Millennium Tower | |
---|---|
General information | |
Type | Residential condominiums |
Location | 301 Mission Street San Francisco, California |
Coordinates | 37°47′25″N122°23′46″W / 37.7904°N 122.3961°W |
Construction started | 2005 |
Completed | 2009 |
Opening | April 23, 2009 |
Cost | US$350 million [1] |
Owner | Mission Street Development, LLC |
Height | |
Antenna spire | 645 ft (197 m) |
Roof | 605 ft (184 m) |
Top floor | 592 ft (180 m) |
Technical details | |
Floor count | 58 |
Floor area | 1,151,017 sq ft (106,933.0 m2) |
Lifts/elevators | 12 |
Design and construction | |
Architect(s) | Handel Architects |
Developer | Millennium Partners |
Structural engineer | DeSimone Consulting Engineers |
Main contractor | Webcor Builders |
Other information | |
Number of units | 419 [2] |
References | |
[3] [4] [5] [6] |
301 Mission Street is a high-rise residential building [7] [5] [8] in the South of Market district of downtown San Francisco. [1] A mixed-use, primarily residential high rise, it is the tallest residential building [5] and the 6th-tallest overall in San Francisco. In May 2016, [9] residents were informed the main tower was both sinking and tilting, [10] resulting in several lawsuits concerning repair costs and whether the existence of the tilt had been withheld from buyers. [9] [10]
Opened to residents on April 23, 2009, [11] [12] 301 Mission includes two buildings: a 12-story tower located on the northeast of the property, [4] [1] and Millennium Tower, a 58-story, [7] [5] [8] 645-foot-tall (197 m) condominium skyscraper. [1] The blue-gray glass, late-modernist buildings are bounded by Mission, Fremont, and Beale Streets, and the north end of the Salesforce Transit Center site. [11] [12] In total, the project has 419 residential units, [2] with 53 of those units in the smaller tower. [1] The larger tower's highest level, 58 floors above the ground, [4] [11] [12] is listed as the 60th, because floors 13 and 44 are missing for superstitious reasons. [13]
Developed by Mission Street Development LLC, an affiliate of Millennium Partners, [14] the US$350 million project was designed by Handel Architects, engineered by DeSimone Consulting Engineers and built by Webcor Builders. At 645 feet (197 m), it is the tallest concrete structure in San Francisco, the fourth-tallest building in San Francisco, and the tallest built since 345 California Street in 1986. [1] [15] [16] It was the tallest residential building west of the Mississippi River, but has been surpassed by The Austonian in Texas. [17] The tower is slender, with each floor containing 14,000 square feet (1,300 m2) of floor space. [18] In addition to the 58-story tower, there is a 125-foot (38 m), 11-story tower on the northeast end of the complex. [15] Between the two towers is a 43-foot (13 m), two-story glass atrium. [2] In total, the project has 419 units. [2]
The residences are expensive; a penthouse unit sold for $13 million in December 2016. [19] [20] The bottom 25 floors of the main tower are marketed as Residences while the floors from 26 to the top are marketed as Grand Residences. As happens with many high-rises, there is no thirteenth floor because of superstitions related to triskaidekaphobia. Neither is there a forty-fourth floor, because the number four is considered unlucky by many Asians.[ citation needed ] The 53 units in the separate 12-story tower are marketed as City Residences. [1] Below street level, there are 434 parking spaces in a five-level subterranean garage located under the 11-story tower. [15] The building is located next to the site of the Salesforce Transit Center. The tower's design was marketed as resembling a translucent crystal, and was, until accompanied by much larger adjacent buildings, a landmark for the Transbay Redevelopment and the southern skyline of San Francisco. [18]
Resident services include a private concierge and access to the 20,000-square-foot (1,900 m2) Owner's Club Level, which features amenities such as a private lounge, wine cellar, and fitness center. The development's "lifestyle" program organizes cultural events. [13] The development accommodates the International Smoke restaurant and bar, located on the ground floor. [21] [13]
Millennium Partners first proposed the development in 2002 with 163 condominiums, 108 rentals and a 136-unit "extended stay" hotel. [22] The project was approved in 2003 by the S.F. Planning Commission 4–1 and construction began in 2005. The only vote against the project came from Planning Commissioner Sue Lee. [15] The development was the first high rise built downtown in 20 years. According to Modern Luxury, a proposed 52-story skyscraper at nearby 80 Natoma by developer Jack Myers which would also have a similar cast in place concrete construction, was rejected by the city's Department of Building Inspections (DBI) after an outside peer review. The Millennium Tower received no such scrutiny, since Millennium Partners would not submit to a peer review, as that study would have potentially delayed construction by years. [23] Treadwell & Rollo, the geotechnical engineer for Millennium Tower, were also the geotechnical engineer for the scrapped project at 80 Natoma. [24]
