The Clarence Railway was an early railway company that operated in north-east England between 1833 and 1853. The railway was built to take coal from mines in County Durham to ports on the River Tees and was a competitor to the Stockton and Darlington Railway (S&DR). It suffered financial difficulty soon after it opened because traffic was low and the S&DR charged a high rate for transporting coal to the Clarence, and the company was managed by the Exchequer Loan Commissioners after July 1834. An extension of the Byers Green branch was opened in 1839 by the independent West Durham Railway to serve collieries in Weardale.

Contents

The Stockton and Hartlepool Railway opened in 1841 to connect the Clarence to Hartlepool Docks and the Hartlepool West Harbour & Dock opened in West Hartlepool in 1844. On 17 May 1853 the Clarence Railway, Hartlepool West Harbour & Dock and Stockton and Hartlepool Railway were merged to become the West Hartlepool Harbour and Railway. The West Hartlepool Harbour and Railway became part of the North Eastern Railway in 1865.

The line from Ferryhill to Stockton has been identified by Campaign for a Better Transport as a priority 1 candidate for reopening. [1]

History

Clarence Railway
BSicon CONTg.svg
BSicon exCONTg.svg
Bishop Auckland
BSicon BHF-xL.svg
BSicon exBHF-R.svg
BSicon eKRWg+l.svg
BSicon exKRWr.svg
BSicon exCONTgq.svg
BSicon eABZgr.svg
BSicon exCONTg.svg
West Durham Railway
to Collieries
BSicon eABZg2.svg
BSicon exSTRc3.svg
BSicon exHST.svg
Byers Green (2nd station)
Coundon
BSicon exSTRc1.svg
BSicon STR.svg
BSicon exHST2+4.svg
BSicon exSTRc3.svg
BSicon exHST.svg
Byers Green (1st station)
Byers Green (3rd station)
BSicon STR.svg
BSicon exSTRc1.svg
BSicon exHST2+4.svg
BSicon exSTRc3.svg
BSicon GRZq.svg
BSicon exSTR.svg
Shildon Tunnel
BSicon TUNNEL1.svg
BSicon exSTRc1.svg
BSicon vGRZ-.svg
BSicon exABZg+4.svg
NER extension │Clarence Railway
Shildon
BSicon HST.svg
BSicon exABZg+l.svg
BSicon exCONTfq.svg
Page Bank Branch
to Collieries
Stockton & Darlington Railway
to Brussleton Lane & Collieries
BSicon exCONTgq.svg
BSicon lENDE@Gq.svg
BSicon ABZg+r.svg
BSicon exHST.svg
Spennymoor
Shildon Sidings
BSicon eDST.svg
BSicon exABZgl.svg
BSicon exKBSTeq.svg
Tudhoe Iron Works
BSicon STR.svg
BSicon exCONTgq.svg
BSicon exABZg+r.svg
Binchester Colliery Railway
to Binchester Colliery
Newton Aycliffe
BSicon pHST.svg
BSicon exABZg+l.svg
BSicon exKBSTeq.svg
East Howle Colliery
BSicon CONTgq.svg
BSicon lGRZ3+1.svg
BSicon xABZgr.svg
BSicon exSTR.svg
Simpasture
BSicon exKHSTaq.svg
BSicon exABZgr.svg
BSicon exSTR.svg
BSicon CONTg.svg
Authorised Deanery Branch
to Shildon (not built)
BSicon exABZg+Ll.svg
BSicon exLCONTfq.svg
BSicon exSTR.svg
BSicon STR.svg
BSicon exSTRc2.svg
BSicon exCONT3.svg
Demons Bridge
BSicon exKHSTaq.svg
BSicon exABZg+r.svg
BSicon exSTR.svg
BSicon exSTRc2.svg
BSicon STR.svg
BSicon exSTR3+1.svg
BSicon exLLSTR3+l.svg
BSicon exSTRc4.svg
BSicon exLCONTfq.svg
Authorised Durham Branch
to Durham (not built)
Coxhoe
BSicon exSTR.svg
BSicon exABZg2.svg
BSicon exSTRc3.svg
BSicon lhSTRc3a.svg
BSicon STRc2.svg
BSicon ABZg3.svg
BSicon exABZ+1l.svg
BSicon exKHSTeq.svg
BSicon exSTRc4.svg
BSicon exLSTRq.svg
BSicon exLCONTfq.svg
Authorised Sherburn Branch
to Sherburn (not built)
BSicon exSTR.svg
