Electricity sector in Brazil

Last updated

Electricity sector of Brazil
Data
Electricity coverage (2016)97% (total), (LAC total average in 2005: 92%)
Installed capacity (2021)181,532 MW
Share of fossil energy 17%
Share of renewable energy 83% (60% hydroelectric)
GHG emissions from electricity generation (2003)20 MtCO2
Average electricity use (2007)2,166 kWh per capita (USA: 12,300 kWh per capita)
Distribution losses (2005)14%
Consumption by sector
(% of total)
Residential34% (2006)
Industrial25% (2006)
Commercial22% (2006)
Public sector13% (2006)
Rural6% (2006)
Tariffs and financing
Average residential tariff
(US$/kW·h, 2007)
0.153; (LAC average in 2005: 0.115)
Average industrial tariff
(US$/kW·h, 2005)
0.113; (LAC average in 2005: 0.107)
Average commercial tariff
(US$/kW·h, June 2005)
0.142
Services
Sector unbundlingYes
Share of private sector in generation10%
Competitive supply to large usersYes
Competitive supply to residential usersNo
Institutions
No. of service providers6 main (generation), 5 main (transmission), 49 (distribution)
Responsibility for regulationANEEL-Electricity Regulatory Agency
Responsibility for policy-settingMinistry of Mines and Energy
Responsibility for the environmentMinistry of the Environment
Electricity sector lawYes (2004)
Renewable energy lawNo
CDM transactions related to the electricity sector91 registered CDM project; 9,034,000 tCO2e annual emissions reductions

Brazil has the largest electricity sector in Latin America. Its capacity at the end of 2021 was 181,532 MW. [1] The installed capacity grew from 11,000 MW in 1970 with an average yearly growth of 5.8% per year. [2] Brazil has the largest capacity for water storage in the world, [3] being dependent on hydroelectricity generation capacity, which meets over 60% of its electricity demand. The national grid runs at 60 Hz and is powered 83% from renewable sources. This dependence on hydropower makes Brazil vulnerable to power supply shortages in drought years, as was demonstrated by the 2001–2002 energy crisis. [4]

Contents

The National Interconnected System (SIN) comprises the electricity companies in the South, South-East, Center-West, North-East and part of the North region. Only 3.4% of the country's electricity production is located outside the SIN, in small isolated systems located mainly in the Amazonian region. [5]

Electricity supply and demand

Installed capacity

Installed capacity by source in Brazil (2023) [6]
Circle frame.svgNatural gas: 17,613 MW (7.7%)Biomass: 16,923 MW (7.4%)Others (Oil, coal, imports): 20,328 MW (8.8%)
  •   Hydro: 109,909 MW (47.8%)
  •   Solar: 35,739 MW (15.5%)
  •   Wind: 27,660 MW (12.0%)
  •   Natural gas: 17,613 MW (7.7%)
  •   Biomass: 16,923 MW (7.4%)
  •   Nuclear: 1,990 MW (0.9%)
  •   Others (Oil, coal, imports): 20,328 MW (8.8%)
Sources of electricity in Brazil, 2000-2020 Electricity generation in Brazil by energy source.png
Sources of electricity in Brazil, 2000–2020
  • Installed capacity does not mean the amount of energy generated. Solar energy, for example, only generates around 20% of installed capacity, while wind energy can generate 40 to 60%. Each source has a different generation.

At the end of 2021 Brazil was the 2nd country in the world in terms of installed hydroelectric power (109.4 GW) and biomass (15.8 GW), the 7th country in the world in terms of installed wind power (21.1 GW) and the 14th country in the world in terms of installed solar power (13.0 GW) - on track to also become one of the top 10 in the world in solar energy. [7] At the end of 2021, Brazil was the 4th largest producer of wind energy in the world (72 TWh), behind only China, USA and Germany, and the 11th largest producer of solar energy in the world (16.8 TWh). [8]

The main characteristic of the Brazilian energy matrix is that it is much more renewable than that of the world. While in 2019 the world matrix was only 14% made up of renewable energy, Brazil's was at 45%. Petroleum and oil products made up 34.3% of the matrix; sugar cane derivatives, 18%; hydraulic energy, 12.4%; natural gas, 12.2%; firewood and charcoal, 8.8%; varied renewable energies, 7%; mineral coal, 5.3%; nuclear, 1.4%, and other non-renewable energies, 0.6%. [9]

In the electric energy matrix, the difference between Brazil and the world is even greater: while the world only had 25% of renewable electric energy in 2019, Brazil had 83%. The Brazilian electric matrix was composed of: hydraulic energy, 64.9%; biomass, 8.4%; wind energy, 8.6%; solar energy, 1%; natural gas, 9.3%; oil products, 2%; nuclear, 2.5%; coal and derivatives, 3.3%. [9]

Generation capacity in Brazil is still dominated by hydroelectric plants, [4] which accounted for 77% of total installed capacity, [10] with 24 plants above 1,000 MW. In the old days, about 88 percent of the electricity fed into the national grid is estimated to came from hydroelectric generation, with over 25% coming from a single hydropower plant, the massive 14 GW Itaipu dam facility, located between Brazil and Paraguay on the Paraná River. [4] Natural gas generation is second in importance, representing about 10% of total capacity, [10] close to the 12% goal for 2010 established in 1993 by the Ministry of Mines and Energy. [11]

This reliance on abundant hydroelectric resources allegedly reduces the overall generation costs. However, this large dependence on hydropower made the country especially vulnerable to supply shortages in low-rainfall years (see The 2001–2002 crisis below). [12]