On September 6, 2010, Dan Goodwin, also known as SpiderDan and Skyscraperman, scaled the outside of the tower using suction cups. Following the climb, Goodwin was arrested by the San Francisco police, who charged him with trespassing and creating a public nuisance. [25]
In 2013, the building sold its final unit, generating US$750 million in total sales, a 25 percent return on the estimated US$600 million in development costs. [2]
After developers disclosed to authorities in 2015 that the building was sinking and tilting, [26] the public was notified of the problem in 2016. [10] [27] Treadwell & Rollo's geotechnical design for the foundation of the main tower consists of a concrete slab built on 60-to-90-foot deep (18 to 27 m) concrete friction piles through the fill and young bay mud, and embedded into dense Colma sand (sand deposited during the last ice age 12,000–100,000 years ago and the penultimate layer before bedrock). A number of other buildings in 301 Mission Street's area have used similar systems, although due to varying earth conditions, others have pushed piles directly into the bedrock 200 feet (61 m) below. [28] [29] An examination in 2016 showed the building had sunk 16 inches (41 cm) with a two-inch (5.1 cm) tilt at the base and an approximate six-inch (15 cm) tilt at the top of the tower. [30] The building is leaning toward the northwest, [30] [31] [32] and this has caused cracks in the building's basement and the pavement surrounding the tower. [33] As of 2018, the sinking had increased to 18 inches (46 cm) with a lean of 14 inches (36 cm). [34] Measurements in 2022 show the tilt increased to 28 inches (71 cm), as measured from the roof. [35]
The developer blames the sinking problem on the Transbay Joint Powers Authority (TJPA), who were responsible for construction of the neighboring Transbay Transit Center (TTC). [30] The sinking problem had reportedly started before TTC construction even broke ground, [29] and TJPA asserted the building had already settled 10 inches (25 cm), well past the original maximum vertical settling prediction of 5.5 inches (14 cm) in 20 years, by the time TJPA began removing the timber piles under the prior Transbay Terminal in 2011. [36] The building's homeowners association, represented by general counsel Adrian Adams of Adams Stirling PLC, retained Dan Petrocelli of O’Melveny & Myers, to sue Webcor, Millennium Partners, and the TJPA. [37] Originally, the homeowners association hired David Casselman to sue the TJPA instead of developer Millennium Partners, as Casselman noted that "inverse condemnation law allows residents to collect legal fees on top of any award, whereas suing the developer will steer up to 40 percent of any award to lawyers". [30] [23]
Another group of tenants who disagree with the homeowners association, led by resident and patent litigator Jerry Dodson, is suing Millennium Partners, the City of San Francisco, and the TJPA. [9] [30] In breaking with Casselman and the homeowners association, Dodson has regarded Millennium Partners as the responsible culprit. [23]
In November 2016, the city of San Francisco filed suit against the tower's developer Mission Street Developers LLC, claiming that the developers withheld information on the sinking problems from potential apartment buyers. [14] [26] Mission Street Developers rejected the city's claims. [38]
Sage Engineers has been hired by Millennium Partners to provide an engineering study on the sinking problem. Some experts have prognosticated that the cost to fix the tilt could exceed the liability insurance held by Millennium Partners and the building's various construction vendors. If the TJPA is found to be at fault, San Francisco taxpayers could end up paying for the repairs. [9]
As of 2017 [update] , a city inspection found that the building was still safe to occupy, though there was damage to the foundation and electrical system. [8]
In March 2017, the homeowners association filed suit against Millennium Partners, Webcor, Handel Architects, Treadwell & Rollo, DeSimone Consulting Engineers, Arup, and Transbay Joint Powers Authority. They are seeking $200 million to cover repairs and damages. [39]
In early September 2018, residents reported hearing various "creaking sounds". At around 2:30 a.m. on the morning of Saturday, September 8, 2018, residents reported hearing a loud "popping sound". On Sunday, the following day, a resident located in a corner unit on the 36th floor discovered a cracked window. The glass used in the building's windows and façade is rated to withstand hurricane-force winds, leading to concern that the crack was a symptom of a much larger structural failure. [40]
Again in March 2023, the San Francisco Fire Department, [41] as well as numerous first-hand witnesses, reported panes of glass falling from the tower during a windstorm. These panes fell and shattered near pedestrians on Mission Street. No injuries were reported.
