Temporary Generation North

Last updated

Temporary Generation North
Temporary Generation North
CountryAustralia
Location Elizabeth South
Coordinates 34°44′38″S138°39′11″E / 34.744°S 138.653°E / -34.744; 138.653 Coordinates: 34°44′38″S138°39′11″E / 34.744°S 138.653°E / -34.744; 138.653
Statusdecommissioned
Commission date November 2017
Decommission dateQ1 2021
Owner(s) Government of South Australia
Operator(s) Nexif Energy from May 2020
Thermal power station
Primary fuelDiesel
Turbine technology gas turbine
Power generation
Make and model General Electric TM2500
Units decommissioned5
Nameplate capacity 154MW

Temporary Generation North and its smaller sibling Temporary Generation South were gas turbine power stations in South Australia. They were bought by the Government of South Australia in 2017 as a response to the 2016 South Australian blackout and load-shedding in February 2017.

Temporary Generation North was five open cycle gas turbines installed at the former Holden site in Elizabeth South, a northern suburb of Adelaide. [1] It was closed in the first quarter of 2021 so that the turbines could be moved to become the Snapper Point Power Station at Outer Harbor. [2]

The generators were purchased to be used only in emergency shortfalls in electricity supply to the grid, such as in extreme weather. Both sets were first used on 24 January 2019 to deal with a supply shortfall in Victoria. [1]

The intent of the Weatherill ALP state government was that the turbines would be converted from diesel fuel to natural gas and moved to a single location while remaining owned by the government. [3]

In August 2019, the state government (following the 2018 election, now controlled by the Liberal party) announced that it had arranged 25-year leases of the power stations to two different companies, with the leases taking effect from May 2020. Both companies operate wind farms in South Australia. [4] The five northern generators were leased to Nexif Energy and are being relocated to a new site at Outer Harbor and operating on natural gas, intended to be before the end of 2020. Nexif Energy also proposes to convert them to combined cycle with a steam turbine in the following few years. [5] This schedule was delayed by the COVID-19 pandemic, with Temporary Generation North closing in the first quarter of 2021, and Snapper Point in commissioning as of April 2022. [2] [6]

Related Research Articles

Electricity sector in India Electricity generation and distribution in India

India is the third largest producer of electricity in the world. The national electric grid in India has an installed capacity of 399.467 GW as of 31 March 2022. Renewable power plants, which also include large hydroelectric plants, constitute 39.2 % of total installed capacity. During the fiscal year (FY) 2019-20, the gross electricity generated by utilities in India was 1,383.5 TWh and the total electricity generation in the country was 1,598 TWh. The gross electricity consumption in FY2019 was 1,208 kWh per capita. In FY2015, electric energy consumption in agriculture was recorded as being the highest (17.89%) worldwide. The per capita electricity consumption is low compared to most other countries despite India having a low electricity tariff.

Liddell Power Station

Liddell Power Station is a coal-powered thermal power station with four 500 megawatts (670,000 hp) GEC steam driven turbine alternators for a combined electrical capacity of 2,000 megawatts (2,700,000 hp).

Hybrid power Combinations between different technologies to generate electric power

Hybrid power are combinations between different technologies to produce power.

Wind power in Australia Overview of wind power in Australia

Wind power is one of the main renewable energy sources in Australia and contributed 10% of electricity supplied in 2020, with 37.5% total renewable energy supply. Australia has greatly distinguished conditions for harvesting wind power. Abundant wind resources may be located close to population centres in the southern parts of the country and on the slopes of the Great Dividing Range in the east.

AGL Energy

AGL Energy Ltd is an Australian listed public company involved in both the generation and retailing of electricity and gas for residential and commercial use. AGL is Australia's largest electricity generator, and the nation's largest carbon emitter. The company has an operated generation capacity of 10,984 MW. 85% of the company's generation comes from the burning of coal. The company emits 42,227,180 Total Scope 1 Emissions. AGL is also a significant investor, owner, and operator, of renewable energy assets.

As of August 2020 Chile had diverse sources of electric power: for the National Electric System, providing over 99% of the county's electric power, hydropower represented around 26.7% of its installed capacity, biomass 1.8%, wind power 8.8%, solar 12.1%, geothermal 0.2%, natural gas 18.9%, coal 20.3%, and petroleum-based capacity 11.3%. Prior to that time, faced with natural gas shortages, Chile began in 2007 to build its first liquefied natural gas terminal and re-gasification plant at Quintero near the capital city of Santiago to secure supply for its existing and upcoming gas-fired thermal plants. In addition, it had engaged in the construction of several new hydropower and coal-fired thermal plants. But by July 2020 91% of the new capacity under construction was of renewable power, 46.8% of the total solar and 25.6% wind, with most of the remainder hydro.

The electricity sector in New Zealand uses mainly renewable energy; such as hydropower, geothermal power and increasingly wind energy. As of 2019, 82% of electricity is generated from renewable sources, making New Zealand one of the countries with the lowest carbon dioxide emissions from electricity generation. Electricity demand grew by an average of 2.1% per year from 1974 to 2010 but decreased by 1.2% from 2010 to 2013.

