Horns Rev Offshore Wind Farm

Last updated
Horns Rev
HornsRev Blavandshuk.jpg
Horns Rev 1 wind farm with Horns Rev A substation platform
Horns Rev Offshore Wind Farm
Country Denmark
LocationHorns Rev, East North Sea
Coordinates 55°31′47″N7°54′22″E / 55.52972°N 7.90611°E / 55.52972; 7.90611
StatusOperational
Construction beganMay 2008 (II)
2016 (III)
Commission date 2002 (I)
November 2009 (II)
2019 (III)
Construction cost€448 million [1] (II)
€1 billion [2] (III)
Owner(s) Vattenfall (60%),Ørsted (40%) (I)
Ørsted (II)
Vattenfall (III)
Operator(s) Vattenfall (I)
Ørsted (II)
Vattenfall (III)
Wind farm
Type Offshore
Max. water depth6–14 m (20–46 ft) (I)
9–17 m (30–56 ft) (II)
11–19 m (36–62 ft) (III)
Distance from shore14–20 km (9–12 mi) (I)
30 km (19 mi) (II)
29–44 km (18–27 mi) (III)
Hub height70 m (230 ft) (I)
68 m (223 ft) (II)
105 m (344 ft) (III)
Rotor diameter80 m (262 ft) (I)
93 m (305 ft) (II)
164 m (538 ft) (III)
Rated wind speed9.7 m/s (32 ft/s) (I)
10 m/s (33 ft/s) (II)
14 m/s (46 ft/s) (III)
Power generation
Units operational80 × 2 MW (I)
91 × 2.3 MW (II)
49 × 8.3 MW (III)
Make and model Vestas: V80-2.0 (I)
Siemens: SWT 2.3-93 (II)
MHI Vestas: V164 (III)
Nameplate capacity 160 MW [3] (I)
209 MW (II)
406.7 MW (III)
Capacity factor 47.7% [4] (II)
Annual net output 600 GW·h [5] (I)
External links
Website www.hornsrev.dk
www.dongenergy.com
corporate.vattenfall.com
Commons Related media on Commons
Horns Rev Offshore Wind Farm
Wind farm layout

Horns Rev is an offshore wind farm in Danish waters in the North Sea.

Contents

The wind farm was built in three phases, the first coming online in 2002, the second in 2009 and the third in 2019. Horns Rev 1, the first phase, was the first large-scale offshore wind farm in the world, with a capacity of 160 MW. [3] [6]

Horns Rev 1

Horns Rev's location in relation to the wind farms of the German Bight Map of the offshore wind power farms in the German Bight.png
Horns Rev's location in relation to the wind farms of the German Bight

Horns Rev 1, built by Danish energy company Elsam (later DONG, now Ørsted) was the first large-scale offshore wind farm in the world. Its capacity of 160 MW was four times that of the previous largest, the Middelgrunden at 40 MW. [7] [8] It was the first offshore wind farm in the North Sea, the first to use the monopile foundation type and the first to have its transformer on an adjacent platform rather than onshore. [9] Technologies used for the first time at Horns Rev 1 have since become industry standard.

The farm has 80  Vestas V80 wind turbines, each generating 2.0 MW. They were installed by the Danish offshore wind farm services provider A2SEA in 2002, the last turbine coming into operation on 11 December 2002. A guaranteed price of 0.453 DKK/kWh was agreed for the first 42,000 hours of generation. [10]

In 2005, 60% of the wind farm was sold to Vattenfall, also the operator of the park, for DKK2bn. [11] [ unreliable source? ]

The turbines are laid out in an oblique 8 by 10 grid over an area of 5 km × 3.8 km, with 560 m between turbines in both directions. A radar measures details of the wind patterns, improving local short-term forecasting. [12] [13]

The main method of transport to the first wind park is an adapted Eurocopter EC-135 helicopter, [14] used to hoist workers to and from a small platform on each turbine. Sea conditions render the area inaccessible to boats for large parts of the year.

