Bujagali Hydroelectric Power Station

Last updated

Bujagali Dam
Bujagali detail.jpg
River Nile, 5 km (3 mi) downstream of Bujagali Dam.
Uganda location map.svg
Red pog.svg
Location of Bujagali Power Station
Placement on map is approximate
Africa location map.svg
Red pog.svg
Bujagali Hydroelectric Power Station (Africa)
World location map (equirectangular 180).svg
Red pog.svg
Bujagali Hydroelectric Power Station (Earth)
Location Bujagali, Uganda
Coordinates 00°29′54″N33°08′15″E / 0.49833°N 33.13750°E / 0.49833; 33.13750
Construction began2007
Opening date2012
Construction costUS$862 million
Dam and spillways
Type of dam Gravity dam
Impounds Victoria Nile
Power Station
Commission date2012 [1]
Turbines 5
Installed capacity 250 MW (340,000 hp)
Annual generation 1,100 GWh

The Bujagali Power Station is a hydroelectric power station across the Victoria Nile that harnesses the energy of its namesake; the Bujagali Falls, in Uganda. Construction began in 2007 and concluded in 2012. It was officially inaugurated on 8 October 2012 by Ugandan President Yoweri Museveni and Aga Khan IV in the presence of African politicians and investors. [1]

Contents

The capacity of the power station is 250 megawatts. The station was the largest hydroelectric energy source in Uganda, at the time it was commissioned. However, the planned Karuma and Ayago power stations would be larger. The funding for the station was a source of some concern, as investors joined and departed from the project. As of July 2014, the plant was managed by Bujagali Energy Limited, which selected Italian contractor Salini Impregilo to develop the project. [2]

Location

The power station lies across the Victoria Nile, about 15.5 kilometres (10 mi) north-west of the central business district of the city of Jinja and immediately north of the former location of the Bujagali Falls. [3] It is at the border between Buikwe District to the west and Jinja District to the east. The coordinates of Bujagali Power Station are 0° 29'54.00"N, 33° 08' 15.00"E (latitude:0.498325; longitude:33.137500). [4]

History

As far back as 2001, the government of Uganda started to plan the construction of a hydroelectric power plant at Bujagali Falls. The original developers included AES Energy from the United States and the Madhvani Group from Uganda. In the midst of fraud investigations, [5] the first project was abandoned in 2003 when AES Energy pulled out of the deal, citing a protracted process because of objections from environmentalists. [6] [7] The project was delayed due to protracted negotiations between investors and representatives of the Soga cult of the water spirit Budhagaali, whose main shrines were seen as inextricably linked to the strength of the waterfall. Ultimately agreement was reached between the parties. [8]

A new consortium, Bujagali Energy Limited, was created by Sithe Global Power LLC, from the United States, and Industrial Promotion Services, a division of the Aga Khan Fund for Economic Development, and was tasked with developing the project. [9] Construction of the dam and powerhouse started in June 2007. Salini Impregilo was selected to be the lead contractor. [10] The power station began commercial operations on 1 August 2012. [7] At the peak of construction activity, the project employed over 2,500 people, including about 2,200 Ugandan nationals. [11]

Ownership

As of September 2016, the shareholders in Bujagali Energy Limited were as outlined in this reference. [12] In May 2018, the Daily Nation newspaper reported that Jubilee Holdings Limited was set to invest an additional KSh4.4 billion (US$44 million) in the business, in addition to the KSh5.5 billion (US$55 million) that it had already invested. [13]

Shareholding In Bujagali Energy Limited In 2016
RankName of OwnerPercentage Ownership
1 Jubilee Investment Company [14]
2 Government of Uganda [12]
3 Sithe Global Power 65.0 [12]
4 Industrial Promotion Services [12]
5 Aga Khan Fund for Economic Development [12]
Total100.0

In mid-2018, SN Power (today Scatec) of Norway acquired the shareholding previously owned by Sithe Global Power of the United States. The acquisition of that shareholding, held through an SPV called SG Bujagali Holdings Limited (SGBH), was completed by 1 August 2018. [15] [16]

The ownership of the power station as of August 2018 is as illustrated in the table below. [15] [16]