On December 4, 2018, Ronald Hamburger, the senior principal engineer at Simpson Gumpertz & Heger, revealed in a press release a final resolution to the Millennium Tower's tilting and sinking problem by underpinning the building. The proposed solution would have involved the installation of 52 piles along the north and west sides of the tower beneath the sidewalk that reach down 250 ft (76.2 m) into the bedrock of downtown San Francisco and be tied with the original 60–90 ft (18.3–27.4 m) deep foundation piles. It was estimated that about 50% of the tilt could be evened out over a period of 10 years as the south and eastern sides of the building would come back into re-alignment with the now sunken north and western sides of the building, at which point the remaining south and eastern sides of the building can be anchored to the bedrock, permanently resolving the tilting and sinking of the building. The fix was estimated to cost about $100 million. [42] [43] The lawsuits are being consolidated into a global agreement and work was expected to start in mid-November 2020. [44] Funding for the fix includes $30 million from taxpayers via the Transbay Joint Powers Authority. [45]
In November 2020, the $100 million "perimeter pile upgrade" repair project began with a planned 52 pilings to be sunk to bedrock. These pilings would be tied to the existing foundation to mitigate further sinking. The building's tilting problem came under renewed scrutiny following the deadly collapse of Champlain Towers South in Surfside, Florida, in June 2021. [46] The repair project was halted in August 2021 after monitoring indicated that the building had unexpectedly sunk an additional inch on the Fremont Street side after 39 of the 52 piles were installed. The one inch drop translates to an additional 5 inches of lean on the 58th floor. [47] On September 10, 2021, San Francisco city officials told Millennium Tower management to not resume construction work until the city reviews an updated construction approach. [48] In February 2022, Hamburger had also discovered that the tower had moved one inch away from an adjacent building containing the parking garage. This gap does not pose a structural safety hazard and is unlikely to worsen during repair work, but reversing the shift would allow the reopening of one of the parking garage elevators. [49]
In August 2022, San Francisco building officials agreed to a scaled-down plan to allow engineers to do the work needed to support one corner of the building. The revised plan relies on just 18 piles, instead of the original 52, to anchor the high-rise to bedrock on the two sides where it leans and tilts the most, on Mission and Fremont streets. With the scaled-down plan, the fix was completed in June 2023. [50] [51]
The building has garnered several awards from several engineering and architectural organisations. [6]
One Rincon Hill is an upscale residential complex on the apex of Rincon Hill in San Francisco, California, United States. The complex, designed by Solomon, Cordwell, Buenz and Associates and developed by Urban West Associates, consists of two skyscrapers that share a common townhouse podium. It is part of the San Francisco skyline and is visible from several parts of the Bay Area.
The Paramount, or 680 Mission Street at Third, is a 40-story rental-apartment tower that is located South of Market just outside the Financial District on Mission Street in San Francisco.
555 Mission Street is a 33-story, 147 m (482 ft)[A] office tower in the South of Market area of San Francisco, California. Construction of the tower began in 2006 and the tower was finished on September 18, 2008. It was the tallest office building constructed in San Francisco in the 2000s, and is the 25th tallest building in San Francisco.
The San Francisco Transbay development is a completed redevelopment plan for the neighborhood surrounding the Salesforce Transit Center site, South of Market near the Financial District in San Francisco, California. The new transit center replaced the since-demolished San Francisco Transbay Terminal, and new skyscrapers, such as Salesforce Tower, took advantage of the height increases allowed through the San Francisco Transit Center District Plan. The sale of several land parcels formerly owned by the state and given to the managing Transbay Joint Powers Authority helped finance the construction of the transit center.
One Market Plaza is a complex of three office buildings at 1 Market Street along the San Francisco Embarcadero. The historic 11-story Southern Pacific Building, also known as "The Landmark", was completed in 1916, and incorporated into the development in 1976 that includes the 43-storey 172 metres Spear Tower, and the 27-storey, 111 metres Steuart Tower. At over 1.5 billion pounds, the complex is considered the heaviest development in San Francisco.
140 New Montgomery Street is a 26-floor Art Deco mixed-use office tower located in San Francisco's South of Market district, close to the St. Regis Museum Tower and the San Francisco Museum of Modern Art. Constructed in 1925 as a modern headquarters for The Pacific Telephone & Telegraph Co., it was originally known as The Pacific Telephone & Telegraph Company Building or simply the Telephone Building, and, after 1984, as The Pacific Bell Building or The PacBell Building.