Glanford Brigg Power Station Gas-fired power station in North Lincolnshire, England

Glanford Brigg Power Station is a gas-fired power station in North Lincolnshire, England. It is capable of firing diesel as a substitute of natural gas. It is situated on the River Ancholme, beside the Sheffield to Cleethorpes via Brigg Line, outside the town of Brigg, with its name coming from the former name for the town. It has a generating capacity of 240 megawatts (MW).

Electricity sector in the United Kingdom Overview of the electricity sector in the United Kingdom

The United Kingdom has a National Grid that covers most of mainland Great Britain and several of the surrounding islands, as well as some connectivity to other countries. The electrical sector supplies power at 50 Hz AC, and ~240 volts is supplied to consumers. In 2020 the electricity sector's grid supply came from 55% low-carbon power, 36.1% fossil fuelled power, and 8.4% imports. Renewable power is showing strong growth, while fossil fuel generator use in general and coal use in particular is shrinking, with historically dominant coal generators now mainly being run in winter due to pollution and costs, and contributed just 1.6% of the supply in 2020.

South Australia is a leader in utility-scale renewable energy generation, and also produces gas and uranium for electricity generation. Gas production is mostly concentrated in the Cooper Basin in the state's north-east. Gas is delivered from these fields by pipeline to users interstate and to Port Adelaide where it fuels three separate gas-fired power plants. Uranium is also mined in South Australia, though nuclear power generation is prohibited nationally. The Olympic Dam mine is the world's single largest known deposit of uranium and represents 30% of the world's total uranium resource. Many utility-scale wind farms and solar farms have been commissioned during the 21st century and geology with potential for geothermal energy has also been identified but is yet to be developed.

The South Australian blackout of 2016 was a widespread power outage in South Australia that occurred as a result of storm damage to electricity transmission infrastructure on 28 September 2016. The cascading failure of the electricity transmission network resulted in almost the entire state losing its electricity supply, affecting 850,000 SA customers. Kangaroo Island did not lose its supply, as the Kangaroo Island power station had been built to supply the island for the contingency of a failure in the power cable under the Backstairs Passage.

The Hornsdale Wind Farm is an electricity generator in the locality of Hornsdale in the south-west of the Narien Range, north of Jamestown, South Australia. It consists of 99 wind turbines with a generation capacity of 315 megawatts (422,000 hp). The plant is owned and operated by Neoen, a French renewable energy company.

The Lincoln Gap Wind Farm is a wind farm in the vicinity of Lincoln Gap on northeastern Eyre Peninsula in South Australia, Australia. It consists of 59 wind turbines and generates a total of 212 MW of electricity. Construction began in late 2017 and was initially expected to be commissioned in late 2018. Construction was delayed in July 2018 when unexploded ordnance was discovered on the site, left from historic military testing. The site is not far from the Cultana Training Area.

Channel Island Power Station is the largest power station in the Northern Territory of Australia. It is positioned on an island in the Middle Arm of Darwin Harbour, supplying electricity to the Darwin-Katherine Interconnected System. It is currently owned and operated by Territory Generation. Most of the island surrounding the facility is protected from development as the Channel Island Conservation Reserve.

Temporary Generation South and its larger sibling Temporary Generation North were gas turbine power stations in South Australia. They were bought by the Government of South Australia in 2017 as a response to the 2016 South Australian blackout and load-shedding in February 2017.

Nexif Energy is a Singapore-based company that owns and operates wind farms and other renewable energy projects in several countries. It is a joint venture of Nexif and Denham Capital founded in August 2015.

The Snapper Point Power Station is a gas turbine power station under development at Outer Harbor, South Australia, beside the older Pelican Point Power Station.

References

  1. 1 2 "Power generators switched on for first time as SA, Victoria suffer through heatwave". ABC News . 25 January 2019. Retrieved 30 June 2019.
  2. 1 2 Thompson, Sarah; Macdonald, Anthony; Boyd, Tim (28 March 2021). "Advisers pitch to sell Denham's Nexif as renewables run hot". Australian Financial Review . Archived from the original on 28 March 2021. Retrieved 9 June 2022.
  3. MacLennan, Leah (13 November 2017). "Generators installed at former Holden site and desal plant to reduce summer blackout risk". ABC News . Retrieved 30 June 2019.
  4. Siebert, Bension (29 August 2019). "Leasing out state-owned diesel generators will push prices down: expert". InDaily . Retrieved 30 August 2019.
  5. "NEXIF ENERGY TO PROVIDE 154MW OF RELIABLE GAS GENERATION TO THE SOUTH AUSTRALIAN POWER GRID". Nexif Energy. 28 August 2019. Retrieved 30 August 2019.
  6. Tisheva, Plamena (26 April 2022). "Nexif Energy completes 222-MW Aussie wind project, closes refinancing". Renewables Now. Retrieved 9 June 2022.