005-03)
Construction costA$700 million
Owner(s) Infigen Energy
Wind farm
Type Onshore
Power generation
Units operational112
Make and model Vestas
Nameplate capacity 278.5 MW
Capacity factor 34%
Storage capacity 52 MW·h
External links
Website www.infigenenergy.com/lake-bonney/
Commons Related media on Commons

Lake Bonney Wind Farm is a wind farm near Millicent, South Australia, Australia. The wind farm is south of, and contiguous with, Canunda Wind Farm. Both are built along the Woakwine Range - a line of stabilised sand dunes that once were coastal.

Contents

The project was built in three stages. Stage 1 comprises 46 turbines each having a rated capacity of 1.75 MW (total 80.5 MW) and was finished in March 2005. Construction of Stage 2 began in November 2006 and was finished around April 2008. Stage 2 comprises 53 turbines of 3 MW (total 159 MW). Stage 3 comprises 13 turbines of 3 MW of total 39 MW). [1] Stage 3 construction commenced in February 2009 and was commissioned in September 2009. [2]

The owner of the Lake Bonney Wind Farm is Infigen Energy, previously known as Babcock and Brown Wind Partners. Wind turbines are serviced under a post-warranty service agreement [3] by the turbine manufacturer Vestas.

Battery storage

It was announced in August 2018 that a battery storage power station would be added to the wind farm to provide firmer commitments to provide electricity, system security and ancillary services to the electricity grid. The project would cost A$38 million to install, including $5 million from the government of South Australia and $5 million from the Australian Renewable Energy Agency (ARENA). The battery is rated at 25 MW and 52 MW·h, and is connected to the Mayurra substation. [4] Like the similar Hornsdale Power Reserve, the battery will operate independently of the wind farm in the electricity market, and connect to the grid at the same point as the wind farm. [5] Construction of the battery was completed in May 2019, [6] and testing began in November 2019. [7] In 2020, its Frequency Control Ancillary Service (FCAS) earned $230,000 per MWh installed. [8]

See also

Related Research Articles

<span class="mw-page-title-main">Portland Wind Farm</span>

The Portland wind farm is one of Australia's largest wind farms. Located on the coast of south-western Victoria near the city of Portland, it consists of four separate sites, all of which have been completed as of 2015. Completion of the entire 195 MW project was expected in 2011, at a capital cost of A$330 million.

<span class="mw-page-title-main">Solar power in Australia</span>

Solar power is a fast growing industry in Australia. As of September 2022, Australia's over 3.27 million solar PV installations had a combined capacity of 28,177 MW photovoltaic (PV) solar power, of which at least 4,258 MW were installed in the preceding 12 months. In 2019, 59 solar PV projects with a combined capacity of 2,881 MW were either under construction, constructed or due to start construction having reached financial closure. Solar accounted for 9.9% of Australia's total electrical energy production in 2020.

<span class="mw-page-title-main">Canunda Wind Farm</span>

Canunda Wind Farm is a $92.5 million, 46 MW wind power project located on grazing land approximately 16 kilometres south of Millicent, and 6 kilometres west of Tantanoola in South Australia. It is jointly owned by GDF Suez Energy AustraliaEn 72%) and Mitsui (28%).

<span class="mw-page-title-main">Wind power in South Australia</span> South Australian use of wind turbines to generate electricity

Wind power became a significant energy source within South Australia over the first two decades of the 21st century. In 2015, there was an installed capacity of 1,475 MW, which accounted for 34% of electricity production in the state. This accounted for 35% of Australia's installed wind power capacity. In 2021, there was an installed capacity of 2052.95 MW, which accounted for 42.1% of the electricity production in the state in 2020.

<span class="mw-page-title-main">Emu Downs Wind Farm</span> Wind farm in Western Australia

The Emu Downs Wind Farm is a 79.2 MW wind farm in Western Australia. It was a 50:50 joint development between Griffin Energy and Stanwell Corporation. The site is approximately 200 kilometres north of Perth, near Cervantes. Construction of the $180 million project commenced in November 2005, and the project was commissioned in October 2006.

South Australia is a leader in utility-scale renewable energy generation, and also produces gas and uranium for electricity generation. Gas production is mostly concentrated in the Cooper Basin in the state's north-east. Gas is delivered from these fields by pipeline to users interstate and to Port Adelaide where it fuels three separate gas-fired power plants. Uranium is also mined in South Australia, though nuclear power generation is prohibited nationally. The Olympic Dam mine is the world's single largest known deposit of uranium and represents 30% of the world's total uranium resource. Many utility-scale wind farms and solar farms have been commissioned during the 21st century and geology with potential for geothermal energy has also been identified but is yet to be developed.