By the end of 2016, the breakdown of generation by source was: [10]

SourceNumber of plantsInstalled capacity (MW) % Total
Hydroelectricity125996,92564.5%
Gas15612,9658.6%
Oil22008,8775.9%
Biomass50414,0019.3%
Nuclear21,9901.3%
Coal133,3892.3%
Wind41310,1240.2%
Total installed capacity4,707150,33894.3%
Contracted imports5,8505.7%
Available power156,271100%

Source: Ministry of Mines and Energy, 2016

As summarized in the table above, Brazil has two nuclear power plants, Angra 1 (657 MW) and Angra 2 (1,350 MW), both of them owned by Eletronuclear, a subsidiary of the state-owned (Mixed economy) Eletrobrás. [13]

New generation projects

Brazil needs to add 6000 MW of capacity every year in order to satisfy growing demand from an increasing and more prosperous population. The Brazilian Ministry of Energy has decided to generate 50% of new supplies from hydropower, 30% from wind and biomass such as bagasse, and 20% from gas and other sources. Wind in the North-East is strongest during the dry season when hydropower plants produce less, so the two energy sources are seasonally complementary. [14]

Hydroelectric plants

Brazil has an untapped hydropower potential of 180,000 MW, including about 80,000 MW in protected regions for which there are no development plans. The government expects to develop the rest by 2030. Most new hydropower plants are run-of-river plants that are less damaging to the environment, because their reservoirs are small. However, they are more vulnerable to droughts and less efficient, because only a fraction of their capacity can be used during the dry season. [14]

The National Agency for Electricity (ANEEL) has commissioned feasibility studies for several hydroelectric plants (small, medium and large) in the period 2006–2008. These studies correspond to a total potential capacity of 31,000 MW. In 2007, Ibama, the environmental agency, gave approval for the construction of two new dams, the Jirau Dam (3,300 MW) and the Santo Antônio Dam (3,150 MW), on the Madeira River in the state of Rondônia. [15] The bid for the Santo Antônio plant was awarded in December 2007 to Madeira Energy, with a 39% participation from state-owned Furnas, while the bid for the Jirau plant will be launched in May 2008. [16] The government is also pursuing development of the controversial 11,000 MW Belo Monte Dam in the state of Pará, on the Xingu River. IBAMA approved Belo Monte's provisional environmental license in February 2010 despite internal uproar from technicians over incomplete data. [17]

Nuclear plants

Also in 2007, Electronuclear was granted permission to resume construction of Angra 3, a 1,350 MW plant, and is currently in the process of selecting a site for a fourth nuclear power plant. [13] In February 2014, Eletrobras Eletronuclear awarded contracts to begin construction, with an estimated completion date of 2018. [18] [ unreliable source? ]

Thermoelectric plants

Currently, the development of gas-fired thermoelectric power is somewhat jeopardized by the lack of secure gas supplies. In fact, having a secure gas contract is a prerequisite to build a new thermoelectric plant and to participate in a new energy auction (see Energy auctions below). In order to counter the risk of unavailability of gas supplies, Brazil is in the initial stages of planning to build two LNG terminals that would likely come on-stream around 2010. However, in the meantime, several thermoelectric plants are converting their machinery to dual-fuel capacity (oil and gas). [19]

Demand

Total electricity consumed in 2007 was 410 terawatt hour (TWh), while annual consumption per capita for the same year averaged 2,166 kWh. [20] The share of consumption by sector was as follows: [21]

Electricity demand is expected to grow an average of 3.6% in the next few years, leading to total estimated consumption of 504 TWh and average per capita consumption of 2,527 kWh. [22] [ when? ]

In Brazil, capacity addition traditionally lagged behind demand growth. [4] Electricity demand is expected to continue to grow at a quick pace. The income elasticity of demand for electricity is estimated by Eletrobras at above unity. Between 1980 and 2000, electricity demand increased on average by 5.4 percent per year while GDP grew by 2.4 percent on average per year. Investment is therefore needed to boost generation and transmission capacity because there is limited excess supply, despite the reduction in demand following the energy rationing program implemented in 2001 in response to the energy crisis. [3]

Access to electricity

Brazil, together with Chile, is the country with the highest access rate in Latin America. The power sector in Brazil serves more than 50 million customers, which corresponds to about 97% of the country's households, who have access to reliable electricity. [4]

Service quality

Interruption frequency and duration

Interruption frequency and duration are very close to the averages for the LAC region. In 2005, the average number of interruptions per subscriber was 12.5, while duration of interruptions per subscriber was 16.5 hours. The weighted averages for LAC were 13 interruptions and 14 hours respectively. [23]

Distribution losses

Distribution losses in 2005 were 14%, well in line with the 13.5% average for the LAC region [23] but about double that of an OECD country such as the Great Britain, with 7% distribution losses. [24]

Responsibilities in the electricity sector

Policy and regulation

The Ministry of Energy and Mines (MME) has the overall responsibility for policy setting in the electricity sector while ANEEL , which is linked to the Ministry of Mines and Energy, is the Brazilian Electricity Regulatory Agency created in 1996 by Law 9427. ANEEL's function is to regulate and control the generation, transmission and distribution of power in compliance with the existing legislation and with the directives and policies dictated by the Central Government. [25] The National Council for Energy Policies (CNPE), is an advisory body to the MME in charge of approving supply criteria and "structural" projects while the Electricity Industry Monitoring Committee (CMSE) monitors supply continuity and security. [26]

