The Lava Ridge Wind Project is a proposed wind energy plant to be built in the Magic Valley region of Idaho. [1] [2] It would have a maximum of 400 wind turbines generating a nameplate capacity of over 1000 MW, making it one of the most powerful wind farms in the United States. The project has faced opposition, in part due to turbines and infrastructure potentially being visible from the site of the former Minidoka internment camp. On June 6, 2024, the Bureau of Land Management issued their final environmental impact statement, outlining their preferred alternative, which would reduce the project's footprint by approximately 50% compared to the original proposal. [3] On December 9, it approved a final project with up to 241 turbines, the closest of which to Minidoka National Historic Site would be 9 miles away. [4]
The Bureau of Land Management (BLM) manages federal lands in the United States, including the land that the project is being proposed for. Soon after taking office, President Biden signed an executive order which set a goal to increase onshore renewable energy production on Department of the Interior lands. [5]
The BLM has been asked by Congress to increase production of renewable energy on federal lands to at least "25 gigawatts of electricity from wind, solar, and geothermal energy projects by not later than 2025." [6] By May 9, 2023, the BLM approved projects representing approximately 37% of that goal, and by April 11, 2024, the BLM had surpassed their goal more than a year early. [7] [8]
There are already 170 wind turbines within 30 miles of the project area with a total generating capacity of 280 MW. [9] Additionally, there are several other wind and solar projects proposed near the project. A project of similar size and capacity (1,500 MW), Taurus Wind, would be directly west of Lava Ridge. Salmon Falls Wind (800 MW) would be located approximately 30 miles south of Lava Ridge. Three solar projects located just east of US 93 to the north and south of Midpoint Substation would cover 10,000 acres with a combined capacity of over 1,000 MW. [10]
Magic Valley Energy, LLC (a subsidiary of LS Power) initially submitted a plan of development to the BLM in February 2020. After revisions, the plan was resubmitted in August 2022. The draft environmental impact statement (EIS) published in 2023 identifies five alternatives (A–E). Alternative A would deny the project, Alternative B is the plan presented by MVE, and Alternatives C, D, and E would have smaller footprints and energy generation (see pictured). [10]
The project is notable for its potential use of very large 6 MW wind turbines with hubs 460 feet (140 m) tall and blades up to 280 feet (85 m) long, reaching a maximum height of 740 feet (230 m) into the air. [10] Groups opposed to the project have negatively commented on the height of these turbines, comparing it to twice the height of the Statue of Liberty [305 feet (93 m) from ground level] and the Space Needle [605 feet (184 m)]. [11] [12]
The final environmental impact statement outlined the BLM's preferred alternative, which reduced the siting corridors from 84,051 acres to 44,758 acres. The maximum turbine size was reduced from 6 MW to 5 MW (limited at 660 feet (200 m) tall), and the maximum number of turbines was reduced from 400 to 241. The maximum estimated generating capacity was reduced from 2,094 MW to 1,205 MW. The estimated annual generation was reduced from 6.4-8.3 TWh with all 6-MW turbines to 3.7-4.8 TWh with all 5-MW turbines. [13]
Alternative | Footprint size | Wind turbines | Estimated generation capacity | Estimated annual generation in terawatt hours (TWh) for the project operating at 35%–45% net capacity factor | Annual generation in comparison to Alternative B |
---|---|---|---|---|---|
B (original proposal) | 197,474 acres | Up to 400 3-MW turbines or up to 349 6-MW turbines | 1,200–2,094 MW | 3.7–4.7 TWh with all 3-MW turbines 6.4–8.3 TWh with all 6-MW turbines | - |
Preferred | 103,864 acres | Up to 241 3-MW or 5-MW turbines | 723–1,205 MW | 2.2–2.9 TWh with all 3-MW turbines 3.7–4.8 TWh with all 5-MW turbines | 38% reduction (3-MW 42% reduction (5-MW) |
C | 146,389 acres | Up to 378 3-MW turbines or up to 259 6-MW turbines | 1,134–1,554 MW | 3.5–4.5 TWh with all 3-MW turbines 4.8–6.1 TWh with all 6-MW turbines | 5% reduction (3-MW) 26% reduction (6-MW) |
D | 110,315 acres | Up to 280 3-MW turbines or up to 179 6-MW turbines | 840–1,074 MW | 2.6–3.3 TWh with all 3-MW turbines 3.3–4.2 TWh with all 6-MW turbines | 30% reduction (3-MW) 49% reduction (6-MW) |