The farm has an availability of 96–97%. Two turbines are burnt out, and uneconomic to replace with less than 10 years left. [14] Grout between monopile and tower was damaged by vibrations, requiring a costly fix. [15]

Horns Rev 2

In May 2008, Dong Energy began construction of the second wind farm in the Horns Rev area, Horns Rev 2. Construction was completed in September 2009 [16] and was inaugurated on September 17, 2009 by Prince Frederik on the Poseidon accommodation platform. [17] When inaugurated, Horns Rev 2 was the largest offshore wind farm in the world until Thanet Wind Farm opened on 23 September 2010. [17] [18]

For the year of 2012, HR2 reached a capacity factor of 52.0%. [4] It receives 51.8 øre/kWh for the first 50,000 hours, paid by electricity consumers. [10] The farm has had some cable outages, [19] [20] and blades are being renovated. [21]

The Horns Rev 2 consists of 91  Siemens Wind Power SWT 2.3-93 wind turbines with a total generating capacity of 209 MW. [18] The foundations are monopiles like on Horns Rev 1.

It has the first offshore wind farm accommodation platform in the world, named Poseidon. It is connected by walkway to the transformer platform, [22] and is 750 square metres (8,100 sq ft) large with 3 decks and weighs 422 tons. On-site accommodation is cheaper and more efficient than transporting service personnel by boat 2 hours from Esbjerg harbour 60 kilometres (37 mi) away. A turbine is visited 10 times a year on average, mostly for routine service, and 1-2 times for fixing faults. [23] Flying people by helicopter to turbines like on Horns Rev  1 is not possible on Horns Rev 2 as the turbines there are not built for it, although the transformer platform has a helipad. [24] Poseidon has 24 rooms of 12 square meters each fitted with TV and internet. There is a gym, kitchen, dining room, laundry room, and a study room. Inspired by Poseidon, a similar platform is being built at the DanTysk wind farm. [25]

Horns Rev 3

In April 2012, most of the Danish Folketing (parliament) agreed to send out tenders in 2013 for a 400 MW wind farm at Horns Rev called Horns Rev 3, and a 600 MW at Kriegers Flak in the Baltic Sea, both likely receiving 90 øre/kWh for the first 50,000 hours. [10] This is expected to raise wind power in Denmark above the 39% of annual electricity production (as of 2014), [26] which includes the 400 MW Anholt Offshore Wind Farm. [27] [28] The Danish Energy Agency expects construction candidates for Horns Rev 3 to have experience with installing and operating a large offshore wind farm. [29] [30] Some of the area is an old minefield from World War Two. [31] Four bidders were qualified for the tender. [32]

Vattenfall won the tender in February 2015, at a price of 77 øre/kWh, well below the 105 øre at Anholt. [33] Vattenfall states that they bid unaggressively against strong competition without sacrificing margins. [34] The price reduction contributes to a smaller "green subsidy" (PSO) over the next years. [35] [36] Horns Rev 3 consists of a total of 49 MHI Vestas V164-8.3 MW units, capable of producing 406.7 MW. [37] Three transformers were installed in July 2016. [38] The first turbines started to produce electricity for the grid in December 2018, [39] and the last turbine was installed in January 2019. [40] The official inauguration of Horns Rev 3 was on 22 August 2019. [41]

See also

Related Research Articles

<span class="mw-page-title-main">Horns Rev</span>

Horns Rev is a shallow sandy reef of glacial deposits in the eastern North Sea, about 15 km (9.3 mi) off the westernmost point of Denmark, Blåvands Huk. The reef contains the Horns Rev Offshore Wind Farm.

Ørsted A/S is a Danish multinational energy company. Headquartered in Fredericia, Denmark, Ørsted is the largest energy company in Denmark. The company adopted its current name on 6 November 2017. It was previously known as DONG.

