G Line | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | RapidRide | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator | King County Metro | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Garage | Ryerson Base | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Began service | September 14, 2024 [1] | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Route | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Seattle, Washington | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Start | Downtown Seattle | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Via | Madison Street | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
End | Martin Luther King Jr. Way in Madison Valley | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Length | 2.1 mi (3.4 km) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stops | 21 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The RapidRide G Line is a RapidRide bus service in Seattle, Washington, operated by King County Metro on Madison Street between Downtown Seattle and Madison Valley. It uses five-door articulated buses to serve a mix of side and center platforms at its 21 stations. The line opened for service on September 14, 2024, and cost $133.4 million to construct; it features several sections with bus lanes and transit signal priority.
The G Line travels 2.5 miles (4.0 km) between 1st Avenue in Downtown Seattle and Martin Luther King Jr. Way in Madison Valley on Madison Street. [2] [3] The line has 2.8 miles (4.5 km) of dedicated transit lanes [1] and 1.14 miles (1.83 km) of mixed-traffic business access and transit lanes. [4] : 18 The project included the reconstruction of 36 intersections to upgrade traffic signals and 50 blocks of refurbished sidewalks. [5]
The route begins near Colman Dock, the city's ferry terminal, at a station on 1st Avenue. [2] This station was planned to be shared with a future Seattle Streetcar extension. Within Downtown Seattle, buses travel eastbound on Spring Street and westbound on Madison Street in transit lanes, stopping near the Symphony light rail station at 3rd Avenue and the Seattle Central Library at 5th Avenue. The route crosses over Interstate 5 into First Hill, where the two directions merge after 9th Avenue onto Madison, continuing to run in center transit-only lanes. The G Line crosses Broadway, with a station connecting to the First Hill Streetcar, and passes the campus of Seattle University before transitioning to mixed traffic east of 15th Avenue. The route continues into Madison Valley, serving several curbside stations, before terminating at Martin Luther King Jr. Way near the Washington Park Arboretum. [4] : 8–11
The G Line serves 21 total stops on its route, including 10 stops in each direction and the western terminal near Colman Dock. [4] : 8 Stations are approximately 60 feet (18 m) long and feature off-board fare payment (including ticket vending machines), raised platforms for level boarding, branded shelters, real-time arrival information, and other features. [4] : 10 [6]
Station [4] : 8–9 | Layout | Notes |
---|---|---|
1st Avenue | Side platform | Western terminus, shared with future Seattle Streetcar project. Connection to Colman Dock (Washington State Ferries), King County Water Taxi, and Kitsap Fast Ferries. |
3rd Avenue | Side platforms | Connections to Link 1 Line and RapidRide C, D, E, and H Lines. |
5th Avenue | Side platforms | |
8th Avenue | Center platform (Westbound) Side platform (Eastbound) | |
Terry Avenue | Center platform | |
Summit Avenue/ Boylston Avenue | Center platform | Connection to First Hill Streetcar |
12th Avenue/ 13th Avenue/ Union Street | Center platform | |
17th Avenue | Side platforms | |
22nd Avenue | Side platforms | Connection to future 23rd Ave RapidRide Line |
24th Avenue | Side platforms | Connection to future 23rd Ave RapidRide Line |
27th Avenue/ Martin Luther King Jr. Way | Side platforms | Eastern terminus |
The G Line, internally designated as Route 677, runs 23 hours per day with a headway of 6 minutes on weekdays and 15 minutes during weekends, and weekday mornings and evenings. [7] [4] : 14 It has the highest frequency of any bus route in the King County Metro system. [8] Travel times from Downtown Seattle to Madison Valley are projected to improve from 16 minutes to 10 minutes with the G Line. [9] The line is projected to carry 12,000 to 18,000 daily passengers. [10]
The G Line is operated by 60-foot-long (18 m), articulated, hybrid buses with low floors and doors on both sides. Plans to purchase new trolleybuses for this line were dropped in March 2019 [11] after New Flyer Industries stated that the desired model would not be available in a single vehicle. [12] Metro was unable to find another North American manufacturer willing to build articulated trolleybuses that could handle the very steep grades on the westernmost portion of the line (18–19%). [11]
The New Flxyer XDE60 buses have a total of five doors, three on the right and two on the left, for boarding at stations in the center and side of the roadway. [2] [4] : 14
The G Line project is expected to cost $120 million, and will be funded by a mix of sources. [13] Funding will be provided by a grant from the Federal Transit Administration (FTA), the 2015 Move Seattle levy, and the 2016 Sound Transit 3 ballot measure. [14] [15] [16] The FTA awarded a $59.9 million Small Starts grant to the city government for the project in April 2021. [17]
The Madison Street corridor was identified as a bus rapid transit candidate in the 2012 Transit Master Plan, adopted by the city of Seattle with input from King County Metro. [18] While other routes were given feasibility studies for streetcars, as part of a new municipal system, Madison Street was considered too steep to support rail transit. [19] The Madison Street corridor, from Downtown Seattle to Madison Park, was historically served by cable car service from 1890 until 1940, when they were scrapped and replaced with motor buses and trolleybuses on modern-day routes 11 and 12. [19] [20]