BSicon exSTRc1.svg
BSicon STRc2.svg
BSicon lhSTRc1a.svg
BSicon exSTR.svg
BSicon xhKRX.svg
BSicon exUWu3.svg
BSicon STRc4.svg
BSicon xABZg3.svg
BSicon exSTR.svg
BSicon STRc2.svg
BSicon STRc2.svg
BSicon xKRZ3+1o.svg
BSicon exUWu1.svg
BSicon STRc4.svg
BSicon ABZ3+1xl.svg
BSicon exSTR.svg
BSicon exABZ+4r.svg
BSicon exSTR.svg
BSicon v-STR+1.svg
BSicon vSTR+1-.svg
BSicon STRc4.svg
BSicon exSHI1r.svg
BSicon STRc4.svg
BSicon exCONTf.svg
BSicon exWBRUCKE1.svg
BSicon WASSER+r.svg
BSicon exlv-BHF-L.svg
BSicon v-STR.svg
BSicon exlvBHF-R-.svg
BSicon vSTR-.svg
Ferryhill
BSicon CONTgq.svg
BSicon xKRZo.svg
BSicon LSTRq.svg
BSicon LWASSER.svg
BSicon v-STRr.svg
BSicon STRq.svg
BSicon SHI1+r.svg
BSicon vSTRr-.svg
Chilton Branch
to Collieries
BSicon exSTR.svg
BSicon LWASSER.svg
BSicon exCONTgq.svg
BSicon eABZg+r.svg
BSicon exSTR2.svg
BSicon exSTRc3.svg
BSicon WASSER2.svg
BSicon WSTRc3.svg
BSicon eABZg+l.svg
BSicon exCONTfq.svg
Fishburn Branch
to Fishburn Colliery
BSicon exSTRc1.svg
BSicon exSTR2+4.svg
BSicon WSTRc1.svg
BSicon exSTRc3.svg
BSicon WASSERl+4.svg
BSicon WBRUCKE1.svg
BSicon exSTRc1.svg
BSicon exSTR2+4.svg
BSicon exSTRc3.svg
BSicon eHST.svg
Sedgefield
BSicon exSTRc1.svg
BSicon eABZg+4.svg
Stillington Junction
BSicon eHST.svg
Stillington
BSicon eABZg+l.svg
BSicon exKBSTeq.svg
Carlton Iron Works
BSicon eHST.svg
Redmarshall
BSicon ekABZg3.svg
BSicon exCONTgq.svg
BSicon exkABZq1.svg
BSicon exkSTRc4.svg
BSicon exkSTRc2.svg
BSicon eKRZu.svg
BSicon exkABZq+3.svg
BSicon exCONTfq.svg
BSicon ekABZg+1.svg
Norton Junction
BSicon STRc2.svg
BSicon exlvHST@F-.svg
BSicon ABZ23.svg
BSicon STRc3.svg
BSicon STRc2.svg
BSicon ABZ3+1l.svg
BSicon STRc1.svg
BSicon STRc4.svg
BSicon STRq.svg
BSicon ABZ2+4r.svg
BSicon STRc3.svg
BSicon STR+1.svg
BSicon STRc4.svg
BSicon STRc1.svg
BSicon eHST+4.svg
Norton-on-Tees
BSicon v-GRZ.svg
BSicon e3ABZg+1.svg
BSicon ex3STRq-.svg
BSicon ex3STR+4.svg
BSicon eHST.svg
Billingham-on-Tees
BSicon STRc2.svg
BSicon vGRZ-.svg
BSicon xABZg3.svg
BSicon exLSTR.svg
BSicon ABZgl.svg
BSicon CONTfq.svg
North Stockton
BSicon STRc2.svg
BSicon BHF3+1.svg
BSicon STRc4.svg
BSicon exSTR.svg
BSicon exLSTR.svg
BSicon eHST.svg
Belasis Lane
BSicon CONT1.svg
BSicon STRc4.svg
BSicon exBHF.svg
BSicon exLSTR.svg
BSicon STR.svg
Stockton (Clarence)
BSicon exKBSTe.svg
BSicon exkSTR2.svg
BSicon KBSTaq.svg
BSicon ABZgr.svg
BSicon WASSERq.svg
BSicon WASSERq.svg
BSicon WASSERq.svg
BSicon exkSTRc1.svg
BSicon WASSER2+r.svg
BSicon exkSTRl+4.svg
BSicon WSTRc3.svg
BSicon vGRZ-.svg
BSicon eABZgr+r.svg
NER branch │Clarence Railway
BSicon WSTRc1.svg
BSicon WASSER+4.svg
BSicon eHST.svg
Haverton Hill
BSicon exBS2c2.svg
BSicon WASSER.svg
BSicon eSHI2gr.svg
Port Clarence
BSicon exKSTRe~L.svg
BSicon exlHST~L.svg
BSicon WASSER.svg
BSicon exKSTRe~R.svg
BSicon exlHST~R.svg
BSicon STR.svg
BSicon eKBSTa.svg
ConocoPhillips Oil Refinery
BSicon WASSER.svg
BSicon v-GRZ.svg
BSicon ABZgl.svg
BSicon ABZqr+l.svg
BSicon ENDEeq.svg
Clarence RailwayNER extension
Port Clarence Sidings
BSicon WASSER.svg
BSicon KBSTe.svg
BSicon STR.svg
BSicon WDOCKSa.svg
BSicon KBSTaq.svg
BSicon ABZglr.svg
BSicon KBSTeq.svg
BSicon WDOCKSm.svg
BSicon WDOCKSc3.svg
BSicon KBSTe.svg
Seal Sands Oil Terminal
BSicon WDOCKSlf.svg
BSicon WDOCKSm.svg
BSicon WDOCKSm.svg
BSicon WDOCKSm.svg

