Glenwood Generating Station | |
---|---|
Country | United States |
Location | Glenwood Landing, Long Island, New York |
Coordinates | 40°49′39″N73°38′51″W / 40.82750°N 73.64750°W |
Status | In service |
Power generation | |
Nameplate capacity |
|
External links | |
Commons | Related media on Commons |
Glenwood Generating Station is a power station in Glenwood Landing, New York owned by National Grid USA. It is mainly known for being the former site of an architecturally significant 1920s brick power station. That building and an adjacent 1950s station were demolished over the course of 2013 to 2015, due to their obsolescence as well as the excessive cost of safely retaining the building given its poor condition. Four smaller gas turbine peaking generators remain in operation, as does the Y-50 Cable connection across Long Island Sound.
Station 2 was constructed in the 1920s and was considered significant as an example of early 20th-century industrial architecture. It was designed in an industrial Beaux-Arts style, with large arched windows and stringcourse intended to prevent it from becoming an eyesore given its proximity to affluent communities. It was constructed with Flemish bond brickwork and decorative limestone elements. [1] [2] It was also constructed to minimize noise and ash pollution. Buildings with such architectural detail were usually found in urban areas, making the Glenwood plant unusual for being far from urban areas at the time of its construction. [3]
The building was divided into three sections: a narrow four-story administration section to the north containing offices; a five-story turbine room containing a large open space with decorated glazed buff brick walls; and a six-story boiler house mainly filled with equipment, topped by six 140-foot smoke stacks (ultimately reaching 265 feet above the floor slab). At the time of its demolition the New York State Office of Parks, Recreation and Historic Preservation determined that it appeared to meet the criteria for listing on the National Register of Historic Places, triggering an alternative use analysis. Given the building's poor condition after three decades of disuse, the excessive cost of making the building structurally sound prevented any plans to retain or renovate it. [1] [2]
The first facility on the site was Station 1, constructed in 1906 and expanded during World War I, which existed until at least 1939. The Station 2 building was constructed from 1928 to 1931 by the Nassau Power and Light Company, a predecessor of the Long Island Lighting Company (LILCO). [1] [2] The extra generating capacity was needed due to a sixfold increase in Long Island's electricity demand from 1910 to 1925. The expansion also reflected LILCO's then-novel philosophy of using few centralized power plants interconnected by transmission lines, rather than many small plants distributed through the region. [3] In 1936 it was described as "the key electric generating plant of the Long Island system," [4] and its control room managed LILCO's entire system. [3] In 1939 it was upgraded to burn both coal and oil, and in 1946 natural gas capability was added. [1] [2]
In 1942, a 3-hour power outage caused by testing of new distribution circuits affected seven major factories producing material for World War II. These included the Grumman plant in Bethpage and the Republic Aviation plant in Farmingdale, where workers staged an impromptu baseball game while they waited for power to return. Local hospitals and Mitchel Field were able to continue operating under auxiliary power. [5] Although sabotage was not suspected, it caused the colonel in charge of civilian protection for Nassau County to request that the Army guard the power station. [6]
The two units of Station 3 became operational in 1952 and 1954. [7] At the time The New York Times called it "one of the most modern power plants in the country," with both mechanical and electrostatic precipitators for dust and ash collection, as well as valve silencers and noise barriers. It was the first turbine generator mounted on an open deck in the Northeastern United States. Two similar units were constructed about the same time on the South Shore in the new Far Rockaway Power Station and E. F. Barrett Power Station. [8]
In 1967, a 15 MW GE Frame 5 gas turbine generator was constructed for black start, peaking, and emergency purposes. [9]
In 1972, the Town of Oyster Bay board unanimously denied LILCO a permit to further expand the plant with five 50 MW gas turbines, citing air-quality concerns and the effects of the 1970s energy crisis. Town Supervisor John W. Burke at the time noted the board's recognition that "in view of the fuel shortage, construction of gas turbines just seems out of step with the direction being taken by the average consumer, who lowers his thermostat and wears a sweater in his home to reduce the amount of fuel burning." [10] Nevertheless, two GE Frame 7B gas turbine generators were constructed that year. [9]
In 1978, the Y-50 Cable was constructed between Westchester County's Dunwoodie North Substation and the Glenwood Generating Station, via the Long Island Sound. [11] [12] [13]
The Station 2 generating units were taken out of operation in 1978, [14] but as late as 2009 the building was used for such purposes as a waste water treatment facility for the adjacent operational units, office and warehouse space, and transmission and fiber optic lines. [15]
In 1998, as part of a state-brokered deal, LILCO's power generation facilities, including the Glenwood plant, were absorbed into KeySpan Energy, with the public Long Island Power Authority (LIPA) taking over transmission and delivery functions. [16] [17] KeySpan would be acquired by National Grid in 2007. [18]
In 2001, LIPA proposed building two mini-turbines at Glenwood Landing as part of a plan to build ten such plants across Long Island to avoid the risk of rolling blackouts in the face of increased demand like those experienced in California the previous year, given strain on the system from a heat wave in 2001. The pair of turbines produced 79 MW, just under an 80 MW threshold that would have triggered a full regulatory and environmental review. [19] [20] [21] The new turbines were completed by May 2002, and were the first of the ten to enter operation. [22] [23]