E | 122,444 acres | Up to 269 3-MW turbines or up to 194 6-MW turbines | 807–1,164 MW | 2.5–3.2 TWh with all 3-MW turbines 3.6–4.6 TWh with all 6-MW turbines | 33% reduction (3-MW) 44% reduction (6-MW) |
Annual bird deaths are estimated at an average of 3,240–5,654 for Alternative B. [10]
The BLM will issue its final record of decision at least 30 days after the final EIS was published on June 6, 2024. [14] Reactions to the Final EIS were mostly consistent existing concerns from the various stakeholders. [15]
Following the results of the 2024 US presidential election, many community members believe that the incoming Republican administration would result in the BLM moving to reject the project. [16]
Some Idaho Republican lawmakers have opposed the project, including US Senator James E. Risch who argued to Secretary of the Interior Deb Haaland that most of Idaho's in-state energy generation already comes from renewable hydroelectric dams, [7] though the state also must import one third of its electricity. [17] Most of the project's power will be exported through the already approved Southwest Intertie Project (SWIP), also being developed by LS Power, which runs south to Las Vegas and Southern California. [1]
Jerome, Minidoka, and Lincoln counties passed resolutions in opposition to the project in 2022 before the release of the draft EIS. Jerome County Commissioner Charles Howell stated that he "[had] not heard one person in the community support the project." [18] During construction, lands which are currently being used for cattle grazing will be temporarily off limits to ranchers. MVE has stated that the land will be reopened for grazing after construction, pointing to "literally thousands of wind turbines between Texas and North Dakota that are on operating cattle ranches." [19] Residents have also expressed concerns about noise from blasting to construct roads and bases for the towers, as well as use of water resources during construction. [1] Communications and emergency services groups have warned that the towers may disrupt signals and accommodations may be needed. [20]
Supporters say that it will generate tax revenue, which is projected to be around $1 million for Lincoln County alone. [21] Additionally, Idaho currently imports most of its energy from other states, and this project would help Idaho increase its energy independence. John Robin, public lands director of the Idaho Conservation League argued that “although some of the purchasers might be in California, once the electricity is in the grid, it's available for the whole region and ... reduce fossil fuel emissions. We all benefit from that.” [21] If constructed, Idaho Power will likely purchase power to meet its renewable energy goal of 100% renewable energy by 2045. [1]
The proposed Taurus Wind project, with a similar size, scope, and area, has also faced local opposition. [22]
In Alternative B, the nearest turbine would be 1.7 miles from the Minidoka visitor center; in Alternative C it would be 5.5 miles away. [10] : 3–167, 3–182 Opponents from the Japanese American community say that the visual and auditory impact of wind turbines in the background of Minidoka National Historic Site detracts from its somber nature. Robyn Achilles, executive director of Friends of Minidoka compared it to other locations, saying "You wouldn't build a huge wind project over another concentration camp, or Gettysburg, or the Washington Monument." Friends of Minidoka has continued its opposition to the project, including the scaled back alternatives. It is also asking for a 237,000 acre area around Minidoka to be protected as an "area of critical environmental concern." [23] [7]
The BLM's preferred siting alternative reduced the original project area by 50% to ensure all wind turbines would be at least 9 miles from Minidoka National Historic Site. [24] Along with the turbine height limit, this would substantially reduce visual impact. [25]
Under the Fort Bridger Treaty of 1868, Shoshone people are allowed to hunt off the reservation on "unoccupied lands of the United States so long as game may be found thereon." The Shoshone-Bannock Tribe expressed concerns related to how the project would impact hunting and gathering, as well as the night sky, which would be illuminated by safety lights on the turbines. [10]
Tidal power or tidal energy is harnessed by converting energy from tides into useful forms of power, mainly electricity using various methods.