Origins

Founder's share of Clarence Railway Company, issued 23 May 1828 in Stockton Clarence Railway 1828.jpg
Founder's share of Clarence Railway Company, issued 23 May 1828 in Stockton

The S&DR opened in 1825 linking Stockton-on-Tees with the coal fields in the Shildon area via Darlington, [2] although a more direct, northerly route to Stockton had support in that town. [3] The promoters of a competing Tees and Weardale Railway, supported by Christopher Tennant, petitioned Parliament in 1823 for permission for a railway from the coal field south of Durham to the River Tees to allow onward transport by sea. [4] This application failed as the standing orders had not been complied with, [5] and another in 1824 failed, partly due to opposition to use of steam locomotives. [6] By 1826 the S&DR had outgrown the port in Stockton and initially a port was proposed on the north bank of the Tees near Haverton Hill, but a branch to Middlesbrough on the south bank was proposed at a meeting in July 1827, and this was ratified by the shareholders that October. [7]

A map of the Clarence Railway in 1835 Clarence Railway Map.svg
A map of the Clarence Railway in 1835

The Tees & Weardale promoters developed a new scheme to transport coal to Haverton Hill: a main line that formed a junction the S&DR at Simpasture, a branch to the Deanery estate and a branch to Stockton that would provide a shorter route than the S&DR. This route didn't go into Weardale, so it was named Clarence Railway after the Duke of Clarence, later King William IV. [8] The line was surveyed by Tennant with Edward Steel, an early assistant of Stephenson, the railway was supported by a town meeting in Stockton, and Henry Blanshard leased Coxhoe colliery for a high price from the Hale sisters, on condition they use their family's influence to promote the railway. [9]

The Clarence Railway Act received Royal Assent on 23 May 1828, [10] for a 26-mile-73-chain (43.3 km) line from Haverton Hill to Simpasture with three branches, one to the Deanery estate near Bishop Auckland, another to Broom Hill, 2 miles (3.2 km) north of Ferryhill and a third to Stockton. [11] The route was surveyed again, this time by George Leather, who suggested different route that was straighter and with better gradients. Samphire Batts replaced Haverton Hill as the terminus, as this would allow loaded ships in the docks at low water. Branches were planned to Sherburn via Coxhoe, Durham via Shincliffe, Byers Green and to the S&DR at West Auckland, [12] although this last branch was not in the bill put before Parliament. [13] Opposed by the S&DR and also the Marquis of Londonderry, who was building a port at Seaham and planning a railway to the pits at Rainton (near Houghton le Spring), the second Clarence Railway Act received royal assent on 1 June 1829. The new railway was 45 miles 23 chains (72.9 km) long; the main line to Samphire Batts was now 15 miles (24 km) long, the City of Durham branch was 13 miles (21 km), and there were four other branches to Stockton, Deanery, Sherburn and Byers Green. [14] Due to the objection of Robert Surtees of Mainsforth, locomotives were not permitted on parts of the Byers Green and City of Durham branches. [15]

Opening and early operation

Further Acts in 1832 and 1833 allowed for two more branches and the Durham branch to be cut short at Shincliffe. [10] Construction involved heavy earthworks, such a 67-foot (20 m) deep cutting through solid rock near Ferryhill and a 75-foot (23 m) high embankment at Whitton or Bishopton Beck. With the main line built between Simpasture and Samphire Batts, the Stockton branch complete, the Durham branch ready as far as Thrislington and the Sherburn branch as far as Quarrington, the company needed to earn some income. It started carrying coal on its main line in August 1833, and in a year had reduced the traffic over the S&DR to Stockton from over 26,000 tons to under 9,500 tons. [16] In October 1833, the Clarence started shipping coal for export, but the S&DR continued to charge the landsale rate, rather than the lower export rate. [17]

The drops at Port Clarence Port Clarence drop (crop).jpg
The drops at Port Clarence

