Solar River Project

Last updated

Solar River Project
Solar River Project
CountryAustralia
Locationnorth of Robertstown, South Australia
Coordinates 33°47′S139°23′E / 33.78°S 139.38°E / -33.78; 139.38
StatusProposed
Construction beganMid-2022 (proposed)
Construction costA$450 million
Solar farm
Type Flat-panel PV
Collectors 628,000 (stage 1)
Site area5,000 hectares (12,000 acres)
Power generation
Nameplate capacity 200 MW (stage 1)
200 MW (stage 2)
Storage capacity 120 MW·h (stage 1)
150 MW·h (stage 2)

Solar River Project is a proposed photovoltaic power station planned to be built near Robertstown in South Australia. [1] The project received development approval from the Government of South Australia in June 2018 and was expected to start construction early in 2019. [2] However, as of November 2021, the project was still proposed to be constructed, but work on site was not expected until at least the second half of 2022. [3]

The company developing it is based at the University of Adelaide's venture incubator, ThincLab. [4] The project has the support of the Ngadjuri people and the Regional Council of Goyder.[ citation needed ]

Stage 1 includes 200 MW of solar photovoltaic electricity generation and a 120 MW·h lithium ion battery system and was proposed to start construction early in 2019, generating its first generation before the end of the same year. Stage 1 will consist of one hundred single-axis tracker arrays each generating 2 MW and approximately 310 by 180 metres (1,020 by 590 ft) [5] for a total area of 3,200 by 1,800 metres (10,500 by 5,900 ft). Stage 2 is proposed to provide another 200 MW of generation and a 150 MW·h battery. [5]

The land is north of Goyder's Line and 6 kilometres (3.7 mi) north of the Goyder Highway on crown land unsuitable for cropping due to the low rainfall. [6]

Downer Group was engaged in January 2019 for early contractor involvement, with construction expected to commence in July 2019 and stage 1 to take two years to build. The project had provision for three more stages, depending on market and network conditions. [7] In July, the project's website said that construction would start in the fourth quarter of 2019. [8] By November 2019, this had slipped to the first quarter of 2020. [9]

Alinta Energy had committed to buy 75% of the solar farm's output for 15 years, [10] [11] however that contract expired due to delays in the project caused by issues such as the withdrawal of Downer Group as EPC contractor. [12]

The grid-connected battery will be supplied by GE Renewable Energy. It is expected to be 100MW/300MWh, larger than any grid-connected batteries in the world at the time of its announcement in 2019. [13]

Related Research Articles

<span class="mw-page-title-main">Solar power in Australia</span>

Solar power is a fast-growing industry in Australia. As of June 2023, Australia's over 3.52 million solar PV installations had a combined capacity of 32,095 MW photovoltaic (PV) solar power, of which at least 4,389 MW were installed in the preceding 12 months. In 2019, 59 solar PV projects with a combined capacity of 2,881 MW were either under construction, constructed or due to start construction having reached financial closure. Solar accounted for 12.4% of Australia's total electrical energy production in 2021.

Project EnergyConnect is a new electricity transmission line under construction which will connect the South Australia and New South Wales districts of the National Electricity Market in Australia. Riverlink was a previous working title for the project, drawn from a proposal first raised in 1999. The Australian Energy Market Operator used RiverLink in its proposal for this interconnector, but the transmission companies in South Australia (ElectraNet) and New South Wales (TransGrid) now call it EnergyConnect.

<span class="mw-page-title-main">Wind power in South Australia</span> South Australian use of wind turbines to generate electricity

Wind power became a significant energy source within South Australia over the first two decades of the 21st century. In 2015, there was an installed capacity of 1,475 MW, which accounted for 34% of electricity production in the state. This accounted for 35% of Australia's installed wind power capacity. In 2021, there was an installed capacity of 2052.95 MW, which accounted for 42.1% of the electricity production in the state in 2020.

<span class="mw-page-title-main">CS Energy</span>

CS Energy is an Australia-based electricity generating company fully owned by the Government of Queensland with its head office located in Fortitude Valley, Brisbane. The company was established in 1997 and employs more than 500 staff. Adam Aspinall is the Board Chair and Darren Busine is the Chief Executive Officer.

<span class="mw-page-title-main">Solar power in Hawaii</span> Overview of solar power in the U.S. state of Hawaii

The energy sector in Hawaii has rapidly adopted solar power due to the high costs of electricity, and good solar resources, and has one of the highest per capita rates of solar power in the United States. Hawaii's imported energy costs, mostly for imported petroleum and coal, are three to four times higher than the mainland, so Hawaii has motivation to become one of the highest users of solar energy. Hawaii was the first state in the United States to reach grid parity for photovoltaics. Its tropical location provides abundant ambient energy.

South Australia is a leader in utility-scale renewable energy generation, and also produces gas and uranium for electricity generation. Gas production is mostly concentrated in the Cooper Basin in the state's north-east. Gas is delivered from these fields by pipeline to users interstate and to Port Adelaide where it fuels three separate gas-fired power plants. Uranium is also mined in South Australia, though nuclear power generation is prohibited nationally. The Olympic Dam mine is the world's single largest known deposit of uranium and represents 30% of the world's total uranium resource. Many utility-scale wind farms and solar farms have been commissioned during the 21st century and geology with potential for geothermal energy has also been identified but is yet to be developed.

<span class="mw-page-title-main">Electricity sector in Australia</span>

The Australian electricity sector has been historically dominated by coal-fired power stations, but renewables are forming a rapidly growing fraction of supply.

