Currently, Turkey has no operating commercial nuclear reactors. However, four VVER-1200 reactors at the Akkuyu Nuclear Power Plant, are currently under construction and expected to come online in 2025. [1] The government is aiming for 20 GW of nuclear. [2]
The nuclear power debate has a long history, with the 2018 construction start in Mersin Province being the sixth major attempt to build a nuclear power plant since 1960. [3] Nuclear power has been criticised as very expensive to taxpayers. [4]
Plans for Sinop Nuclear Power Plant and another at İğneada have stalled. [5] The country is considering buying small modular reactors. [6]
Turkey's nuclear activities started soon after the first International Conference on the Peaceful Uses of Atomic Energy, held in Geneva in September 1955. In 1961, a 1 MW test reactor at Çekmece Nuclear Research and Training Center was commissioned for educational and research purposes. [7] As stated by the World Nuclear Association, the first endeavour was a feasibility report in 1970 involving a 300 MWe facility. Then in 1973, the electricity authority agreed to construct a demonstration plant of 80 MWe. In 1976, Akkuyu, a site 45 kilometers west of the southern city Silifke, was chosen as the nuclear power plant site. The Prime Ministry Atomic Energy Authority issued a license for this place. [8] An effort to develop multiple plants failed in 1980 due to a failure of ensuring financial guarantees by the government, that viewed coal plants in Turkey as more favorable. Turkey suspended work on nuclear plants due to the Chernobyl disaster that occurred in the Soviet Union in 1986. In 1988, the TEK Nuclear power plants Department was closed. [9]
In 1993, a nuclear plant was included in the country's investment scheme. However, the revised bidding requirements were not issued until 1996. Bids were issued by Atomic Energy of Canada Limited, the Westinghouse Electric Company-Mitsubishi Heavy Industries consortium and the Framatome-Siemens consortium for a 2000 MWe plant at Akkuyu. The final bid deadline was in 1997, but the government postponed its several times, until the preparations were scrapped due to financial difficulties. [5]
In May 2004, the Minister of Energy and Natural Resources Hilmi Güler said "We will meet with the countries that produce these plants soon" and brought the issue of nuclear power plant back to the agenda. In his statement, Güler stated that the technical investigations on nuclear power plants are continuing and that negotiations will be held soon. [8] Güler announced that the construction of the first power plant will begin in 2007. [10] In 2006, the northern Turkish city of Sinop, located near the Black Sea, was designated to host a commercial nuclear power plant. According to World Nuclear Association, the Sinop site has the advantage of cooling the water temperature approximately 5-degree Celsius lower than those at Akkuyu, helping each thermal reactor to achieve approximately 1 percent greater power output. A 100 MWe demonstration plant was to be installed there. Subsequently, 5000 MWe of additional plants were to come into operation from 2012 onwards. For construction and service, a form of public-private partnership (PPP) has been anticipated. The government said it aimed to have a total of 4500 MWe of energy running from three nuclear power stations by the end of 2015. Talks were happening with AECL over two 750 MWe CANDU reactors. The pressurized water reactor was also favoured by the government. The first reactors, totalling some 5000 MWe, were to be installed at Akkuyu, as the location already was approved. At the same time, the licensing for Sinop was still progressing. [5]
A new legislation on the construction and maintenance of nuclear power plants was enacted by the Turkish Parliament in 2007. [11] The bill called for the establishment of requirements for the design and operation of the plants by the Turkish Atomic Energy Authority (TAEK). It enables the government to grant purchase guarantees to firms for the total energy produced in nuclear power plants. Waste control and decommissioning were also covered by the bill. Turkey started to be subjected to the Paris Convention on Third Party Liability in the Field of Nuclear Energy. Criteria for developers who will build and run nuclear power plants were issued soon after this legislation.