In January 1834 the railway opened as far as Quarrington on the Sherburn branch and a staith was opened at Haverton Hill; Port Clarence opened at Samphire Batts a few months later. Traffic was low and in financial difficulty the company asked the Exchequer Loan Commissioners to take over management in July, and the line was managed from London. [18] A branch to Chilton Pit was authorised in 1833 and opened in 1835 and the Byers Green branch opened on 31 March 1837; the City of Durham branch was not built north of Ferryhill, and nor was the Deanery branch. [19] [20] The line was mainly double track, originally laid with 38 pounds per yard (19 kg/m) rails, but later heavier ones weighing 44–45 lb/yd (22–22 kg/m) were used; trains ran on the right. [21] Horses were used exclusively until 1835, when a colliery owner began trains using his locomotives after having obtained permission from Surtees; the Clarence Railway used them from the following year. [22] A passenger service was operated over the Clarence Railway between Stockton and Coxhoe from January 1836, initially by a contractor using horse-drawn coaches. A service using steam locomotives hauling two carriages began in June 1838, a new contractor providing the carriages and two locomotives, Victoria and Norton. The three services a day ran the 16+14 miles (26.2 km) at an average speed of 18 miles per hour (29 km/h); the fare was 2s outside and 2s 6d inside; a horse omnibus provided a connecting service between Coxhoe and Durham.

Locomotives

In 1839 the Clarence owned twelve locomotives for hauling mineral trains; these travelled at 8 miles per hour (13 km/h). [23] [24] By 1840, locomotives included:

NumberNameWheelsBuilderDate introducedComments
Victoria ? ?1838
Norton ? ?1838
Coxhoe 0-6-0 Timothy Hackworth 1840 [25]
Evenwood0-6-0Timothy Hackworth1840 [26]

West Durham Railway

Plans for a South Durham Railway, connecting the Clarence Railway's Byers Green branch with the collieries in Weardale, was presented to Parliament in 1836, but the bill failed in the House of Lords [27] and amended plans failed again the following year. [28] In March 1837 some wagons of coal were drawn by horse on temporary track laid on the Byers Green branch to allow the Clarence Railway to show the line had been opened within the limit of time specified in its Act; the branch was only fully open in 1841. [29] Work started on the West Durham Railway (WDR) in 1837, effectively an extension of the Byers Green branch to Willington Colliery; an Act for the line received royal assent on 4 July 1839.

A 2+14 miles (3.6 km) section of line had opened on 12 June, although coal was not carried until 19 October, as before then locomotives were unable to be used on the Byers Green branch. From Byers Green a stationary engine was used to haul loaded wagon up a 58 mile (1.0 km) incline, the River Wear was crossed by a 206 feet (63 m) bridge and there were two more inclines before the terminus. [30] [31] The line was primarily for minerals, although there was a Saturday market-day train to Stockton; [32] in 1854 this was still horse-drawn to Ferryhill, a dandy cart was used by the horse after it started the train at Byers Green. [33]

Stockton and Hartlepool Railway

Christopher Tennant, who had moved to Hartlepool, backed the Hartlepool Dock & Railway (HD&R) and this was given permission on 1 June 1832 for a line from the coal miles in central Durham to a port at Hartlepool. With a 14-mile (23 km) main line, 9+14 miles (14.9 km) of branch and 65 acres (26 ha) of land set aside for the docks, [34] trains ran between Thornley pit and Castle Eden after January 1835, Hartlepool dock opened that July and on 23 November the first train ran the 12+14 miles (19.7 km) between Haswell and Hartlepool. By the end of that year there was 14+12 miles (23.3 km) of line operational. [35]

Throston Engine House was built to haul wagons from the Stockton and Hartlepool to the staiths at the docks Throston Engine House, Hartlepool - geograph.org.uk - 1609851.jpg
Throston Engine House was built to haul wagons from the Stockton and Hartlepool to the staiths at the docks

In 1837 the Great North of England, Clarence & Hartlepool Junction Railway (GNEC&HJR) obtained permission for a line connecting the HD&R with the Byers Green branch, thus giving access to Hartlepool Dock bypassing Stockton. The Stockton and Hartlepool Railway was built to keep the traffic on the Clarence by building a branch from Billingham to Hartlepool. [28] Work started in 1839, without an Act of Parliament, and the line officially opened to passengers on 9 February 1841, although freight had travelled earlier. [lower-alpha 1] At Hartlepool an HD&R locomotive took trains forward to a 14 feet (4.3 m) inclined plane to a new Victoria Dock. [37] The S&HR was incorporated by an Act that received Royal Assent on 30 June 1842. [38]

The WDR closed for some weeks at the beginning of 1842 as it was short of money. This had an adverse effect on the revenues of the Clarence, the Exchequer Loan Commissioners taking possession of the railway that September, to sell it by public auction, although the debt was paid by raised by issuing and selling more shares. [39] The Stockton and Hartlepool Railway leased the Clarence Railway for 21 years from 2 September 1844, and the Clarence paid its first dividend, of 1+12 per cent, in 1845. [40] [41]

