Tailem Bend Solar Power Farm

Last updated

Tailem Bend Solar Power Farm
Tailem Bend Solar cropped.jpg
Tailem Bend Solar Farm
Tailem Bend Solar Power Farm
CountryAustralia
Location Tailem Bend, South Australia
Coordinates 35°17′S139°29′E / 35.28°S 139.49°E / -35.28; 139.49
StatusOperational
Construction beganApril 2018 [1]
Commission date 30 May 2019
Construction costA$200m
Owner(s)Vena Energy (subsidiary of Global Infrastructure Partners)
Operator(s)Vena Energy
Solar farm
Type Flat-panel PV
Collectors 391,500 [2]
Site area200 hectares (490 acres)
Power generation
Nameplate capacity 95 MW (licence limit)

The Tailem Bend Solar Power Farm is a solar power farm near Tailem Bend in South Australia. It has 108MW of generation capacity but is limited to supplying 95MW to the national grid. An additional 85MW is proposed in stage 2. [3] It is developed and owned by Singapore-based Vena Energy, a new name for the former Equis Energy following acquisition by Global Infrastructure Partners in January 2018. [4] The output will be sold to Snowy Hydro for retail sale under its Lumo Energy brand. [5] Stage 2 is also expected to provide battery storage. [6]

The solar farm covers 200 hectares (490 acres) of land with more than 390,000 photovoltaic solar panels. [7] The panels are mounted on fixed-angle racks. [8] The site is a joint development between Equis and Snowy Hydro. Snowy Hydro also had plans to establish a 28MW diesel generator at the site. [9]

UGL was contracted in February 2018 to build the first stage, which was expected to be connected to the power grid in the first quarter of 2019. A second stage to generate an additional 111MW is also being planned. [10]

The Tailem Bend solar farm received its generation licence on 30 January 2019, [2] and was expected to start commissioning in February, with full production from mid-April. Its theoretical capacity is 108MW, but the licence limits it to 95MW to ensure it can deliver reactive power to the grid. The 95MW Tailem Bend solar farm began production on 4 March 2019 [11] and officially opened on 30 May 2019. [12] Vena Energy expects to proceed with the completion of stage two of the Tailem Bend solar farm, which will be similar in scale to the first stage. Vena Energy also has plans for a Tailem Bend Battery Energy Storage Project.[ needs update ] The plan for a nearby diesel generator has been dropped. [13]

Related Research Articles

Snowy Hydro Limited is an electricity generation and retailing company in Australia that owns, manages, and maintains the Snowy Mountains Hydro-electric Scheme which consists of nine hydro-electric power stations and sixteen large dams connected by 145 kilometres (90 mi) of tunnels and 80 kilometres (50 mi) of aqueducts located mainly in the Kosciuszko National Park. Snowy Hydro also owns and operates two gas-fired power stations in Victoria and one in New South Wales, three diesel power stations in South Australia and owns two electricity retailing businesses, Red Energy and Lumo Energy.

Collinsville Power Station is located in Collinsville, Whitsunday Region, Queensland, Australia. It had five coal powered steam turbines with a combined generation capacity of 190 MW of electricity. The coal-fired power station closed in 2013. A solar power farm generating 42MW has been built on adjacent land.

<span class="mw-page-title-main">Solar power in Australia</span>

Solar power is a fast-growing industry in Australia. As of December 2022, Australia's over 3.36 million solar PV installations had a combined capacity of 29,683 MW photovoltaic (PV) solar power, of which at least 3,922 MW were installed in the preceding 12 months. In 2019, 59 solar PV projects with a combined capacity of 2,881 MW were either under construction, constructed or due to start construction having reached financial closure. Solar accounted for 12.4% of Australia's total electrical energy production in 2021.

<span class="mw-page-title-main">Renewable energy in Australia</span>

Renewable energy in Australia includes wind power, hydroelectricity, solar photovoltaics, heat pumps, geothermal, wave and solar thermal energy.

<span class="mw-page-title-main">Australian Renewable Energy Agency</span> Independent agency of the Australian federal government

The Australian Renewable Energy Agency (ARENA) is an independent agency of the Australian federal government, established in 2012 to manage Australia's renewable energy programs, with the objective of increasing supply and competitiveness of Australian renewable energy sources.

<span class="mw-page-title-main">Electricity sector in Australia</span>

The Australian electricity sector has been historically dominated by coal-fired power stations, but renewables are forming a rapidly growing fraction of supply.