A civil nuclear deal with the United States came into effect in 2008, [12] a nuclear cooperation deal with South Korea was established in June 2010, [13] and two more deals were signed with China in 2012. [14] The following year, the International Atomic Energy Agency (IAEA) performed the Integrated Nuclear Infrastructure Review (INIR) in Turkey to evaluate the country's advancement in the planning for a new nuclear power scheme. Although the review was positive, the IAEA advised Turkey to complete the national nuclear energy strategy and to improve the regulating agency. [5]
In 2007 a bill concerning construction and operation of nuclear power plants and the sale of their electricity was passed by parliament. It also addresses waste management and decommissioning, providing for a National Radioactive Waste Account and a Decommissioning Account, which generators will pay into progressively. [15]
The International Atomic Energy Agency (IAEA) has recommended "enacting a law on nuclear energy which establishes an independent regulatory body and putting a national policy in place that covers a wide range of issues, as well as further developing the required human resources". [16]
In 2018, Turkey created the Nuclear Regulatory Authority. It took over most of the duties of Turkish Atomic Energy Authority (TAEK) like issueing licenses and permits to companies operating nuclear energy and ionizing radiation facilities. [17] [18] TAEK was renamed as TENMAK, and it is now exclusively liable for the management of radioactive waste. [5] According to a scholar, providing concessions for nuclear power plants via international agreements rather than competitive tenders means such projects cannot be challenged in the constitutional court. [19]
Since 1979, a TRIGA research reactor has been running at the Istanbul Technical University named the ITU TRIGA Mark-II Training and Research Reactor. It is supervised by the Turkish Atomic Energy Authority (TAEK). It is the second operational and third installed nuclear research reactors in Turkey, the other being the Çekmece Nuclear Research and Training Center.
The Akkuyu Nuclear Power Plant (Turkish: Akkuyu Nükleer Güç Santrali) is a large nuclear power plant in Turkey under construction in Akkuyu, Büyükeceli, Mersin Province. [20] It is expected to generate around 10% of the country's electricity when completed. [21] The official launch ceremony took place in April 2015. [22]
In May 2010, Russia and Turkey signed an agreement that a subsidiary of Rosatom would build, own, and operate a power plant in Akkuyu comprising four 1,200 MWe VVER1200 units. Construction of the first reactor commenced in April 2018. [23] In February 2013, Russian nuclear construction company Atomstroyexport (ASE) and Turkish construction company Özdoğu signed the site preparation contract for the proposed Akkuyu Nuclear Power Plant. The contract includes excavation work at the site. [24]
It is expected to be the first build–own–operate nuclear power plant in the world. [25] [26]While Turkey's nuclear journey, which started with Adnan Menderes in 1956, has been subject to obstacles for approximately 70 years due to different reasons, this national ideal; Akkuyu Nuclear Power Plant, which started in the 1970s and has not progressed for more than 40 years, was established within the scope of the National Energy Strategy put forward by Berat Albayrak, when he was the Minister of Energy and Natural Resources in 2017. In fact, the production license of Akkuyu Nuclear Power Plant was prepared and construction permit was granted in October 2017. Construction started with the groundbreaking ceremony held in April 2018.
It was reported that this project, which had not been started for over 70 years due to various reasons, had come to the groundbreaking process of the power plant as a result of the intensive efforts of the Minister of Energy and Natural Resources Berat Albayrak in his second year of duty at the Ministry of Energy.
Akkuyu Nuclear Reactor, with its 4800 MW installed power capacity and annual electricity production of 35 billion kWh, will meet 10% of Turkey's electrical energy needs alone and with its investment cost of 20 billion dollars, it is the largest project in the history of the Republic.