To prevent traffic being diverted over the shorter GNEC&HJR to Hartlepool, the WDR was linked to the Clarence Railway by 97 yards (89 m) line over private land; as this was not limited by Act and the Clarence was able to change whatever toll it wished. The GNEC&HJR also found it lacked permission in its Act of 1837 to cross the Clarence to reach the Byers Green. Unable to come to an agreement it returned to Parliament in 1843, where the GNEC&HJR was able to fix a toll for traffic on the short private line and gain permission to build a bridge over the line. However, the Clarence Railway still refused to co-operate building a bridge over the line and it was 1846 before the railway was completed. [42] [41]

Hartlepool West Harbour & Dock

The Clarence, Stockton and Hartlepool and West Durham Railways highlighted on an 1854 railway map Map of West Hartlepool Docks and Railway.svg
The Clarence, Stockton and Hartlepool and West Durham Railways highlighted on an 1854 railway map

The Hartlepool West Harbour & Dock received permission on 23 May 1844, [43] and this opened on the Stranton shore on 1 June 1847. [44] Port Clarence suffered as traffic was being diverted to Hartlepool and the relationship between the S&HR and the Clarence Railway became strained. Some Clarence shareholders suggested a merger with the Stockton and Darlington Railway. Tennant had died in 1839; [45] Ralph Ward Jackson had backed the S&HR and Hartlepool West Harbour & Dock [46] and now negotiated a permanent lease of the Clarence from 1 January 1851. The Hartlepool West Harbour and Stockton and Hartlepool Railway were united from 1 July 1851. [47] By an Act given Royal Assent on 30 June 1852, the Clarence Railway, Hartlepool West Harbour & Dock and Stockton and Hartlepool Railway were merged to become the West Hartlepool Harbour and Railway on 17 May 1853; [48] Clarence Railway shareholders held the majority of the shares with voting rights. [49]

West Hartlepool Harbour and Railway

In 1852, the Leeds Northern Railway (LNR) reached Stockton and formed a junction with the Clarence Railway Stockton branch; an alliance had been formed and in anticipation the West Harbour had been enlarged from 13 to 44 acres (5.3 to 17.8 ha). [50] From the following year the West Hartlepool moved services to the LNR Stockton station and this became known as North Stockton, the 1848 S&DR station becoming South Stockton. [51] A price war broke out between the LNR and York, Newcastle and Berwick Railway (YN&BR), the fare for the 238 miles (383 km) between Leeds and Newcastle dropping to two shillings. [lower-alpha 2] [53]

The West Hartlepool Harbour and Dock as it opened in 1847 Harbour and Dock, West Hartlepool in 1847.jpg
The West Hartlepool Harbour and Dock as it opened in 1847

In 1862, the WHH&R was in financial difficulty, and as a result of legal action it was discovered that the company owned over £3,700,000, above the permitted £2,800,000; the level of debenture debt was almost three times that allowed. The company had purchased collieries and steam ships costing £1,000,000. [54] Jackson was held responsible, and he resigned in April, although a report the following year showed there had been good commercial reasons for buying the collieries and ships. [55] The debt was able to be converted into shares in 1863 and the new board sold the ships at a loss, but it was not possible to sell the coal mines, as the trade in coal being depressed at the time due to the American Civil War. [56] Jackson suggested merger of the WHH&R and NER in a letter to the Railway Times in April 1864, and this was agreed later that year. An Act was gained the following year [57] and the companies merged in June or July 1865. [lower-alpha 3]

Later history

The Leeds Northern Railway opened from Melmerby to Stockton in June 1852. The line continued beyond the Leeds Northern station at Bishopton Lane and joined the Clarence Railway North Shore branch a little further north at a location later called North Shore Junction. There was an accident here on 21 July 1852 when a Clarence passenger train from Ferryhill was run into by a short train of vans and trucks which was reversing along the North Shore branch towards the junction. In his report [58] Capt. Wynne of the Board of Trade criticised the conflicting signals at the new junction and pointed out that there should have been a crossover to allow Clarence trains (which were still using the right-hand running line) to cross over to the correct line before proceeding towards the Leeds Northern station.

The merger of the West Durham Railway with the NER was agreed in 1866 and was complete in 1870. [59] The NER opened a new line to Bishop Auckland in 1885 from the Byers Green branch and the passenger service was diverted over this line, a new station opening at Byers Green. [60] The West Durham Railway closed west of Todhills in 1891. [32] From 1913, former Clarence Railway lines were electrified with 1,500 V DC overhead lines and electric locomotives hauled coal trains between Shildon and Erimus marshalling yard, which had opened in 1908 between Middlesbrough and Thornaby. The trains took the former S&DR line from Shildon to Simpasture Junction, joining the former Clarence Railway line to Carlton, where a later line allowed access to the Stockton to Middlesbrough extension. The locomotives operated for 20 years, but then coal traffic had reduced, which made it uneconomical to maintain the electrification system. [61]