A design concept for the service was first presented for public comment in 2014, featuring two options for the eastern terminus, at 23rd Avenue or Martin Luther King Jr Way (MLK Way). A public survey was conducted and found higher support for the MLK Way terminus, as well as preferences for station locations and transfers to other transit routes. [21] In February 2016, the Seattle City Council approved a locally preferred alternative for the project and endorsed it to pursue federal funding. [22]
Residents of a condominium building on the line opposed the construction of a traction power substation that would be needed for the trolleybuses, citing possible health risks from exposure to electromagnetic fields. [23] Portions of properties along the route were acquired for construction of wider sidewalks and platforms, including the patio space of queer bar Pony. [24]
As of 2017, construction on the project was planned to begin in mid-2018, with the line scheduled to open in 2019. [13] However, it was later reported that uncertainty around federal funding was expected to delay construction. [25] Reflecting those delays and following an FTA review, in March 2020 the projected opening date was pushed back to 2023. [26] A further delay to 2024 and a budget increase to $133.4 million was announced in August 2020 due to an updated consultant review amid potential impacts of the COVID-19 pandemic. [10]
A groundbreaking ceremony was held on September 30, 2021, with Federal Transit Administrator Nuria Fernandez in attendance. [27] Construction on Madison Street began in October 2021. [28] A ribbon-cutting ceremony was held on August 29, 2024, to mark the completion of construction. [29] The G Line opened on September 14, 2024, with a community celebration; [8] several routes in the area also changed to connect with the line. [1] [30]
The first days of service included issues with real-time arrival signs at stations, the curb-activated doors on buses, and signal priority issues. [31] Three of the line's center platform stations opened with temporary steel plates in the busway due to construction defects that left the platforms too low for level boarding. A total of 25 shelters at stations are also planned to be rebuilt due to frame and paint issues. [32]
Sound Transit (ST), officially the Central Puget Sound Regional Transit Authority, is a public transit agency serving the Seattle metropolitan area in the U.S. state of Washington. It manages the Link light rail system in Seattle and Tacoma, regional Sounder commuter rail, and Sound Transit Express bus service. The agency also coordinates the regional ORCA fare card system, which is also used by local transit operators. In 2019, Sound Transit services carried a total of 48 million passengers and averaged over 161,000 riders on weekdays.
The Downtown Seattle Transit Tunnel (DSTT), also referred to as the Metro Bus Tunnel, is a 1.3-mile-long (2.1 km) pair of public transit tunnels in Seattle, Washington, United States. The double-track tunnel and its four stations serve Link light rail trains on the 1 Line as it travels through Downtown Seattle. It runs west under Pine Street from 9th Avenue to 3rd Avenue, and south under 3rd Avenue to South Jackson Street. 1 Line trains continue north from the tunnel to Lynnwood City Center and south through the Rainier Valley past Seattle–Tacoma International Airport to Angle Lake station as part of Sound Transit's light rail network.
King County Metro, officially the King County Metro Transit Department and often shortened to Metro, is the public transit authority of King County, Washington, which includes the city of Seattle. It is the eighth-largest transit bus agency in the United States. In 2023, the system had a ridership of 78,121,600, or about 277,400 per weekday as of the third quarter of 2024. Metro employs 2,477 full-time and part-time operators and operates 1,540 buses.
The 1 Line, formerly Central Link, is a light rail line in Seattle, Washington, United States, and part of Sound Transit's Link light rail system. It serves 23 stations in King and Snohomish counties, traveling 33 miles (53 km) between Lynnwood City Center and Angle Lake stations. The line connects Lynnwood, Mountlake Terrace, Shoreline, the University District, Downtown Seattle, the Rainier Valley, and Seattle–Tacoma International Airport. The 1 Line carried over 26 million total passengers in 2023, with an average of nearly 80,000 daily passengers on weekdays. It runs for 20 hours per day on weekdays and Saturdays, with headways as low as six minutes during peak hours, and reduced 18-hour service on Sundays and holidays.
Lynnwood Transit Center is a bus station and light rail station in Lynnwood, Washington. It is the largest transit hub in southwestern Snohomish County and is served by Community Transit and Sound Transit Express. The transit center also includes a parking garage with 1,670 spaces and bicycle facilities.
Tukwila International Boulevard station is a light rail station in Tukwila, Washington, United States. It is located between SeaTac/Airport and Rainier Beach stations on the 1 Line from Seattle–Tacoma International Airport to Downtown Seattle. The station consists of two elevated side platforms enclosed within a structure northeast of the interchange of State Route 99 and State Route 518. As one of seven park and rides along the line, it includes 600 parking spaces in two lots.
International District/Chinatown station is a light rail station that is part of the Downtown Seattle Transit Tunnel in Seattle, Washington, United States. The station is located at the tunnel's south end, at 5th Avenue South and South Jackson Street in the Chinatown-International District neighborhood, and is served by the 1 Line of Sound Transit's Link light rail system. The station is located adjacent to Sound Transit headquarters at Union Station, as well as intermodal connections to Amtrak and Sounder commuter rail at King Street Station and the First Hill Streetcar.