ANEEL and the Ministry of Environment play almost no part in which investment projects go ahead, but they only influence how projects are executed once the decision has been taken. Both have had their bosses resign rather than supporting infrastructure projects in the Amazon. [14]

The Operator of the National Electricity System (ONS) is a non-profit private entity created in August 1998 that is responsible for the coordination and control of the generation and transmission installations in the National Interconnected System (SIN). The ONS is under ANEEL's control and regulation. [5]

The Power Commercialization Chamber (CCEE), successor of MAE (Mercado Atacadista de Energia Electrica), is the operator of the commercial market. The initial role of the operator was to create a single, integrated commercial electricity market, to be regulated under published rules. This role has become more active since now CCEE is in charge of the auction system. [12] The rules and commercialization procedures that regulate CCEE's activities are approved by ANEEL. [27]

Finally, the Power Research Company (EPE) was created in 2004 with the specific mission of developing an integrated long-term planning for the power sector in Brazil. Its mission is to carry out studies and research services in the planning of the energy sector in areas such as power, oil and natural gas and its derivates, coal, renewable energy resources and energy efficiency, among others. Its work serves as input for the planning and implementation of actions by the Ministry of Energy and Mines in the formulation of the national energy policy [28]

The Brazilian electricity model is fully deregulated, which allows generators to sell all of their "assured energy" via freely negotiated contracts with consumers above 3 MW or via energy auctions administered by CCEE (see energy auctions below). . Under this model, distributors are required to contract 100% of their expected demand. Currently, Brazilian generation supply can be sold under four types of markets: [19]

(*The government identifies two types of generation capacity, "old energy" and "new energy". Old energy represents existing plants that were already contracted in the 1990s, while new energy refers to that energy produced by plants that have not yet been built, or by existing plants that meet certain criteria.)

Generation

In Brazil, large government-controlled companies dominate the electricity sector. Federally owned Eletrobras holds about 40% of capacity (including 50% of the Itaipu dam), with state-companies CESP, Cemig and Copel controlling 8%, 7% and 5% of generation capacity respectively. [19]

Generation capacity is shared among the different companies as follows:

CompanyControlling shareholderInstalled capacity (MW) % Total
Eletrobras (1)Federal Gvt.38,11140%
CESPSP State Gvt.7,4518%
CemigMG State Gvt.6,6927%
CopelPR State Gvt.4,5505%
Tractebel Energia GDF Suez 6,8707%
AES Tiete AES Corp. 2,6513%
OthersMostly private sector29,96931%
Brazil Total96,294100%

Source: Eletrobras, CESP, Cemig, Copel, Tractebel Energia, AES Tiete, Ministry of Energy and Mines(1) Considering 6,300MW of Iguaçú

Currently, about 27 percent of the generation assets are in the hands of private investors. Considering the plants under construction, as well as the concessions and licenses already granted by ANEEL, this figure is expected to grow up to 31 percent in the medium term and to reach almost 44 percent over 5–6 years. Private capital participation in the generation business will likely represent 50 percent of the installed capacity in the years to come [4]

Transmission

Brazil's transmission system is growing in importance since adequate transmission capacity is essential to manage the effects of regional droughts, allowing to move power from areas where rainfall is plentiful. As a matter of fact, the rationing that occurred in Brazil in 2001–2002 (see The 2001–2002 crisis below), could have largely been averted if there had been adequate transmission capacity between the south (excess supply) and the southeast (severe deficit). [19]

Transmission has remained almost exclusively under government control through both federal (Eletrobras) and state companies (mainly Sao-Paulo-CTEEP, Minas Gerais-Cemig, and Parana-Copel) until recently.[ when? ] However, under the new sector regulatory model, there are about 40 transmission concessions in Brazil. Most of them are still controlled by the government, with subsidiaries under federal company Eletrobras holding 69% of total transmission lines. [19]

CompanyControlling shareholderConcession areaTransmission lines (km)
Pure transmission companies
CTEEPISA (Colombia)São Paulo State11,837
Terna Participacoes Terna (Italy) Goias, Bahia, Brazilian, Maranhao2,447
Companies with significant transmission operations
CemigState of MGMinas Gerais21,184
CopelState of ParanaParana7,045
Eletrosul, Furnas, Eletronorte, Chesf Eletrobras Throughout Brazil56,384

Source: Bear Stearns 2007

Distribution

In Brazil, there are 49 utilities with distribution concessions [21] and about 64% of Brazilian distribution assets are controlled by private sector companies. [19] The following table lists Brazil's most important distribution companies:

CompanyControlling shareholderConcession areaSales (GWh)Sales (%)
CemigMG State GovtMinas Gerais20,22140%
Enel Enel [29] São Paulo city31,64212.5%
CPFLVBC GroupSão Paulo State outside São Paulo city36,13514.3%
CopelPR State Govt.Parana17,5246.9%
Energias do Brasil EDP São Paulo, Rio Grande do Sul15,8636.3%
CelescSC State GvtSanta Catarina15,1576.0%
Light EDF Río de Janeiro City19,1397.6%
Equatorial (Cemar)GP Investimentos/PactualMaranhao2,7931.1%
Ampla (Cerj)EnersisRio de Janeiro6,8322.7%
OthersMostly private sector87,59434.6%
Brazil Total252,900100.0%