As a result of the Grouping on 1 January 1923, the North Eastern Railway became the North Eastern area of the London and North Eastern Railway (LNER). [62] [63] In 1933, The rest of the former West Durham Railway was closed. [32] In 1939 the services from Spennymoor to Bishop Auckland were withdrawn and the Billingham to Port Clarence services cut back to Haverton Hill. [64]

During World War II, a Royal Ordnance Factory was built at ROF Aycliffe, served by two stations at Simpasture and Demons Bridge. [65] Britain's railways were nationalised on 1 January 1948 and the lines were placed under the control of British Railways. [62] On 31 March 1952 the passenger service was withdrawn from Stockton to Spennymoor via Ferryhill. On 14 June 1954 the public passenger service ceased on the Port Clarence Branch, although workman's trains continued until November 1961. In 1963 the line closed between Simpasture and the junction with the former Durham branch. [66]

Legacy

Train on the freight only Stillington Branch in 2010 Freight train approaching Norton West Junction Geograph-1784486-by-Philip-Barker (crop).jpg
Train on the freight only Stillington Branch in 2010

Current Durham Coast Line passenger services provide one train per hour over the route of the former Clarence Railway from Stockton to Billingham, from where the former Stockton and Hartlepool Railway is taken to Hartlepool; four trains a day travelling between London King's Cross and Sunderland use the route. [67] The line to Port Clarence was previously used by an irregular freight service, this having ceased between late 2018 and early 2019, the branch signalled for one train working. [68] The freight only Stillington Branch follows the route of the former Clarence Railway Durham branch to Ferryhill south junction. As of  2012 this two track railway carries three freight services a day, but this could be increased if freight is diverted from the East Coast Main Line. It is planned to carry out any necessary infrastructure works to allow the diversion of Intercity Express Programme Class 800 and 801 units over the line by 2019. [69]

The Auckland Way Railway Path follows the route of the Byers Green branch from Spennymoor, taking the route of the later NER branch to Bishop Auckland at Byers Green. [70]

References and notes

Notes

  1. Hoole (1974, p. 146) states the line was open for freight on 12 December 1840, whereas Tomlinson (1915, pp. 344–346) mentions a train of coal travelled in January.
  2. Two shillings in 1852 was worth about the same as £11.56 today. [52]
  3. Tomlinson (1915, p. 619) gives the date as 1 July, Awdry (1990, p. 164) states 5 July, and the National Archive website entry for the West Hartlepool Harbour and Railway Company gives 30 June.

Related Research Articles

<span class="mw-page-title-main">Stockton and Darlington Railway</span> English railway company, 1825 to 1863

The Stockton and Darlington Railway (S&DR) was a railway company that operated in north-east England from 1825 to 1863. The world's first public railway to use steam locomotives, its first line connected collieries near Shildon with Darlington and Stockton in County Durham, and was officially opened on 27 September 1825. The movement of coal to ships rapidly became a lucrative business, and the line was soon extended to a new port at Middlesbrough. While coal waggons were hauled by steam locomotives from the start, passengers were carried in coaches drawn by horses until carriages hauled by steam locomotives were introduced in 1833.

<span class="mw-page-title-main">North Eastern Railway (United Kingdom)</span> British railway company, active 1854–1922

The North Eastern Railway (NER) was an English railway company. It was incorporated in 1854 by the combination of several existing railway companies. Later, it was amalgamated with other railways to form the London and North Eastern Railway at the Grouping in 1923. Its main line survives to the present day as part of the East Coast Main Line between London and Edinburgh.

<span class="mw-page-title-main">Durham Coast Line</span>

The Durham Coast Line is an approximately 39.5-mile (63.6 km) railway line running between Newcastle and Middlesbrough in North East England. Heavy rail passenger services, predominantly operated Northern Trains, and some freight services operate over the whole length of the line; it provides an important diversionary route at times when the East Coast Main Line is closed. Light rail services of the Tyne and Wear Metro's Green Line also operate over the same tracks between a junction just south of Sunderland station and Pelaw Junction.

<span class="mw-page-title-main">Stockton railway station (County Durham)</span> Railway station in County Durham, England

Stockton is a railway station on the Durham Coast Line, which runs between Newcastle and Middlesbrough via Hartlepool. The station, situated 5 miles 45 chains (9.0 km) west of Middlesbrough, serves the market town of Stockton-on-Tees in County Durham, England. It is owned by Network Rail and managed by Northern Trains.

<span class="mw-page-title-main">Newcastle and North Shields Railway</span> Former English railway

The Newcastle & North Shields Railway opened in June 1839 from a temporary terminus in Carliol Square in Newcastle upon Tyne to North Shields. The railway was absorbed by the Newcastle & Berwick Railway in November 1844. The Newcastle & Berwick Railway was itself absorbed by the York, Newcastle and Berwick Railway, and this became part of the North Eastern Railway in 1854.