Shareholding In Bujagali Energy Limited In 2018
RankName of OwnerPercentage Ownership
1 Jubilee Investment Company [14]
2 Government of Uganda [12]
3 SN Power (today Scatec) [15] [16] 65.0 [12]
4 Industrial Promotion Services [12]
5 Aga Khan Fund for Economic Development [12]
Total100.0

Construction costs

The estimated costs for the dam and power plant was US$800 million. Another $62 million was spent on building a high voltage transmission line from Jinja to Kawanda, near Kampala, a distance of about 80 kilometres (50 mi). Bujagali Energy Limited invested approximately US$190 million of its own money into the project. The rest of the funds were borrowed from the following international lenders: [17]

  1. International Finance Corporation (IFC), a member of the World Bank Group
  2. African Development Bank
  3. European Investment Bank
  4. German Investment Corporation
  5. KfW
  6. PROPARCO of France
  7. French Development Agency
  8. Netherlands Development Finance Company
  9. Absa Group Limited
  10. BNP Paribas
  11. Nedbank
  12. Standard Chartered Bank

In March 2018, the Board of Directors of IFC and MIGA approved plans to refinance in excess of US$400 million in construction debt owed by Bujagali Energy Limited, the project SPV. The approval includes US$423 million in guarantees, in support of the project. The refinancing will extend the tenor of the existing loans made in 2007, by the lenders listed above. This, along with tax waivers from the Ugandan government, will lower the cost of electricity to the consumer and stimulate economic growth in the country, where only 26 percent of the population (8 percent in rural areas) had access to grid-electricity at that time. [18]

Completion date

The project was completed in 2012, although partial power generation started in 2011. [19]

In April 2010, The EastAfrican , a Kenyan weekly publication, indicated that the opening of the dam would be phased, one unit at a time. [20] On 2 February 2012, Ugandan newspapers reported the commissioning of the first turbine of the power station. [21] In May 2012, the third 50 megawatt turbine was commissioned, bringing output to 150 megawatts. [22] On 15 June 2012, Ugandan press reports indicated that the fourth and fifth turbines had come online, bringing total output to 250 megawatts. The plant officially began commercial operation on 1 August 2012. [23] [24]

On 8 October 2012, the project was officially inaugurated by Ugandan President Yoweri Museveni and Aga Khan IV in the presence of African politicians and investors. [25]

The cost of power

As of October 2016, the dam's utilization rate was approximately 70 percent. The power generated cost the end user about US$0.11/kilowatt-hour, which was the highest rate in the East African Community. [26] In September 2016, the government of Uganda began negotiations with equity partners and lenders to restructure the financing of the dam to reduce the cost to the end-user to about US$0.072/kilowatt-hours. [26]

See also

Related Research Articles

<span class="mw-page-title-main">Jinja, Uganda</span> Place in Eastern Region, Uganda

Jinja is a city in the Eastern Region of Uganda, located on the north shore of Lake Victoria.

<span class="mw-page-title-main">Nalubaale Hydroelectric Power Station</span> Dam in Jinja

Nalubaale Power Station, formerly known as Owen Falls Dam, is a hydroelectric power station across the White Nile near its source at Lake Victoria in Uganda. Nalubaale is the Luganda name for Lake Victoria.

<span class="mw-page-title-main">Owen Falls</span> Waterfall in Uganda

The Owen Falls was a waterfall on the White Nile in Uganda near the city of Jinja. The falls, together with the nearby Ripon Falls, were submerged in 1954 with the completion of the Nalubaale Hydroelectric Power Station. The dam that houses the power station was originally named Owen Falls Dam, but was later renamed Nalubaale Dam and the name of the power station was also changed, from Owen Falls Power Station to Nalubaale Power Station.

<span class="mw-page-title-main">Energy in Uganda</span>

Burning of renewable resources provides approximately 90 percent of the energy in Uganda, though the government is attempting to become energy self-sufficient. While much of the hydroelectric potential of the country is untapped, the government decision to expedite the creation of domestic petroleum capacity coupled with the discovery of large petroleum reserves holds the promise of a significant change in Uganda's status as an energy-importing country.