Source: Bear Stearns, 2007

Renewable energy resources

In Brazil, hydroelectricity supplies about 60% of total electricity demand. It is estimated that about 70% of the overall hydroelectricity potential of the country, is still unexploited. [19]

At the end of 2021 Brazil was the 2nd country in the world in terms of installed hydroelectric power (109.4 GW) and biomass (15.8 GW), the 7th country in the world in terms of installed wind power (21.1 GW) and the 14th country in the world in terms of installed solar power (13.0 GW) - on track to also become one of the top 10 in the world in solar energy. From 2013, Brazil started to deploy wind energy on a large scale, and from 2017, it started to deploy solar energy on a large scale, to diversify its energy portfolio and avoid the problems arising from dependence on hydroelectricity. [30]

The potential for wind energy, which is concentrated in the Northeast, is very large. Brazil's gross wind resource potential was estimated, in 2019, to be about 522 GW (this, only onshore), enough energy to meet three times the country's current demand. [31] [32]

PROINFA

In 2002, the government of Brazil created a Program to Foster Alternative Sources of Electric Power (PROINFA). The program aims to increase the participation of wind power sources, biomass sources and small hydropower systems in the supply of the Brazilian grid system through Autonomous Independent Producers (PIA). The medium to long-term objective (i.e. 20 years) of the program is that the defined sources supply 15% of the annual market growth until they reach 10% of the nation's annual electric power demand/total consumption. [33]

History

Situation prior to the reforms: the state-dominated model

The power sector in Brazil was essentially in government's hands until the early 1990s. The sector had seen remarkable development in the 1970s. However, by the late 1980s, the state-ownership model was on the verge of collapse. This delicate situation was the result of heavily subsidized tariffs and a revenue shortfall in the sector of about US$35 billion, which led to the delay in the construction of about 15 large hydro plants due to lack of funds for investment. Efforts to address the deterioration of the sector were not successful, a situation that further intensified the need for deep reforms. A major commitment was made by President Cardoso to carry out a substantial reform of the Brazilian electricity sector. The first reforms introduced in the power sector were aimed to allow the participation of private capital and also to improve its economic situation. [4]

1990s reforms

The Project for Restructuring the Brazilian Electric Sector, RESEB, which laid down the first steps for the implementation of the power sector reform, was initiated in 1996 during the administration of President Cardoso. The objective of the reform was to build a more competitive power sector with the creation of a level playing field for private sector participation. In addition, state-owned utilities and assets were privatized. Although transmission assets were not privatized, most of the expansion of the transmission network has been carried out by private capital. [4] This reform also led to the creation, in 1996, of ANEEL (Brazil's National Electricity Regulatory Agency), a quasi-independent regulatory body in charge of overseeing the electricity sector. However, the main restructuring steps were taken with the enactment of the 1998 Law (Law 9648/98). Those steps included the creation of an independent operator of the national transmission system (ONS) and an operator of the commercial market (MAE), which did not become operational until 2001. [4]

As a result of the reforms of the power sector, new capital was attracted, both in terms of privatization and greenfield projects. Some of the state-owned generation capacity was acquired by foreign investors such as Tractebel, AES, Prisma Energy, El Paso and Duke, which became significant producers. In addition, local investors such as industrial groups, large customers, utilities and pension funds also invested heavily in the national generation sector. Other companies such as EdF ( Électricité de France ), Endesa and Chilectra focused on the distribution segment, a segment in which privatization brought improved quality of service and a reduction of theft, non-payments and technical losses. [4]

However, the reforms were not successful in preventing the energy crisis that was to unfold in 2001. Installed capacity expanded by only 28 percent between 1990 and 1999, whereas electricity demand increased by 45 percent. [3] In 1999, as the power shortage was already foreseen, the President Cardoso Administration made efforts to increase private investment in the electricity sector through a Priority Thermal Power Program (PPT) that aimed at the expeditious construction of more than 40 gas-fired thermal plants. Unfortunately, the needed investment did not materialize and the crisis became unavoidable. [4]

2001–2002 crisis and the government's response

Brazil was faced with one of the most serious energy crises in its history in 2001–2002. The crisis was the direct result of a sequence of a few years drier than average in a country with over 80% of hydroelectric generation capacity. Additionally, several delays in the commissioning of new generation plants and transmission problems in the third circuit from the Itaipu hydropower plant accounted for a third of the energy deficit. Reservoir levels reached such low levels that supply could not be ensured for more than four months. [4]

It was soon clear that strict demand reduction programs would be needed to avoid widespread blackouts. In June 2001, the government created the Crisis Management Board (CGE), chaired by President Cardoso himself. The CGE received special powers among which was the authority to set up special tariffs, implement compulsory rationing and blackouts, and bypass normal bidding procedures of the purchase of new plant equipment. Instead of resorting to rolling blackouts, the government chose to apply a quota system. Quotas were established for all the consumers based on historical and target consumption level, applying bonuses for consumption well below the prescribed level, penalties for over-consumption and some freedom for the large users to trade their quotas in a secondary market. The government's goal of reducing historical consumption levels by at least 20% for an eight-month period was successfully achieved, with the government having to pay over US$200 million in bonuses to residential, industrial, and commercial customers. This achievement allowed the system to overcome that long period without blackouts and brownouts [34] and proved the potential of demand-side management and energy efficiency efforts, which were able to create a virtual capacity of 4,000 MW, helping the country to bridge the supply demand gap in a very economic way. In addition, the government launched a program for contracting emergency generation capacity, with bids for a total of 2,100MW of new thermal capacity accepted. [4]