<span class="mw-page-title-main">Vestas</span> Danish wind turbine company

Vestas Wind Systems A/S is a Danish manufacturer, seller, installer, and servicer of wind turbines that was founded in 1945. The company operates manufacturing plants in Denmark, Germany, the Netherlands, Taiwan, India, Italy, Romania, the United Kingdom, Spain, Sweden, Norway, Australia, China, Brazil, Poland and the United States, and employs 29,000 people globally.

<span class="mw-page-title-main">Wind power in Denmark</span>

Denmark was a pioneer in developing commercial wind power during the 1970s, and today a substantial share of the wind turbines around the world are produced by Danish manufacturers such as Vestas—the world's largest wind-turbine manufacturer—along with many component suppliers. Furthermore, Denmark has—as of 2022—the 2nd highest amount in the world of wind power generation capacity installed per capita, behind only neighboring Sweden.

<span class="mw-page-title-main">Nysted Wind Farm</span> Danish offshore wind farm

The Nysted Wind Farm is a Danish offshore wind farm close to the Rødsand sand bank near Lolland. Gravity base foundations are used rather than piles due to ice conditions.

<span class="mw-page-title-main">Burbo Bank Offshore Wind Farm</span>

The Burbo Bank Offshore Wind Farm is a 348 MW offshore wind farm located on the Burbo Flats in Liverpool Bay on the west coast of the UK in the Irish Sea. It consists of an original 90 MW wind farm commissioned in 2007 and a 258 MW extension completed in 2017.

<span class="mw-page-title-main">Offshore wind power</span> Wind turbines in marine locations for electricity production

Offshore wind power or offshore wind energy is the generation of electricity through wind farms in bodies of water, usually at sea. There are higher wind speeds offshore than on land, so offshore farms generate more electricity per amount of capacity installed. Offshore wind farms are also less controversial than those on land, as they have less impact on people and the landscape.

<span class="mw-page-title-main">DanTysk</span>

DanTysk is a 288 megawatt (MW) offshore wind farm in the North Sea 70 kilometres (43 mi) west of the island Sylt, in the German EEZ at the border to Denmark. The wind farm operates 80 Siemens Wind Power's SWT-3.6-120 turbines with a capacity of 3.6 MW each.

<span class="mw-page-title-main">Gunfleet Sands Offshore Wind Farm</span>

Gunfleet Sands Offshore Wind Farm is a 172 MW wind farm about 7 kilometres (4.3 mi) off the Clacton-on-Sea coast in the Northern Thames Estuary.

<span class="mw-page-title-main">Anholt Offshore Wind Farm</span> Danish offshore wind power wind farm

Anholt Offshore Wind Farm is a Danish offshore wind power wind farm in the Kattegat, between Djursland and Anholt island. With a nameplate capacity of 400 megawatts (MW), it is one of the largest offshore wind farm in the world and was the largest in Denmark from 2013 to 2019. A cable from the wind farm to Anholt replaces most of the diesel-powered electricity on the island.

<span class="mw-page-title-main">Electricity sector in Denmark</span> Overview of the electricity sector in Denmark

Denmark's western electrical grid is part of the Synchronous grid of Continental Europe whereas the eastern part is connected to the Synchronous grid of Northern Europe via Sweden.

<span class="mw-page-title-main">Westermost Rough Wind Farm</span>

Westermost Rough Wind Farm is an offshore wind farm 8 kilometres (5 mi) north east of Withernsea off the Holderness coast, in the North Sea, England. The farm covers an area of approximately 35 km2 (14 sq mi) with a generation capacity of approximately 210 MW. It became operational in May 2015.

<span class="mw-page-title-main">Vestas V164</span> Three-bladed offshore wind turbine

The Vestas V164 is a three-bladed offshore wind turbine, produced by Vestas, with a nameplate capacity of up to 10 megawatts, a world record. Vestas revealed the V164's design in 2011 with the first prototype unit operated at Østerild in northern Denmark in January 2014. The first industrial units were installed in 2016 at Burbo Bank, off the west coast of the United Kingdom. By 2021, Vestas had produced 500 of the series.