Kennedy Energy Park is a wind, solar and storage hybrid power station approximately 20 km south east of Hughenden and 290 km southwest of Townsville in Queensland.

Aurora Solar Thermal Power Project was a planned solar power tower solar thermal power plant to be located north of Port Augusta in South Australia. It was planned to generate 150 MW of electricity after it was completed in 2020. Storage capacity would have been up to 8 hours at full power. The facility was expected to produce 495 GWh of electricity annually. It was to be 30 kilometres (19 mi) north of Port Augusta on Carriewerloo Station.

The Bungala Solar Power Farm is a solar power farm in Emeroo and Wami Kata near Port Augusta in South Australia. The first stage was connected to the grid in May 2018, and the second stage was connected to the grid in early November 2018. The project gradually reached full power in 2020.

The Lincoln Gap Wind Farm is a wind farm in the vicinity of Lincoln Gap on northeastern Eyre Peninsula in South Australia, Australia. It consists of 59 wind turbines and generates a total of 212 MW of electricity. Construction began in late 2017 and was initially expected to be commissioned in late 2018. Construction was delayed in July 2018 when unexploded ordnance was discovered on the site, left from historic military testing. The site is not far from the Cultana Training Area.

Solar River Project is a proposed photovoltaic power station planned to be built near Robertstown in South Australia. The project received development approval from the Government of South Australia in June 2018 and was expected to start construction early in 2019. However, as of November 2021, the project was still proposed to be constructed, but work on site was not expected until at least the second half of 2022.

<span class="mw-page-title-main">Murra Warra Wind Farm</span>

The Murra Warra Wind Farm is one of Australia's largest wind farms. Located on the plains of north-western Victoria, approximately 25 kilometres (16 mi) north of the city of Horsham, it consists of 99 wind turbines with a maximum tip height of 220m.

Tasmania, as an advanced economy with a globally high standard of living, uses a great deal of energy. Distinctive features of energy use in Tasmania include the high fraction of hydroelectricity usage, the absence of coal-fired electrical generation, relatively light usage of natural gas, particularly for domestic use, and a wide use of domestic wood-burning stoves. Energy production through hydroelectricity has been politically contentious, and conflicts over Tasmanian hydroelectric projects were integral to the formation of Green parties in Australia and across the world.

Bango Wind Farm is a wind farm under construction in the Australian state of New South Wales. It is being developed by CWP Renewables between the towns of Yass and Boorowa. Construction began in August 2019.22 of the turbines have been erected and 10 of those are fully operational. It is expected to be completed late in 2021.

References

  1. "Tailem Bend Solar Project" (PDF). Tailem Topics. Tailem Bend Progress Association. September 2018. p. 20. Retrieved 18 January 2019.
  2. 1 2 "Electricity Generation Licence". Essential Services Commission of South Australia. 30 January 2019. Retrieved 4 February 2019.
  3. "New Developments". Australian Energy Market Operator. 10 May 2019. Retrieved 18 June 2019.
  4. "Equis Energy changes name to Vena Energy". Asian Power. Charlton Media Group. 4 May 2018. Retrieved 18 January 2019.
  5. Parkinson, Giles (14 February 2018). "Equis gets finance for 127MW solar farm in South Australia". RenewEconomy. Retrieved 15 February 2018.
  6. Mazengarb, Michael (30 May 2019). "Tailem Bend solar farm officially opens, now for second stage and battery" . Retrieved 18 June 2019.
  7. "Tailem Bend Solar Farm". Aussie Renewables. Retrieved 15 February 2018.
  8. Jacobs Group (23 December 2016). "Tailem Bend Solar Project" (PDF). Development application. Government of South Australia. Retrieved 15 February 2018.
  9. "Tailem Bend solar farm will boost Lumo Energy push into SA market". ABC News. 8 February 2017. Retrieved 15 February 2018.
  10. Strathearn, Peri (20 February 2018). "Tailem Bend solar power plant: Equis Energy contracts UGL to build $200 million facility". Murray Valley Standard . Fairfax Regional Media . Retrieved 20 February 2018.
  11. Vorrath, Sophie (4 March 2019). "South Australia's second biggest solar farm begins production". RenewEconomy. Retrieved 4 August 2019.
  12. Mazengarb, Michael (29 May 2019). "Tailem Bend solar farm officially opens, now for second stage and battery". RenewEconomy. Retrieved 4 August 2019.
  13. Parkinson, Giles (4 February 2019). "South Australia's second big solar farm gets generation licence, to start production". Renew Economy. Retrieved 4 February 2019.