Rajasthan Atomic Power Station

Last updated

Rajasthan Atomic Power Station
Rawatbhata Nuclear Powerplant.jpg
Rajasthan Atomic Power Station
CountryIndia
Coordinates 24°52′20″N75°36′50″E / 24.87222°N 75.61389°E / 24.87222; 75.61389
StatusOperational
Construction began1963
Commission date 16 December 1973
Operator Nuclear Power Corporation of India Ltd (NPCIL)
Nuclear power station
Reactors8
Reactor type PHWR
Reactor supplierUnits 1 & 2: AECL
Units 3 to 8: NPCIL
Cooling towers8 × Natural Draft
Cooling source Rana Pratap Sagar Dam, Chambal River
Power generation
Units operational1 × 200 MW
4 × 220 MW
Make and modelUnits 1 & 2: CANDU
Units 3 to 6: IPHWR-220
Units 7 & 8: IPHWR-700
Units under const.2 × 700 MW
Units decommissioned1 × 100 MW
Nameplate capacity 1080 MW
Capacity factor 78.07% (2020-21) [1]
Annual net output 7386 GW.h (2020-21) [1]
External links
Website Nuclear power Corporation of India Ltd
Commons Related media on Commons

The Rajasthan Atomic Power Station (RAPS; also Rajasthan Atomic Power Project - RAPP) is a nuclear power plant located at Rawatbhata in the state of Rajasthan, India. It is the fourth largest nuclear power plant in the country after the Kudankulam Nuclear Power Plant, Kakrapar Atomic Power Station, and Tarapur Atomic Power Station interms of installed capacity.

Contents

History

Rawatbhata Nuclear Powerplant Rawatbhata Nuclear Powerplant.jpg
Rawatbhata Nuclear Powerplant

The construction of the Douglas Point Nuclear Generating Station Canada began in 1961 with a CANDU (Canada Deuterium Uranium) pressurised heavy water reactor (PHWR) capable of producing 220  MW of electricity. Two years after the construction of the Rajasthan Atomic Power Project (RAPP) commenced, two similar reactors were built in the state of Rajasthan. Ten years later, in 1973 RAPS-1 was put into service. In 1974 after India conducted Smiling Buddha, its first nuclear weapons test Canada stopped its support of the project, delaying the commissioning of RAPS-2 until 1981. [2]

In the context of the Indian atomic program, two more PHWR with an output of 220 MW each were built. They cost around 570 million dollars. RAPS-3 became critical on 24 December 1999, RAPS-4 became critical on 3 November 2000. Commercial operations began on 1 June 2000 for unit 3, and on 23 December 2000 for unit 4.

Two more reactors (RAPS-5 and RAPS-6) with 220 MWe have also been built, with unit 5 beginning commercial operation on 4 February 2010, and unit 6 on 31 March 2010. [3]

Two of the new Indian-designed 700 MWe series of the reactor (RAPP-7 and RAPP-8) are under construction in Rajasthan.

In November 2012, the International Atomic Energy Agency (IAEA) intensively audited over several weeks two reactors at the Rajasthan Atomic Power Station for safety. It has been concluded that the reactors are among the best in the world, the indigenously made 220 MW atomic plants can withstand a Fukushima type of accident, even suggesting that the "safety culture is strong in India" and that India emerged a winner with a high global safety rank. [4]

First concrete for unit 7 was poured on 18 July 2011, [5] with commercial operation expected by 2016. Unit 7 and unit 8 will cost together an estimated Rs 123.2 billion (US$2.6 billion). [6]

In 2024 the AERB granted permission for unit 7 fuel loading and addition of moderator. The 19 September 2024, unit 7 started a controlled fission chain reaction. [7]

Incidents

By 2003 RAPS-1 had experienced numerous problems due to leaks, cracks in the end-shield and turbine blade failures, had undergone repairs and appeared to be generating 100 MW of electricity, with RAPS-2 reportedly generating 200 MW. [2]

On 29 August 2006, a 90% iron meteorite weighing 6.8 kilograms (15 lb) fell in Kanvarpura village, near the power station. The Deputy Director-General (western region) of the Geological Survey of India, R.S. Goyal, said that devastation on an "unimaginable scale" would have ensued had the object struck the station. [8] However, the kinetic energy of a meteorite of this size is smaller than that of jet aircraft frequently used as a basis for impact resistance of containment structures. [9] [10]