Station 3's utilization decreased from 43 percent in 2001 to 11.2 percent in 2005. As of 2009, the power station was used as a peaking power plant operating in the summer, with two operational natural gas steam-electric generating units with a combined 210 MW capacity. It had a once-through water cooling system using water from the adjacent Hempstead Harbor. [15] By 2014 the Station 2 building had deteriorated to the point where it was nearing condemnation. [14]
In 2011 it was announced that the Glenwood Landing station would be shut down and demolished along with its sister plant in Far Rockaway. The two stations were described as the oldest and least efficient of the power plants on Long Island, with the closures saving $76 million through 2015. [24]
Local resident Karin Barnaby campaigned to renovate Station 2 for commercial and cultural uses rather than demolish it, pointing to other redeveloped historic power plants in the United States such as the Pratt Street Power Plant in Baltimore and the Homan Square Power House in Chicago. [25] Despite collecting 780 signatures for a petition, this was rejected due to the excessive cost of renovating the building given its poor condition. [14] Demolition was estimated to cost $8 million, as opposed to $31 million to make the building structurally sound without improving it, and $100 million to renovate it into a mixed-use development including an exhibition hall in the old turbine room. Using the building for new power generation capacity was deemed unfeasible because modern generation equipment was incompatible with the building design. [2]
Demolition of the plant raised concern about the financial effects on the local North Shore School District, as the over $20 million annual tax payments from the plant provided 20 percent of the district's budget. [4] This led to fears of a 15–19% increase in residential taxes in late 2014. However, it was determined that according to state law there could be no more than a 1% increase in property taxes for a given tax class as a result of a decreased tax assessment in another class (the four tax classes being residential, cooperatives/condominiums, commercial, and utilities). The financial effects on the district would thus have to be mitigated by increased taxes on remaining utilities in the district, as well as a $2.5 million one-time grant from the state arranged by local state legislators. [26] [27] The site's municipal and school payments in lieu of taxes fell from $23.2 million in 2012 to $16.6 million in 2015. [28]
Station 3 was demolished in November 2013, and demolition of Station 2 was completed in 2015. National Grid opted for a controlled deconstruction rather than an implosion or using a wrecking ball. [14] The demolition of Station 2 required the relocation of a peregrine falcon nest from the top of one of the smoke stacks. [1] After demolition and land remediation had been completed, the area was planned to be paved over with asphalt and offered to developers. [14]
The three smaller gas-turbine peaking generators built by LILCO in 1967 and 1972 remained in operation, [9] as did the two constructed in 2002. [29] In addition, three electrical substations, three fuel tanks, and a water tower elsewhere on the site remained in operation. [1] [14]
In 2017, National Grid proposed raising the legal power output limit of the two 2002 peaking plants from 79.9 MW to 94 megawatts. [29] In 2020, the 15 MW generator from 1967 was shuttered, leaving four more operational, [30] and the two 1972 generators had water injection systems installed, to comply with stricter air emissions regulations. [31] As of 2020, Glenwood Generating Station's remaining 232 MW nameplate capacity made it the eighth largest power generation facility on Long Island. That year it generated 107.7 GWh, which placed twelfth. [32]
A power station, also referred to as a power plant and sometimes generating station or generating plant, is an industrial facility for the generation of electric power. Power stations are generally connected to an electrical grid.
The Ironbridge power stations refers to a series of two power stations that occupied a site on the banks of the River Severn at Buildwas in Shropshire, England. The Ironbridge B Power Station was operated by E.ON UK but the site is now owned by Haworth Group. The station stands near the Ironbridge Gorge World Heritage Site. Originally powered by coal, they were converted to use 100% biomass fuel. Ironbridge B Power Station stopped generating electricity on 20 November 2015, with the decommissioning process continuing into 2017. The main phase of the 27-month demolition process began at 11:00 GMT on 6 December 2019, commencing with the four cooling towers.
The Holyrood Thermal Electric Generating Station built by Newfoundland and Labrador Hydro Corporation is located near the community of Holyrood, in Conception Bay, Newfoundland, Canada.
The Shoreham Nuclear Power Plant was a completed General Electric nuclear boiling water reactor located adjacent to Long Island Sound in East Shoreham, New York.
The Long Island Lighting Company, or LILCO ("lil-co"), was an electrical power company and natural gas utility for Long Island, New York, serving 2.7 million people in Nassau, Suffolk and Queens counties, from 1911 until 1998.
Long Island Power Authority is a municipal subdivision of the State of New York that owns the electric transmission and electric distribution system serving all of Long Island and a portion of New York City known as the Rockaways. LIPA was originally created under the Long Island Power Act of 1985 to acquire the Long Island Lighting Company (LILCO)'s electric and natural gas infrastructure after the cancellation of the Shoreham Nuclear Power Plant. LIPA acquired LILCO's transmission system in May 1998, while the remainder of LILCO's natural gas-related infrastructure merged with Brooklyn Union Gas to form KeySpan Energy.