<span class="mw-page-title-main">Ministry of Energy and Mineral Development (Uganda)</span>

The Ministry of Energy and Mineral Development, also Ministry of Energy, Oil and Mineral Development is one of the governmental bodies of Uganda. The ministry has the function of developing and implementing policies related to electricity, minerals, petroleum and petroleum products. The ministry is part of the national cabinet and is headed by a cabinet minister. The current Cabinet Minister of Energy is [Hon. Ruth Ssentamu Nankabirwa].

Umeme Limited is the largest energy distributor in Uganda, distributing about 97 percent of all electricity used in the country. The shares of the stock of the company are listed on the Uganda Securities Exchange (USE) and are cross listed on the Nairobi Stock Exchange (NSE). As of December 2021, the company's total assets were approximately UGX:2.664 trillion, with shareholders' equity of approximately UGX:893.15 billion.

<span class="mw-page-title-main">Kiira Hydroelectric Power Station</span> Power station in Uganda

Kiira Hydroelectric Power Station, is a hydroelectric power station in Uganda, with an installed capacity of 200 megawatts (270,000 hp).

Nyagak Power Station is a 3.5 megawatts (4,700 hp) mini hydroelectric power plant in Uganda.

The Karuma Hydroelectric Power Station is a 600 MW hydroelectric power project under construction in Uganda. When completed, it will be the largest power-generating installation in the country.

Isimba Hydroelectric Power Station is a 183.2 megawatts (245,700 hp) hydroelectric power station commissioned on 21 March 2019 in Uganda. Construction of this dam began in April 2015 and was completed in January 2019. Commercial operations began on 21 March 2019.

<span class="mw-page-title-main">Source of the Nile Bridge</span> Bridge in Uganda

The Source of the Nile Bridge, also New Jinja Bridge, which was commissioned on 17 October 2018, by the President of Uganda, is a cable-stayed bridge across the Victoria Nile in Uganda. It replaced the Nalubaale Bridge, which was built in 1954.

The Muzizi Power Station is a proposed 45 megawatts (60,000 hp) hydroelectric power project in Uganda. The project, which has been planned for several years, has received a funding commitment from KfW and the French Development Agency.

Ayago Hydroelectric Power Station, also Ayago Power Station, is a planned 840 megawatt hydroelectric power project to be constructed in Uganda. If it is built, Ayago would be the largest power station in Uganda, based on generating capacity.

Kikagati Hydroelectric Power Station, also referred to as Kikagati Power Station, is a 15.57 MW (20,880 hp) hydroelectric power station, in Uganda.

Nyagak III Power Station is a 6.6 megawatts (8,900 hp) mini hydroelectric power project, under construction in Uganda, the third-largest economy in the East African Community.

Rwimi Hydroelectric Power Station, also Rwimi Power Station, is an operational 5.54 megawatts (7,430 hp) hydroelectric power station in the Western Region of Uganda.

Bujagali Energy Limited (BEL), is an electric energy generating company in Uganda. The company owns and operates the Bujagali Power Station, which was the largest hydropower plant in the country as of July 2014.

The Uganda Electricity Generation Company Limited (UEGCL) is a parastatal company whose primary purpose is to generate electric power for use in Uganda and for sale to neighboring countries. As of December 2017, UEGCL's generation capacity was 380 megawatts, with that capacity planned to increase to over 1,300 megawatts, by 2023.

Kiba Hydroelectric Power Station is a proposed 295 megawatts (396,000 hp) hydroelectric power station in Uganda.