A wind farm or wind park, or wind power plant, is a group of wind turbines in the same location used to produce electricity. Wind farms vary in size from a small number of turbines to several hundred wind turbines covering an extensive area. Wind farms can be either onshore or offshore.
Minidoka National Historic Site is a National Historic Site in the western United States. It commemorates the more than 13,000 Japanese Americans who were imprisoned at the Minidoka War Relocation Center during the Second World War. Among the inmates, the notation 峰土香 or 峯土香 was sometimes applied.
The Soda Mountains are located in the eastern Mojave Desert in San Bernardino County, California, USA. The range lies to the north of Interstate 15 west of the town of Baker.
Wind power in Texas, a portion of total energy in Texas, consists of over 150 wind farms, which together have a total nameplate capacity of over 30,000 MW. If Texas were a country, it would rank fifth in the world; the installed wind capacity in Texas exceeds installed wind capacity in all countries but China, the United States, Germany and India. Texas produces the most wind power of any U.S. state. According to the Electric Reliability Council of Texas (ERCOT), wind power accounted for at least 15.7% of the electricity generated in Texas during 2017, as wind was 17.4% of electricity generated in ERCOT, which manages 90% of Texas's power. ERCOT set a new wind output record of nearly 19.7 GW at 7:19 pm Central Standard Time on Monday, January 21, 2019.
Sunrise Powerlink is a high-voltage power transmission line by San Diego Gas & Electric (SDG&E) in San Diego County, California and Imperial County, California. The project was approved by the United States Forest Service (USFS) in July 2010, the U.S. Bureau of Land Management (BLM) in January 2009 and the California Public Utilities Commission (CPUC) in December 2008. SDG&E stated that the 117-mile (188 km) long 230/500 kilovolt power line would bring 1000 megawatts of renewable energy from the Imperial Valley to San Diego County. The cost of the project was estimated to be $1.9 billion for construction. SDG&E, which was to receive a guaranteed profit of over $1.4 billion from the construction of the line, claimed that the power line was necessary to support future growth of the San Diego region, and its economic benefits to the region would measure on the order of $100 million per year. However, the project has been called one of the most controversial projects ever proposed.
The Forward Wind Energy Center is a 137.85 megawatt (MW) wind farm in Dodge and Fond du Lac County, Wisconsin near the village of Brownsville. The wind farm sits on approximately 4,000 acres of land. "Forward" is the state's motto. The facility is sited in close proximity to the Horicon National Wildlife Refuge and the Horicon Marsh State Wildlife Area which provide nesting areas for waterfowl and a resting area for large numbers of migratory birds.
The Shiloh wind power plant is a wind farm located in the Montezuma Hills of Solano County, California, USA, close to Bird's Landing and Collinsville, 40 miles (64 km) northeast of San Francisco. It has a nameplate capacity of 505 megawatts (MW) of power and was built in four stages between 2005 and 2012. Several additional projects are also located in the Montezuma.
The environmental impact of electricity generation from wind power is minor when compared to that of fossil fuel power. Wind turbines have some of the lowest global warming potential per unit of electricity generated: far less greenhouse gas is emitted than for the average unit of electricity, so wind power helps limit climate change. Wind power consumes no fuel, and emits no air pollution, unlike fossil fuel power sources. The energy consumed to manufacture and transport the materials used to build a wind power plant is equal to the new energy produced by the plant within a few months.
There are a number of wind power projects in the state of Maine, totaling more than 900 megawatts (MW) in capacity. In 2020 they were responsible for 24% of in-state electricity production. In 2019, Maine had more wind capacity than the other five New England states combined, at 923 MW.
New York has 2,192 MW of installed wind power capacity as of 2022. Most of New York's wind power is located in upstate New York as onshore wind farms. New York has set a goal of developing 9,000 MW of offshore installed wind power capacity by 2035 that will power an estimated 6 million homes. As of October 2022, New York has five offshore wind farms in development with approximately 4,300 MW installed capacity.