However, the crisis affected numerous actors. Generators and distributors experienced a 20% reduction in their revenues due to the contraction in consumption. This situation was eventually addressed by an increase of tariffs approved by the government. The financial situation of distributors was also damaged, with customers also suffering from the increase in electricity prices (140% in nominal terms between 1995 and 2002). [4]

2003–2004 reforms: energy auctions

In January 2003, the new administration led by Luiz Inácio Lula da Silva took over among criticism of the reforms introduced in the electricity sector by the administration of President Cardoso, supporting a model in which the system should be fully regulated. The pending privatizations of three generation subsidiaries of the large state-owned utility, Eletrobras, were stopped. However, despite initial expectations, the new administration opted for a model that clearly aims to attract long-term private investment to the sector and that heavily relies on competition. In addition, the existing institutions were preserved and in some cases strengthened, with a new company, EPE, created with the specific mission of developing an integrated long-term planning for the power sector in Brazil. [4]

The new legislative framework was defined by Law 10,848/2004, which established clear, stable and transparent rules aimed at ensuring supply and the continuous expansions of the intrinsic sector activities (generation, transmission and distribution). The expansion was linked to a fair return on investments and to universal service access, together with tariff adjustments. Decree 5,081/2004 approved the regulatory framework for the power sector, specifying specific provisions to achieve the objectives of the reform. [5] One of the defining elements of the model adopted by the new administration is the establishment of energy auctions as the main procurement mechanism for distribution companies to acquire energy to serve their captive consumers. This initiative assisted in the introduction of competition in the power sector and also helped to address some of the existing market imperfections. Under this system, auctions of capacity from new generation projects will be held three to five years in advance of delivery dates. The Ministry of Mines and Energy wants to ensure that the totality of future expansion needs is met and that plants are only built once they have won bids in energy auctions and are guaranteed long-term contracts. The first auction was held in December 2004, with contracts for a total of about 40 GW traded. [4]

Tariffs and subsidies

Tariffs

Average electricity tariffs for the different sectors in 2007 were as follows: [35]

Investment and financing

In the last 20 years, Brazil has been one of the main recipients of private capital investment in its power sector. [4] Total investment by private actors in the power sector between 1994 and 2006 amounted to US$56,586 million in 124 projects. [36] However, despite Brazil's deregulation and higher tariffs in the "new energy" auction system, investment, particularly in generation, has slowed significantly. This situation is not considered to be the result of concerns about the regulatory model or auction pricing caps, but it reflects the lack of available projects. The existing delays in granting environmental licenses and the uncertainties on the Bolivian gas supply, explain to a great extent the lack of hydroelectric and gas-fired thermoelectric projects respectively. [19]

The investment required in power generation over the next 10 years is R$40 billion or around US$24.2 billion (April 29, 2008). This high investment will only be realized if the government succeeds in attracting greater private-sector investment. [20]

Summary of private participation in the electricity sector

In Brazil, large government-controlled companies dominate the electricity sector. Federally owned Eletrobras holds about 40% of capacity (including 50% of Itaipu), with state-companies CESP, Cemig and Copel controlling 8%, 7% and 5% of generation capacity respectively. About 27% of generation assets are currently in the hands of private investors.

Transmission, it has remained almost exclusively under government control through both federal (Eletrobras) and state companies (mainly Sao-Paulo-CTEEP, Minas Gerais-Cemig, and Parana-Copel) until recently.[ when? ] However, under the new sector regulatory model, there are about 40 transmission As for distribution, there are 49 utilities with distribution concessions and about 64% of distribution assets are controlled by private sector companies.

ActivityPrivate participation (%)
Generation10%
Transmissionmostly public
Distribution64%

Electricity and the environment

Responsibility for the environment

The Ministry of the Environment holds the environmental responsibilities in Brazil. One of its associated institutions is Ibama, the Brazilian Institute for the Environment and Renewable Natural Resources, which is in charge of executing the environmental policies dictated by the Ministry regarding environmental licensing; environmental quality control; authorization of the use of natural resources; and environmental monitoring and control among others. [37]

Greenhouse gas emissions

OLADE (Latin American Energy Association) estimated that CO2 emissions from electricity production in 2003 were 20 million tons of CO2, which corresponds to less than 7% of total emissions from the energy sector. [38] This low contribution to emissions from electricity production in comparison with other countries in the region is due to the high share of hydroelectric generation.

CDM projects in electricity

Brazil is host to the largest number of CDM projects in the Latin America region. Registered projects represent 40% of the total in the region and account for 45% of Certified Emission Reductions (CERs) (up to 2012). [39]

As for the power sector, there were 91 projects registered in March 2008, adding up to an estimated total of 9 million tons of CO2 per year. The distribution of projects by category is as follows: [40]

Project typeNumber of projectsktonCO2/year
Biomass energy381,860
Energy efficiency industry149
Energy efficiency own generation190
Energy distribution154
Fossil fuel switch6139
Hydroelectricity231,013
Landfill gas 175,660
Wind4170
TOTAL919,034

Source: UNFCCC

Energy costing of Brazilian electricity

An exergoeconomic assessment accounting for the total and non-renewable unit exergy costs and specific CO2 emissions of Brazilian electricity is performed by Flórez-Orrego et al. (2014), [41] comprising thermal, nuclear, hydro, wind farms and biomass-fired power plants. The analysis starts from the fuel obtainment and continues through the different stages of construction, fuel transportation and processing, operation and decommissioning of the plant, with electricity generation as the desired output. This approach allows the calculation of direct CO2 emissions as well as the upstream and downstream emissions, which play an important role in some technologies. In this way, a better comparison between the utilization of different fuels in the electricity generation can be achieved. An iterative calculation procedure is used to determine the unit exergy costs of electricity and processed fuels, since both electricity and processed fuel are used in their own production routes.