<span class="mw-page-title-main">South Durham and Lancashire Union Railway</span> English railway company

The South Durham and Lancashire Union Railway (SD&LUR) built a railway line linking the Stockton and Darlington Railway near Bishop Auckland with the Lancaster and Carlisle Railway at Tebay, via Barnard Castle, Stainmore Summit and Kirkby Stephen. The line opened in 1861 and became known as the Stainmore Line.

<span class="mw-page-title-main">Scotswood, Newburn and Wylam Railway</span>

The Scotswood, Newburn and Wylam Railway was a railway company that built the 6+12 miles (10.5 km) North Wylam branch or North Wylam loop on the former Newcastle & Carlisle Railway. The loop line opened between 1871 and 1876 and followed the former Wylam waggonway past the cottage where George Stephenson was born. The company was taken over by the North Eastern Railway in 1883.

<span class="mw-page-title-main">York, Newcastle and Berwick Railway</span> Former English railway company

The York, Newcastle and Berwick Railway (YN&BR) was an English railway company formed in 1847 by the amalgamation of the York and Newcastle Railway and the Newcastle and Berwick Railway. Both companies were part of the group of business interests controlled by George Hudson, the so-called Railway King. In collaboration with the York and North Midland Railway and other lines he controlled, he planned that the YN&BR would form the major part of a continuous railway between London and Edinburgh. At this stage the London terminal was Euston Square and the route was through Normanton. This was the genesis of the East Coast Main Line, but much remained to be done before the present-day route was formed, and the London terminus was altered to King's Cross.

<span class="mw-page-title-main">Redmarshall railway station</span> Former railway station in England

Redmarshall railway station was a railway station on the North Eastern Railway, in County Durham.

<span class="mw-page-title-main">Leeds Northern Railway</span> 19th-century British railway company

The Leeds Northern Railway (LNR), originally the Leeds and Thirsk Railway, was an English railway company that built and opened a line from Leeds to Stockton via Harrogate and Thirsk. In 1845 the Leeds and Thirsk Railway received permission for a line from Leeds to Thirsk, part of which opened in 1848, but problems building the Bramhope Tunnel delayed trains operating into Leeds until 1849.

West Auckland railway station served the villages of St Helen Auckland and West Auckland in County Durham, England, between 1833 and 1962. It was on the railway line between Bishop Auckland and Barnard Castle. There was a locomotive depot, which was the only one to be both closed completely and later reopened by the London and North Eastern Railway.

<span class="mw-page-title-main">Byers Green railway station</span> Disused railway station in England

Byers Green railway station was one of three railway stations that served in the village of Byers Green in County Durham, Northeast England.

<span class="mw-page-title-main">Ferryhill railway station</span> Former railway station in England

Ferryhill railway station was located in Ferryhill, County Durham, Northeast England. It was located on what became the East Coast Main Line between Darlington and Durham, close to the junctions with several former branches, including the extant freight-only Stillington Line to Norton-on-Tees and Stockton.

Spennymoor railway station served the town of Spennymoor, County Durham, England from 1845 to 1952 on the Byers Green Branch of the Clarence Railway.

<span class="mw-page-title-main">Hartlepool railway station (Hartlepool Dock & Railway)</span> Former railway station in England

Hartlepool railway station was a railway station that served the Headland area of Hartlepool in the ceremonial county of Durham, North East England. Though originally built as the coastal terminus of the Hartlepool Dock & Railway in 1839, for most of its life the station was the terminus of a shuttle service from the town's main station in West Hartlepool.

<span class="mw-page-title-main">Norton-on-Tees railway station</span> Disused railway station in Norton, County Durham

Norton-on-Tees railway station served the town of Norton, County Durham, England from 1877 to 1960, originally on the Port Clarence Branch of the Clarence Railway.

<span class="mw-page-title-main">Belasis Lane railway station</span> Disused railway station in Billingham, Stockton-on-Tees

Belasis Lane railway station served the ICI Billingham Manufacturing Plant in the town of Billingham, County Durham, England from 1928 to 1964 on the Port Clarence branch of the former Clarence Railway which had become part of the London and North Eastern Railway by the time the station opened.

<span class="mw-page-title-main">Coundon railway station</span> Former railway station in England

Coundon railway station was a railway station that served the villages of Coundon and New Coundon in County Durham, North East England from 1885 to 1939. It was located on the Bishop Auckland to Ferryhill of the North Eastern Railway (NER), an extension of the earlier Byers Green Branch of the Clarence Railway (CR).

<span class="mw-page-title-main">Wellfield railway station</span> Former railway station in Wingate, County Durham, England

Wellfield railway station was a railway station that served the village of Wingate in County Durham, England. It was built by the North Eastern Railway (NER) on the route of the Hartlepool Dock & Railway (HD&R) to allow interchange between the existing line and their newly opened line from Stockton-on-Tees.