<span class="mw-page-title-main">Henrik Stiesdal</span> Danish inventor and businessman

Henrik Stiesdal is a Danish inventor and businessman in the modern wind power industry. In 1978, he designed one of the first wind turbines representing the so-called "Danish Concept" which dominated the global wind industry through the 1980s. Until 2014, Stiesdal was the chief technology officer of Siemens Wind Power. During his professional career, Stiesdal has made more than 175 inventions and has received more than 650 patents related to wind power technology.

Kriegers Flak is a 605 MW offshore wind farm in the Baltic Sea on the Danish part of the reef of the same name. It forms part of a new 400 MW interconnector between Denmark and Germany.

<span class="mw-page-title-main">Avedøre Holme Offshore Wind Farm</span>

Avedøre Holme Offshore Wind Farm is a nearshore wind farm right off the coast of Avedøre, Copenhagen. It was commissioned in 2009 with three 3.6 MW Siemens turbines as a demonstrator project for future offshore wind turbines. Ørsted owns two turbines, and a private collective owns the third. Ørsted and partners build a 2MW hydrogen electrolysis station at Avedøre Power Station supplied by Ørsted's two turbines.

References

  1. "Where the Wind Blows". Nordic Investment Bank. Retrieved 1 December 2011.
  2. "Vattenfall to spend $1.12bn on Danish wind farm". Power Engineering International. Archived from the original on 20 February 2019. Retrieved 19 February 2019.
  3. 1 2 Horns Rev Wind Farm Archived 29 January 2010 at the Wayback Machine , Horns Rev web site. Retrieved 11 March 2010.
  4. 1 2 Andrew (2017-01-26). "Capacity factors at Danish offshore wind farms". energynumbers.info. Archived from the original on 2017-01-29. Retrieved 2017-02-11.
  5. "Horns Rev". Vattenfall. Archived from the original on 13 January 2011. Retrieved 12 January 2011.
  6. Horns Revolution Archived 14 July 2011 at the Wayback Machine , Modern Power Systems 5 October 2002. Retrieved 11 March 2010.
  7. Morgan, Colin. Offshore Wind - State of the Art page 24 Garrad Hassan , 20 October 2004. Retrieved: 19 November 2010.
  8. Larsen, Jens H. The World´s largest off-shore windfarm, Middelgrunden 40MW Archived 2020-05-31 at the Wayback Machine Copenhagen Environment and Energy Office (CEEO), 2001. Retrieved: 19 November 2010.
  9. Horns Rev 1 Offshore Wind Farm C4 Offshore
  10. 1 2 3 "Fremskrivning af PSO-udgifter" [Projection of PSO Expenses](PDF) (in Danish). Danish Energy Agency. 19 May 2014. p. 4. Retrieved 17 January 2015.
  11. "Horns Reef Wind Farm, Denmark". power-technology.com. Retrieved 1 December 2011.
  12. Pinson, Pierre. "Radar@Sea". Archived from the original on 31 October 2019.
  13. PossPOW: Possible Power of Offshore Wind power plants Technical University of Denmark
  14. 1 2 "Horns Rev lærte Vattenfall lektien". Ingeniøren (in Danish). 24 January 2015.
  15. Episode 5. "Incredible Engineering Blunders: Fixed". Discovery UK. Archived from the original on 18 December 2019.{{cite web}}: CS1 maint: numeric names: authors list (link)
  16. James Kanter. Largest Offshore Wind Farm to Go Online Green Inc., 15 September 2009.