As it was expected, fossil-fired power plants presents the highest specific CO2 emissions, with the coal-fired power plants leading the group. However, even though fossil-fired power plants presents the most marked environmental impacts, their total unit exergy costs are much lower than that presented by sugar cane bagasse-fired power plants. This shows that, although almost renewable, the typical configurations of sugar cane bagasse-fired power plants are far from being efficient technologies. Hydro and wind farms present the lowest specific CO2 emissions as well as the lowest unit exergy cost. Due to the high participation of renewable sources in the production of electricity (near to 89% of the total), Brazilian electricity mix emissions are found to be 7.5 and 11.8 times lower than Europe and World electricity mixes. Also, owed to the higher efficiency of hydroelectric power plants, which contribute to the major part of the electricity generation in Brazil, the total unit exergy cost is lower, and thus, exergy efficiency of electricity generation is higher if compared with countries based on fossil fuels for electricity generation.

Apparently, total exergy cost of wind and natural-gas fired technologies are almost the same, but contrarily to the wind power plants, the non-renewable unit exergy costs of NG-fired power plants is practically equal to the total cost. This result is a consequence of the efficiency assumed for wind power plants. If energy storage is to be taken into account for intermittent technologies such as wind farms, the total exergy cost could be slightly increased. The upstream and downstream CO2 emissions in the coal route represent a very small part of the total CO2 emissions, if compared with the direct emissions of coal burning in the power plant. Finally, it is pointed out that controversies related to the flooding dams of vast zones with complex ecosystems should be carefully analysed since, according to the results reported by Dones et al., the GHG emissions could be increased up to achieve emission levels comparable to those of gas combined cycles power plants.

External assistance

Inter-American Development Bank

The Inter-American Development Bank (IDB) is currently (April 2008) supporting several projects and contributing to various technical assistance initiatives in the power sector in Brazil. The most relevant projects with financing from the IDB are:

World Bank

The World Bank is currently (April 2008) supporting three rural poverty reduction projects that include the provision of access to electricity services:

Sources

See also

Notes

  1. https://antigo.aneel.gov.br/web/guest/sala-de-imprensa-exibicao-2/-/asset_publisher/zXQREz8EVlZ6/content/brasil-termina-2021-com-maior-acrescimo-em-potencia-instalada-desde-2016/656877?inheritRedirect=false&redirect=https%3A%2F%2Fantigo.aneel.gov.br%2Fweb%2Fguest%2Fsala-de-imprensa-exibicao-2%3Fp_p_id%3D101_INSTANCE_zXQREz8EVlZ6%26p_p_lifecycle%3D0%26p_p_state%3Dnormal%26p_p_mode%3Dview%26p_p_col_id%3Dcolumn-2%26p_p_col_pos%3D2%26p_p_col_count%3D3%26_101_INSTANCE_zXQREz8EVlZ6_advancedSearch%3Dfalse%26_101_INSTANCE_zXQREz8EVlZ6_keywords%3D%26_101_INSTANCE_zXQREz8EVlZ6_delta%3D15%26p_r_p_564233524_resetCur%3Dfalse%26_101_INSTANCE_zXQREz8EVlZ6_cur%3D5%26_101_INSTANCE_zXQREz8EVlZ6_andOperator%3Dtrue National Agency of Energy
  2. Pottmaier, D.; Melo, C. R.; Sartor, M. N.; Kuester, S.; Amadio, T. M.; Fernandes, C. A. H.; Marinha, D.; Alarcon, O. E. (1 March 2013). "The Brazilian energy matrix: From a materials science and engineering perspective". Renewable and Sustainable Energy Reviews. 19: 678–691. doi:10.1016/j.rser.2012.11.063. ISSN   1364-0321.
  3. 1 2 3 OECD
  4. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 World Bank 2007
  5. 1 2 3 National System Operator (ONS)
  6. "Infográfico". ABSOLAR (in Brazilian Portuguese). Retrieved 14 January 2024.
  7. "RENEWABLE CAPACITY STATISTICS 2022" (PDF). IRENA. Retrieved 19 May 2022.
  8. Hannah Ritchie and Max Roser, Solar Power Generation
  9. 1 2 Matriz Energética e Elétrica
  10. 1 2 3 Ministry of Energy and Mines 2016
  11. Fernandes, Elton; Marcus; Fonseca, A.; Paulo Sergio, R. Alonso (2005). "Natural gas in Brazil's energy matrix: demand for 1995–2010 and usage factors". Energy Policy. 33 (3): 365–386. doi:10.1016/j.enpol.2003.08.006.
  12. 1 2 Lock, Reinier (2005). "The New Electricity Model in Brazil: An Institutional Framework in Transition". The Electricity Journal. 18: 52–61. doi:10.1016/j.tej.2004.12.003.
  13. 1 2 EIA
  14. 1 2 3 "The rights and wrongs of Belo Monte". The Economist. 4 May 2013. Retrieved 4 May 2013.
  15. The Economist
  16. Canal Energia [ permanent dead link ]
  17. ORM Belém
  18. "Angra-3 PWR Nuclear Reactor Project, Brazil".
  19. 1 2 3 4 5 6 7 8 Bear Stearns 2007
  20. 1 2 Economist Intelligence Unit, 2008
  21. 1 2 ABRADEE
  22. Economist Intelligence Unit, 2007
  23. 1 2 Benchmarking data of the electricity distribution sector in Latin America and Caribbean Region 1995-2005
  24. OFGEM
  25. Decree No 2.335, October 6, 1997
  26. Millán, 2006
  27. "CCEE - Câmara de Comercialização de Energia Elétrica". Archived from the original on 16 November 2007. Retrieved 16 June 2008.
  28. pt:Empresa de Pesquisa Energética
  29. "Enel Brasil Investimentos Sudeste, S.A. completed the acquisition of 93.3% stake in Eletropaulo Metropolitana Eletricidade de São Paulo S.A. from Eletrobras Participações S.A. - Eletropar and others for BRL 7.1 billion".
  30. "RENEWABLE CAPACITY STATISTICS 2022" (PDF). IRENA. Retrieved 19 May 2022.
  31. Ventos promissores a caminho
  32. "Brazilian onshore wind potential could be 880 GW, study indicates". Archived from the original on 14 August 2020. Retrieved 1 November 2020.
  33. IEA
  34. ESMAP, 2005. Chapter 4 [ permanent dead link ]
  35. "ANEEL". Archived from the original on 20 May 2011. Retrieved 17 April 2008.
  36. Private Participation in Infrastructure Database
  37. Brazilian Institute for the Environment and Renewable Natural Resources (Ibama)
  38. OLADE Archived 2007-09-28 at the Wayback Machine
  39. UNEP Riso Center. CDM pipeline, March 2008
  40. UNFCCC
  41. Flórez-Orrego, Daniel (2014). "Renewable and non-renewable exergy cost and specific CO2 emission of electricity generation: The Brazilian case". Energy Conversion and Management. 85: 619–629. doi:10.1016/j.enconman.2014.04.058.