The Capricorn Ridge Wind Farm is located in Sterling and Coke counties, Texas. The wind farm does not create any air and water pollution to the surrounding counties. It is a 662.5 MW wind farm, with 342 GE 1.5 MW wind turbines and 65 2.3 MW Siemens turbines that are capable of generating enough electricity for more than 220,000 homes. With all four phases combined, there should be over 400 turbines after the project commissioned in 2007. The wind farm is built, owned and operated by a subsidiary of NextEra Energy Resources, the U.S.' largest wind energy generator who is also known for generating electricity using natural gas, oil solar, wind and nuclear. This company, together with its subsidiaries owns, operates, develops, constructs and manages electricity and energy generating facilities in not only the U.S. but also in Canada and Spain. The project is part owned by San Antonio-based Sullivan Trillian Fund Private Equity. Its property Offtaker is Energy Market- ERCOT.
In 2016, Arizona had 268 megawatts (MW) of wind powered electricity generating capacity, producing 0.5% of in-state generated electricity.
The U.S. state of Massachusetts has vast wind energy resources offshore, as well as significant resources onshore. The 2016 update to the states's Clean Energy and Climate Plan had a goal of reducing 1990 baseline greenhouse gas emissions levels by 25% by 2020. Current goals include installing 3,500 megawatts (MW) of offshore wind power in the state by 2035. However, as of Q4 2021 the state had only 120 MW of wind powered electricity generating capacity, responsible for generating 0.9% of in-state electricity production. The state has awarded contracts to two offshore projects, the 800 MW Vineyard Wind project and 804 MW Mayflower Wind project. Construction began on the Vineyard Wind 1 project on November 18, 2021, after a long fight for approval. Commonwealth Wind was selected for development in 2021, but the developer has attempted to cancel the project due to increased costs. There are eight projects planned for off the southern coast of Massachusetts, though some will deliver power to Rhode Island, Connecticut, and New York.
Modern United States wind energy policy coincided with the beginning of modern wind industry of the United States, which began in the early 1980s with the arrival of utility-scale wind turbines in California at the Altamont Pass wind farm. Since then, the industry has had to endure the financial uncertainties caused by a highly fluctuating tax incentive program. Because these early wind projects were fueled by investment tax credits based on installation rather than performance, they were plagued with issues of low productivity and equipment reliability. Those investment tax credits expired in 1986, which forced investors to focus on improving the reliability and efficiency of their turbines. The 1990s saw rise to a new type of tax credit, the production tax credit, which propelled technological improvements to the wind turbine even further by encouraging investors to focus on electricity output rather than installation.
Despite its high potential for wind energy generation, wind power in Kenya currently contributes only about 16 percent of the country's total electrical power. However, its share in energy production is increasing. Kenya Vision 2030 aims to generate 2,036 MW of wind power by 2030. To accomplish this goal, Kenya is developing numerous wind power generation centers and continues to rely on the nation's three major wind farms: the Lake Turkana Wind Power Station, the Kipeto Wind Power Station, and the Ngong Hills Wind Farm. While these wind power stations are beneficial to help offset fossil fuel usage and increase overall energy supply reliability in Kenya, project developments have also negatively impacted some indigenous communities and the parts of the environment surrounding the wind farms.
Renewable energy in Taiwan contributed to 8.7% of national electricity generation as of end of 2013. The total installed capacity of renewable energy in Taiwan by the end of 2013 was 3.76 GW.
The Chokecherry and Sierra Madre Wind Energy Project is large-scale wind farm currently under construction near Rawlins, Wyoming. If completed as scheduled in 2026, it will likely become the largest wind farm in the United States and one of the largest in the world. Located largely on federal lands, the project is being built in conjunction with the TransWest Express transmission line to supply power to California. Originally slated for completion in 2020, the finish date was extended to 2026 in 2019 amid permitting, environmental, and construction delays.
LS Power is an American independent power company that owns, operates, and develops power generating stations, storage facilities, and transmission lines. Founded in 1990, the company originally focused on developing and selling natural gas power plants, but has since expanded into developing renewable energy plants and transmission lines. The company's approach focuses on competing to win transmission line contracts at a lower price than established utilities and using its large asset portfolio to develop projects with "high barriers to entry." With a combined capacity of 2.3 GW of pumped storage hydropower and lithium-ion battery storage, LS Power has the largest non-utility owned energy storage portfolio in the United States.