In 2013 Turkish Minister of Energy and Natural Resources, Taner Yıldız announced that the government was working on the plans of the third nuclear plant, which was projected to be built after 2023 under the management of Turkish engineers. [28]
In 2015 it was announced that İğneada had been selected as the third site. Technology would have come from US based firm Westinghouse Electric Company in the form of two AP1000 and two CAP1400. [29] [30]
There have been anti-nuclear protests in the past, for example in April 2006, plans to build a nuclear reactor on the Ince peninsula caused a large anti-nuclear demonstration in the Turkish city of Sinop. [31] Greenpeace, who have expressed concerns over earthquakes and the ability of the authorities to protect the public, have opposed these proposals. [32] There are concerns that no site for the waste has yet been selected. [33] In 2022 an opposition MP in Mersin said he was against Akkuyu because it is 51% owned by Russia. [34]
Financing is provided by Russian investors, with 93% from a Rosatom subsidiary. Up to 49% of shares may be sold later to other investors. [35]
Turkish Electricity Trade and Contract Corporation (TETAS) has guaranteed the purchase of 70% power generated from the first two units and 30% from the third and fourth units over a 15-year power purchase agreement. Electricity will be purchased at a price of 12.35 US cents per kW·h and the remaining power will be sold in the open market by the producer. [36] According to energy analysts this price is high. [37] [38]
According to President Erdoğan nuclear power will make the country more economically independent. [39] Although it will be technically possible to ramp power up and down, because fuel is a small part of the cost and operating costs remain the same there is almost no economic benefit in load-following, therefore nuclear is expected to supply baseload power. [40] For baseload power levelized cost of electricity (LCOE) and Value-Added LCOE (VALCOE) are the same. [40] In 2020 Shura Energy Center forecast that for nuclear power that will be 80-85 USD/MWh in 2040. [41]
Operator liability is limited to 700 million euros, and above that will be the responsibility of the Nuclear Damage Detection Commission. [42]Signed contract for the Akkuyu plant foresees the return of nuclear fuel waste to Russia. [43] Other waste and waste from future plants may be stored in Turkey, although it is not yet known where. [44]
The Nyongbyon Nuclear Scientific Research Center (녕변원자력연구소) is North Korea's major nuclear facility, operating its first nuclear reactors. It is located in Nyongbyon County in North Pyongan Province, about 100 km north of Pyongyang. The center produced the fissile material for North Korea's six nuclear weapon tests from 2006 to 2017, and since 2009 is developing indigenous light water reactor nuclear power station technology.
The water-water energetic reactor (WWER), or VVER is a series of pressurized water reactor designs originally developed in the Soviet Union, and now Russia, by OKB Gidropress. The idea of such a reactor was proposed at the Kurchatov Institute by Savely Moiseevich Feinberg. VVER were originally developed before the 1970s, and have been continually updated. They were one of the initial reactors developed by the USSR, the other being the infamous RBMK. As a result, the name VVER is associated with a wide variety of reactor designs spanning from generation I reactors to modern generation III+ reactor designs. Power output ranges from 70 to 1300 MWe, with designs of up to 1700 MWe in development. The first prototype VVER-210 was built at the Novovoronezh Nuclear Power Plant.
Kaiga Generating Station is a nuclear power generating station situated at Kaiga, near the river Kali, in Uttara Kannada district of Karnataka, India. The plant has been in operation since March 2000 and is operated by the Nuclear Power Corporation of India.
Russia is one of the world's largest producers of nuclear energy. In 2020 total electricity generated in nuclear power plants in Russia was 215.746 TWh, 20.28% of all power generation. The installed gross capacity of Russian nuclear reactors is 29.4 GW in December 2020.
Nuclear power plants operate in 32 countries and generate about a tenth of the world's electricity. Most are in Europe, North America and East Asia. The United States is the largest producer of nuclear power, while France has the largest share of electricity generated by nuclear power, at about 70%.
In Pakistan, nuclear power is provided by six commercial nuclear power plants with a net capacity of 3,262 megawatts (3.262 GW) from pressurized water reactors. In 2021, Pakistan's nuclear power plants produced a total of 15.3 terawatt-hours of electricity, which accounted for roughly 10% of the nation's total electric energy generation.
Nuclear power in Switzerland is generated by three nuclear power plants, with a total of four operational reactors (see list below). Since 1985, nuclear power has been contributing approximately 40% of Switzerland's electrical energy. In 2022, it produced 23 terawatt-hours (TWh) of electricity, and accounted for 37% of the nation's gross electricity generation of 62 TWh, while 55% was produced by hydroelectric plants and 8% came from conventional thermal power stations and non-hydro renewable energy sources.
Obninsk Nuclear Power Plant was built in the "Science City" of Obninsk, Kaluga Oblast, about 110 km (68 mi) southwest of Moscow, Soviet Union. Connected to the power grid in June 1954, Obninsk was the first grid-connected nuclear power plant in the world, i.e. the first nuclear reactor that produced electricity industrially, albeit at small scale. It was located at the Institute of Physics and Power Engineering. The plant is also known as APS-1 Obninsk. It remained in operation between 1954 and 2002. Its production of electricity for the grid ceased in 2002; thereafter it functioned as a research and isotope production plant only.