181 Fremont is an 803-foot (245 m) mixed-use skyscraper in the South of Market District of San Francisco, California. The building, designed by Heller Manus Architects, is located adjacent to the Transbay Transit Center and 199 Fremont Street developments. 181 Fremont is owned and operated by Jay Paul Company, which was the sole developer of the project. The entire office portion of the building was leased to Facebook to house its San Francisco office and Instagram division.
The Palace Hotel Residential Tower was a residential skyscraper proposed in 2006, which was to have been built at the corner of Jessie & Annie Streets in the South of Market district of San Francisco, California. At 204 m (669 ft) and 60 stories, it would have been the tallest residential building in the city, and the tallest South of Market. Had it been constructed, prior to the Financial crisis of 2007–2008, the tower would have replaced an annex of the Palace Hotel.
Salesforce East is a 30-story skyscraper in the South of Market district of San Francisco, California.
The Salesforce Transit Center, also known as the Transbay Transit Center, is a transit center in downtown San Francisco. It serves as the primary bus terminal for the San Francisco Bay Area, and is proposed as a possible future rail terminal. The centerpiece of the San Francisco Transbay development, the construction is governed by the Transbay Joint Powers Authority (TJPA). The 1,430-foot-long (440 m) building sits one block south-east of Market Street, a primary commercial and transportation artery.
535 Mission Street is an office skyscraper in the South of Market district of San Francisco, California, opened in November 2014, with 27 stories rising 378 ft (115 m) above street level. It is adjacent to the Transbay Transit Center site and located on the same block as 100 First Plaza, 555 Mission Street, and 101 Second Street.
Salesforce Tower, formerly known as Transbay Tower, is a 61-story supertall skyscraper at 415 Mission Street, between First and Fremont Street, in the South of Market district of downtown San Francisco. Its main tenant is Salesforce, a cloud-based software company. The building is 1,070 feet (326 m) tall, with a top roof height of 970 feet (296 m). Designed by César Pelli and developed by Hines Interests Limited Partnership and Boston Properties, it was the last building designed by Pelli to be completed in his lifetime. As of 2024, Salesforce Tower is the tallest building in San Francisco and the second-tallest building both in California and west of the Mississippi River after the 1,100 feet (335 m) Wilshire Grand Center in Los Angeles.
NEMA, also known as Tenth and Market, is a 754-unit luxury residential apartment complex in the Mid-Market neighborhood of San Francisco, California, United States, across the street from Twitter's corporate headquarters. The complex consists of a 24-story, tower at Jessie and Tenth Streets and a 37-story, tower at Market and Tenth Streets, connected by a nine-story podium along Tenth Street.
340 Fremont Street is a 440-foot (130 m) residential skyscraper in the Rincon Hill neighborhood of San Francisco, California. The tower has 348 residential units on 40 floors.
Oceanwide Center is a mixed-use skyscraper complex on hold in the South of Market neighborhood of San Francisco, California, consisting of two towers.
Park Tower at Transbay is a 43-story, 605-foot (184 m) office skyscraper in San Francisco, California. The tower is located on Block 5 of the San Francisco Transbay development plan at the corner of Beale and Howard Streets, near the Salesforce Transit Center. The tower contains 743,000 square feet (69,000 m2) of office space. The entire office space has been leased by Facebook.
Four Seasons Private Residences at 706 Mission Street, San Francisco is a 43-story, 510 ft (160 m) residential skyscraper under construction in the South of Market district of San Francisco, California. Located across the street from Yerba Buena Gardens and Moscone Center, the tower site is bounded by Mission Street on the south and 3rd Street on the east, and will incorporate the historic Aronson Building in its design. The tower will contain up to 190 condominiums on the upper floors and a permanent home for the Mexican Museum on the bottom four floors.
33 Tehama was a luxury residential apartment complex in South of Market, San Francisco, California. The building is 380 feet (120 m) tall, 35 stories, and contains 403 residential units.
MIRA is a 39-story, 422-foot (129 m) residential skyscraper at 280 Spear Street in San Francisco, California.
{{cite web}}
: CS1 maint: unfit URL (link){{cite web}}
: CS1 maint: unfit URL (link)The shine faded on May 10, 2016, when Agabian attended a homeowners association meeting and was informed that the building had sunk 16 inches into the earth and tilted over 15 inches at its tip and 2 inches at the base, according to suits filed by residents and the city of San Francisco.