<span class="mw-page-title-main">Hart railway station</span> Disused railway station in Hart, County Durham

Hart railway station was a station that served the villages of Hart and Crimdon in County Durham, England.

References

  1. https://bettertransport.org.uk/sites/default/files/research-files/case-for-expanding-rail-network.pdf [ bare URL PDF ]
  2. Tomlinson 1915, pp. 105–107.
  3. Tomlinson 1915, p. 57.
  4. Tomlinson 1915, p. 87.
  5. Tomlinson 1915, p. 88.
  6. Tomlinson 1915, pp. 101–102.
  7. Tomlinson 1915, pp. 166–167.
  8. Tomlinson 1915, pp. 167–168.
  9. Tomlinson 1915, pp. 170–171.
  10. 1 2 Tomlinson 1915, p. 234.
  11. Tomlinson 1915, p. 175.
  12. Tomlinson 1915, pp. 177–178.
  13. Tomlinson 1915, p. 179.
  14. Tomlinson 1915, p. 180.
  15. Tomlinson 1915, pp. 178–181.
  16. Tomlinson 1915, p. 236.
  17. Tomlinson 1915, p. 237.
  18. Tomlinson 1915, p. 239.
  19. Cobb 2006, pp. 447–448, 460.
  20. Hoole 1974, p. 130.
  21. Whishaw 1842, pp. 59, 60–61.
  22. Tomlinson 1915, p. 386.
  23. Hoole 1974, pp. 130–131.
  24. Whishaw 1842, pp. 60–62.
  25. "The Timothy Hackworth Story - Railway Pioneer".
  26. "The Timothy Hackworth Story - Railway Pioneer".
  27. Tomlinson 1915, pp. 289–290.
  28. 1 2 Tomlinson 1915, pp. 297–298.
  29. Tomlinson 1915, p. 312.
  30. Tomlinson 1915, pp. 335–336.
  31. Hoole 1974, pp. 178–179.
  32. 1 2 3 Hoole 1974, p. 180.
  33. Tomlinson 1915, p. 529.
  34. Allen 1974, p. 74.
  35. Allen 1974, p. 75.
  36. Historic England. "Throston Engine House and wall adjoining (1250389)". National Heritage List for England . Retrieved 13 August 2017.
  37. Tomlinson 1915, pp. 344–346.
  38. Hoole 1974, p. 146.
  39. Tomlinson 1915, pp. 475–476.
  40. Allen 1974, p. 102.
  41. 1 2 Tomlinson 1915, pp. 476–477.
  42. Allen 1974, pp. 67, 101–102.
  43. Tomlinson 1915, p. 477.
  44. Tomlinson 1915, p. 486.
  45. Heavsides, Henry. The Annals of Stockton-on-Tees. H. Heavsides & Son. p. 117.
  46. Waller, Philip (2004). "Jackson, Ralph Ward". Oxford Dictionary of National Biography (online ed.). Oxford University Press. doi:10.1093/ref:odnb/37591.(Subscription or UK public library membership required.)
  47. Tomlinson 1915, pp. 509–510.
  48. Hoole 1974, pp. 147–148.
  49. "West Hartlepool Harbour and Railway Company". The Spectator. 11 July 1863. Retrieved 8 February 2014.
  50. Tomlinson 1915, pp. 512–514.
  51. Hoole 1974, p. 144.
  52. UK Retail Price Index inflation figures are based on data from Clark, Gregory (2017). "The Annual RPI and Average Earnings for Britain, 1209 to Present (New Series)". MeasuringWorth. Retrieved 11 June 2022.
  53. Tomlinson 1915, p. 515.
  54. Tomlinson 1915, pp. 599–600.
  55. Tomlinson 1915, p. 602.
  56. Tomlinson 1915, pp. 603, 610.
  57. Tomlinson 1915, p. 614.
  58. Wynne, Capt. G., R.E., Board of Trade report dated 5 August 1852
  59. Tomlinson 1915, pp. 627, 644.
  60. Hoole 1974, p. 160.
  61. Allen 1974, pp. 204–205.
  62. 1 2 Hedges 1981, pp. 88, 113–114.
  63. Allen 1974, p. 234.
  64. Hoole 1974, pp. 132, 169.
  65. "Clarence Railway". Durham History. Retrieved 18 March 2013.
  66. Hoole 1974, pp. 132, 144, 160.
  67. Network Rail 2012, pp. 124–125.
  68. Network Rail 2012, pp. 64–67.
  69. Network Rail 2012, pp. 91–93.
  70. "Auckland Way Railway Path" (PDF). Durham County Council. 2011. Archived from the original (PDF) on 23 February 2014. Retrieved 4 February 2014.

Sources

Further reading