China is one of the world's largest producers of nuclear power. The country ranks third in the world both in total nuclear power capacity installed and electricity generated, accounting for around one tenth of global nuclear power generated. As of February 2023, China has 55 plants with 57GW in operation, 22 under construction with 24 GW and more than 70 planned with 88GW. About 5% of electricity in the country is due to nuclear energy. These plants generated 417 TWh of electricity in 2022 This is versus the September 2022 numbers of 53 nuclear reactors, with a total capacity of 55.6 gigawatt (GW). In 2019, nuclear power had contributed 4.9% of the total Chinese electricity production, with 348.1 TWh.
Atmea was a joint venture between Mitsubishi Heavy Industries (MHI) and EDF Group set up in 2006 to develop, market, license and sell the ATMEA1 reactor, a new generation III+, medium-power pressurized water reactor (PWR). The company was headquartered in Paris. The joint venture was abandoned in 2019.
Slovakia has five operational nuclear reactors, with a combined net power capacity of 2,308 MWe, with a sixth coming on line shortly. Within the EU, Slovakia is one of the pro-nuclear Visegrád Group nations.
Poland currently operates a single research reactor, Maria. It has no operational nuclear reactors for power production, but is to start construction of a plant with three Westinghouse AP1000 reactors in 2026 that was originally planned to be completed in 2033-2036 but is currently expected to only be finished by 2040, and is also intending to build small modular reactors.
In Argentina, about 10% of the electricity comes from 3 operational nuclear reactors: Embalse, a CANDU reactor, and Atucha I and II, two PHWR German designs.
Vietnam is considering developing nuclear power for peaceful purposes based on modern, verified technology since 1995, and firm proposals surfaced in 2006. In November 2016 Vietnam suspended its nuclear power plans. In 2022 industry and trade minister Nguyen Hong Dien announced that developing nuclear power is an “inevitable trend” for Vietnam, and will help the country to become carbon neutral by 2050.
The Akkuyu Nuclear Power Plant is a large nuclear power plant in Turkey under construction in Akkuyu, Büyükeceli, Mersin Province. It is expected to generate around 10% of the country's electricity when completed. The official launch ceremony took place in April 2015.
Energy consumption per person in Turkey is similar to the world average, and over 85 per cent is from fossil fuels. From 1990 to 2017 annual primary energy supply tripled, but then remained constant to 2019. In 2019, Turkey's primary energy supply included around 30 per cent oil, 30 per cent coal, and 25 per cent gas. These fossil fuels contribute to Turkey's air pollution and its above average greenhouse gas emissions. Turkey mines its own lignite but imports three-quarters of its energy, including half the coal and almost all the oil and gas it requires, and its energy policy prioritises reducing imports.
The Çekmece Nuclear Research and Training Center, known as ÇNAEM, is the primary nuclear research and training center of Turkey. The organization was established on March 6, 1958 as a subunit of Turkish Atomic Energy Administration at Küçükçekmece district in the west of Istanbul. The organization's name was coined on August 12, 1960 in conjunction with its location.
The Sinop Nuclear Power Plant is a proposed nuclear plant in Turkey located at Sinop on the Black Sea. Talks with China, Russia and South Korea are ongoing in 2023. If constructed, it will be the country's second nuclear power plant after Akkuyu Nuclear Power Plant.
Turkey uses more electricity per person than the global average, but less than the European average, with demand peaking in summer due to air conditioning. Most electricity is generated from coal, gas and hydropower, with hydroelectricity from the east transmitted to big cities in the west. Electricity prices are state-controlled, but wholesale prices are heavily influenced by the cost of imported gas.
The IPHWR-700 is an Indian pressurized heavy-water reactor designed by the NPCIL. It is a Generation III reactor developed from earlier CANDU based 220 MW and 540 MW designs. It can generate 700 MW of electricity. Currently there are two units operational, 6 units under construction and 8 more units planned, at a combined cost of ₹1.05 lakh crore (US$13 billion).