In June 2012, 38 workers were exposed to tritium when a welding operation went wrong inside the protected environment of the reactor. [11]

Units

PhaseUnit
No.
ReactorStatusCapacity in MWeConstruction startFirst criticality Grid ConnectionCommercial operationClosureNotes
TypeModelNetGross
I1 PHWR CANDU Shut Down-pending decommissioning901001 August 196511 August 197230 November 197216 December 19739 October 2004 [12]
2 PHWR CANDU Operational1872001 April 19688 October 19801 November 19801 April 1981 [13]
II3 PHWR IPHWR-220 Operational2022201 February 199024 December 199910 March 20001 June 2000 [14]
4 PHWR IPHWR-220 Operational2022201 October 19903 November 200017 November 200023 December 2000 [15]
III5 PHWR IPHWR-220 Operational20222018 September 200224 November 200922 December 20094 February 2010 [16]
6 PHWR IPHWR-220 Operational20222020 January 200323 January 201028 March 201031 March 2010 [17]
IV7 PHWR IPHWR-700 Critical63070018 July 201119 September 2024 [18] [19] [20]
8 PHWR IPHWR-700 Under Construction63070030 September 2011 [18] [21]

Current status

Unit 1 was placed under permanent shutdown and is to be decommissioned. Unit 2 to 6 are currently operational. The AERB has give permission to add moderator, fuel and start chain reaction in unit 7 recently. It is expected to come online by the year end. Unit 8 is expected to come online next year. These two are IPHWR-700 reactor. Unit 7 achieved criticality on 19 September 2024. It is expected to come online for commercial operation by the end of the year.

See also

References

  1. 1 2 "Monthly Genration Reports Actual for Apr-2021 : Central Sector Nuclear" (PDF). National Power Portal. Central Electricity Authority. Retrieved 10 October 2021.
  2. 1 2 "Rajasthan Atomic Power Station (RAPS)". Nuclear Threat Initiative . 1 September 2003. Retrieved 18 February 2017.
  3. "Rajasthan Atomic Power Station (RAPS)". Plants Under Operation. Nuclear Power Corporation of India Limited (NPCIL). Archived from the original on 16 July 2011. Retrieved 18 July 2011.
  4. Bagla, Pallava (15 November 2012). "UN's nuclear watchdog: Rajasthan reactors are among world's safest". NDTV.com.
  5. "India begins construction of 25th nuclear plant". The Hindu . 18 July 2011. Retrieved 18 July 2011.
  6. "Construction starts on new Rajasthan units". World Nuclear News . World Nuclear Association (WNA). 18 July 2011. Retrieved 18 July 2011.
  7. "Rajasthan Atomic Power Project-7 goes critical, to start power generation this year". ETEnergyworld.com. 20 September 2024. Archived from the original on 21 September 2024. Retrieved 21 September 2024.
  8. Meteorite fall in Rajasthan village The Hindu, 6 September 2006.
  9. Jiang, Hua; Chorzepa, Mi G. (1 November 2014). "Aircraft impact analysis of nuclear safety-related concrete structures: A review". Engineering Failure Analysis. 46: 118–133. doi:10.1016/j.engfailanal.2014.08.008.
  10. Allain, Rhett (1 March 2013). "How Fast Would a Small Meteor Travel?". Wired.
  11. Bagla, Pallava (30 June 2012). Bhatt, Abhinav (ed.). "Radiation scare in Rajasthan, workers exposed". NDTV.com.
  12. "Rajasthan Atomic Power Station". NPCIL. Retrieved 13 February 2020.
  13. "RAPS-2". PRIS. Retrieved 13 February 2020.
  14. "RAPS-3". PRIS. Retrieved 13 February 2020.
  15. "RAPS-4". PRIS. Retrieved 13 February 2020.
  16. "RAPS-5". PRIS. Retrieved 13 February 2020.
  17. "RAPS-6". PRIS. Retrieved 13 February 2020.
  18. 1 2 "Kakrapar 3 achieves first criticality : New Nuclear - World Nuclear News".
  19. "Indian government takes steps to get nuclear back on track - World Nuclear News". world-nuclear-news.org. Retrieved 28 March 2019.
  20. "RAPS-7". PRIS. Retrieved 13 February 2020.
  21. "RAPS-8". PRIS. Retrieved 13 February 2020.