Pioneer Square station is a light rail station that is part of the Downtown Seattle Transit Tunnel in Seattle, Washington, United States. The station is located under 3rd Avenue at James Street, between Symphony and International District/Chinatown stations. It is served by the 1 Line, part of Sound Transit's Link light rail system, and provides connections to local buses and Colman Dock, a major ferry terminal serving areas west of Seattle.
Symphony station, formerly University Street station, is a light rail station that is part of the Downtown Seattle Transit Tunnel in Seattle, Washington, United States. The station is located under 3rd Avenue at University Street, near Benaroya Hall, and is served by Sound Transit's 1 Line. It is located between Westlake and Pioneer Square stations and has surface connections to buses operated by King County Metro and other providers.
Westlake station is a light rail station that is part of the Downtown Seattle Transit Tunnel in Seattle, Washington, United States. The station is located under Pine Street between 3rd and 6th avenues in Downtown Seattle, near Westlake Center and Westlake Park. It is served by the 1 Line, part of Sound Transit's Link light rail system, and also connected above ground by buses at several stops, the South Lake Union Streetcar, and the Seattle Center Monorail.
RapidRide is a network of limited-stop bus routes with some bus rapid transit features in King County, Washington, operated by King County Metro. The network consists of eight routes totaling 76 miles (122 km) that carried riders on approximately 64,860 trips on an average weekday in 2016, comprising about 17 percent of King County Metro's total daily ridership.
Northgate is a light rail and bus station in the Northgate neighborhood of Seattle, Washington, United States, and part of 1 Line on Sound Transit's Link light rail system. The transit center, located adjacent to the Northgate Mall, has four bus bays served by 22 routes. The station also has parking for 1,475 vehicles.
The First Hill Streetcar, officially the First Hill Line, is a streetcar route in Seattle, Washington, United States, forming part of the modern Seattle Streetcar system. It travels 2.5 miles (4.0 km) between several neighborhoods in central Seattle, including the International District, First Hill, and Capitol Hill. The line has ten stops and runs primarily in mixed traffic on South Jackson Street and Broadway.
South Bellevue station is an elevated light rail station located in Bellevue, Washington, United States, an eastern suburb of Seattle. It opened on April 27, 2024, as the western terminus of the 2 Line of Sound Transit's Link light rail system. The station has a park and ride garage with 1,500 stalls and bus service from King County Metro and Sound Transit Express.
Bellevue Transit Center (BTC) is a bus station and light rail station in Bellevue, Washington, a suburb of Seattle. It is the main transit hub for the Eastside of King County, serving 20 routes from King County Metro and Sound Transit Express. The transit center is the western terminus of the RapidRide B Line, which runs east to Redmond.
Madison Street is a major thoroughfare of Seattle, Washington. The street originates at Alaskan Way on the Seattle waterfront, and heads northeast through Downtown Seattle, First Hill, Capitol Hill, Madison Valley, Washington Park, and Madison Park, ending just east of 43rd Avenue East on Lake Washington. From Broadway to Lake Washington, the street is known as East Madison Street, which accounts for most of its length. It is the only Seattle street that runs uninterrupted from the salt water of Puget Sound in the west to the fresh water of Lake Washington in the east.
The Seattle trolleybus system forms part of the public transportation network in the city of Seattle, Washington, operated by King County Metro. Originally opened on April 28, 1940, the network consists of 15 routes, with 174 trolleybuses operating on 68 miles (109 km) of two-way parallel overhead lines. As of the third quarter of 2024, the system carries riders on an average of 39,500 trips per weekday, comprising about 18 percent of King County Metro's total daily ridership.
The C Line is one of eight RapidRide lines operated by King County Metro in King County, Washington. The C Line began service on September 29, 2012, running between downtown Seattle, West Seattle, Fauntleroy and the Westwood Village Shopping Center in the Westwood neighborhood. The line runs mainly via Westlake Avenue, 3rd Avenue, Washington State Route 99, the West Seattle Bridge, California Avenue and Fauntleroy Way.
Shoreline North/185th station is a Link light rail station on the Lynnwood Link Extension serving Shoreline, Washington. The station is located in a trench on the east side of Interstate 5, on the north side of Northeast 185th Street. It includes an adjacent bus station and two-story parking garage with 360 stalls. The station opened on August 30, 2024, with the rest of the line. Shoreline North/185th station also serves as the terminus of the Swift Blue Line.
Redmond Technology station, formerly Overlake Transit Center, is a bus and light rail station in Redmond, Washington, United States. The bus station opened in 2002 adjacent to State Route 520 on the headquarters campus of Microsoft. It was served by Sound Transit Express and King County Metro, as well as Microsoft's private shuttle buses. The light rail station is the eastern terminus of the 2 Line, part of Sound Transit's Link light rail system, and opened on April 27, 2024.