Related Research Articles

<span class="mw-page-title-main">Hydroelectricity</span> Electricity generated by hydropower

Hydroelectricity, or hydroelectric power, is electricity generated from hydropower. Hydropower supplies one sixth of the world's electricity, almost 4500 TWh in 2020, which is more than all other renewable sources combined and also more than nuclear power. Hydropower can provide large amounts of low-carbon electricity on demand, making it a key element for creating secure and clean electricity supply systems. A hydroelectric power station that has a dam and reservoir is a flexible source, since the amount of electricity produced can be increased or decreased in seconds or minutes in response to varying electricity demand. Once a hydroelectric complex is constructed, it produces no direct waste, and almost always emits considerably less greenhouse gas than fossil fuel-powered energy plants. However, when constructed in lowland rainforest areas, where part of the forest is inundated, substantial amounts of greenhouse gases may be emitted.

<span class="mw-page-title-main">Electricity sector in India</span> Power generation and distribution

India is the third largest producer of electricity in the world. During the fiscal year (FY) 2022–23, the total electricity generation in the country was 1,844 TWh, of which 1,618 TWh was generated by utilities.

<span class="mw-page-title-main">Renewable energy in Brazil</span>

As of 2018, renewable energy accounted for 79% of the domestically produced electricity used in Brazil.

<span class="mw-page-title-main">Energy in Brazil</span> Overview of the production, consumption, import and export of energy and electricity in Brazil

Brazil is the 7th largest energy consumer in the world and the largest in South America. At the same time, it is an important oil and gas producer in the region and the world's second largest ethanol fuel producer. The government agencies responsible for energy policy are the Ministry of Mines and Energy (MME), the National Council for Energy Policy (CNPE), the National Agency of Petroleum, Natural Gas and Biofuels (ANP) and the National Agency of Electricity (ANEEL). State-owned companies Petrobras and Eletrobras are the major players in Brazil's energy sector, as well as Latin America's.

<span class="mw-page-title-main">Electricity sector in Colombia</span>

The electricity sector in Colombia is dominated by large hydropower generation (65%) and thermal generation (35%). Despite the country's large potential for new renewable energy technologies, this potential has been barely tapped. A 2001 law designed to promote alternative energies lacks certain key provisions to achieve this objective, such as feed-in tariffs, and has had little impact so far. Large hydropower and thermal plants dominate the current expansion plans. The construction of a transmission line with Panama, which will link Colombia with Central America, is underway.

The electricity sector in Argentina constitutes the third largest power market in Latin America. It relies mostly on thermal generation and hydropower generation (36%). The prevailing natural gas-fired thermal generation is at risk due to the uncertainty about future gas supply.

As of August 2020 Chile had diverse sources of electric power: for the National Electric System, providing over 99% of the county's electric power, hydropower represented around 26.7% of its installed capacity, biomass 1.8%, wind power 8.8%, solar 12.1%, geothermal 0.2%, natural gas 18.9%, coal 20.3%, and petroleum-based capacity 11.3%. Prior to that time, faced with natural gas shortages, Chile began in 2007 to build its first liquefied natural gas terminal and re-gasification plant at Quintero near the capital city of Santiago to secure supply for its existing and upcoming gas-fired thermal plants. In addition, it had engaged in the construction of several new hydropower and coal-fired thermal plants. But by July 2020 91% of the new capacity under construction was of renewable power, 46.8% of the total solar and 25.6% wind, with most of the remainder hydro.