References

  1. 1 2 New Vision (8 October 2012). "Museveni Commissions Bujagali Dam". New Vision . Retrieved 22 April 2014.
  2. Environmental Justice Atlas (18 December 2015). "Bujagali hydropower project, Uganda". Barcelona, Spain: Environmental Justice Atlas. Retrieved 3 August 2020.
  3. Google (3 August 2020). "Distance Between Downtown Jinja And Bujagali Hydroelectric Power Station" (Map). Google Maps . Google. Retrieved 3 August 2020.
  4. Google (3 August 2020). "Location of Bujagali Hydroelectric Power Station" (Map). Google Maps . Google. Retrieved 3 August 2020.
  5. Pallister, David (3 November 2003). "Africa Dam's Passage 'Eased by Bribes'". The Guardian . Retrieved 22 April 2014.
  6. Lilley, Sasha (28 August 2003). "AES Backs Out of Bujagali Dam Project". CorpWatch. Archived from the original on 17 June 2017. Retrieved 22 April 2014.
  7. 1 2 Kasita, Ibrahim (7 October 2012). "Evolution of the 250MW Bujagali Dam". New Vision . Kampala. Retrieved 7 March 2015.
  8. Reid, Richard (2017). A History of Modern Uganda. United Kingdom: Cambridge University Press. pp. 287–288. ISBN   978-1-107-06720-2.
  9. "About Bujagali Energy Limited". Bujagali Energy Limited. Archived from the original on 23 August 2014. Retrieved 22 April 2014.
  10. "Bujagali Falls Hydropower Dam, Jinja, Uganda". Power Technology. Retrieved 22 April 2014.
  11. Mugabi, Frank (1 April 2015). "Bujagali Dam Near Completion". New Vision . Kampala. Archived from the original on 23 February 2020. Retrieved 14 November 2018.
  12. 1 2 3 4 5 6 7 8 9 Daniel Kalinaki (4 September 2016). "Uganda urges Bujagali investors to take haircut on project to reduce power costs". The EastAfrican . Nairobi. Retrieved 1 June 2018.
  13. John Mutua (31 May 2018). "Jubilee Holdings to pump Sh4.4bn into Bujagali power plant". Daily Nation . Nairobi. Retrieved 1 June 2018.
  14. 1 2 Juma, Victor (23 May 2014). "Jubilee Wins 30-Year Pact to Operate Bujagali". Daily Monitor . Retrieved 1 June 2018.
  15. 1 2 3 Water Power Magazine (19 April 2016). "SN Power to buy SGBH's stake in Bujagali HPP". WaterPowerMagazine.com. London, United Kingdom. Retrieved 1 May 2022.
  16. 1 2 3 Jean Marie Takouleu (1 August 2018). "Uganda: SN Power acquires SGBH's shares in the Bujagali power plant". Afrik21.africa. Paris, France.
  17. Daily Monitor Reporter (12 April 2011). "Nile Diverted Through Bujagali Powerhouse". Daily Monitor . Kampala. Retrieved 22 April 2014.
  18. Press Release (8 March 2018). "IFC and MIGA Boards Support Bujagali Refinancing Package to Reduce Ugandan Electricity Costs". Washington, DC: International Finance Corporation. Archived from the original on 23 February 2020. Retrieved 1 June 2018.
  19. "Uganda Infrastructure Report Q1:2010". Companies and Markets. Archived from the original on 5 October 2011. Retrieved 22 April 2014.
  20. Barigaba, Julius (12 April 2010). "Bujagali Power Project To Come On Stream Unit By Unit In 2011". Nairobi: The EastAfrican . Retrieved 5 May 2014.
  21. Walubiri, Moses (2 February 2012). "Bujagali Dam Opens Today". New Vision . Retrieved 4 May 2014.
  22. Kakamwa, Charles (1 June 2012). "Vice President Commissions Third Bujagali Dam Unit". Kampala: New Vision . Retrieved 5 May 2014.
  23. "Bujagali: Powering Uganda From The Nile" (PDF). International Water Power & Dam Construction. March 2013. Archived from the original (PDF) on 22 October 2013. Retrieved 5 May 2014.
  24. Ketchum, Ryan (1 November 2012). "Developing Bujagali, the Largest Private Sector Investment in Uganda". Hydroworld.com. Retrieved 31 May 2016.
  25. "7 Largest Hydropower Stations in Uganda". World Energy. Archived from the original on 17 July 2020. Retrieved 16 July 2020.
  26. 1 2 Daniel K. Kalinaki (16 October 2016). "Uganda to extend Bujagali tax breaks beyond mid-2017 over high power tariffs". The EastAfrican . Nairobi. Retrieved 16 October 2016.