  17. 1 2 Matthew McDermott. "Denmark Inaugurates World's Largest Offshore Wind Farm - 209 MW Horns Rev 2" Treehugger Archived 2011-09-12 at the Wayback Machine
  18. 1 2 Stromsta, Karl-Erik (17 September 2009). "DONG cuts the ribbon at 209MW Horns Rev 2 project" . ReCharge. NHST Media Group. Retrieved 19 November 2010.
  19. "Søkabel til Horns Rev 2 er ude af drift". 19 October 2015.
  20. "Kabel til havmølleparken Horns Rev 2 er igen i drift". Archived from the original on 2015-12-26. Retrieved 2018-01-14.
  21. "Dong og Siemens giver Horns Rev 2 storstilet vinge-makeover". 28 January 2015.
  22. Accommodation Platform Archived 2011-07-19 at the Wayback Machine , DONG Energy. Retrieved February 2010.
  23. Krøyer, Kent. I kamp mod bølgerne: Teknikere besøger hver havmølle 10 gange om året (in Danish) Ing.dk , 14 December 2009. Accessed: 14 January 2015.
  24. Naming Ceremony Archived 2011-07-19 at the Wayback Machine , DONG Energy. Retrieved February 2010.
  25. Wittrup, Sanne. Vattenfall bygger verdens største beboelsesplatform ved havmøllepark (in Danish) Ing.dk , 14 January 2015. Accessed: 14 January 2015.
  26. Rasmussen, Jesper Nørskov. "Vindmøller slog rekord i 2014 Archived 6 January 2015 at the Wayback Machine " Energinet.dk , 6 January 2015. Accessed: 6 January 2015.
  27. Dyrskjøt, Mette. "Two giant offshore wind park tenders in 2013" Archived 2012-04-25 at the Wayback Machine Dagbladet Børsen , 23 April 2012. Retrieved 23 April 2012.
  28. "Energinet kicks off 1GW offshore work" [ permanent dead link ]reNews, 23 April 2012. Retrieved 23 April 2012.
  29. "Danish Officials Seek Experienced Bidders" OffshoreWind, 11 October 2013. Retrieved: 12 October 2013.
  30. "Draft for prequalification criteria for the tender of Horns Rev 3 offshore wind farm Archived 23 February 2015 at the Wayback Machine " Danish Energy Agency , 10 October 2013. Retrieved: 12 October 2013.
  31. Wittrup, Sanne. "70 tyske miner kan forsinke kommende havmøllepark " Ingeniøren , 23 February 2015. Accessed: 23 February 2015.
  32. Wittrup, Sanne. "Horns Rev 3 er en godbid " Ingeniøren , 16 February 2015. Accessed: 12 March 2015.
  33. Wittrup, Sanne. "Svenske Vattenfall skal bygge Danmarks næste havmøllepark Archived 2015-02-26 at the Wayback Machine " Ingeniøren , 26 February 2015. Accessed: 26 February 2015.
  34. Nielsen, Michael Korsgaard. "Vattenfall: Vi har ikke presset indtjeningen" Berlingske , 12 March 2015.
  35. Wittrup, Sanne. "Regnefejl, billig vind og sene kystmøller sænker prisen på grøn omstilling " Ingeniøren , 27 March 2015. Accessed: 27 March 2015.
  36. PSO prediction
  37. "Horns Rev 3 offshore wind farm Archived 22 October 2016 at the Wayback Machine " Vattenfall , 27 June 2016. Accessed: 29 October 2016.
  38. "Transformer units sent to Horns Rev 3".
  39. "First power for Horns Rev 3" 4C Offshore , 24 December 2018. Accessed: 04 January 2019.
  40. Wittrup, S. (21 January 2019). Alle 49 havvindmøller på plads på Horns Rev 3. ing.dk. Retrieved 15 August 2019.
  41. Mathiesen, K. (6 August 2019). Hvide Sande snupper Horns Rev 3-service fra Esbjerg: Havnedirektør er stadig fortrøstningsfuld. JydskeVestkysten. Retrieved 15 August 2019.