The electricity sector in Peru has experienced large improvements in the past 15 years. Access to electricity has increased from 45% in 1990 to 96.4% in 2018, while service quality and efficiency of service provision improved. These improvements were made possible through privatizations following reforms initiated in 1992. At the same time, electricity tariffs have remained in line with the average for Latin America.

<span class="mw-page-title-main">Electricity sector in Nicaragua</span>

Nicaragua is the country in Central America with the lowest electricity generation, as well as the lowest percentage of population with access to electricity. The unbundling and privatization process of the 1990s did not achieve the expected objectives, resulting in very little generation capacity added to the system. This, together with its high dependence on oil for electricity generation, led to an energy crisis in 2006 from which the country has not fully recovered yet.

<span class="mw-page-title-main">Electricity sector in El Salvador</span>

El Salvador's energy sector is largerly focused on renewables. El Salvador is the largest producer of geothermal energy in Central America. Except for hydroelectric generation, which is almost totally owned and operated by the public company CEL, the rest of the generation capacity is in private hands. With demand expected to grow at a rate of 5% in the coming years, the Government's 2007 National Energy Strategy identified several hydroelectric and geothermal projects as the best option to meet demand in the future and to diversify the country's energy mix.

<span class="mw-page-title-main">Energy in Romania</span>

Energy in Romania describes energy and electricity production, consumption and import in Romania.

<span class="mw-page-title-main">Electricity sector in Uruguay</span>

The electricity sector of Uruguay has traditionally been based on domestic hydropower along with thermal power plants, and reliant on imports from Argentina and Brazil at times of peak demand. Over the last 10 years, investments in renewable energy sources such as wind power and solar power allowed the country to cover in early 2016 94.5% of its electricity needs with renewable energy sources.

The term smart grid is most commonly defined as an electric grid that has been digitized to enable two way communication between producers and consumers. The objective of the smart grid is to update electricity infrastructure to include more advanced communication, control, and sensory technology with the hope of increasing communication between consumers and energy producers. The potential benefits from a smart grid include increased reliability, more efficient electricity use, better economics, and improved sustainability.

<span class="mw-page-title-main">Electricity sector in the United Kingdom</span> Overview of the electricity sector in the United Kingdom

The United Kingdom has a National Grid that covers most of mainland Great Britain and several of the surrounding islands, as well as some connectivity to other countries. The electrical sector supplies power at 50 Hz AC, and ~240 volts is supplied to consumers. In 2020 the electricity sector's grid supply came from 55% low-carbon power, 36.1% fossil fuelled power, and 8.4% imports. Renewable power is showing strong growth, while fossil fuel generator use in general and coal use in particular is shrinking, with historically dominant coal generators now mainly being run in winter due to pollution and costs, and contributed just 1.6% of the supply in 2020.

The Polish energy sector is the fifth largest in Europe. In 2022, the country consumed 13.16 TWh of electricity, importing 3 114 GWh thereof.

<span class="mw-page-title-main">Energy in Spain</span> Overview of the production, consumption, import and export of energy and electricity in Spain

Primary energy consumption in Spain in 2015 was mainly composed of fossil fuels. The largest sources are petroleum (42.3%), natural gas (19.8%) and coal (11.6%). The remaining 26.3% is accounted for by nuclear energy (12%) and different renewable energy sources (14.3%). Domestic production of primary energy includes nuclear (44,8%), solar, wind and geothermal (22,4%), biomass and waste (21,1%), hydropower (7,2%) and fossil (4,5%).

<span class="mw-page-title-main">Solar power in Mexico</span> Overview of solar power in Mexico

Solar power in Mexico has the potential to produce vast amounts of energy. 70% of the country has an insolation of greater than 4.5 kWh/m2/day. Using 15% efficient photovoltaics, a square 25 km (16 mi) on each side in the state of Chihuahua or the Sonoran Desert could supply all of Mexico's electricity.

<span class="mw-page-title-main">Renewable energy in Turkey</span>

Renewables supply a quarter of energy in Turkey, including heat and electricity. Some houses have rooftop solar water heating, and hot water from underground warms many spas and greenhouses. In parts of the west hot rocks are shallow enough to generate electricity as well as heat. Wind turbines, also mainly near western cities and industry, generate a tenth of Turkey’s electricity. Hydropower, mostly from dams in the east, is the only modern renewable energy which is fully exploited. Hydropower averages about a fifth of the country's electricity, but much less in drought years. Apart from wind and hydro, other renewables; such as geothermal, solar and biogas; together generated almost a tenth of Turkey’s electricity in 2022. Türkiye has ranked 5th in Europe and 12th in the world in terms of installed capacity in renewable energy. The share of renewables in Türkiye’s installed power reached to 54% at the end of 2022.

<span class="mw-page-title-main">Electricity sector in Turkey</span> Electricity generation, transmission and consumption in Turkey

Turkey uses more electricity per person than the global average, but less than the European average, with demand peaking in summer due to air conditioning. Most electricity is generated from coal, gas and hydropower, with hydroelectricity from the east transmitted to big cities in the west. Electricity prices are state-controlled, but wholesale prices are heavily influenced by the cost of imported gas.

<span class="mw-page-title-main">Wind power in Uruguay</span>

Wind power in Uruguay generates a rapidly growing proportion of the country's electricity mix. In 2014, Uruguay installed the most wind power capacity per capita in the world. Overall, the majority of Uruguayan electricity generation is derived from hydroelectric sources.