North Shore Central School District is a public school district in Nassau County, New York. It serves several villages and hamlets in the North Shore region of Long Island, specifically Glenwood Landing, Glen Head, Sea Cliff, Old Brookville, and parts of Greenvale and Roslyn Harbor. About 2,567 students attend North Shore schools. It has a single high school, North Shore High School.
The Huntly Power Station is the largest thermal power station in New Zealand and is located in the town of Huntly in the Waikato. It is operated by Genesis Energy Limited, a publicly listed company. The station has five operational generating units – three 250 MW coal-and-gas-fired steam turbine units, a 50 MW gas peaking plant, and a 403 MW combined cycle gas turbine plant. The station also plays an important role in voltage support for the Northland, Auckland and Waikato regions.
Teesside Power Station is a former gas-fired power station, in Redcar & Cleveland, England. Situated near the Wilton chemical complex, the station had combined cycle gas turbines (CCGTs) and open cycle gas turbines (OCGTs), however in 2011 the operation of the CCGT part of the station was suspended, and in 2013 the owners announced its closure and plans to demolish it. Prior to the suspension, the station had a generating capacity of 1875 megawatts (MW), making it the largest of any CCGT power station in Europe. The station could meet almost 3% of the electricity demand for England, Wales and Scotland. Opened in 1993, the station was initially operated by Enron but moved into the hands of PX Ltd after the Enron scandal of 2001, before being bought by Gaz de France and Suez in 2008. The station also worked as a cogeneration plant, providing steam for the Wilton complex.
A black start is the process of restoring an electric power station or a part of an electric grid to operation without relying on the external electric power transmission network to recover from a total or partial shutdown.
The Northport Power Station, known as “The Stacks” by locals, is the largest power generation facility on Long Island. It is a natural gas and conventional oil electric power generating station located on the North Shore of Long Island in Fort Salonga, New York. The facility was built by the Long Island Lighting Company (LILCO) in stages between 1967 and 1977, and since August 2007 it has been owned and operated by National Grid USA. The plant's electric output is distributed by Long Island Power Authority (LIPA).
Blyth Power Station refers to a pair of now demolished coal-fired power stations, which were located on the Northumberland coast in North East England. The two stations were built alongside each other on a site near Cambois in Northumberland, on the northern bank of the River Blyth, between its tidal estuary and the North Sea. The stations took their name from the town of Blyth on the opposite bank of the estuary. Blyth A Power Station was built and opened first but had a smaller generating capacity than its sister station, Blyth B Power Station, which was built to its west four years later. The power stations' four large chimneys were a landmark of the Northumberland skyline for over 40 years; the A Station's two chimneys each stood at 140 metres (460 ft); the B Station's two chimneys were taller, at 170 metres (560 ft) each.
Ravenswood Generating Station is a 2,480 megawatt power plant in Long Island City in Queens, New York City. It is owned and operated by LS Power/Helix Energy Solutions Group. The plant is fueled primarily by fuel oil and natural gas which heats the boilers.
South Fork Wind Farm is a utility-scale offshore wind farm on the Outer Continental Shelf Offshore Rhode Island, providing energy to New York state.
The Y-50 Cable is an undersea and underground high voltage electric transmission cable between Westchester County and Long Island via the Long Island Sound and Hempstead Harbor in New York, United States.
The Richard M. Flynn Power Plant is a power plant in Holtsville, in Suffolk County, on Long Island, in New York, United States. It is operated by the New York Power Authority (NYPA).
The E. F. Barrett Power Station is a power plant in Nassau County, New York, United States. The main plant is in Barnum Island, with outlying facilities in neighboring Island Park and Oceanside. It is operated by National Grid USA.
Port Jefferson Power Station is a fossil-burning power plant in Port Jefferson, New York on Long Island. It is operated by National Grid USA. Its four main steam turbine units were constructed between 1948 and 1960 by the Long Island Lighting Company (LILCO), with the older two decommissioned in 1994.
Caithness Long Island Energy Center is a 350 MW natural gas fired power power plant in Yaphank, New York, on Long Island operated by Caithness Energy. It began operation in 2009 as the first major baseload plant to be built on Long Island in over 30 years, and by 2020 produced the second most net energy generated among power plants on Long Island. A proposal to construct a new unit tripling the capacity of the facility received initial approvals in 2013, but did not proceed and was shelved in 2018.
Bethpage Energy Center is a power station in Bethpage, New York, United States, consisting of two combined cycle plants opened in 1989 and 2005, and one gas turbine peaking plant opened in 2002. The original plant was commissioned by Grumman Aerospace for its Bethpage complex because it was deemed more cost-effective than purchasing power from electric utilities. It was acquired by Calpine in 1998, which expanded the facility with two more plants.