<span class="mw-page-title-main">Battery storage power station</span> Energy storage system using electrochemical secondary cells

A battery storage power station is a type of energy storage power station that uses a group of batteries to store electrical energy. Battery storage is the fastest responding dispatchable source of power on electric grids, and it is used to stabilise those grids, as battery storage can transition from standby to full power in under a second to deal with grid contingencies.

The Beacon Solar Project is a photovoltaic power station in the northwestern Mojave Desert, near California City in eastern Kern County, California. Split into five phases, the combined Beacon solar facilities generate 250 MW of renewable energy for the Los Angeles Department of Water and Power (LADWP). The five phases of the project, fully completed in December 2017, include a total of 903,434 individual solar photovoltaic modules, mounted onto Nextracker single-axis tracking systems.

Aurora Solar Thermal Power Project was a planned solar power tower solar thermal power plant to be located north of Port Augusta in South Australia. It was planned to generate 150 MW of electricity after it was completed in 2020. Storage capacity would have been up to 8 hours at full power. The facility was expected to produce 495 GWh of electricity annually. It was to be 30 kilometres (19 mi) north of Port Augusta on Carriewerloo Station.

Neoen is a French producer of exclusively renewable energy headquartered in Paris, France. Founded in 2008, it develops, finances, builds and operates solar power plants, wind farms and energy storage solutions. As at 31 December 2021, the company's total capacity was 5.4 GW, made up of 50% solar, 38% wind and 12% battery storage. Neoen aims to attain 10 GW in operation and under construction by 2025.

The Lincoln Gap Wind Farm is a wind farm in the vicinity of Lincoln Gap on northeastern Eyre Peninsula in South Australia, Australia. It consists of 59 wind turbines and generates a total of 212 MW of electricity. Construction began in late 2017 and was initially expected to be commissioned in late 2018. Construction was delayed in July 2018 when unexploded ordnance was discovered on the site, left from historic military testing. The site is not far from the Cultana Training Area.

<span class="mw-page-title-main">Murra Warra Wind Farm</span>

The Murra Warra Wind Farm is one of Australia's largest wind farms. Located on the plains of north-western Victoria, approximately 25 kilometres (16 mi) north of the city of Horsham, it consists of 99 wind turbines with a maximum tip height of 220m.

Kiamal Solar Farm is a photovoltaic power station under construction north of Ouyen in western Victoria, Australia. Stage 1 is expected to be completed by the end of 2019. It is owned by Total Eren, a renewable energy subsidiary of TotalEnergies When completed, stage 1 at 256MW will be Victoria's largest solar farm. Construction began in October 2018. It has energy offtake agreements with Mars Australia, Flow Power and Alinta Energy.

The Port Augusta Renewable Energy Park is a combined wind and solar farm under construction south of Port Augusta in South Australia, Australia. The solar farm is planned to be at the northern end of the site, west of the Augusta Highway and south of Sundrop Farms. The wind turbines will be on both sides of the Augusta Highway, extending south as far as the road to Horrocks Pass. Construction formally started in October 2020 and is estimated to take about 18 months to complete. The total site is about 5,400 hectares.

Goyder South Wind Farm is the first stage of the Goyder Renewables Zone development near Burra, South Australia. The Goyder South Wind Farm will be on the hills south-east of the town of Burra.

References

  1. May, Jason (4 December 2017). "Solar River Project Development Application" (PDF). Application on notification – Crown Development. Retrieved 27 June 2018.
  2. Evans, Richard (25 June 2018). "Groundbreaking Solar River Project to slash the cost of renewable energy to 90,000 SA homes". The Advertiser . Retrieved 27 June 2018.
  3. Zerner, Mel (26 November 2021). "Renewables Projects Update Report". What's Happening in Goyder. Retrieved 13 December 2021.
  4. "Reliable renewable energy is possible with The Solar River Project". University of Adelaide. 26 June 2018. Retrieved 27 June 2018.
  5. 1 2 Bloch, Michael (26 June 2018). "Massive Solar + Storage Facility For South Australia To Proceed". Solar Quotes Blog. Retrieved 27 June 2018.
  6. "Major PV solar farm approved in outback South Australia". The LEAD. 25 June 2018. Retrieved 27 June 2018.
  7. Etheridge, Michelle (28 January 2019). "Major milestone for Solar River renewable energy project in SA's Mid North". The Advertiser. Retrieved 25 February 2019.
  8. "The Solar River Project". Archived from the original on 4 July 2019. Retrieved 4 July 2019. Project Construction Start Date Q4 2019{{cite web}}: CS1 maint: unfit URL (link)
  9. "The Solar River Project". Archived from the original on 4 July 2019. Retrieved 5 November 2019. Project Construction Start Date Q1 2020
  10. Vorrath, Sophie (18 July 2019). "Alinta signs up for huge solar and battery project in South Australia". Renew Economy . Retrieved 19 July 2019.
  11. Russell, Chris (17 July 2019). "Solar River project at Robertstown to sell power to Alinta Energy". The Advertiser. Retrieved 19 July 2019.
  12. Parkinson, Giles (4 September 2020). "Solar River solar and battery project still confident, despite loss of Alinta contract". Renew Economy . Retrieved 13 December 2021.
  13. Vorrath, Sophie (19 September 2019). "GE to supply world's biggest battery for South Australia Solar River project". Renew Economy . Retrieved 19 September 2019.