<span class="mw-page-title-main">Infigen Energy</span>

Infigen Energy (Infigen), operating under this name since 29 April 2009, is a developer, owner and operator of renewable energy generation assets in Australia. Infigen's wind farm portfolio has an installed capacity of 557 MW. Most of Infigen's assets generate electricity from renewable sources and are eligible to sell Large-scale Generation Certificates (LGCs) under the mandatory Renewable Energy Target scheme, which operates in Australia under the Renewable Energy (Electricity) Act 2000. Since 2020, Infigen Energy has been a subsidiary of Iberdrola.

<span class="mw-page-title-main">Electricity sector in Australia</span>

The Australian electricity sector has been historically dominated by coal-fired power stations, but renewables are forming a rapidly growing fraction of supply.

Kennedy Energy Park is a wind, solar and storage hybrid power station approximately 20 km south east of Hughenden and 290 km southwest of Townsville in Queensland.

The Hornsdale Wind Farm is an electricity generator in the locality of Hornsdale in the south-west of the Narien Range, north of Jamestown, South Australia. It consists of 99 wind turbines with a generation capacity of 315 megawatts (422,000 hp). The plant is owned and operated by Neoen, a French renewable energy company.

Hornsdale Power Reserve is a 150 MW grid-connected energy storage system owned by Neoen co-located with the Hornsdale Wind Farm in the Mid North region of South Australia, also owned by Neoen.

The Lincoln Gap Wind Farm is a wind farm in the vicinity of Lincoln Gap on northeastern Eyre Peninsula in South Australia, Australia. It consists of 59 wind turbines and generates a total of 212 MW of electricity. Construction began in late 2017 and was initially expected to be commissioned in late 2018. Construction was delayed in July 2018 when unexploded ordnance was discovered on the site, left from historic military testing. The site is not far from the Cultana Training Area.

<span class="mw-page-title-main">Tailem Bend Solar Power Project</span>

The Tailem Bend Solar Power Project is a solar power farm near Tailem Bend in South Australia. It has 108MW of generation capacity but is limited to supplying 95MW to the national grid. An additional 85MW is proposed in stage 2. It is developed and owned by Singapore-based Vena Energy, a new name for the former Equis Energy following acquisition by Global Infrastructure Partners in January 2018. The output will be sold to Snowy Hydro for retail sale under its Lumo Energy brand. Stage 2 is also expected to provide battery storage.

The Dalrymple ESCRI battery is a 30 MW / 8 MW·h grid-connected battery array near Stansbury on Yorke Peninsula in South Australia. Its role is to provide improved reliability and stability to the electricity network on Yorke Peninsula and South Australia.

Dundonnell Wind Farm is at Dundonnell, 23 kilometres (14 mi) northeast of Mortlake in the Australian state of Victoria. Construction began in January 2019 and was completed in 2020 with 80 Vestas wind turbines with a capacity to generate 336MW of electricity. The drive trains and hubs were assembled at the former Ford Australia site in Geelong.

The Port Augusta Renewable Energy Park is a combined wind and solar farm under construction south of Port Augusta in South Australia, Australia. The solar farm is planned to be at the northern end of the site, west of the Augusta Highway and south of Sundrop Farms. The wind turbines will be on both sides of the Augusta Highway, extending south as far as the road to Horrocks Pass. Construction formally started in October 2020 and is estimated to take about 18 months to complete. The total site is about 5,400 hectares.

Taiba N'Diaye Wind Power Station,, is a 158.7 MW (212,800 hp) wind power plant in Senegal. The power station is the largest wind power station in West Africa, by generation capacity.

Shell Energy Australia provides gas, electricity, environmental products and energy productivity services to commercial and industrial customers.

References

  1. Wind power and wind farms in South Australia: Wind in the Bush
  2. "Lake Bonney Wind Farm Stage 3". www.aurecongroup.com. Retrieved 5 September 2021.
  3. "INFIGEN EXECUTES POST-WARRANTY SERVICES AGREEMENTS WITH VESTAS" (PDF). Archived from the original (PDF) on 2 June 2012. Retrieved 22 January 2016.
  4. Washington, David (15 August 2018). "Another big battery to be built in SA". InDaily . Retrieved 15 August 2018.
  5. Moret, Glen (15 November 2018). "South Australia's $38 million Tesla battery site on track to charge in 2019, giving Infigen more opportunities". ABC South East SA. Retrieved 25 January 2019.
  6. "Lake Bonney Battery Energy Storage System". Infigen Energy . Retrieved 30 August 2019.
  7. Parkinson, Giles (5 November 2019). "Lake Bonney battery charges up for first time in South Australia". RenewEconomy.
  8. Parkinson, Giles (23 February 2021). "Dalrymple big battery delivers biggest bang for megawatt hour of storage". RenewEconomy.